Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 47.41 12.92 27.25  
1 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Based Pipe Water Supply Scheme for Abasgarh mouza. , SM/16296 Augmentation Material Requisition To Resource Division RTOR000206/2023-2024 1422/MD 04/05/2023 Resource Division 18.38 0.00 0 0
2 PASCHIM MEDINIPUR Midnapore Mechanical Augmentation of Ground Based Pipe Water Supply Scheme for Abasgarh mouza. , SM/16296 Augmentation QUOTATION MONEY FOR T W NO 3 OF ABASHGARH WATER SUPPLY SCHEME [ REF- CONSUMER ID 203990474, UNDER RAJABAZAR CCC, WBSEDCL ] BILL/00156/2023-2024 BP-2023-24-43 19/05/2023 WBSEDCL 0.31 0.00 0 0
3 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Based Pipe Water Supply Scheme for Abasgarh mouza. , SM/16296 Augmentation Sinking of 150 X 100 mm dia. X 150 Mtr. Depth Rig bored Tube well for boosting purpose including FHTC, Valve chamber and other ancillary works of under Augmentation of Abasgarh W/S Scheme under Midnapore Division, PHE Dte. AE Sadar Sub-division JE1 Sadar Sub-division ORD/000670/2022-2023 723/MD 09/03/2023 35 WATER LINK 11.31 6.41 56.68 50
4 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Based Pipe Water Supply Scheme for Abasgarh mouza. , SM/16296 Augmentation Preparation of D.P.R (Consultancy work) in connection with the Functional House Hold Tap Connection for Rejuvenation / Augmentation of existing Abasgarh PWSS within Midnapore Saar Block under Midnapore Division, P.H.E. Dte. AE Sadar Sub-division JE1 Sadar Sub-division ORD/001012/2021-2022 531/MD 21/03/2022 10 GOBINDA MAITY 2.26 2.14 94.69 100
5 PASCHIM MEDINIPUR Midnapore Mechanical Augmentation of Ground Based Pipe Water Supply Scheme for Abasgarh mouza. , SM/16296 Augmentation Providing and installation of submersible pumping machineries and other electromechanical equipment at newly sunk tube well at Additional TW III of Abasgarh water supply scheme under Midnapore Mechanical Division, P.H.E. DTE. Sri Bikash Das, AE/Midnapur Mechanical Sub-Division-I Sri Mahadev Dutta, JE/Midnapur Mechanical Sub-Division- ORD/000110/2023-2024 428/MMSD-I 24/04/2023 15 SUJOY RANJAN BHOWMICK 4.37 4.37 100 100
6 PASCHIM MEDINIPUR Midnapore Mechanical Augmentation of Ground Based Pipe Water Supply Scheme for Abasgarh mouza. , SM/16296 Augmentation Providing and Installation of Submersible pumping machineries and other electromechanical equipments for Augmentation of Ground Based Pipe Water Supply Scheme for Abasgarh mouza. under JJM Program under MMD PHE Dte. Sri Bikash Das, AE/Midnapur Mechanical Sub-Division-I Sri Mahadev Dutta, JE/Midnapur Mechanical Sub-Division- ORD/002002/2022-2023 904/W/MMD 27/03/2023 180 ECO ENTERPRISE 10.78 0.00 0 40
Total 47.40 12.92 27.25