Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
47 806.05 582.21 72.23  
1 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Formal order for the work of Supplying& laying of different dia HDPE pipe line with necessary allied works at Anandapur Mouza(JL-89),Block -Kanksa under Augmentation of Kanksa (Zone-I W/s Scheme under DWSD ,PHE Dte ORD/000395/2021-2022 197/DWSD 16/02/2022 30 AMAR CONSTRUCTION 27.51 15.36 55.83 0
2 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal work order for the work of Providing functional household tap connection (FHTC) in connection with JAL JEEBAN MISSION(JJM) at Annandapur mouza (JL-89) under command area of Kanksa Zone-I piped W/s Scheme of of Kanksa Block under Durgapur W/S Division, PHE Dte.(SL-24) ORD/000269/2020-2021 1324/DWSD 09/12/2020 45 M/S KALYANI ENTERPRISE 18.17 18.25 100.44 0
3 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Formal order for the work of Sinking of 1No(300X200 mm) dia tube well 150 mtr deep by direct rotary method using PVC pipe and fibber glass reinforced epoxy resin slotted at Tube well No-03 site at Anandapur under Kanksa block (Zone-I) for Augmentation of ground water base Kanksa (Zone-I) piped W/s Scheme under DWSD ,PHE Dte ORD/000396/2021-2022 196/DWSD 16/02/2022 30 RANJIB GHATAK 10.43 10.22 97.99 0
4 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Construction of pump house cum chlorine room at AnandaPur H/W site of ground water base Kanksa(Zone-I) pipe W/s Scheme under DWSD ,PHE Dte (SL-04) ORD/000403/2021-2022 241/A/DWSD 25/02/2022 45 CHANDAN HAZRA 4.99 4.89 98 0
5 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Formal order for the work of Sinking of 1 No Tube well 250 mm X 150 mm big dia Tube well 150 mtr deapth direct rotary rig method using PVC pipe & fiber glass rein forced epoxy resin slotted TW No-1 Part-A site at Shilampur Pump house under Kanksa block (Zone-I) for Kanksa piped W/s Scheme (Zone-I) under DWSD, PHE Dte (SL-11) ORD/000099/2022-2023 748/DWSD 10/05/2022 10 RANJIB GHATAK 10.68 10.67 99.91 0
6 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Rearing of pump house -I boundary wall and plinth protection at Silampur under Kanksa (Zone-I) for Augmentation of ground water based Kanksa (Zone-I) piped W/s Scheme under DWSD, PHE Dte.(SL-13) ORD/000449/2021-2022 428/DWSD 30/03/2022 15 BASANTI TRADERS 4.84 1.46 30.17 0
7 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Trail bore for 2 Nos (300x200 mm dia) tube well by direct rotary method at Annandapur and Shilampur pump house at Kanksa (Zone-I) for Augmentation of ground water of Kanksa (Zone-I) piped W/s Scheme under DWSD, PHE Dte (SL-04) ORD/000048/2022-2023 583/DWSD 21/04/2022 7 RANJIB GHATAK 3.91 3.91 100 0
8 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Urgent repairing of 250 mm dia pipe line and UPVC pipe line with necessary allied works at Silampur ,Gungbill an Aymma Biswanathpur distribution area under Kanksa (Zone-I) Pipe W/s Scheme under DWSD, PHE Dte. ORD/000447/2021-2022 426/DWSD 30/03/2022 10 MD AAMIR KHAN 4.82 4.76 98.76 0
9 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Quatation for Kanksa Zone -I Pump house no -03 VCH/000232/2022-2023 BP-2022-23-103 02/07/2022 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED 9.97 0.00 0 0
10 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Preparation and Submission of DPR for Augmentation of KRISHNAPUR PWSS under KANKSA Development Block under Durgapur Water Supply Division, P.H.E Dte. (Sl No - 05) ORD/000180/2023-2024 918/DWSD 22/06/2023 7 CARTO 0.78 0.00 0 0
11 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Preparation and Submission of DPR for Augmentation of KANCHANPUR (PART - B) under DURGAPUR-FARIDPUR Block under Durgapur Water Supply Division, P.H.E Dte. (Sl No -08) ORD/000189/2023-2024 1236/DWSD 31/07/2023 7 MEASURE LAND 0.78 0.00 0 0
12 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Preparation and Submission of DPR for Augmentation of KRISHNAPUR (PART - B) under DURGAPUR-FARIDPUR Block under Durgapur Water Supply Division, P.H.E Dte. (Sl No -07) ORD/000188/2023-2024 1237/DWSD 31/07/2023 7 MEASURE LAND 0.78 0.00 0 0
