Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 101.34 48 47.37  
1 BANKURA Bankura Mechanical Augmentation of Indas Water Supply Scheme , SM/17684 Augmentation Augmentation of Indas Water Supply Scheme BILL/00188/2023-2024 28/06/2023 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 1.50 0.00 0 0
2 BANKURA Bankura Division Augmentation of Indas Water Supply Scheme , SM/17684 Augmentation Sinking of1 no. 300mm X 200mm X 250m deep Tubewell by Rig boring method including interconnection with 100 mm dia. G.I. Pipe for INDAS piped water supply scheme within Indas Block under Bishnupur Sub-Division of Bankura Division P.H.E Dte. Assistant Engineer Junior Engineer ORD/000670/2023-2024 2624/BQA 21/09/2023 330 D. S. ENTERPRISE 18.93 11.26 59.48 70
3 BANKURA Bankura Division Augmentation of Indas Water Supply Scheme , SM/17684 Augmentation Sinking of Tubewell and Construction of Boundary Wall & Pump House for Augmentation of Indas Piped Water Supply Scheme. Assistant Engineer ORD/001355/2024-2025 3172/BQA 24/12/2024 90 BEAUTY CHATTERJEE 26.99 0.00 0 0
4 BANKURA Bankura Division Augmentation of Indas Water Supply Scheme , SM/17684 Augmentation Construction of Pump House (Switch Room cum Chlorine Room) with Sanitary & Water Supply arrangement (size 5.0 m x 4.0 m) for INDAS Water Supply Scheme wihin Indas block under Bishnupur Sub Division of Bankura Division P.H.E. Dte. Assistant Engineer Junior Engineer ORD/000675/2023-2024 2626/BQA 21/09/2023 514 ARIJIT GUHA 6.60 6.54 99.09 92
5 BANKURA Bankura Division Augmentation of Indas Water Supply Scheme , SM/17684 Augmentation Construction of boundary wall approx 60 mtr long for INDAS water supply scheme in Indas Block under Bishnupur Sub Division of Bankura Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000867/2023-2024 3016/BQA 03/11/2023 60 GOLAM KHAJA KHAN 4.44 4.43 99.77 90
6 BANKURA Bankura Mechanical Augmentation of Indas Water Supply Scheme , SM/17684 Augmentation New Service Connection for INDUS BPHC CAMPUS (JL NO-14, PLOT-1947)Water supply scheme under Bankura Mechanical Division PHE DTE BILL/00013/2024-2025 19/04/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 3.82 0.00 0 0
7 BANKURA Bankura Mechanical Augmentation of Indas Water Supply Scheme , SM/17684 Augmentation New Service Connection for INDUS BPHC CAMPUS (JL NO-14, PLOT-1947)Water supply scheme under Bankura Mechanical Division PHE DTE BILL/00012/2024-2025 BP-2024-25-8 10/05/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 3.82 0.00 0 0
8 BANKURA Bankura Mechanical Augmentation of Indas Water Supply Scheme , SM/17684 Augmentation Acceptance cum Formal work order for the work of Providing, installation of Pumping machinery with other electro mechanical accessories for Augmentation of Indas water supply scheme under indus Block under Bankura Mechanical Division, PHE Dte. Dist Bankura Assistant Engineer Junior Engineer ORD/000117/2024-2025 428/BMD 27/06/2024 300 M/S BIPUL BANERJEE 35.24 25.77 73.13 40
Total 101.32 48.00 47.37