Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
10 427.76 227.4 53.16  
1 PASCHIM BARDHAMAN RCFA Division -I Augmentation PWSS of RCFA Part-II (Zone-2A) Block - Andal, Dist - Paschim Bardhaman , SM/12226 Augmentation Acceptance cum work order for Laying & Pushing by adopting trench less technology (e.g. Jack Pushing Method etc0 at Bagdiha to Sidhapur Road and Bagdiha OHR to Bahadurpur under Jamuria Block under Augmentation of Bagdiha PWSS under RCFA Division-I PHE Dte. Assistant Engineer 2 Junior Engineer ORD/000600/2023-2024 3282/RCD-I 08/11/2023 15 SIMA ENTERPRISE 6.34 6.02 94.95 100
2 PASCHIM BARDHAMAN RCFA Division -I Augmentation PWSS of RCFA Part-II (Zone-2A) Block - Andal, Dist - Paschim Bardhaman , SM/12226 Augmentation Material Requisition To Resource Division RTOR000018/2023-2024 2956/RCD-I 11/10/2023 0 Resource Division 6.78 0.00 0 0
3 PASCHIM BARDHAMAN RCFA Division -I Augmentation PWSS of RCFA Part-II (Zone-2A) Block - Andal, Dist - Paschim Bardhaman , SM/12226 Augmentation Acceptance cum work order Distribution Network and allied work for Ukhra area of RCFA Part-II Piped Water Supply Scheme allied work under RCFA Division-I PHE Dte. (Zone-2A)(Sl. No. 13) Assistant Engineer 2 Junior Engineer ORD/000845/2022-2023 1080/RCD-I 23/03/2023 90 GITASREE FABRICATION 97.20 0.00 0 80
4 PASCHIM BARDHAMAN RCFA Division -I Augmentation PWSS of RCFA Part-II (Zone-2A) Block - Andal, Dist - Paschim Bardhaman , SM/12226 Augmentation Acceptance cum work order for construction of chlorine room of size (4.50 X 3.50 m) at (Zone-XIII) of Baraboni block for Improvement of RCFA Pt-I piped Water Supply under RCFA Div-I, PHE Dte. in the district of Paschim Bardhaman. Assistant Engineer 2 Junior Engineer ORD/000738/2022-2023 677/RCDI 24/02/2023 15 ZEROTH CONTROL SYSTEM 4.61 3.89 84.38 100
5 PASCHIM BARDHAMAN RCFA Division -I Augmentation PWSS of RCFA Part-II (Zone-2A) Block - Andal, Dist - Paschim Bardhaman , SM/12226 Augmentation Acceptance cum work order for Laying & pushing of 600 mm dia RCC (NP3) Hume pipe by adopting trench less technology (e.g. Jack Pushing Method etc) at Srirampur Workshop road near Railway Workshop under Ondal Block under RCFA Division-I PHE Dte. Assistant Engineer 2 Junior Engineer ORD/000670/2023-2024 3437/RCD-1 24/11/2023 15 M/S UNIT CONSTRUCTION 9.31 9.31 100 100
6 PASCHIM BARDHAMAN RCFA Division -I Augmentation PWSS of RCFA Part-II (Zone-2A) Block - Andal, Dist - Paschim Bardhaman , SM/12226 Augmentation Acceptance cum work order Concrete road cutting and mending work for laying distribution pipe line at Das Para (Sansad-XIX) at Ukhra area Block ¿ Andal and Pandabeswar under Augmentation of RCFA Part-II (Zone-2A) PWSS under RCFA Division-I PHE Dte. (Sl No. 17) Assistant Engineer 2 Junior Engineer ORD/000903/2022-2023 1161/RCD-I 24/03/2023 15 JYOGOMAYA ENTERPRISE 2.01 1.94 96.52 100
7 PASCHIM BARDHAMAN RCFA Division -I Augmentation PWSS of RCFA Part-II (Zone-2A) Block - Andal, Dist - Paschim Bardhaman , SM/12226 Augmentation Formal work order for Additional work for allied work in connection with in connection supply, laying fitting, fixing of 15 mm NB PVC (Schedule 80) / 2020 mm OD HDPE (PE 80, PN 6) pipe with all necessary specials piece etc. all complete for Augmentation of Sub-Station Water Based Piped Water Supply Scheme for Amritnagar Zone-II under RCFA Division-I PHE Dte. Assistant Engineer 2,Assistant Engineer 3 Junior Engineer ORD/000904/2023-2024 158/RCD-I 22/01/2024 435 MRITYUNJOY MUKHERJEE & CO. 213.03 182.47 85.65 85
8 PASCHIM BARDHAMAN RCFA Division -I Augmentation PWSS of RCFA Part-II (Zone-2A) Block - Andal, Dist - Paschim Bardhaman , SM/12226 Augmentation Acceptance cum Work Order for Additional works of Concrete dismantling, Concrete restoration, Bolder cutting and other allied works at distribution network of Augmentation PWSS of RCFA Part-II (Zone-2A) under RCFA Div-I,PHE Dte. Assistant Engineer 2 Junior Engineer ORD/000053/2024-2025 1743/RCD-I 18/07/2024 255 SWATI CORPORATION 67.64 21.06 31.14 30
9 PASCHIM BARDHAMAN RCFA Division -I Augmentation PWSS of RCFA Part-II (Zone-2A) Block - Andal, Dist - Paschim Bardhaman , SM/12226 Augmentation Acceptance cum work order for Left out part at Banbahal village distribution pipe line Zone-4A under Pandabeswar Block for smooth running of water supply near Shankarpur area of Augmentation PWSS of RCFA Part-II (Zone-2A) under RCFA Division-I PHE Dte. Assistant Engineer 2,Assistant Engineer 4 Junior Engineer ORD/000238/2025-2026 1460/RCD-I 15/05/2025 30 BABA LOKNATH ENTERPRISE 18.07 0.00 0 80
10 PASCHIM BARDHAMAN RCFA Division -I Augmentation PWSS of RCFA Part-II (Zone-2A) Block - Andal, Dist - Paschim Bardhaman , SM/12226 Augmentation Acceptance cum work order Concrete road cutting mending works for laying of distribution pipe line at Kankardanga Part (Sansad-VIII) at Ukhra area Block-Andal and Pandabeswar under Augmentation of RCFA Part-II (Zone-2A) PWSS under RCFA Division-I PHE Dte. (Sl No. 19) Assistant Engineer 2 Junior Engineer ORD/000909/2022-2023 1163/RCD-I 24/03/2023 15 MS KALYAN ENTERPRISE 2.77 2.71 97.83 100
Total 427.76 227.40 53.16