Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
1 69.35 0 0  
1 PASCHIM MEDINIPUR Midnapore Division Regular Upkeep of Drinking Water Testing Laboratory in Paschim Medinipur Under Midnapore Division, PHE dte. Related to Water Quality Monitoring and Surveillance Support Activities under Jal Jeevan Mission. , SM/18277 Support-WQMSP Repairing and Renovation work of an existing damaged PHE Dte. Laboratories building in connection with different 08 (Eight) Nos. Sub-District Water Testing Laboratories under Midnapore Division, PHE Dte. of Paschim Medinipur District. AE/RWS Midnapore Sub Division JE RWS Kharagpur Sub-Division(Debra),JE RWS Kharagpur Sub-Division( Sabang),JE RWS Midnapur Sub-Division( Dantan-I),JE1 Sadar Sub-division,JE2 Ghatal Sub-division,JE2 Kharagpur Sub Division,JE2 Sadar Sub-division,JE3 Kharagpur Sub-division ORD/000333/2024-2025 3576/MD 06/12/2024 240 D M CONSTRUCTION 69.35 0.00 0 75
Total 69.35 0.00 0