Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
3 | 1.16 | 0 | 0 | ||||||||||||||
1 | PASCHIM MEDINIPUR | Midnapore Division | Retrofitting to accommodate FHTC under JJM in Palashi Piped Water Supply Scheme. , SM/06930 | Retrofitting | FHTC data entry. | VCH/001286/2021-2022 | 844364 | 18/01/2022 | ANIRBAN CHAKRABORTY | 0.20 | 0.00 | 0 | 0 | ||||
2 | PASCHIM MEDINIPUR | Midnapore Division | Retrofitting to accommodate FHTC under JJM in Palashi Piped Water Supply Scheme. , SM/06930 | Retrofitting | FHTC data entry. | VCH/001287/2021-2022 | 844364 | 18/01/2022 | SOVANDEB MANNA | 0.10 | 0.00 | 0 | 0 | ||||
3 | PASCHIM MEDINIPUR | Midnapore Division | Retrofitting to accommodate FHTC under JJM in Palashi Piped Water Supply Scheme. , SM/06930 | Retrofitting | Supply & installation of 20 KVA output diesel Generator set on monthly hire basis including day to day operation and maintenance of the same for alternative electrical arrangement in the office of Assistant Engineer, Kharagpur Sub Division and also Kharagpur WTP Water Testing Lab situated within the Inda PHE Complex etc. under Midnapore Division, PHE Dte. [Period from 03.02.2021 to 02.02.2022] | AE Kharagpur Sub-division | ORD/000881/2020-2021 | 57/AE/KSD | 02/02/2021 | 12 | PULLOCK KUMAR GHOSH | 0.86 | 0.00 | 0 | 0 | ||
Total | 1.16 | 0.00 | 0 |