| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 11 | 515.55 | 129.2 | 25.06 | ||||||||||||||
| 1 | PASCHIM BARDHAMAN | RCFA Division -I | Augmentation of Jamuria (Rural) (Zone-II) PWSS. , SM/10640 | Augmentation | Formal work order for augmentation of Jamuria (Rural)(zone-I) piped water supply scheme including FHTC & allied work within Jamuria Block under RCFA Div-I, PHE Dte.(Part-B) | ORD/000599/2022-2023 | 16/RCD I | 05/01/2023 | 30 | DIP CONSTRUCTION | 0.00 | 0.00 | NAN | 0 | |||
| 2 | PASCHIM BARDHAMAN | RCFA Division -I | Augmentation of Jamuria (Rural) (Zone-II) PWSS. , SM/10640 | Augmentation | Sub Soil Investigation for 200 cum capacity RCC Over Head Reservoir of Jamuria Block for Augmentation of Jamuria Rural-II Piped Water Supply Scheme under RCFA Division-I PHE Dte. in the District of Paschim Bardhaman | Assistant Engineer 2 | Junior Engineer | ORD/000524/2022-2023 | 3137/RCDI | 12/12/2022 | 7 | P.K TEWARY DRILLING CO. | 0.55 | 0.00 | 0 | 0 | |
| 3 | PASCHIM BARDHAMAN | RCFA Division -I | Augmentation of Jamuria (Rural) (Zone-II) PWSS. , SM/10640 | Augmentation | Preparation of DPR & Route Survey for Augmentation of Jamuria (Rural) (Zone-II) Piped Water Supply Scheme Block-Jamuria, Dist-Paschim Bardhaman under RCFA Division-I PHE Dte. (Sl No. 13) | Assistant Engineer 2 | Junior Engineer | ORD/000250/2022-2023 | 2230/RCD I | 15/09/2022 | 15 | APEX ENGINEERING | 3.58 | 3.58 | 100 | 0 | |
| 4 | PASCHIM BARDHAMAN | RCFA Division -I | Augmentation of Jamuria (Rural) (Zone-II) PWSS. , SM/10640 | Augmentation | Material Requisition To Resource Division | RTOR000005/2022-2023 | 2345/RCD-I | 28/09/2022 | 0 | Resource Division | 9.24 | 0.00 | 0 | 0 | |||
| 5 | PASCHIM BARDHAMAN | RCFA Division -I | Augmentation of Jamuria (Rural) (Zone-II) PWSS. , SM/10640 | Augmentation | Acceptance cum work order for Construction of High Lift Pump House at Riverside H/W site under Augmentation of Jamuria Rural (Zone I & II) Water Supply Scheme under RCFA Division-I PHE Dte. | Assistant Engineer 2 | Junior Engineer | ORD/000573/2022-2023 | 3282/RCDI | 20/12/2022 | 90 | GLOBAL CONSTRUCTION | 31.24 | 27.01 | 86.46 | 90 | |
| 6 | PASCHIM BARDHAMAN | RCFA Division -I | Augmentation of Jamuria (Rural) (Zone-II) PWSS. , SM/10640 | Augmentation | Acceptance cum work order for Distribution network for Augmentation of Jamuria Rural- II Piped Water Supply Scheme including FHTC work (Segment- I) under Jamuria Block in the district of Paschim Bardhaman Under RCFA Division - I PHE Dte. | Assistant Engineer 2 | Junior Engineer | ORD/000100/2024-2025 | 2120/RCD-I | 27/08/2024 | 60 | SIMA ENTERPRISE | 46.06 | 0.00 | 0 | 40 | |
| 7 | PASCHIM BARDHAMAN | RCFA Division -I | Augmentation of Jamuria (Rural) (Zone-II) PWSS. , SM/10640 | Augmentation | Distribution network for Augmentation of Jamuria Rural-II Piped Water Scheme including FHTC work Block Jamuria, Dist Paschim Bardhaman under RCFA Div-I PHE Dte. | Assistant Engineer 2 | Junior Engineer | ORD/000292/2022-2023 | 2449/RCD-I | 13/10/2022 | 180 | JOY HIND TUBEWELLS | 236.71 | 59.28 | 25.04 | 100 | |
| 8 | PASCHIM BARDHAMAN | RCFA Division -I | Augmentation of Jamuria (Rural) (Zone-II) PWSS. , SM/10640 | Augmentation | Acceptance cum Work Order for Rising Main of Augmentation of Jamuria Rural (Zone-I & II) under RCFA Division-I PHE Dte (sl.no-14) | Assistant Engineer 2 | Junior Engineer | ORD/000773/2022-2023 | 805/RCD-I | 06/03/2023 | 60 | M/S MONDAL ENTERPRISE | 22.77 | 8.18 | 35.92 | 40 | |
| 9 | PASCHIM BARDHAMAN | RCFA Division -I | Augmentation of Jamuria (Rural) (Zone-II) PWSS. , SM/10640 | Augmentation | Acceptance cum work order for Additional work of Distribution Network for Augmentation of Jamuria (Rural) (Zone-II) Piped Water Supply Scheme including FHTC & allied work within Jamuria Block under RCFA Division-I PHE Dte. (Part- A) | Assistant Engineer 2 | Junior Engineer | ORD/000111/2024-2025 | 2133/RCD-I | 27/08/2024 | 146 | M/S B.K. CONSTRUCTION | 20.94 | 10.82 | 51.67 | 65 | |
| 10 | PASCHIM BARDHAMAN | RCFA Division -I | Augmentation of Jamuria (Rural) (Zone-II) PWSS. , SM/10640 | Augmentation | Acceptance cum work order for Distribution network for Augmentation of Jamuria Rural-II Piped Water Supply Scheme including FHTC work (Segment-III) under Jamuria Block in the the District of Paschim Bardhaman under RCFA Division-I PHE Dte. | Assistant Engineer 2 | Junior Engineer | ORD/000112/2024-2025 | 2134/RCD-I | 27/08/2024 | 374 | DAWN CONSTRUCTION | 95.92 | 20.33 | 21.19 | 40 | |
| 11 | PASCHIM BARDHAMAN | RCFA Division -I | Augmentation of Jamuria (Rural) (Zone-II) PWSS. , SM/10640 | Augmentation | Acceptance cum work order for Distribution network for Augmentation of Jamuria Rural- II Piped Water Supply Scheme including FHTC work (Segment- II) under Jamuria Block in the district of Paschim Bardhaman under RCFA Division - I PHE Dte. | Assistant Engineer 2 | Junior Engineer | ORD/000118/2024-2025 | 2117/RCD-I | 27/08/2024 | 804 | MS SAMANTA CONSTRUCTION | 48.54 | 0.00 | 0 | 100 | |
| Total | 515.54 | 129.20 | 25.06 | ||||||||||||||