13 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Preparation and Submission of DPR for Augmentation of KANCHANPUR PWSS under KANKSA Development Block under Durgapur Water Supply Division, P.H.E Dte. (Sl No - 03) ORD/000178/2023-2024 916/DWSD 22/06/2023 7 CARTO 0.78 0.00 0 0
14 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Preparation and Submission of DPR for Augmentation of TILAKCHANDRAPUR PWSS under KANKSA Development Block under Durgapur Water Supply Division, P.H.E Dte. (Sl No-04) ORD/000179/2023-2024 917/DWSD 22/06/2023 7 MEASURE LAND 0.78 0.00 0 0
15 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Formal order for the work Supplying ,laying and aligning of HDPE distribution pipe line and allied works at Railpar Saradapally Mouza under command area of Augmentation of Kanksa (Zone-II/D) under DWSD ,PHE Dte (Part-A) ORD/000394/2021-2022 184/DWSD 11/02/2022 30 M/S S. CHOUDHURY 96.45 37.88 39.27 100
16 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Formal order for the work of Supplying & laying of different dia HDPE pipe line with necessary allied works at Silampur mouza(JL-90) block -Kanksa under Augmentation of Kanksa (Zone-I) piped W/s Scheme under DWSD, PHE Dte (SL-01) JUNIOR ENGINEER-2 ORD/000006/2022-2023 651/DWSD 22/04/2022 25 MD AAMIR KHAN 91.75 82.05 89.43 60
17 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Sanitary arrangement and plumbing works at Molandighi H/W site Pump house No-1 Tube well No-01 for Bistupur pipe W/S Scheme under DWSD,PHE Dte (SL-10) ORD/000204/2022-2023 1076/DWSD 12/07/2022 25 CHATTERJEE CONSTRUCTION 4.82 1.16 24.07 100
18 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Sanitary arrangement and plumbing works and other allied works at Sarada Pally H/W Site Pump house No-2 &T.W-02 for Augmentation of Kanksa (Zone-II/D) pipe W/S Scheme under DWSD,PHE Dte (SL-09) ORD/000203/2022-2023 1075/DWSD 12/07/2022 25 MUKHERJEE ENTERPRISE 4.82 1.37 28.42 100
19 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Additional work at RCC O HR site at Silampur under Augmentation of Kanksa (Zone-I) Piped W/s Scheme under DWSD,PHE Dte ORD/000038/2023-2024 763/DWSD. 22/05/2023 20 MD AAMIR KHAN 6.88 2.84 41.28 80
20 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Additional work of supplying and laying of different dia HDPE pipe line with necessary allied works at Aymabiswanath ,Gangbill mouza(JL-82,83) block-Kanksa under Augmentation of Kanksa Zone-I piped W/S scheme under DWSD,PHE Dte (SM/10208) ORD/000070/2023-2024 1067/DWSD 12/07/2023 30 TARA PRASAD SARKAR 96.72 74.03 76.54 100
21 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Supplying , fitting , fixing and fabrication of sign board With Necessary allied Work at different Placeses of ongoing New PWSS &Augamentation Scheme (As per Departmental Approved drawing & Direction) in connection with Augmentation of Kanksa Zone - I Pipe W/S Scheme ( JJM) Work under Durgapur Water Supply Division ,PHE Dte. (Sl - 06) ORD/000131/2023-2024 15/SPOT/DWSD 16/06/2023 7 AMARANJALI CONSTRUCTION 0.96 0.00 0 0
22 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance order for the work of Details route survey ,drawing design of distribution network & preparation of estimates and DPR in connection with the JJM (FHTC) of Augmentation of Kanksa (Zone-I) piped W/S Scheme DWSD,PHE Dte (Sl-04) ORD/000180/2021-2022 1420/DWSD 27/09/2021 30 SRIJAN ECOLOGICAL UPLIFTMENT PVT. LTD. 5.52 5.52 100 0
23 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Formal order for the work of Replaying of 160 mm /110 mm dia HDPE main pipe line at Panagarh to Shilampur road of Kanksa (Zone-I) W/s Scheme under DWSD, PHE Dte ORD/000261/2021-2022 1708/DWSD 08/12/2021 30 MAK CONSTRUCTION CO. 9.64 9.83 101.97 0
24 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Laying of 90 mm dia HDPE pipe line and withdrawing of 90 mm dia UPVC and laying the same in opposite flank of road with necessary allied works at Anandapur mouza,ICDS to Dompara under Kanksa (Z-I) W/s Scheme ,Block -Kanksa for cambat of upcoming drought unde DWSD , PHE Dte . (SL-01) ORD/000356/2021-2022 73/DWSD 21/01/2022 10 RANJIB GHATAK 1.78 1.79 100.56 0
