Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
26 1,253.57 1,017.92 81.2  
1 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Preparation of D.P.R. for different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Bainchberia Water Supply Scheme under Tamluk Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000159/2021-2022 1163/TD 01/12/2021 7 HORIZEN 9.35 9.23 98.72 100
2 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Supply of sluice valve & delivery at Chapbasan Store for Bahichberia PWSS within Nandakumar Dev. Block and under Tamluk Sub-Division of Tamluk Division PHE Dte.(PART-B) Assistant Engineer Junior Engineer ORD/000323/2022-2023 1232/TD 07/09/2022 15 J.S. CONSTRUCTION 3.61 3.61 100 100
3 PURBA MEDINIPUR Central Drilling Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation REPAIRING OF PTO AND OTHER FOR RIG MACHINE JOHN/DR/1500-III UNDER CMSD-I (D), CDD, PHE DTE. ORD/000251/2021-2022 214/CMSD-I(D) 09/11/2021 15 PADMA ENGINEERING & CO. 4.52 0.72 15.93 0
4 PURBA MEDINIPUR Central Drilling Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation PROVIDING DRILLING CREW AND OTHER ALLIED WORKS FOR CONSTRUCTION OF TUBE WELL (300MM X 200MM X 230 MTRS DEPTH) BY UTILIZING DEPARTMENTAL MACHINERIES FOR BAICHBERYA W/S SCH (REPLACEMENT TW-II) NANDAKUMAR BLOCK PURBA MEDINIPUR DISTRICT, CDD, PHE DTE. ORD/000010/2022-2023 433/CDD 23/05/2022 30 PADMA ENGINEERING & CO. 13.86 12.78 92.21 100
5 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Supply of sluice valve & delivery at Chapbasan Store for Bahichberia PWSS within Nandakumar Dev. Block and under Tamluk Sub-Division of Tamluk Division PHE Dte.(PART-A) Assistant Engineer Junior Engineer ORD/000324/2022-2023 1231/TD 07/09/2022 15 J.S. CONSTRUCTION 3.14 3.14 100 100
6 PURBA MEDINIPUR Central Drilling Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation PROVIDING DRILLING CREW AND OTHER ALLIED WORKS FOR CONSTRUCTION OF TUBE WELL (300MM X 200MM X 250 MTRS DEPTH) BY UTILIZING DEPARTMENTAL MACHINERIES FOR BAICHBERIA W/S SCH (TW-III), NANDAKUMAR BLOCK UNDER PURBA MEDINIPUR DISTRICT, CDD, PHE DTE. Driller In Charge Junior Engineer ORD/000269/2022-2023 1231/CDD 16/11/2022 30 PADMA ENGINEERING & CO. 18.95 16.13 85.12 100
7 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Sinking of 300mm. x 200mm. dia. x 240 mtr. Deep Additional Tube well by direct rotary rig method at 4th Tube well Site of Baichberia Water Supply Scheme within Nandakumar Block under Tamluk Sub-Division, of Tamluk Division P.H.E. Dte. Purba Medinipur. Assistant Engineer Junior Engineer ORD/000104/2022-2023 480/TD 03/06/2022 21 TAPAS KUMAR GIRI 17.39 0.00 0 0
8 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Construction of (3.60 Mtr. X 3.00 Mtr.) Switch Room cum Chlorine Room with water supply & sanitary arrangement (as per Deptt. drawing) at 3rd tube well sites of Bahichberia Water Supply Scheme under Tamluk Sub Division, PHE Dte. Purba Medinipur. Assistant Engineer Junior Engineer ORD/000632/2022-2023 2482/TD 16/01/2023 30 SK. NUR ISLAM 4.85 4.85 100 25
9 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Repairing & renovation of Construction of Switch Room cum Chlorine Room with water supply & sanitary arrangement (as per Deptt. drawing) at 2nd tube well site of Bahichberia Water Supply Scheme under Tamluk Sub Division of Tamluk Division, PHE Dte. Purba Medinipur . Assistant Engineer Junior Engineer ORD/000639/2022-2023 2483/TD 16/01/2023 30 S.K. MONDAL 3.53 3.52 99.72 0
10 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Land filling work for entrance approach & 3rd tube well site of Bahichberia Water Supply Scheme for augmentation of Bahichberia pwss under Tamluk Sub Division of Tamluk Division, PHE Dte. Purba Medinipur. Assistant Engineer ORD/000746/2022-2023 1086/TSD 22/08/2022 15 J.S. CONSTRUCTION 1.72 1.54 89.53 100
11 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Material Requisition To Resource Division RTOR000012/2022-2023 84/TD 08/04/2022 0 Resource Division 53.93 0.00 0 0
12 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Material Requisition To Resource Division RTOR000034/2022-2023 650/TD 27/06/2022 0 Resource Division 39.34 0.00 0 0
13 PURBA MEDINIPUR Midnapore Mechanical Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Electric quotation for Baichberya PWSS Tube Well- III (Ref. ID - 203911567) BILL/00159/2022-2023 BP-2022-23-129 13/03/2023 0 WBSEDCL 8.28 0.00 0 0
14 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Laying of rising main, Construction of Boundary Wall and Repairing & Renovation of Construction of Boundary wall with allied work for Bahichberia PWSS in Nandakumar Dev. Block including supply of all labour & materials within Tamluk Sub-Division under Tamluk Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000135/2023-2024 270/TD 20/04/2023 630 S.K. MONDAL 29.92 4.51 15.07 80
