Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
1 7.24 3.5 48.34  
1 PASCHIM BARDHAMAN RCFA Division -I Operational Charges of PHED Managed Laboratories Related to Water Quality Monitoring & Surveillance under Jal Jeevan Mission under RCFA Division-I PHE Dte. , SM/19257 Support-WQMSP Acceptance cum work order for Work Engaging expert 1(one) no Chemist,1(One) no Bacteriologist and 1(One)no Lab Assistant for the testing of water from different PWSS making different types of Testing Report,Communicated with the facilitator of different Gram Panchayat under Kanksa Block of Sub District NABL laboratory under RCFA Div-I PHE Dte.(365 days) (01.11.2024 to 31.10.2025) Assistant Engineer 3,Assistant Engineer 5 Assistant Engineer 5,Junior Engineer 6 ORD/000367/2024-2025 2562/RCD-I 30/10/2024 365 BABA LOKNATH ENTERPRISE 7.24 3.50 48.34 100
Total 7.24 3.50 48.39