Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 1,715.07 1,270.43 74.07  
1 SOUTH 24 PARGANAS South 24 Pgs W/S Division I Augmentation of laying distribution system to extend the benefit of 100% Households in ZONE-II at KULTALI block within Mega surface water based water supply scheme of Falta-Mathurapur dist.- South 24 pgns. Under south 24 pgns water supply division-I, PHE , SM/18223 Augmentation Material Requisition To Resource Division RTOR000295/2023-2024 2433/SWD-I 30/09/2023 0 Resource Division 92.47 0.00 0 0
2 SOUTH 24 PARGANAS South 24 Pgs W/S Division I Augmentation of laying distribution system to extend the benefit of 100% Households in ZONE-II at KULTALI block within Mega surface water based water supply scheme of Falta-Mathurapur dist.- South 24 pgns. Under south 24 pgns water supply division-I, PHE , SM/18223 Augmentation Laying distribution system of piped water supply at Zone-IIA (JALABERIA) of Kultali Block, under BARUIPUR Sub-Division, for ¿Mega Surface water based water supply scheme for Falta-Mathurapur, District South 24 parganas¿ under South 24 Parganas W/S Division - I, P.H.E. Dte. AE BSD JE-2 ORD/000401/2021-2022 2597/SWD-I 15/03/2022 120 SPA ENTERPRISE 631.68 582.50 92.21 70
3 SOUTH 24 PARGANAS South 24 Pgs W/S Division I Augmentation of laying distribution system to extend the benefit of 100% Households in ZONE-II at KULTALI block within Mega surface water based water supply scheme of Falta-Mathurapur dist.- South 24 pgns. Under south 24 pgns water supply division-I, PHE , SM/18223 Augmentation Construction of 1250 Cu.m. capacity 20 M. staging height R.C.C. Over Head Water Reservoir as per departmental design, drawing & specification including R.C.C. Bored Pile & Pile Cap of piped water supply within Zone-II at Jalaberia Mouza of Kultali Block for the "Mega Surface Water Based Water Supply Scheme, Dist. South 24 Parganas" under Baruipur Sub-Division of South 24 Paraganas Water Supply Division-I Division of PHE Dte. AE BSD JE-2 ORD/000014/2022-2023 866/SWD-I 13/07/2022 300 M/S PATH MAKERS 322.19 309.12 95.94 91
4 SOUTH 24 PARGANAS South 24 Pgs W/S Division I Augmentation of laying distribution system to extend the benefit of 100% Households in ZONE-II at KULTALI block within Mega surface water based water supply scheme of Falta-Mathurapur dist.- South 24 pgns. Under south 24 pgns water supply division-I, PHE , SM/18223 Augmentation Restoration of boundary wall at Headworks site of Zone-II within kultali block, under Augmentation of laying distribution system to extend the benefit of 100% Households in Zone-II at KULTALI block within Mega Surface Water Based Water Supply Scheme of Falta-Mathurapur dist. South 24 Pgns. under South 24 Pgns. Water Supply Division-I, PHE Dte. (TSM/ 016053) AE BSD JE RWS ORD/000250/2023-2024 1492/SWD-I 19/07/2023 60 A.B. ASSOCIATES 14.14 13.23 93.56 100
5 SOUTH 24 PARGANAS South 24 Pgs W/S Division I Augmentation of laying distribution system to extend the benefit of 100% Households in ZONE-II at KULTALI block within Mega surface water based water supply scheme of Falta-Mathurapur dist.- South 24 pgns. Under south 24 pgns water supply division-I, PHE , SM/18223 Augmentation joynagar Jalaberia Kultali Road from 7.47 Kmp to 8.00 Kmp restoration of Paver Block,from 8.00 Kmp to 9.5 Kmp & 16.0 Kmp to 18.50 Kmp restoration of Head Shoulder due to laying of pipes by PHED under Lakshmikantapur Highway Sub-Division of Diamond Harbour Highway Division, P.W(Roads) Directorate in the District of South 24 Parganas BILL/00639/2024-2025 BP-2024-25-364 02/10/2024 0 EXECUTIVE ENGINEER, DIAMOND HARBOUR HIGHWAY DIVISION PW(ROADS) DTE. 10.48 0.00 0 0
6 SOUTH 24 PARGANAS South 24 Pgs W/S Division I Augmentation of laying distribution system to extend the benefit of 100% Households in ZONE-II at KULTALI block within Mega surface water based water supply scheme of Falta-Mathurapur dist.- South 24 pgns. Under south 24 pgns water supply division-I, PHE , SM/18223 Augmentation Laying distribution system of piped water supply at Zone-IIB (JALABARIA MOUZA) of Kultali Block, under BARUIPUR Sub-Division, for ¿Mega Surface water based water supply scheme for Falta-Mathurapur, District South 24 parganas¿ under South 24 Parganas W/S Division - I, P.H.E. Dte. AE BSD JE-1 ORD/000402/2021-2022 2600/SWD-I 15/03/2022 1350 MAHAVIR PUMPS MANUFACTURING PVT LTD 644.11 365.58 56.76 65
Total 1,715.07 1,270.44 74.07