Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
4 86.85 29.75 34.25  
1 ALIPURDUAR Alipurduar Division AUGMENTATION OF SALSALABARI WATER SUPPLY SCHEME. , SM/10670 Augmentation New Laying of UPVC/DI Pipe line, dismantling concrete road and recasting same and other allied works at Salsalabari PWSS under Alipurduar Division, PHE Dte. Alipurduar Sadar Sub Division RWS Alipurduar - II Block ORD/000284/2022-2023 1638/ALD 19/09/2022 60 NARENDRA BHADANI. 30.82 29.60 96.04 96
2 ALIPURDUAR Alipurduar Division AUGMENTATION OF SALSALABARI WATER SUPPLY SCHEME. , SM/10670 Augmentation Construction of pumphouse, boundary wall,laying of UPVC pipeline & rising main connection for Salsalabari PWSS proposed 4th TW site PWSS under Alipurduar Division, PHE Dte. Alipurduar Sadar Sub Division RWS Alipurduar - II Block ORD/000515/2022-2023 3400/ALD 16/03/2023 90 BRAJA GOPAL SAHA 39.58 0.00 0 0
3 ALIPURDUAR Alipurduar Division AUGMENTATION OF SALSALABARI WATER SUPPLY SCHEME. , SM/10670 Augmentation Laying of new UPVC / DI pipeline for filling of Gap in the distribution system and laying of delivery line connection, Land Development works, Construction of surface drain, supply of CIDF specials and other allied works in connection with the Salsalabari PWSS under Alipurduar Division, PHE Dte. Alipurduar Sadar Sub Division Alipurduar Sub Division ORD/000359/2023-2024 2745/ALD 14/12/2023 420 MATRI ENTERPRISE 16.16 0.00 0 100
4 ALIPURDUAR Alipurduar Division AUGMENTATION OF SALSALABARI WATER SUPPLY SCHEME. , SM/10670 Augmentation Providing FHTC in school in Salsalabari PWSS under Alipurduar Division P.H.E Dte. Alipurduar Sadar Sub Division Alipurduar Sub Division,RWS Alipurduar - II Block ORD/000497/2022-2023 3361/ALD 14/03/2023 30 HARIDAS GHOSH 0.29 0.15 51.72 100
Total 86.85 29.74 34.25