Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
21 928.98 744.29 80.12  
1 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Preparation of design (Pile and Pile Cap) drawing for foundation of different capacity OHR of Sumatinagar Zone-II PWSS under JJM at Sagar Block under Kakdwip Sub-Division of Alipore Division P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/000078/2023-2024 62/KSD 02/05/2023 4 GEOTECHNICAL ENGINEERS CONSORTIUM 0.49 0.49 100 100
2 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Sinking of 02 Nos. 250mm x 150mm dia. 360 mtr. deep Tubewell by D.R. Rig method using UPVC Pipe & Pre-packed Resin Bonded Gravel Filter for Augmentation of Sumatinagar (Zone-I & II) W/S Scheme, Block - Sagar for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/000774/2022-2023 6646/AD 14/11/2022 45 SARADA CONSTRUCTION 45.89 27.91 60.82 100
3 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Sinking of 01 No. 250mm x 150mm dia. 360 mtr. deep Tubewell Replacement Tubewell (damaged due to natural calamities) by D.R. Rig method using UPVC Pipe & Pre-packed Resin Bonded Gravel Filter at 1st Tubewell Site for Augmentation of Sumatinagar (Zone-I & II) W/S Scheme, Block - Sagar for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/000420/2023-2024 1909/AD 01/08/2023 30 SARADA CONSTRUCTION 24.12 23.31 96.64 100
4 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Conducting route survey, design distribution network and preparation & submission of DPR for each of different new water supply scheme / each Augmentation water supply scheme (SUMATINAGAR (ZONE - I & II) PWSS) including Functional Household Tap Connection (FHTC) for implementation of JJM at Sagar Block under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division ORD/001057/2022-2023 4648/AD 06/09/2022 45 VOYAGER 8.14 8.14 100 100
5 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Development of Land for sinking of 02 nos. tubewell for Sumatinagar Zone - II W/S scheme under JJM, Block : Sagar under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/000989/2023-2024 504/KSD 03/10/2023 7 SARADA CONSTRUCTION 2.57 2.54 98.83 100
6 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Material Requisition To Resource Division RTOR000498/2023-2024 4824/AD 20/12/2023 0 Resource Division 34.63 0.00 0 0
7 S24 Pgns Mechanical AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Payment of electricity bill for new service connection under SMD, PHE Dte. BILL/00016/2023-2024 BP-2023-24-34 18/05/2023 0 WBSEDCL 5.87 0.00 0 0
8 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Construction of Household Tap Platform at different household etc. for Augmentation of Sumatinagar (Zone - I & II) W/S Scheme, Block - Sagar for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (Part-C) (SM/13569) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/000154/2024-2025 2492/AD 14/06/2024 30 FIDERE MARINE SERVICES PVT. LTD. 6.12 0.00 0 0
9 S24 Pgns Mechanical AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Supply & installation of LED board at Zone-I & II, P.H. No-1 & 2 of Sumatinagar Aug water supply scheme, under South 24-Pgs Mechanical Division PHE Dte.[Block-Sagar] Assistant Engineer -I Junior Engineer ORD/000563/2024-2025 795-AE-I-SMD 11/06/2024 15 PS & ASSOCIATES 0.82 0.00 0 0
10 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Laying distribution system, Functional Household Tap Connection (FHTC) to all households for Augmentation of Sumatinagar (Zone-I & II) Water Supply Scheme, Block - Sagar for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (Part-C) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/000775/2022-2023 6647/AD 14/11/2022 30 FIDERE MARINE SERVICES PVT. LTD. 12.01 11.49 95.67 100
11 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Laying distribution system, Functional Household Tap Connection (FHTC) to all households for Augmentation of Sumatinagar (Zone-I & II) Water Supply Scheme, Block - Sagar for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (Part-D) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/000777/2022-2023 6648/AD 14/11/2022 45 RANJIT CONSTRUCTION 7.99 7.71 96.5 100