25 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Formal order for the work of Supplying & laying of different dia HDPE pipe line with necessary allied works at Ayma Biswanathpur and Gangbil Mouza (JL-82/83) block -Kanksa under Augmentation of Kanksa (Zone-I) piped W/s Scheme under DWSD, PHE Dte (SL-02) ORD/000007/2022-2023 658/DWSD 22/04/2022 25 TARA PRASAD SARKAR 77.97 77.17 98.97 100
26 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Formal order for the work of Construction of 350 M3 capacity , 20 mtr staging height RCC Over head Reservoir (OHR) at Silampur Pump House No-1 of Augmentation of Kaksa piped W/s Scheme under Durgapur W/S Division, PHE Dte ORD/000013/2022-2023 652/DWSD 22/04/2022 184 MD AAMIR KHAN 83.27 74.24 89.16 85
27 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Construction boundary wall at Shilampur pump house No-1 under Augmentation of ground water base Kanksa (Zone-I) piped W/s Scheme under DWSD ,PHE Dte (SL-16) ORD/000131/2022-2023 818/DWSD 23/05/2022 20 BASANTI TRADERS 10.89 9.18 84.3 100
28 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum Formal work-Order for the work of ---Sanitary arrangement and plumbing works at Sarada Pally H/W Site Pump house No-3 for Augmentation of Kanksa (Zone-II/D) pipe W/S Scheme under DWSD,PHE Dte (SL-04) ORD/000197/2022-2023 1054/DWSD 07/07/2022 25 CHATTERJEE CONSTRUCTION 4.82 1.36 28.22 100
29 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Additional FHTC and necessary allied works at Silampur(JL-90) mouza of Augmentation of Kanksa (Zone-I) piped W/s Scheme under DWSD,PHE Dte (SL-01) ORD/000257/2022-2023 1574/DWSD 02/11/2022 15 MD AAMIR KHAN 7.26 7.12 98.07 100
30 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Additional FHTC and necessary allied works at Ayma Biswanathpur(JL-82),Ganbil(JL-83) mouza of Augmentation of Kanksa (Zone-I) piped W/s Scheme under DWSD,PHE Dte (SL-02) ORD/000258/2022-2023 1575/DWSD 02/11/2022 15 TARA PRASAD SARKAR 23.21 23.20 99.96 100
31 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance order for the work of Supplying and laying of 150 mm dia DIC (K9) & 150 mm dia HDPE pipe line with necessary allied works at Kanksa block of Anandpur to Silampur under Augmentation of Kanksa (Zone-I) piped W/s Scheme (JJM) under DWSD ,PHE Dte ORD/000445/2022-2023 108/DWSD 24/01/2023 20 A.K.D. ENTERPRISE 4.96 4.78 96.37 100
32 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Construction of boundary wall at railpar Saroda Pally head works site pump house No-III WT_3 for Augmentation of Kanksa (Zone-I) piped W/s Scheme under DWSD ,PHE Dte ORD/000088/2023-2024 721/DWSD 11/05/2023 25 CHATTERJEE CONSTRUCTION 14.80 9.48 64.05 100
33 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Construction of boundary wall at Railpar Saroda Pally H/W site pump house no-2/TW-II for Augmentation of Kanksa Zone-I) piped W/s Scheme under DWSD ,PHE Dte . ORD/000101/2023-2024 1106/DWSD 14/07/2023 40 MUKHERJEE ENTERPRISE 14.79 9.46 63.96 100
34 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Supply, delivery & installation of Poly vinayle laminated board including framework for different Head Work site of New PWSs (JJM) under Kanksa Zone- I W/S Scheme under EE/DWSD/ PHE Dte. (Sl- 04) ORD/000136/2023-2024 1189/DWSD 25/07/2023 15 JOY GURU ENTERPRISE 0.82 0.82 100 100
35 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Additional trail bore by direct Rotary method drilling using Rig machin at Kanchanpur/Basdebpur H/W Site for newly sinking of Well No-I and II under Augmentation of Kanksa (Zone-I) piped W/s scheme under DWSD, PHE Dte ORD/000149/2023-2024 1280/DWSD 07/08/2023 10 JOY GURU ENTERPRISE 2.27 2.27 100 100
36 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of repairing of office room and necessary allied works under Augmentation of Kanksa Zone-I piped W/s Scheme under DWSD, PHE Dte ORD/000141/2023-2024 1271/DWSD 07/08/2023 15 A.K.D. ENTERPRISE 4.90 1.74 35.51 100
