Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
15 617.75 34.54 5.59  
1 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Preparation and submission of Detailed Project Report of "JULPIA Ground Water Based Piped Water Supply Scheme" in BISHNUPUR-I block under Surface Water Based Water Supply Scheme in the Arsenic affected areas of South 24-Pgns. district AE SWSD-II ORD/000420/2022-2023 467/SWD-I C 24/05/2022 15 CHAYANIKA ENGINEERING CONSULTANCY 2.62 2.62 100 100
2 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Material Requisition To Resource Division RTOR000121/2022-2023 3249/SWD-I 01/03/2023 Resource Division 37.13 0.00 0 0
3 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Laying Distribution System with providing Functional Household Tap Connection (FHTC) and Construction of Pump House with water supply and sanitary arrangement (as per deptt. drawing) of JULPIA PIPE WATER SUPPLY SCHEME in BISHNUPUR-I Block for Augmentation of surface water based water supply scheme in the arsenic affected areas of South 24 Parganas District. (No of FHTC = 901) [TSM/014900] AE SWSD-II ORD/000002/2023-2024 21/SWD-I 05/04/2023 90 MITHU BUILDERS 185.57 0.00 0 0
4 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Additional work for sinking of Rig bored 250 mm x 150 mm dia. & 300 mtr. deep Tube well to achieve 66 mtr. housing pipe by Rotary Method for JULPIA PWSS of Bishnupur-I Block for Augmentation of Surface Water Based W/S Scheme in the Arsenic Affected Areas of South 24-Parganas district under South 24-Parganas W/S Division- I, P.H.E. Dte. [TSM/014900] AE SWSD-II JE1 ORD/000634/2022-2023 3278/SWD-I 03/03/2023 15 MOMINUL BISWAS 1.57 0.00 0 0
5 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Sinking of Rig bored 250mm x 150mm dia. & 300 mtr. deepTubewell having 66 mtr. housing pipe by Rotary method at Second Tubewell site for JULPIA PWSS of BISHNUPUR-I block for Augmentaion of Surface Water Based W/S Scheme in the Arsenic Affected Areas of South 24 Pgs district under South 24-Parganas W/S Division-I, P.H.E. Dte. [TSM/014900] AE SWSD-II JE1 ORD/000554/2022-2023 3044/SWD-I 20/02/2023 30 TAPAS KUMAR GIRI 15.90 0.00 0 0
6 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Construction of (Size 4.80mX3.66m) Pump House with water supply and sanitary arrangement (as per Deptt. drawing) of JULPIA Pipe Water Supply Scheme in Bishnupur-I block under South 24-Pgns W/S Divn-I, PHE Dte. (SM/12234) AE SWSD-II JE1 ORD/000434/2022-2023 2578/SWD-I 10/01/2023 60 BAKSHI ENTERPRISE 6.05 5.67 93.72 100
7 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Restoration of damages due to laying of water supply line of PHE Directorate near chainage 10.00 kmp of Amtala - Baruipur Road in the district of South 24 pgs under South 24 pgs. Division, PWD during the year 2022-2023 (Estimated cost Rs.53,10,997/- x 50% = 2655499/-) BILL/01314/2023-2024 BP-2023-24-456 03/11/2023 EXECUTIVE ENGINEER, SOUTH 24 PGS. DIVISION, PWD 26.55 0.00 0 0
8 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Sinking of Rig bored 250mm x 150mm dia & 300 mtr. deep Tubewell by Rotary method for JULPIA Piped Water Supply Scheme in the Arsenic affected areas of South 24-Pgn. in BISHNUPUR-I Block Under South 24 Parganas W/S Division-I, PHE Dte. [TSM/014900] AE SWSD-II JE1 ORD/000592/2023-2024 2754/SWD-I 07/11/2023 30 SAIKAT ENTERPRISE 15.03 0.00 0 0
9 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Additional work for sinking of Rig bored 250 mm x 150 mm dia. & 300 mtr. deep Tube well to achieve 66 mtr. housing pipe by Rotary Method for JULPIA PWSS of BISHNUPUR-I Block for Augmentation of Surface Water Based W/S Scheme in the Arsenic Affected Areas of South 24-Parganas district under South 24-Parganas W/S Division- I, P.H.E. Dte. [SM/12234] AE SWSD-II JE1 ORD/000785/2023-2024 1068/SWD-I 04/03/2024 15 SAIKAT ENTERPRISE 1.57 0.00 0 0
10 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Land development at JULPIA Piped Water Supply Scheme for 1st Tubewell site in the Arsenic Affected Areas of South 24 Parganas District in Bishnupur-I Block under South 24-Pgns. W/S Sub Division-II, PHE Dte. (SM/12234) ORD/000838/2023-2024 1255/SWD-I 13/03/2024 15 HASIBA ENTERPRISE 2.65 0.00 0 0
11 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Payment for final 50% amount of the estimate value after completion of restoration work near chainage 10 km on Amtala Baruipur road as per minutes of the meeting taken by HMIC, PHED with SE's on 12/09/2022 whose total estimate value Rs.53,10,997/-, Less advance 50% payment Rs.26,55,499/-, So. Payment to be made Rs.26,55,498/- BILL/00063/2024-2025 BP-2024-25-52 09/05/2024 EXECUTIVE ENGINEER, SOUTH 24 PGS. DIVISION, PWD 26.55 0.00 0 null
12 SOUTH 24 PARAGANAS S24 Pgns Mechanical PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Payment of Quotation for new service connection at Julpia PWSS, PH No. - I (Dag No. - 152) Application No. - 1007646826 Reference ID - 106555248 BILL/00151/2024-2025 BP-2024-25-47 09/05/2024 WBSEDCL 5.28 0.00 0 null
13 SOUTH 24 PARAGANAS S24 Pgns Mechanical PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Supply, installation and commissioning of submersible pumping machinery along with allied accessories at P.H. 1&2, of Julpia water supply scheme under South 24 Pgs. Mechanical Division, PHE Dte. [Block: Bishnupur-I] Assistant Engineer -II Junior Engineer ORD/000509/2022-2023 348/SMD 09/02/2023 90 AHALYA ENGINEERING WORKS 22.78 7.80 34.24 30
14 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Construction of Boundary Wall & other allied works at 12 (twelve) nos. Head Work Sites of different PWSS within Bishnupur-I Block, Dist.-South 24-Parganas for Augmentation of Surface Water based Water Supply Scheme in the Arsenic Affected areas of South 24-Parganas District. AE SWSD-II JE1,JE2,JE4 ORD/000209/2023-2024 1377/SWD-I 12/07/2023 150 CONCORD PROJECTS PVT. LTD. 105.47 0.00 0 15
15 SOUTH 24 PARAGANAS South 24 Pgs W/S Division I PROPOSED GROUND WATER BASED JULPIA PIPED WATER SUPPLY SCHEME TO ACCOMMODATE FHTC IN BISHNUPUR-I BLOCK UNDER SOUTH 24 PARGANAS DISTRICT. , SM/12234 Augmentation Laying Distribution System with providing Functional Household Tap Connection (FHTC) for Ground Water Based JULPIA Pipe Water Supply Scheme for Augmentation of Surface Water Based Water Supply Scheme in the Arsenic Affected Areas of South 24 Pgs. Dist. in BISHNUPUR-I Block under South 24 Pgs. District. [No. of FHTC=901 nos.] AE SWSD-II JE1 ORD/000421/2022-2023 2566/SWD-I 10/01/2023 90 RELIABLE CONSTRUCTIONS 163.03 18.45 11.32 40
Total 617.76 34.54 5.59