Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
13 560.04 287.15 51.27  
1 PURBA MEDINIPUR Tamluk Division Augmentation of Ground Water Based Piped Water Supply Scheme for Golaranji , SM/09447 Augmentation Preparation of D.P.R. for different works for providing Functional Household Tap Connection (FHTC) by Augmentation of Golaranji Water Supply Scheme under Tamluk Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000322/2021-2022 1615/TD 14/01/2022 20 GEOTECHNICAL ENGINEERS CONSORTIUM 3.46 3.04 87.86 100
2 PURBA MEDINIPUR Tamluk Division Augmentation of Ground Water Based Piped Water Supply Scheme for Golaranji , SM/09447 Augmentation Sinking of 250 mm. x 150 mm. dia. x 250 mtr. deep tube well by direct rotary rig method for 3rd Tubewell (Mouza - Gonara, JL No. - 187, Plot No. -41)of Golaranij Water Supply Scheme under Contai Sub-Division of Tamluk Division P.H.E. Dte. Purba Medinipur. Assistant Engineer Junior Engineer ORD/000035/2022-2023 134/TD 19/04/2022 21 MENAKA ENTERPRISE 13.26 0.00 0 0
3 PURBA MEDINIPUR Tamluk Division Augmentation of Ground Water Based Piped Water Supply Scheme for Golaranji , SM/09447 Augmentation Supply and Delivery of CIDF Sluice Valve for laying of distribution pipe line and allied works for Rejuvenation of Golaranij Water Supply Scheme under Contai Sub-Division of Tamluk Division in Purba Medinipur District. Assistant Engineer Junior Engineer ORD/000534/2023-2024 1835/TD 08/08/2023 20 RAMESH & SHANTI ENGINEERING WORKS 4.20 4.20 100 100
4 PURBA MEDINIPUR Tamluk Division Augmentation of Ground Water Based Piped Water Supply Scheme for Golaranji , SM/09447 Augmentation Material Requisition To Resource Division RTOR000024/2021-2022 1249/TD 13/12/2021 0 Resource Division 10.87 0.00 0 0
5 PURBA MEDINIPUR Tamluk Division Augmentation of Ground Water Based Piped Water Supply Scheme for Golaranji , SM/09447 Augmentation Material Requisition To Resource Division RTOR000060/2021-2022 1273/TD 12/09/2022 0 Resource Division 18.08 0.00 0 0
6 PURBA MEDINIPUR Midnapore Mechanical Augmentation of Ground Water Based Piped Water Supply Scheme for Golaranji , SM/09447 Augmentation Providing and Installation of Submersible pumping machineries and other electromechanical equipments for Augmentation of Ground Water Based Piped Water Supply Scheme for Golaranji, Block Potashpur I, District - Purba Medinipur under JJM Program under MMD PHE Dte. Sri Srinath Ranjan Ghosh, AE/Haldia Electrical Sub-Divi Sri Sukanta Mondal, JE/Haldia Electrical Sub-Division. ORD/001914/2022-2023 816/W/MMD 24/03/2023 180 MEGA SOLAR ENERGY 11.79 0.00 0 85
7 PURBA MEDINIPUR Central Drilling Augmentation of Ground Water Based Piped Water Supply Scheme for Golaranji , SM/09447 Augmentation Providing drilling crews Including Allied Materials for construction of Tube Well ( 250mm X150mm) at Golaranji W/S Scheme within Purba Medinipur District under Central Drilling Division, P.H.E. Dte. Driller In Charge Junior Engineer ORD/000179/2023-2024 1412/CDD 20/09/2023 149 MENAKA ENTERPRISE 11.26 9.61 85.35 100
8 PURBA MEDINIPUR Midnapore Mechanical Augmentation of Ground Water Based Piped Water Supply Scheme for Golaranji , SM/09447 Augmentation Quotation Bill for New Service connection at T/W NO-III Of GOLARANIJ W/S Scheme under MMD, PHE, Dte. Block- POTASHPUR-I, AMARSI C.C.C. Ref. Memo No- 2004609771/QUOT/03 DT. 21-02-2024 Application NO- 2004609771 Application type-New connection Reference Id- 204223235 BILL/04385/2023-2024 BP-2023-24-823 13/03/2024 0 WBSEDCL 5.82 0.00 0 0
