| Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 7 | 29.81 | 1.5 | 5.03 | ||||||||||||||
| 1 | ALIPURDUAR | Kalchini | Northern Mechanical Division II | Dima Tea Garden Piped Water Supply Scheme , SM/05189 | New | Supply, delivery of Electro Mechanical components at DIMA TEA GARDEN Water Supply Scheme IN THE Dist OF Alipurduar under NMD-II,PHE.Dte. | ORD/000576/2020-2021 | 1458/NMD-II | 02/02/2021 | 30 | TALUKDAR ENTERPRISE | 8.42 | 0.00 | 0 | 0 | ||
| 2 | ALIPURDUAR | Kalchini | Alipurduar Division | Dima Tea Garden Piped Water Supply Scheme , SM/05189 | New | Laying of DI Pipe line and others misc. works at Jateswar PWSS under Alipurduar Division , PHE Dte. | VCH/000741/2020-2021 | 395/20-21 | 11/02/2021 | 0 | SREE MAA CONSTRUCTION & CO. | 3.50 | 0.00 | 0 | 0 | ||
| 3 | ALIPURDUAR | Kalchini | Northern Mechanical Division II | Dima Tea Garden Piped Water Supply Scheme , SM/05189 | New | Operation and Guarding of Pumping machinery at Pump House No. I under DIMA TG W/S Scheme. In the dist. Of ALIPURDUAR | ORD/000507/2021-2022 | 761/NMD-II | 08/07/2021 | 365 | SUBODH KUMAR BANIK | 2.97 | 0.00 | 0 | 0 | ||
| 4 | ALIPURDUAR | Kalchini | Northern Mechanical Division II | Dima Tea Garden Piped Water Supply Scheme , SM/05189 | New | Operation and Guarding of Pumping machinery at Pump House No. II , Under DIMA TG W/S Scheme, in the dist. Of Alipurduar. | ORD/000325/2021-2022 | 692/NMD-II | 07/07/2021 | 365 | BONANZA ENTERPRISE | 2.97 | 0.00 | 0 | 0 | ||
| 5 | ALIPURDUAR | Kalchini | Northern Mechanical Division II | Dima Tea Garden Piped Water Supply Scheme , SM/05189 | New | "Supply and delivery of Calcium Hypochlorite [Ca(Ocl)₂] granules at different PWSS under Kalchini block in the dist. of Alipurduar under Northern Mechanical Division-II,PHE Dte. | ORD/000518/2021-2022 | 1071/NMD-II | 10/09/2021 | 20 | R.K ENTERPRISE | 1.85 | 0.00 | 0 | 0 | ||
| 6 | ALIPURDUAR | Kalchini | Alipurduar Division | Dima Tea Garden Piped Water Supply Scheme , SM/05189 | New | Construction of approach road & car parking area with paver block & chequered tiles at Jainty WSS under Alipurduar Division, PHE Dte. | Alipurduar RWS,Alipurduar Sadar Sub Division | Alipurduar Sub Division,RWS Alipurduar - I Block | ORD/000331/2021-2022 | 2107/ALD | 05/01/2022 | 30 | DAS ENTERPRISE | 5.02 | 1.50 | 29.88 | 77 |
| 7 | ALIPURDUAR | Kalchini | Alipurduar Division | Dima Tea Garden Piped Water Supply Scheme , SM/05189 | New | Repairing of UPVC pipeline, ferrule and other allied works for Dima TG under Alipurduar Division, PHE Dte. | HQ-A.E | RWS Kumargram Block | ORD/000168/2025-2026 | 1776/ALD | 18/08/2025 | 45 | TAPASH DAS | 5.08 | 0.00 | 0 | 0 |
| Total | 29.80 | 1.50 | 5.03 | ||||||||||||||