H2- Exception Report on Scheme

Update Data
Rs. in Lakh
Sl. No. Division District Block Scheme Name Scheme Category Sub Division Name of AE entrusted Name of JE entrusted Date of Sanction Date of Commencement Target Date of Completion Date Of Updation Work Order Issued FHTCs Sanctioned Cost Payment Physical Progress (in %) Financial Progress (in %)
1 1 0 199.99 0   0
1 Bolpur Mechanical Division BIRBHUM Khoyrasol Solarisation for NET metering of different PWSS at different Blocks under Bolpur Mechanical Division,PHED,SM/16381 IOT Central Mechanical Sub-DivisionIII Assistant Engineer-III Junior Engineer 28/02/2023 14/06/2023 31/08/2023 12/06/2023 1 0 199.99 0.00 0 0
Total 1 0 199.99 0   0