Sl. No. | Division
Working Divisions
|
System Order No
System generated Order No. for the Work Order as per PHED-MIS
|
Order Date
Date of Issuance of the Work Order as per PHED-MIS
|
Memo Number
Memo no. for Work Order Provided by the Divisions as per PHED-MIS
|
Vendor Name
Vendor Appointed Against this Work Order as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Order Value
Value of Work as mentioned in the Work Order
|
---|---|---|---|---|---|---|---|
20 | 19.25 | ||||||
1 | Barasat Division | ORD/000549/2024-2025 | 22/10/2024 | 1213/HSD | RANJIT KUMAR MANDAL | Work order for Hiring of one no. DIESEL MOTOR CAB (BS-VI) on daily hire basis for use of the Assistant Engineer, HASNABAD SUB-DIVISION, PHE DTE. Period from 01.11.24 to 30.04.25. | 0.86 |
2 | Barasat Division | ORD/000022/2024-2025 | 12/06/2024 | 629/HSD | DEB PRASAD GHOSH. | Acceptance cum work order for Sinking of 1 Nos. 330.00 mtr. Deep 100 X 50 mm. dia. Trial-cum-production Tube well fitted with Indian Mark - II pump with PVC pipe & strainers at T/W site-1 for Sahebkhali w/s scheme (Zone-II), Hingalganj block under Hasna | 3.50 |
3 | Barasat Division | ORD/000303/2024-2025 | 07/08/2024 | 870/HSD | BIBHAS PAL. | Acceptance cum work order for Installation of scheme information board at different villages of various PWSS of Minakhan block within Hasnasbad Sub-Division under Barasat Division, P.H.E.Dte. (Part-K). | 0.87 |
4 | Barasat Division | ORD/000398/2024-2025 | 07/08/2024 | 889/HSD | M.R.CONSTRUCTION. | Acceptance cum work order for Installation of scheme information board at different villages of various PWSS of Hingalganj block within Hasnasbad Sub-Division under Barasat Division, P.H.E.Dte. (Part-G). | 0.87 |
5 | Barasat Division | ORD/000561/2024-2025 | 23/10/2024 | 1217/HSD | SARKAR ENTERPRISE | Work order for Hiring of one no. DIESEL MOTOR CAB (BS-VI) on daily basis for smooth implementation of JJM work under office of the Assistant Engineer, HASNABAD SUB-DIVISION, PHE DTE. Period from 01.11.24 to 31.01.25 | 0.44 |
6 | Barasat Division | ORD/000304/2024-2025 | 07/08/2024 | 872/HSD | BIBHAS PAL. | Acceptance cum work order for Installation of scheme information board at different villages of various PWSS of Minakhan block within Hasnasbad Sub-Division under Barasat Division, P.H.E.Dte. (Part-L). | 0.87 |
7 | Barasat Division | ORD/000305/2024-2025 | 07/08/2024 | 874/HSD | S.M.TRADERS. | Acceptance cum work order for Installation of scheme information board at different villages of various PWSS of Minakhan block within Hasnasbad Sub-Division under Barasat Division, P.H.E.Dte. (Part-M). | 0.87 |
8 | Barasat Division | ORD/000316/2024-2025 | 07/08/2024 | 884/HSD | BIBHAS PAL. | Acceptance cum work order for Installation of scheme information board at different villages of various PWSS of Hingalganj block within Hasnasbad Sub-Division under Barasat Division, P.H.E.Dte. (Part-D). | 0.88 |
9 | Barasat Division | ORD/000318/2024-2025 | 07/08/2024 | 886/HSD | BIBHAS PAL. | Acceptance cum work order for Installation of scheme information board at different villages of various PWSS of Hingalganj block within Hasnasbad Sub-Division under Barasat Division, P.H.E.Dte. (Part-E). | 0.87 |
