Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 1,297.14 12.68 0.98  
1 Alipore Division AUGMENTATION OF BHANGAN KHALI PIPED WATER SUPPLY SCHEME BLOCK-BASANTI UNDER CANNING SUB-DIVISION OF ALIPORE DIVISION,PHE DTE , Inter connection and rising main with supply of specials of Augmentation of Bhangankhali W/S Scheme, Block-Basanti under Canning Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Canning sub division Junior Engineer,1 CSD ORD/000493/2023-2024 1793/AD 26/07/2023 60 M/S KRISHNA MONDAL 88.05 0.00 0 0
2 Alipore Division AUGMENTATION OF BHANGAN KHALI PIPED WATER SUPPLY SCHEME BLOCK-BASANTI UNDER CANNING SUB-DIVISION OF ALIPORE DIVISION,PHE DTE , Material Requisition To Resource Division RTOR000034/2023-2024 239/AD 24/04/2023 0 Resource Division 142.93 0.00 0 0
3 Alipore Division AUGMENTATION OF BHANGAN KHALI PIPED WATER SUPPLY SCHEME BLOCK-BASANTI UNDER CANNING SUB-DIVISION OF ALIPORE DIVISION,PHE DTE , Construction of OHR (500 cum.), Laying of Distribution System, Providing Functional Household Tap Connection etc. of Ground Water Based Augmentation Piped Water Supply Scheme for the Bhangankhali,Block - Basanti under Canning Sub Division of Alipore Division, PHE Dte. Assistant Engineer, Canning sub division Junior Engineer, 2 CSD,Junior Engineer,1 CSD ORD/000352/2023-2024 1661/AD 20/07/2023 300 SPA ENTERPRISE 636.93 10.70 1.68 5
4 Alipore Division AUGMENTATION OF BHANGAN KHALI PIPED WATER SUPPLY SCHEME BLOCK-BASANTI UNDER CANNING SUB-DIVISION OF ALIPORE DIVISION,PHE DTE , Renovation of Pump House No. 3 and its boundary wall of Bhangankhali W/S Scheme, under Basanti Block of Canning Sub-Division of Alipore Division, PHE Dte. (2nd Call) Assistant Engineer, Canning sub division Junior Engineer, 2 CSD ORD/002514/2023-2024 1605/CSD 28/02/2024 30 DIPA CHHETRI 2.03 1.98 97.54 95
5 Alipore Division AUGMENTATION OF BHANGAN KHALI PIPED WATER SUPPLY SCHEME BLOCK-BASANTI UNDER CANNING SUB-DIVISION OF ALIPORE DIVISION,PHE DTE , RESTORATION OF KOLKATA BASANTI ROAD FROM 68.00 TO 96.255 KM BLOCK CANNING I UNDER SOUTH 24 PARGANAS HIGHWAY DIVISION, DAMAGED CAUSED DUE TO LAYING OF WATER PIPE LINE BY PHED UNDER CSD BILL/01320/2024-2025 BP-2024-25-684 04/10/2024 0 EXECUTIVE ENGNEER, 24 PGS. HIGHWAY DIVN, P.W.(ROADS) DEPTT. 416.07 0.00 0 0
6 S24 Pgns Mechanical AUGMENTATION OF BHANGAN KHALI PIPED WATER SUPPLY SCHEME BLOCK-BASANTI UNDER CANNING SUB-DIVISION OF ALIPORE DIVISION,PHE DTE , Supply, installation and commissioning of submersible pumping machinery along with allied accessories at P.H. 1 for Augmentation of Bhangankhali water supply scheme under South 24 Pgs. Mechanical Division, PHE Dte. [Block: Basanti] (SM/18286) Assistant Engineer Junior Engineer ORD/000081/2025-2026 1442/SMD 22/05/2025 135 M/S. A.K. BANERJEE 11.13 0.00 0 0
Total 1,297.13 12.68 0.98