Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
6 | 186.25 | 0 | 0 | ||||||||||||||
1 | KALIMPONG | Kalimpong -I | Neorakhola W/S & Mtc.Div. | GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR YOKPRINTAM KHASMAHAL (PART) UNDER SAMTHAR G.P, BLOCK : KALIMPONG - I, DISTRICT:KALIMPONG , SM/16512 | New | Material Requisition To Resource Division | RTOR000034/2023-2024 | 279/NKWSMD | 17/05/2023 | Resource Division | 0.84 | 0.00 | 0 | 0 | |||
2 | KALIMPONG | Kalimpong -I | Neorakhola W/S & Mtc.Div. | GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR YOKPRINTAM KHASMAHAL (PART) UNDER SAMTHAR G.P, BLOCK : KALIMPONG - I, DISTRICT:KALIMPONG , SM/16512 | New | Demand raised for forest clearance of JJM scheme under Kalimpong Division PHED | BILL/00456/2023-2024 | BP-2023-24-289 | 01/11/2023 | WEST BENGAL PARIVESH CAMPA | 16.72 | 0.00 | 0 | 0 | |||
3 | KALIMPONG | Kalimpong -I | Neorakhola W/S & Mtc.Div. | GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR YOKPRINTAM KHASMAHAL (PART) UNDER SAMTHAR G.P, BLOCK : KALIMPONG - I, DISTRICT:KALIMPONG , SM/16512 | New | Continuation Engagement of 02 (Two) numbers Computer Operator (Graduate with Certificate in Computer Application) for the works related to Jal Jeevan Mission / Jal Swapno at the Office of the Executive Engineer, Neorakhola Water Supply and Maintenance Division, Public Health Engineering Directorate from 01/12/2023 to 31/01/2024. | Assistant Engineer II | Junior Engineer I | ORD/000253/2023-2024 | 1468/NKWSMD | 01/12/2023 | 60 | THE ELECTRIC SPHERE | 0.81 | 0.00 | 0 | 0 |
4 | KALIMPONG | Kalimpong -I | Neorakhola W/S & Mtc.Div. | GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR YOKPRINTAM KHASMAHAL (PART) UNDER SAMTHAR G.P, BLOCK : KALIMPONG - I, DISTRICT:KALIMPONG , SM/16512 | New | FOREST PAYMENT | BILL/00962/2023-2024 | BP-2023-24-650 | 28/03/2024 | WEST BENGAL PARIVESH CAMPA | 5.55 | 0.00 | 0 | 0 | |||
5 | KALIMPONG | Kalimpong -I | Neorakhola W/S & Mtc.Div. | GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR YOKPRINTAM KHASMAHAL (PART) UNDER SAMTHAR G.P, BLOCK : KALIMPONG - I, DISTRICT:KALIMPONG , SM/16512 | New | FOREST PAYMENT | BILL/00962/2023-2024 | BP-2023-24-650 | 28/03/2024 | WEST BENGAL PARIVESH CAMPA | 5.55 | 0.00 | 0 | 0 | |||
6 | KALIMPONG | Kalimpong -I | Neorakhola W/S & Mtc.Div. | GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR YOKPRINTAM KHASMAHAL (PART) UNDER SAMTHAR G.P, BLOCK : KALIMPONG - I, DISTRICT:KALIMPONG , SM/16512 | New | PROPOSED GRAVITY BASED PIPED WATER SUPPLY SCHEME FOR YOKPRINTAM KHASMAHAL (PART) UNDER SAMTHAR G.P, BLOCK : KALIMPONG-I, DISTRICT : KALIMPONG. | ORD/000007/2023-2024 | 96/NKWSMD | 28/04/2023 | 120 | PASANG LAMA | 156.78 | 0.00 | 0 | 60 | ||
Total | 186.26 | 0.00 | 0 |