Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
11 368.38 113.96 30.94  
1 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I Ground water based RAMNAGAR (ZONE-I) piped water supply scheme to accommodate FHTC in BARUIPUR block under South 24 Parganas W/S Division-I, PHE Dte for AUGMENTATION of surface water based W/S scheme in the Arsenic Affected Areas of South 24 Parganas dist , SM/15755 Augmentation Material Requisition To Resource Division RTOR000108/2023-2024 294/SWD-I 25/04/2023 Resource Division 19.94 0.00 0 0
2 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I Ground water based RAMNAGAR (ZONE-I) piped water supply scheme to accommodate FHTC in BARUIPUR block under South 24 Parganas W/S Division-I, PHE Dte for AUGMENTATION of surface water based W/S scheme in the Arsenic Affected Areas of South 24 Parganas dist , SM/15755 Augmentation Preparation and submission of Detailed Project Report of RAMNAGAR(I) Ground Water Based Piped Water Supply Scheme in BARUIPUR PURBA Assembly Constituency of BARUIPUR Block under Surface Water Based Water Supply Scheme in the Arsenic affected areas of South 24-Pgns. district. AE BSD ORD/000407/2021-2022 1945/SWD-I 27/01/2022 30 ENVIROTECH SOLUTIONS 2.76 2.69 97.46 0
3 SOUTH 24 PARAGANAS S24 Pgns Mechanical Ground water based RAMNAGAR (ZONE-I) piped water supply scheme to accommodate FHTC in BARUIPUR block under South 24 Parganas W/S Division-I, PHE Dte for AUGMENTATION of surface water based W/S scheme in the Arsenic Affected Areas of South 24 Parganas dist , SM/15755 Augmentation Payment of electricity bill for new service connection under SMD, PHE Dte. BILL/01503/2023-2024 BP-2023-24-174 02/08/2023 WBSEDCL 2.88 0.00 0 0
4 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I Ground water based RAMNAGAR (ZONE-I) piped water supply scheme to accommodate FHTC in BARUIPUR block under South 24 Parganas W/S Division-I, PHE Dte for AUGMENTATION of surface water based W/S scheme in the Arsenic Affected Areas of South 24 Parganas dist , SM/15755 Augmentation Sinking of 02 (Two) nos. Rig bored 250mm x 150mm dia. & 300 mtr. deepTubewell having 66 mtr. housing pipe by Rotary method for RAMNAGAR (ZONE-I) PWSS to accommodate FHTC in BARUIPUR block for Augmentation of Surface Water Based W/S Scheme in the Arsenic Affected Areas of South 24 Pgs district under South 24-Parganas W/S Division-I, P.H.E. Dte. [TSM/018210] AE BSD ORD/000631/2022-2023 3258/SWD-I 02/03/2023 30 MUNNA AGROTECH ENTERPRISE 31.76 15.60 49.12 100
5 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I Ground water based RAMNAGAR (ZONE-I) piped water supply scheme to accommodate FHTC in BARUIPUR block under South 24 Parganas W/S Division-I, PHE Dte for AUGMENTATION of surface water based W/S scheme in the Arsenic Affected Areas of South 24 Parganas dist , SM/15755 Augmentation Construction of Boundary Wall, Chlorine Room along with Laying of Distribution System, Rising Main, Providing Functional Household Tap Connection (FHTC) for Augmentation of RAMNAGAR (PART-I) MOUZA Piped Water Supply Scheme of BARUIPUR Block for implementation of JJM under Surface Water Based Water Supply Scheme in the Arsenic affected areas of South 24-Pgns district. [No. of FHTC = 1885] [TSM/018210] AE BSD JE RWS ORD/000160/2023-2024 843/SWD-I 05/06/2023 90 SRIKRISHNA CO OP LABOUR CONT AND CONS SOCIETY LTD 276.76 80.89 29.23 70