15 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Laying left out portion of 90 mm dia UPVC pipe line ( 3991.00 mtr ) with allied works to facilitating the FHTC connection for Bainchberia Water Supply Scheme under Tamluk Sub-Division of Tamluk Division, PHE Dte. ( Part-A) Assistant Engineer ORD/000289/2024-2025 3054/TD 19/09/2024 25 HYDROTECH ASSOCIATES 17.58 0.00 0 0
16 PURBA MEDINIPUR Midnapore Mechanical Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Providing and Installation of Submersible pumping machineries and other electromechanical equipments at Newly sunk Replacement Tube well - II of Baichberiya water supply scheme under Midnapore Mechanical Division, PHE Dte. Sri Srinath Ranjan Ghosh, AE/Haldia Electrical Sub-Divi Sri Tanmoy Shee, JE/Haldia Electrical Sub-Division. ORD/001137/2022-2023 2118/W/MMD 28/11/2022 458 RITESH ENTERPRISE 12.17 11.30 92.85 90
17 PURBA MEDINIPUR Central Drilling Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Providing drilling crew and other allied works for construction of Tube Well ( 300mm X200mm X 250 Mtrs. Depth) by utilising Departmental Machineries at Baichberia , Nandakumar Block under Purba Midnapore District, Central Drilling Division, P.H.E. Dte. Driller In Charge Junior Engineer ORD/000529/2022-2023 1229/CDD 16/11/2022 390 MENAKA ENTERPRISE 18.61 15.55 83.56 100
18 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Material Requisition To Resource Division RTOR000202/2023-2024 1103/TD 18/03/2024 0 Resource Division 0.19 0.00 0 0
19 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Material Requisition To Resource Division RTOR000055/2024-2025 2002/TD 14/06/2024 0 Resource Division 2.64 0.00 0 0
20 PURBA MEDINIPUR Midnapore Mechanical Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Qoutation bill for T/W -IV of Baichberia water supply scheme BILL/03565/2023-2024 BP-2023-24-608 07/02/2024 0 WBSEDCL 3.80 0.00 0 0
21 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Augmentation of ground water based Bahichberia Water Supply Scheme by providing Laying of Distribution pipe line and FHTC work and Construction of RCC Over Head Reservoir 900 cum and staging height 20.00 mtr. With allied work including Sub Soil Investigation within Nandakumar Dev. Block under Tamluk Sub-Division of Tamluk Division, PHE Dte. Purba Medinipur. Assistant Engineer Junior Engineer ORD/000003/2022-2023 56/TD 05/04/2022 922 JAYANTA KUMAR MONDAL 952.26 917.45 96.34 99
22 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Repairing & renovation of Construction of Switch Room cum Chlorine Room with water supply & sanitary arrangement (as per Deptt. drawing) at 1st tube well site of Bahichberia Water Supply Scheme under Tamluk Sub Division of Tamluk Division, PHE Dte. Purba Medinipur Assistant Engineer Junior Engineer ORD/000615/2022-2023 79/TSD 13/01/2023 690 J.S. CONSTRUCTION 2.61 0.00 0 0
23 PURBA MEDINIPUR Midnapore Mechanical Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Providing and Installation of Submersible pumping machineries and other electromechanical equipments at Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme in Purba Medinipur District, under JJM Program under MMD PHE Dte. Sri Srinath Ranjan Ghosh, AE/Haldia Electrical Sub-Divi Sri Tanmoy Shee, JE/Haldia Electrical Sub-Division. ORD/000046/2023-2024 1219/W/MMD 25/04/2023 860 BHABANI PRASAD MANNA 27.19 12.79 47.04 50
24 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Dismentling of existing damaged godown at Bainchberia and its adj mouzas Water Supply Scheme under Tamluk Sub Division of Tamluk Division PHE Dte. Assistant Engineer Junior Engineer ORD/000569/2024-2025 195/TSD 22/01/2025 30 SUDIP MANNA 2.12 0.00 0 0
25 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Continuation work order for Hiring of one no Diesel Motor Cabs(Luxary taxi) (Standerd non air conditioned) Bharat stage-IV, on daily rate basis (including Govt. Holidays as and when required) having contract carriage permit from RTA for the office of Executive Engineer, Tamluk Division ,PHE Dte. Under Tamluk Division for the period from 01.11.2024 upto 31.10.2025 i.e 12 (Twelve) Months. Assistant Engineer Junior Engineer ORD/000657/2024-2025 1636/TSD 30/10/2024 239 TAPAS SANTRA 1.14 0.80 70.18 0
26 PURBA MEDINIPUR Tamluk Division Different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Baichberia Water Supply Scheme , SM/10122 Augmentation Hiring of one no. Diesel Motor Cabs(Luxury taxi commercial standard non air conditioned) Bharat stage-IV, bearing Vehicle No-WB-29F-4919 on daily rate basis (including Govt. Holidays as and when required) having contract carriage permit from RTA for the office of the Assistant Engineer, Tamluk Sub Division under Tamluk Division ,PHE Dte. within Purba Medinipur District For the period from 07.08.2025 to 06.02.2026.(06 Months) Assistant Engineer Junior Engineer ORD/000404/2025-2026 2671/TSD 06/08/2025 184 KHOKAN SAMANTA 0.87 0.00 0 10
Total 1,253.59 1,017.94 81.2