37 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Dismantling of concrete road and bituminous road of Augmentation of Kanksa zone I/B piped W/s Scheme with construction of boundary wall renovation of all existing structure repairing of all retaining structure left out LDS FHTC Reconnection of FHTC at Kanksa (Part),Debipur(Part),Panagarh(Part) ,Prayagpur(Part) mouza of JL-86,87,88 of Kanksa Block under DWSD ,PHE Dte JUNIOR ENGINEER-2 ORD/000200/2023-2024 1090/DWSD 13/07/2023 30 MAK CONSTRUCTION CO. 23.98 23.91 99.71 100
38 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Preparation and Submission of DPR for Augmentation of Kanksa Zone - I (PART - B) under Kanksa Block under Durgapur Water Supply Division, P.H.E Dte. (Sl No - 05) ORD/000186/2023-2024 1239/DWSD 31/07/2023 7 CARTO 0.78 0.78 100 100
39 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Replacement of existing pipeline for Physical certificate of HarGhar Jal IN connection of JJM of Augmentation of Kanksa (Zone-I ) piped W/s Scheme under DWSD ,PHE Dte JUNIOR ENGINEER-2 ORD/000201/2023-2024 1092/DWSD 13/07/2023 30 MD AAMIR KHAN 36.07 34.74 96.31 100
40 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Material Requisition To Resource Division RTOR000013/2022-2023 399/DWSD 03/03/2023 0 Resource Division 7.39 0.00 0 0
41 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Road restoration at Panagarh Silampur Road (ch 2.5 KM to 3.5 KM) to be executed by Executive Engineer, Asansol Highway Division, PWD Roads directorate for the work of repairing of damaged at Panagarh Silampur BILL/00176/2022-2023 BP-2022-23-333 15/03/2023 0 EXECUTIVE ENGINEER , ASANSOL HIGHWAY DIVISION, PWD ROADS 18.00 0.00 0 0
42 PASCHIM BARDHAMAN Central Mechanical Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Supply & Installation of Submersible Pumping Machinery , Voltage Stabilizer, Chlorination system and internal House wiring for Tube well no.- 1 & 2 at Augmentation of Kanksa Zone - I Water Scheme under CMD, PHE Dte., Dist.- Paschim-Bardhaman. Driller In-Charge Junior Engineer ORD/000070/2023-2024 2570/CMD 06/06/2023 30 MS DAS ELECTRIC CO 19.35 9.41 48.63 46
43 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of construction of pump house cum chlorine room at Silampur pump house No-I H/W site for Augmentation of Kanksa (Zone-I) piped W/s Scheme under DWSD,PHE Dte ORD/000148/2023-2024 1279/DWSD 07/08/2023 45 MUKHERJEE ENTERPRISE 6.41 0.00 0 100
44 PASCHIM BARDHAMAN Asansol Mechanical Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Providing & fitting, fixing of lighting luminaries of pump house with yard lighting arrangement and other allied works at Pump House No-01 under Augmentation of Kanksa Zone-I Water Supply Scheme, Block- Kanksa, Dist.- Paschim Bardhaman under Asansol Mechanical Division, P.H.E. Dte. Assistant Engineer-II Junior Engineer-1,Junior Engineer-3 ORD/000315/2024-2025 1809/AMD 29/10/2024 30 M/S A.D.ENTERPRISE 2.97 0.00 0 0
45 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Construction of latrine and boundary wall of pump house cum chlorine room and necessary allied works at Anandpur H/W site for Augmentation of Kanksa (Zone-I) piped W/s Scheme under DWSD, PHE Dte ORD/000043/2023-2024 767/DWSD 22/05/2023 15 CHANDAN HAZRA 6.76 6.56 97.04 100
46 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Continuation for the work of Providing functional house hold tap connection (FHTC) in connection with JJM for Domra mouza-68 under command area of Trilakchandrapur piped W/s Scheme at Kanksa Block under DWSD, PHE Dte ORD/000426/2021-2022 347/DWSD 17/03/2022 1110 AMARANJALI CONSTRUCTION 3.03 0.00 0 100
47 PASCHIM BARDHAMAN Durgapur W/S Division Augmentation of ground water based piped W/s scheme for Kanksa (Zone-I) to accommodate FHTC ,Block-Kanksa,Dist-Paschim Bardhaman(WB) , SM/10208 Augmentation Acceptance cum formal order for the work of Additional work for supplying and laying of different dia HDPE pipe line with FHTC and necessary allied Works at Anandapur (JL-89) mouza of Augmentation of Kanksa (Zone-I) piped W/s Scheme under DWSD,PHE Dte. (SL-03) ORD/000259/2022-2023 1576/DWSD 02/11/2022 847 RANJIB GHATAK 12.79 0.00 0 100
Total 806.00 582.20 72.23