6 SOUTH 24 PARAGANAS S24 Pgns Mechanical Ground water based RAMNAGAR (ZONE-I) piped water supply scheme to accommodate FHTC in BARUIPUR block under South 24 Parganas W/S Division-I, PHE Dte for AUGMENTATION of surface water based W/S scheme in the Arsenic Affected Areas of South 24 Parganas dist , SM/15755 Augmentation Supply & Fixing main switch & Bus bar at Pump House no-1 & 2 of Ramnagar (Zone-I) W/S Scheme under SMD, P.H.E. Dte.(Block-Baruipur) Assistant Engineer Junior Engineer ORD/002381/2023-2024 1452/SMSD 30/11/2023 15 ELECTRICAL & MECHANICAL ENGINEERING CORPORATION 0.58 0.58 100 100
7 SOUTH 24 PARAGANAS S24 Pgns Mechanical Ground water based RAMNAGAR (ZONE-I) piped water supply scheme to accommodate FHTC in BARUIPUR block under South 24 Parganas W/S Division-I, PHE Dte for AUGMENTATION of surface water based W/S scheme in the Arsenic Affected Areas of South 24 Parganas dist , SM/15755 Augmentation Improvement of outdoor Illumination arrangement with allied works at Pump House no-1 of Ramnagar (Zone-I) W/S Scheme under SMD, P.H.E. Dte. (Block-Baruipur) Assistant Engineer Junior Engineer ORD/002345/2023-2024 1454/SMSD 30/11/2023 15 ELECTRICAL & MECHANICAL ENGINEERING CORPORATION 0.92 0.91 98.91 100
8 SOUTH 24 PARAGANAS S24 Pgns Mechanical Ground water based RAMNAGAR (ZONE-I) piped water supply scheme to accommodate FHTC in BARUIPUR block under South 24 Parganas W/S Division-I, PHE Dte for AUGMENTATION of surface water based W/S scheme in the Arsenic Affected Areas of South 24 Parganas dist , SM/15755 Augmentation Improvement of outdoor Illumination arrangement with allied works at Pump House no-2 of Ramnagar (Zone-I) W/S Scheme under SMD, P.H.E. Dte. (Block-Sonarpur) Assistant Engineer Junior Engineer ORD/002347/2023-2024 134/SMSD 02/02/2024 15 ELECTRICAL & MECHANICAL ENGINEERING CORPORATION 0.92 0.62 67.39 100
9 SOUTH 24 PARAGANAS S24 Pgns Mechanical Ground water based RAMNAGAR (ZONE-I) piped water supply scheme to accommodate FHTC in BARUIPUR block under South 24 Parganas W/S Division-I, PHE Dte for AUGMENTATION of surface water based W/S scheme in the Arsenic Affected Areas of South 24 Parganas dist , SM/15755 Augmentation Supply & installation of LED board at P.H. No- 1 & 2 of RAMNAGAR (Zone-I) water supply scheme under South 24 Pgs Mechanical Division PHE Dte.[ Block- Baruipur ] Assistant Engineer Junior Engineer ORD/002198/2023-2024 354/SMSD 20/03/2024 15 DITHI ENTERPRISE 0.78 0.39 50 100
10 SOUTH 24 PARAGANAS S24 Pgns Mechanical Ground water based RAMNAGAR (ZONE-I) piped water supply scheme to accommodate FHTC in BARUIPUR block under South 24 Parganas W/S Division-I, PHE Dte for AUGMENTATION of surface water based W/S scheme in the Arsenic Affected Areas of South 24 Parganas dist , SM/15755 Augmentation Supply, installation and commissioning of submersible pumping machinery along with allied accessories at P.H. 1 &2 for Augmentation of Ramnagar (Zone-I) water supply scheme under South 24 Pgs. Mechanical Division, PHE Dte. [Block: Baruipur] Assistant Engineer Junior Engineer ORD/000062/2023-2024 1056/SMD 18/04/2023 90 ELECTRICAL & MECHANICAL ENGINEERING CORPORATION 25.66 12.28 47.86 100
11 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I Ground water based RAMNAGAR (ZONE-I) piped water supply scheme to accommodate FHTC in BARUIPUR block under South 24 Parganas W/S Division-I, PHE Dte for AUGMENTATION of surface water based W/S scheme in the Arsenic Affected Areas of South 24 Parganas dist , SM/15755 Augmentation Distressed / Affected stretches of different road under P&RD Deptt. in West Bengal due to pipeline laying work by PHED [Sl. No.25] BILL/00485/2024-2025 BP-2024-25-293 11/09/2024 WBSRDA SOUTH 24 PGS ALIPORE 5.42 0.00 0 0
Total 368.37 113.96 30.94