12 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Laying distribution system, Functional Household Tap Connection (FHTC) to all households for Augmentation of Sumatinagar (Zone-I & II) Water Supply Scheme, Block - Sagar for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (Part-B) [No. of FHTC =835] Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/000813/2022-2023 6754/AD 15/11/2022 120 UCON 140.93 121.47 86.19 100
13 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Allied works for pile and pile cap portion regarding the construction of 250 cum. capacity 20 mtr. staging height R.C.C. Over Head Reservoir as per departmental design, drawing and specification including R.C.C. Bored pile and pile cap upto pedestal at Sumatinagar (Zone-I & II), South 24 Parganas, Sagar Block under Kakdwip Sub-Division of Alipore Division P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/000281/2023-2024 1431/AD 13/07/2023 45 GROWING CONCERN 41.85 34.65 82.8 100
14 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Supplying, fitting, fixing and delivery of different dia. specials for Augmentation of Sumatinagar (Zone-I and II) W/S Scheme under JJM, Block- Sagar under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/000720/2023-2024 2537/AD 28/08/2023 30 ANANTA KUMAR GIRI 8.71 8.71 100 100
15 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Making and fixing of permanent display board at headwork site of Mahishamari Zone - I & II, Sumatinagar Zone - I & II PWSS under JJM at Sagar Block under Kakdwip Sub-Division of Alipore Division P.H.E.D. Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/002153/2023-2024 948/KSD 19/12/2023 5 BIMALENDU GIRI 0.81 0.40 49.38 100
16 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Construction of boundary wall along with Land Development, Plinth Protection and Approach Road for Pump House at 2nd Tubewell Site for Augmentation of Sumatinagar (Zone-I and II) W/S scheme, Block - Sagar under JJM of Kakdwip Sub-Division under Alipore Division, P.H.E. Dte. (For Zone - II) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/002176/2023-2024 813/AD 05/02/2024 45 M/S. MA BHABANI CONSTRUCTION 11.71 10.23 87.36 100
17 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Material Requisition To Resource Division RTOR000965/2023-2024 1758/AD 27/03/2024 0 Resource Division 28.55 0.00 0 0
18 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Material Requisition To Resource Division RTOR000542/2023-2024 26/AD 02/01/2024 0 Resource Division 10.31 0.00 0 0
19 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Construction of 250 cum. Over Head Reservoir (OHR), (20 mtr. Staging Height) including design & drawing of pile foundation & pile cap after soil investigation along with 2 nos. Pump House and Laying distribution system, Rising Main, Functional Household Tap Connection (FHTC) to all households including O & M for Augmentation of Sumatinagar (Zone-I & II) Water Supply Scheme, Block - Sagar for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (Part-A) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_5, Kakdwip Sub Division ORD/001063/2022-2023 8204/AD 06/12/2022 848 GROWING CONCERN 509.34 478.05 93.86 98
20 S24 Pgns Mechanical AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Supply, installation and commissioning of submersible pumping machinery along with allied accessories at P.H. 1&2, Zone-I & II for Augmentation of Sumatinagar water supply scheme under South 24 Pgs. Mechanical Division, PHE Dte. [Block: Sagar] Assistant Engineer -I,Assistant Engineer -II Junior Engineer ORD/000341/2022-2023 3745/SMD 29/12/2022 949 RELIABLE CONSTRUCTION 20.25 9.19 45.38 75
21 Alipore Division AUGMENTATION FOR GROUND WATER BASED SUMATINAGAR (ZONE - I & II) PIPE WATER SUPPLY SCHEME Phase-B, UNDER ALIPORE DIVISION, BLOCK : SAGAR, DISTRICT : SOUTH 24 PARGANAS , Repairing of 1 no. Pump House, Earth Filling, Boundary Wall Painting and Repair, Approach Road at 1st Tubewell site for Sumatinagar (Zone-I) Water Supply Scheme, Block - Sagar for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H.E. Dte. (SM/13569) (SM/09394) (SM/08792) Assistant Engineer, Kakdwip Sub Division Juniour Engineer_3, Kakdwip Sub Division ORD/000339/2025-2026 3045/AD 30/06/2025 45 PALASH HALDAR 7.87 0.00 0 0
Total 928.97 744.30 80.12