10 | Barasat Division | ORD/002232/2023-2024 | 13/07/2023 | 791/HSD | SUBHASH BOSE | Acceptance cum work order for Emergent resting of newly laid UPVC distribution pipeline by bamboo pilling at Mistri para near Pump House No.-1 of Jeliakhali Purbakhanda w/s scheme, Sandeshkhali-II Block under Hasnabad Sub-Division, PHE Dte. | 0.99 |
11 | Barasat Division | ORD/000560/2024-2025 | 30/07/2024 | 804/HSD | SARKAR ENTERPRISE | Work order for Hiring of one no. DIESEL MOTOR CAB (BS-VI) on daily basis for smooth implementation of JJM work under office of the Assistant Engineer, HASNABAD SUB-DIVISION, PHE DTE. Period from 01.08.24 to 31.10.24. | 0.44 |
12 | Barasat Division | ORD/000399/2024-2025 | 07/08/2024 | 887/HSD | S.M.TRADERS. | Acceptance cum work order for Installation of scheme information board at different villages of various PWSS of Hingalganj block within Hasnasbad Sub-Division under Barasat Division, P.H.E.Dte. (Part-F). | 0.88 |
13 | Barasat Division | ORD/000397/2024-2025 | 07/08/2024 | 878/HSD | M.R.CONSTRUCTION. | Acceptance cum work order for Installation of scheme information board at different villages of various PWSS of Hingalganj block within Hasnasbad Sub-Division under Barasat Division, P.H.E.Dte. (Part-A). | 0.87 |
14 | Barasat Division | ORD/000299/2024-2025 | 07/08/2024 | 867/HSD | SARKAR ENTERPRISE & CO. | Acceptance cum work order for 2 no. pump connection at PH No.-1 & 2 in connection with Augmentation for Mohanpur water supply scheme (Z-II), Minakhan block under Hasnabad Sub-Division, P.H.E. Dte. | 1.17 |
15 | Barasat Division | ORD/000315/2024-2025 | 07/08/2024 | 882/HSD | BIBHAS PAL. | Acceptance cum work order for Installation of scheme information board at different villages of various PWSS of Hingalganj block within Hasnasbad Sub-Division under Barasat Division, P.H.E.Dte. (Part-C). | 0.87 |
16 | Barasat Division | ORD/000319/2024-2025 | 07/08/2024 | 890/HSD | BIBHAS PAL. | Acceptance cum work order for Installation of scheme information board at different villages of various PWSS of Hingalganj block within Hasnasbad Sub-Division under Barasat Division, P.H.E.Dte. (Part-H). | 0.87 |
17 | Barasat Division | ORD/002520/2023-2024 | 09/01/2024 | ABDULALIMMONDAL | ABDUL ALIM MONDAL. | Acceptance cum work order for 1 no. pump connection at PH No.-2 in connection with Augmentation of Gabberia water supply scheme, Sandeshkhali-II block under Hasnabad Sub-Division, P.H.E. Dte. | 0.79 |
18 | Barasat Division | ORD/000314/2024-2025 | 07/08/2024 | 880/HSD | BIBHAS PAL. | Acceptance cum work order for Installation of scheme information board at different villages of various PWSS of Hingalganj block within Hasnasbad Sub-Division under Barasat Division, P.H.E.Dte. (Part-B). | 0.87 |
19 | Barasat Division | ORD/000311/2024-2025 | 07/08/2024 | 883/HSD | SRI KRISHNA CO-OP-LABOUR CONTRACT AND CONST SOC LTD. | Acceptance cum work order for 1 no. pump connection at PH No.-1 in connection with Augmentation for Noorpur water supply scheme, Minakhan block under Hasnabad Sub-Division, P.H.E. Dte. | 0.60 |
20 | Barasat Division | ORD/000396/2024-2025 | 07/08/2024 | 876/HSD | M.R.CONSTRUCTION. | Acceptance cum work order for Installation of scheme information board at different villages of various PWSS of Minakhan block within Hasnasbad Sub-Division under Barasat Division, P.H.E.Dte. (Part-N). | 0.87 |
Total | 19.25 |