H2- Exception Report on Scheme

Update Data
Rs. in Lakh
Sl. No. Division District Block Scheme Name Scheme Category Sub Division Name of AE entrusted Name of JE entrusted Date of Sanction Date of Commencement Target Date of Completion Date Of Updation Work Order Issued FHTCs Sanctioned Cost Payment Physical Progress (in %) Financial Progress (in %)
17 19 0 1,135.47 109.16   10
1 Bankura Mechanical Division BANKURA Sonamukhi Construction of Grid- connection solar photo-voltaic system for Kanaipur pumping station of Panchal PWS scheme,Dist: Bankura.,SM/10271 IOT Bankura Mechanical Sub-Division Assistant Engineer 25/02/2022 28/04/2022 31/03/2024 09/10/2023 1 0 16.95 9.23 98 54
2 Bankura Mechanical Division BANKURA Barjora Construction of Grid-Connected solar photo -voltaic system for Beliatore PWSS scheme, Dist- Bankura,SM/15311 IOT Bankura Mechanical Sub-Division Assistant Engineer 09/02/2023 05/04/2023 31/03/2024 10/10/2023 1 0 21.98 11.48 73 52
3 Bankura Mechanical Division BANKURA Bankura - II Construction of Grid-Connected solar photo -voltaic system for Ekteswar PWSS scheme Dist Bankura,SM/15312 IOT Bankura Mechanical Sub-Division Assistant Engineer 09/02/2023 19/04/2023 31/03/2024 14/12/2023 1 0 34.74 10.89 88 31
4 Bankura Mechanical Division BANKURA Patrasayer Construction of Grid-Connected solar photo -voltaic system for Patrasayer PWSS scheme Dist Bankura,SM/15313 IOT Bankura Mechanical Sub-Division Assistant Engineer 09/02/2023 19/09/2023 31/03/2024 27/02/2024 1 0 8.35 2.73 44 33
5 Bankura Mechanical Division BANKURA Vishnupur Construction of Grid-Connected solar photo -voltaic system for Radhanagar PWSS scheme Dist Bankura,SM/15314 IOT Bankura Mechanical Sub-Division Assistant Engineer 09/02/2023 10/02/2023 31/10/2023 23/08/2023 1 0 31.01 16.40 75 53
6 Bankura Mechanical Division BANKURA Simlapal Construction of Grid-Connected solar photo -voltaic system for Laxmisagar PWSS scheme Dist Bankura,SM/15315 IOT Bankura Mechanical Sub-Division Assistant Engineer 09/02/2023 23/03/2023 31/03/2024 28/03/2024 1 0 6.80 0.00 40 0
7 Bankura Mechanical Division BANKURA Patrasayer Construction of Grid-Connected solar photo -voltaic system for Nabakishor PWSS scheme Dist Bankura,SM/15316 IOT Bankura Mechanical Sub-Division Assistant Engineer 09/02/2023 20/09/2023 31/03/2024 27/02/2024 1 0 11.26 2.01 42 18
8 Bankura Mechanical Division BANKURA Sarenga Construction of Grid-Connected solar photo -voltaic system for Sarenga PWSS scheme Dist Bankura,SM/15317 IOT Bankura Mechanical Sub-Division Assistant Engineer 09/02/2023 17/04/2023 09/08/2023 12/06/2023 1 0 42.20 0.00 0 0
9 Bankura Mechanical Division BANKURA Bankura - I Construction of Grid-Connected solar photo -voltaic system for Sanabandh PWSS scheme Dist Bankura,SM/15318 IOT Bankura Mechanical Sub-Division Assistant Engineer 09/02/2023 23/05/2023 31/03/2024 14/12/2023 1 0 34.74 12.28 98 35
10 Bankura Mechanical Division BANKURA Jaypur Construction of Grid-Connected solar photo -voltaic system for Pump House I of Moynapur PWS scheme Dist Bankura,SM/15328 IOT Bankura Mechanical Sub-Division Assistant Engineer 09/02/2023 23/03/2023 09/08/2023 12/06/2023 1 0 14.34 0.00 0 0
11 Bankura Mechanical Division BANKURA Chhatna Construction of Grid-connected Solar Photo-Voltaic system for IBS Uppargora pumping station of Chhatna-Saltora PWSS scheme,Dist: Bankura,SM/15329 IOT Bankura Mechanical Sub-Division Assistant Engineer 09/02/2023 10/05/2023 31/03/2024 30/11/2023 1 0 366.53 21.87 50 6
12 Bankura Mechanical Division BANKURA Saltora Construction of Grid-connected Solar Photo-Voltaic system for Kukrakuri intake pumping station of Chhatna-Saltora PWSS scheme,Dist: Bankura,SM/15330 IOT Bankura Mechanical Sub-Division Assistant Engineer 09/02/2023 17/08/2023 09/08/2023 12/06/2023 1 0 366.53 0.00 0 0
13 Bankura Mechanical Division BANKURA Jaypur Construction of Grid-connected Solar Photo-Voltaic system for Joypur pump house-I of Joypur PWSS scheme,Dist: Bankura,SM/16932 IOT Bankura Mechanical (Drill) Sub-Division Assistant Engineer Junior Engineer 16/03/2023 17/04/2023 16/09/2023 12/06/2023 1 0 9.77 0.00 0 0
14 Bankura Mechanical Division BANKURA Kotulpur Construction of Grid-connected Solar Photo-Voltaic system for Katulpur pump house-I(OHR site) of Kotulpur PWSS scheme,Dist: Bankura,SM/16963 IOT Bankura Mechanical Sub-Division Assistant Engineer 16/03/2023 17/04/2023 16/09/2023 12/06/2023 1 0 11.12 0.00 0 0
15 Bankura Mechanical Division BANKURA Sonamukhi Construction of Grid-connected Solar Photo-Voltaic system for Rampur pump house-I of Rampur PWSS scheme,Dist: Bankura,SM/16965 IOT Bankura Mechanical Sub-Division Assistant Engineer 16/03/2023 04/05/2023 31/03/2024 25/01/2024 1 0 6.92 1.74 72 25
16 Bankura Mechanical Division BANKURA Khatra Construction of Grid-connected Solar Photo-voltaic System for Mukutmonipur Pumping Station of Mukutmonipur PWS Scheme, Dist: Bankura. ,SM/17238 IOT Bankura Mechanical (Drill) Sub-Division Driller-in-Charge 15/03/2023 15/09/2023 31/03/2024 31/01/2024 3 0 140.97 20.53 80 15
17 Bankura Mechanical Division BANKURA Sarenga Construction of Grid-Connected solar photo -voltaic system for Chhoto Birbhanpur PWSS scheme Dist Bankura,SM/17239 IOT Bankura Mechanical Sub-Division Assistant Engineer 15/03/2023 17/04/2023 15/09/2023 12/06/2023 1 0 11.26 0.00 0 0
Total 19 0 1,135.47 109.16   10