Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
14 687.47 185.26 26.95  
1 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal, District - Paschim Medinipur. , SM/09585 Augmentation Continuation work order for the work of Round the Clock Guarding Arrangements to protect the Govt. properties / materials etc. at different Places of Kharagpur Sub-Division Stores / Office premises stackyard etc. under Midnapore Division, PHE Dte. [For the period 4 months i.e. from 01.04.2021 to 31.07.2021] [Considering Zone - 'A' as per Joint Labour Commissioner order vide Memo No. - 352 /Stat/2RW/76/266/LCS/JLC, Dated - 27.12.2019] AE Ghatal Sub-division ORD/000850/2020-2021 606/MD 30/03/2021 122 M/S. OXFORD SECURITY SERVICE 3.75 0.00 0 0
2 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal, District - Paschim Medinipur. , SM/09585 Augmentation Continuation Work Order for the work of Conducting of Route survey in connection with the FHTC of existing PWSS Ranirbazar (Block-Ghatal) to be Augmentation/ Rejuvenation under Midnapore Division, P.H.E Dte. AE Ghatal Sub-division ORD/001039/2021-2022 1647/MD 22/09/2021 10 SRIJAN ECOLOGICAL UPLIFTMENT PVT. LTD. 1.02 1.02 100 0
3 PASCHIM MEDINIPUR Midnapore Mechanical Augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal, District - Paschim Medinipur. , SM/09585 Augmentation Electric quotation Ghatal CCC at Ranisimulia, Ranirbazar Water supply scheme under MMD PHE Dte VCH/002770/2022-2023 BP-2022-23-58 23/11/2022 0 WBSEDCL 0.30 0.00 0 0
4 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal, District - Paschim Medinipur. , SM/09585 Augmentation Purchasing of materials for the augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal. District - Paschim Medinipur. VCH/000459/2022-2023 11/08/2022 0 EXECUTIVE ENGINEER,RESOURCES DIVISION PHE DTE. 13.67 0.00 0 0
5 PASCHIM MEDINIPUR Midnapore Mechanical Augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal, District - Paschim Medinipur. , SM/09585 Augmentation Providing and Installation of Submersible pumping machineries and other electromechanical equipments at Newly sunk Replacement Tube well at Pump House-II under Ranirbazar water supply scheme under Midnapore Mechanical Division, PHE Dte. Dist - Paschim Medinipur. Sri Bikash Das, AE/Midnapur Mechanical Sub-Division-I Sri Mahadev Dutta, JE/Midnapur Mechanical Sub-Division- ORD/001133/2022-2023 2114/W/MMD 28/11/2022 120 M/S EMMESS 11.37 10.10 88.83 0
6 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal, District - Paschim Medinipur. , SM/09585 Augmentation Laying of Rising Main including interconnection of Augmentation of Ranirbazar & its adjoining mouzas W/S Scheme of Ghatal block under Ghatal Sub-Division within Midnapore Division, P.H.E. Dte. (Length- 2,470 Mtr.) AE Ghatal Sub-division JE1 Ghatal Sub-division ORD/000593/2022-2023 344/MD 31/01/2023 14 A-PLUS 9.63 0.00 0 0
7 PASCHIM MEDINIPUR Midnapore Mechanical Augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal, District - Paschim Medinipur. , SM/09585 Augmentation Providing and Installation of Submersible pumping machineries and other electromechanical equipments at Newly sunk Tube well at Pump House-III under Ranirbazar water supply scheme under Midnapore Mechanical Division, PHE Dte. Dist - Paschim Medinipur. Sri Bikash Das, AE/Midnapur Mechanical Sub-Division-I Sri Mahadev Dutta, JE/Midnapur Mechanical Sub-Division- ORD/001076/2022-2023 1968/W/MMD 20/10/2022 120 BUSR ENGINEERING 10.79 10.51 97.41 99
8 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal, District - Paschim Medinipur. , SM/09585 Augmentation Exigency basis laying casing pipe under Bitumineous pucca road crosssing (Near Baliaghata bus stop,Bablatola Maruti Showroom,Chanak para Soni Mandir) of Khakurda to Ghatal PWD Road of Ranapur W/S Scheme within Ghatal Sub-Division, PHE.Dte. AE Ghatal Sub-division ORD/000524/2022-2023 171/AE/GSD 01/04/2022 2 ANNAPURNA TUBEWELL WORKS 3.64 3.48 95.6 0
9 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal, District - Paschim Medinipur. , SM/09585 Augmentation Material Requisition To Resource Division RTOR000033/2021-2022 2278/MD 31/12/2021 0 Resource Division 13.67 0.00 0 0
10 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal, District - Paschim Medinipur. , SM/09585 Augmentation Material Requisition To Resource Division RTOR000125/2022-2023 225/MD 02/02/2023 0 Resource Division 74.42 0.00 0 0
11 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal, District - Paschim Medinipur. , SM/09585 Augmentation Chandrakona to Ghatal Road from Chainage 36.600 Kmp to 42.00 Kmp Restoration of damages due to laying of proposed underground pipeline by PHE Deptt in the district of Paschim Medinipur. BILL/00126/2023-2024 BP-2023-24-81 08/05/2023 0 EXECUTIVE ENGINEER, P.W.D 80.00 0.00 0 0
12 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal, District - Paschim Medinipur. , SM/09585 Augmentation Cutting concrete & bitumen road for Laying Rising main & Distribution pipeline for Augmentation of Ranirbazar W/S Scheme within Ghatal block under Ghatal Sub-Division of Midnapore Division, PHE Dte. AE Ghatal Sub-division JE1 Ghatal Sub-division ORD/000842/2023-2024 638/MD 06/03/2024 30 A-PLUS 12.82 0.00 0 0
13 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal, District - Paschim Medinipur. , SM/09585 Augmentation Laying distribution pipe line, Pump House, FHTC & construction of R.C.C. Over Head Reservoir of capacity 350 Cum (including Pile) and staging height 20.00 mtr. with allied work including Sinking of Deep Tube Well for Augmentation of Ranirbazar and its adjoining mouzas W/S Scheme in Ghatal Block including supply of all labour & materials within Ghatal Sub-Division under Midnapore Division, PHE Dte. AE Ghatal Sub-division JE1 Ghatal Sub-division ORD/000009/2022-2023 606/MD 04/04/2022 1240 M/S. A.R. ENTERPRISE. 448.80 160.15 35.68 40
14 PASCHIM MEDINIPUR Midnapore Division Augmentation of Ground Water Based Piped Water Supply Scheme for Ranirbazar to Accommodate FHTC, Block - Ghatal, District - Paschim Medinipur. , SM/09585 Augmentation Supply of C.I.D.F. Sluice valve C.I.Jeffy coupler for distribution and rising main pipe line for Augmentation of Ranirbazar water supply scheme under Ghatal Sub-Division of Midnapore Division, P.H.E.Dte AE Ghatal Sub-division JE1 Ghatal Sub-division ORD/000644/2022-2023 108/AE/GSD 13/02/2023 7 M/S. GEO 3.59 0.00 0 100
Total 687.45 185.25 26.95