| Sl No. | Division | Physical progress is < 100% but Target Date Exceeded |
Physical Progress % > 80% but Finacial Progress % <10% |
Target date is Blank |
|---|---|---|---|---|
| 56 | 6,928 | 159 | 415 | |
| 1 | Office of the CE,Head Quarter | 4 | 0 | 12 |
| 2 | Alipore Division | 447 | 1 | 14 |
| 3 | Barasat Division | 236 | 2 | 15 |
| 4 | Nadia Division | 258 | 0 | 2 |
| 5 | Murshidabad Division | 305 | 11 | 13 |
| 6 | North 24 Pgs W/S Division I | 61 | 0 | 9 |
| 7 | Midnapore Division | 469 | 7 | 17 |
| 8 | Tamluk Division | 411 | 1 | 6 |
| 9 | Bankura Division | 634 | 4 | 10 |
| 10 | RCFA Division I | 48 | 0 | 8 |
| 11 | Nadia Arsenic Division I | 35 | 5 | 5 |
| 12 | Durgapur W/S Division | 108 | 0 | 1 |
| 13 | Purulia Division | 83 | 1 | 10 |
| 14 | Howrah Division | 13 | 1 | 5 |
| 15 | Hooghly Division | 386 | 4 | 8 |
| 16 | Burdwan Division | 301 | 0 | 13 |
| 17 | Birbhum Division | 164 | 2 | 12 |
| 18 | Raiganj Division | 271 | 6 | 18 |
| 19 | Jalpaiguri Division | 225 | 1 | 9 |
| 20 | Coochbehar Division | 298 | 0 | 12 |
| 21 | Siliguri W/S Division | 104 | 0 | 5 |
| 22 | Neorakhola W/S Mnt. Division | 255 | 7 | 21 |
| 23 | Darjeeling Division | 2 | 0 | 0 |
| 24 | Kalimpong Division | 11 | 0 | 0 |
| 25 | Malda Division | 194 | 0 | 10 |
| 26 | Malda Arsenic Area W/S Division | 68 | 0 | 4 |
| 27 | Balurghat Division | 283 | 3 | 7 |
| 28 | Electrical Division | 4 | 0 | 0 |
| 29 | South 24 Pgs Mechanical Division | 0 | 4 | 5 |
| 30 | Central Mechanical Division | 2 | 0 | 1 |
| 31 | Asansol Mechanical Division | 3 | 0 | 4 |
| 32 | Purulia Mechanical Division | 3 | 1 | 1 |
| 33 | Bolpur Mechanical Division | 1 | 0 | 3 |
| 34 | Midnapore Mechanical Division | 125 | 27 | 5 |
| 35 | Bankura Mechanical Division | 14 | 0 | 2 |
| 36 | Resources Division | 9 | 0 | 95 |
| 37 | Eastern Mechanical Division | 5 | 12 | 4 |
| 38 | Malda Mechanical Division | 2 | 5 | 1 |
| 39 | Northern Mechanical Division | 24 | 8 | 1 |
| 40 | Special Investigation Division | 0 | 0 | 0 |
| 41 | Survey Division | 0 | 0 | 0 |
| 42 | Investigation Unit | 0 | 0 | 6 |
| 43 | Planning and Design Division IV | 0 | 0 | 7 |
| 44 | South 24 Pgs. W/S Division - I | 360 | 0 | 14 |
| 45 | Barasat Arsenic Division | 29 | 0 | 5 |
| 46 | Nadia Arsenic Civil Division II | 66 | 1 | 0 |
| 47 | Berhampur Division I | 175 | 6 | 0 |
| 48 | Berhampur M/E Division | 0 | 6 | 1 |
| 49 | WSSO | 0 | 0 | 0 |
| 50 | Project Management Unit,WBPWSP,Purulia | 0 | 0 | 1 |
| 51 | Alipurduar Division | 227 | 2 | 3 |
| 52 | Kurseong Division | 24 | 0 | 1 |
| 53 | Northern Mechanical Division II | 15 | 0 | 1 |
| 54 | Project Implementation Unit,Purba Midnapur(ADB) | 1 | 0 | 0 |
| 55 | Jhargram Division | 159 | 6 | 7 |
| 56 | Jhargram Mechanical Division | 6 | 25 | 1 |
| Total | 6,928 | 159 | 415 | |