9 PURBA MEDINIPUR Tamluk Division Augmentation of Ground Water Based Piped Water Supply Scheme for Golaranji , SM/09447 Augmentation Augmentation of ground water based Golaranij Water Supply Scheme by providing Laying of Distribution pipe line and FHTC work and Construction of R.C.C. Over Head Reservoir of capacity 250 cum and staging height 20.00 mtr. with allied work including Sub Soil Investigation within Potashpur-I Dev. Block under Contai Sub Division of Tamluk Division, PHE Dte. Purba Medinipur Assistant Engineer Junior Engineer ORD/000381/2022-2023 1370/TD 23/09/2022 180 KISHORE GHOSH 392.47 262.56 66.9 70
10 PURBA MEDINIPUR Tamluk Division Augmentation of Ground Water Based Piped Water Supply Scheme for Golaranji , SM/09447 Augmentation Name of Work: i) Laying Rising main and other allied works Augmentation of Golaranij W/S Scheme within Patashpur-I Block under Contai Sub-Division of Tamluk Division, PHE Dte. Purba Medinipur. ii) Construction of Boundary Wall (as per Departmental Design & Drawing) at Head works site for Augmentation of Golaranij PWSS within Patashpur-I Block under Contai Sub-Division of Tamluk Division, P.H.E.Dte.Purba Medinipur.(Length-136.00 mtr.) iii) Construction of Boundary Wall (as per Departmental Design & Drawing) at 3rd TW site for Augmentation of Golaranij PWSS within Patashpur -I Block under Contai Sub-Division of Tamluk Division, P.H.E.Dte.Purba Medinipur.(Length-60.00 mtr.) Assistant Engineer Junior Engineer ORD/000870/2022-2023 3221/TD 14/03/2023 828 M/S. PRADIP PRADHAN 35.86 4.46 12.44 80
11 PURBA MEDINIPUR Tamluk Division Augmentation of Ground Water Based Piped Water Supply Scheme for Golaranji , SM/09447 Augmentation Repair and Renovation of Pump House & Boundary Wall and others allied works for 1st Tube well site and 2nd Tube Well site at Golaranij Water Supply Scheme in Patashpur-I Block within Contai Sub-Division under Tamluk Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000355/2024-2025 3318/TD 22/10/2024 30 BADAL CHANDRA GOLE 4.92 0.00 0 100
12 PURBA MEDINIPUR Tamluk Division Augmentation of Ground Water Based Piped Water Supply Scheme for Golaranji , SM/09447 Augmentation Laying Distribution Pipe Line With allied Works of Left Out Area for Augmentation Of Golaranij Water Supply Scheme within Patashpur-I Block under Contai Sub-Division of Tamluk Division, PHE Dte., Purba Medinipur District. (PHASE-II) Assistant Engineer Junior Engineer ORD/001201/2023-2024 738/TD 28/02/2024 275 KISHORE GHOSH 44.24 0.00 0 100
13 PURBA MEDINIPUR Tamluk Division Augmentation of Ground Water Based Piped Water Supply Scheme for Golaranji , SM/09447 Augmentation Construction of 3.60 mtr x3.00mtr. Size Switch Room cum Chlorin Room (as per Departmental Design & Drawing) without sanitary & water supply arrangements including Plinth Protection at 3rd Tube Well site for Golaranij W/S Scheme within Patashpur-I Block under Contai Sub-Division of Tamluk Division, P.H.E.Dte.Purba Medinipur.(For Low Land) Assistant Engineer Junior Engineer ORD/000714/2022-2023 1212/TD 06/09/2022 60 BADAL CHANDRA GOLE 3.81 3.28 86.09 100
Total 560.02 287.14 51.27