Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 1,047.13 129.29 12.35  
1 PURBA MEDINIPUR Tamluk Division Ground Water Based Piped Water Supply Scheme for Madhabpur Zone-I , SM/10725 Augmentation Material Requisition To Resource Division RTOR000283/2022-2023 2636/TD 02/02/2023 Resource Division 18.68 0.00 0 0
2 PURBA MEDINIPUR Midnapore Mechanical Ground Water Based Piped Water Supply Scheme for Madhabpur Zone-I , SM/10725 Augmentation Providing and Installation of Submersible pumping machineries and other electromechanical equipments for Ground Water Based Piped Water Supply Scheme for Madhabpur Zone-I, Block Egra II, District - Purba Medinipurunder JJM Program under MMD PHE Dte. Sri Srinath Ranjan Ghosh, AE/Haldia Electrical Sub-Divi Sri Sukanta Mondal, JE/Haldia Electrical Sub-Division. ORD/000077/2023-2024 1279/W/MMD 04/05/2023 180 MENAKA ENTERPRISE 25.14 0.00 0 0
3 PURBA MEDINIPUR Tamluk Division Ground Water Based Piped Water Supply Scheme for Madhabpur Zone-I , SM/10725 Augmentation Repaire of Pump House , Boundary Wall construction of boundary wall & Land development approch road under JJM with allied work for Madhabpur (Z-I) PWSS within Egra-II Block including supply of all labour & materials under Digha Sub-Division of Tamluk Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000379/2023-2024 1023/TD 07/06/2023 40 KAMAL KUMAR ROY 41.68 0.00 0 0
4 PURBA MEDINIPUR Tamluk Division Ground Water Based Piped Water Supply Scheme for Madhabpur Zone-I , SM/10725 Augmentation Laying of Distribution pipe line to accommodate FHTC with new construction of R.C.C. Elevated Reservoir of capacity 400cum and staging height 20.00 mtr. as per Departmental Drawing with allied works including supply of all labour & materials for Augmentation of Madhabpur Zone-I Water Supply Scheme within Egra-II. Block under Digha sub-division of Tamluk Division, P.H.E.Dte, Purba Medinipur. Assistant Engineer Junior Engineer ORD/000553/2022-2023 2183/TD 20/12/2022 180 GUPTA ENTERPRISE. 638.56 82.65 12.94 15
5 PURBA MEDINIPUR Tamluk Division Ground Water Based Piped Water Supply Scheme for Madhabpur Zone-I , SM/10725 Augmentation Material Requisition To Resource Division RTOR000111/2022-2023 1665/TD 03/11/2022 Resource Division 141.02 0.00 0 0
6 PURBA MEDINIPUR Tamluk Division Ground Water Based Piped Water Supply Scheme for Madhabpur Zone-I , SM/10725 Augmentation Name of Work: Sinking of 4 (Four) nos. Tube Well at different sites. Name of Sites: i) Sinking of 300mm. x 200mm. dia. x 220 mtr. Deep Tube well by direct rotary rig method for Head Work site Tube Well of Madhabpur Zone-I Water Supply Scheme within Egra-II Block under Digha Sub-Division, of Tamluk Division P.H.E. Dte. Purba Medinipur. ii) Sinking of 300mm. x 200mm. dia. x 220 mtr. Deep Tube well by direct rotary rig method for Head Work site Tube Well of Madhabpur Zone-II Water Supply Scheme within Egra-II Block under Digha Sub-Division, of Tamluk Division P.H.E. Dte. Purba Medinipur. iii) Sinking of 300mm. x 200mm. dia. x 220 mtr. Deep Tube well by direct rotary rig method for 2nd Tube Well site Tube Well of Madhabpur Zone-II Water Supply Scheme within Egra-II Block under Digha Sub-Division, of Tamluk Division P.H.E. Dte. Purba Medinipur. iv) Sinking of 300mm. x 200mm. dia. x 220 mtr. Deep Tube well by direct rotary rig method for 3rd Tube Well site Tube Well of Madhabpur Zone-II Water Supply Scheme within Egra-II Block under Digha Sub-Division, of Tamluk Division P.H.E. Dte. Purba Medinipur. Assistant Engineer Junior Engineer ORD/000487/2022-2023 1909/TD 25/11/2022 40 OSMAN SEKH 69.99 0.00 0 25
7 PURBA MEDINIPUR Tamluk Division Ground Water Based Piped Water Supply Scheme for Madhabpur Zone-I , SM/10725 Augmentation Laying of Balance portion for Distribution pipe line by UPVC pipes with allied works for Madhakhali Zone-I & its adjoining mouzas Water Supply Scheme within Bhagwanpur-II Block under Contai Sub-Division of Tamluk Division, PHE Dte. Purba Medinipur district. Assistant Engineer Junior Engineer ORD/000587/2023-2024 2189/TD 01/09/2023 45 SWARUPANANDA DAS 95.53 46.64 48.82 98
8 PURBA MEDINIPUR Tamluk Division Ground Water Based Piped Water Supply Scheme for Madhabpur Zone-I , SM/10725 Augmentation Requirement of additional pipeline to accommodate FHTC for Augmentation of Madhabpur Zone-I Water Supply Scheme within Egra-II Block under Digha Sub-Division of Tamluk Division, P.H.E. Dte. within Purba Medinipur District. Assistant Engineer Junior Engineer ORD/000604/2023-2024 2197/TD 01/09/2023 25 DEBABRATA DAS 16.53 0.00 0 0
Total 1,047.13 129.30 12.35