Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 287.55 145.72 50.68  
1 PASCHIM BARDHAMAN RCFA Division -I AUGMENTATION PWSS OF RCFA PART-II (ZONE-12B) UNDER RCFA DIVISION-I PHE DTE. , SM/12031 Augmentation Material Requisition To Resource Division RTOR000029/2023-2024 2945/RCD-I 11/10/2023 0 Resource Division 6.78 0.00 0 0
2 PASCHIM BARDHAMAN RCFA Division -I AUGMENTATION PWSS OF RCFA PART-II (ZONE-12B) UNDER RCFA DIVISION-I PHE DTE. , SM/12031 Augmentation Acceptance cum work order for Allied work of Distribution Network including FHTC & allied work at Ondal Block of RCFA Part-II (Zone-12 A) Piped Water Scheme under RCFA Division-I PHE Dte. Assistant Engineer 2 Junior Engineer ORD/000669/2023-2024 3436/RCD-1 24/11/2023 60 MRITYUNJOY MUKHERJEE & CO. 81.28 48.77 60 65
3 PASCHIM BARDHAMAN RCFA Division -I AUGMENTATION PWSS OF RCFA PART-II (ZONE-12B) UNDER RCFA DIVISION-I PHE DTE. , SM/12031 Augmentation Acceptance cum work order for Health assessment of existing OHR of Barabani (910 Cum) and ancillary structures conducting Non-Destructive Test and thorough visual observation under RCFA Division-I PHE Dte. Assistant Engineer 2 Junior Engineer ORD/000539/2023-2024 3018/RCD-I 16/10/2023 15 SIRCON ENGINEERING SERVICES 4.95 4.95 100 100
4 PASCHIM BARDHAMAN RCFA Division -I AUGMENTATION PWSS OF RCFA PART-II (ZONE-12B) UNDER RCFA DIVISION-I PHE DTE. , SM/12031 Augmentation 100 mm dia water pipe line with 600 mm dia MS Casing pipe line (Jal Jeevan Mission) by R.C.F.A Division-1, PHE DTE, Asansol in between Parasia Siding ¿ New Jambad Siding at Km. CB-2/15-16 in Asansol Division of Eastern Railway under AUGMENTATION PWSS OF RCFA PART-II (ZONE-12B) UNDER RCFA DIVISION-I PHE DTE. BILL/00863/2024-2025 396/24-25 28/10/2024 0 EASTERN RAILWAY 4.58 0.00 0 0
5 PASCHIM BARDHAMAN RCFA Division -I AUGMENTATION PWSS OF RCFA PART-II (ZONE-12B) UNDER RCFA DIVISION-I PHE DTE. , SM/12031 Augmentation Formal Work Order for Distribution network for RCFA Part-II piped Water Supply Scheme including FHTC & allied work under RCFA Div-I, PHE Dte.(Zone-12B)(Segment-2). Assistant Engineer 2 Junior Engineer ORD/000631/2022-2023 485/RCDI 03/02/2023 60 M/S SINGH & KONAR CONSTRUCTION 155.21 92.00 59.27 80
6 PASCHIM BARDHAMAN RCFA Division -I AUGMENTATION PWSS OF RCFA PART-II (ZONE-12B) UNDER RCFA DIVISION-I PHE DTE. , SM/12031 Augmentation Acceptance cum work order for Construction of CWR (Clear Water Reservoir) of capacity 200 cum & allied work at Shankarpur under Pandabeswar H/W Site within Pandabeswar Block for Augmentation of PWSS of RCFA Part-II (Zone-12B) under RCFA Division-I PHE Dte. Assistant Engineer 2 ORD/000558/2024-2025 162/RCD-I 08/01/2025 90 DIP CONSTRUCTION 34.75 0.00 0 0
Total 287.55 145.72 50.68