Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 2,444.72 296.67 12.14  
1 HOOGHLY Arambag Hooghly Division GROUND WATER BASED MADHABPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY DISTRICT , SM/18288 New Material Requisition To Resource Division RTOR000497/2023-2024 3057/1/Hug 11/10/2023 0 Resource Division 17.17 0.00 0 0
2 HOOGHLY Arambag Electrical GROUND WATER BASED MADHABPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY DISTRICT , SM/18288 New Quotation Bill for New Service Connection at Madhabpur W/S. Sch. TW-I BILL/04165/2023-2024 399 09/11/2023 0 WBSEDCL 3.86 0.00 0 0
3 HOOGHLY Arambag Electrical GROUND WATER BASED MADHABPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY DISTRICT , SM/18288 New Quotation for new service connection charge at Madhabpur PWSS, TW - II BILL/04371/2023-2024 463 01/12/2023 0 WBSEDCL 8.57 0.00 0 0
4 HOOGHLY Arambag Electrical GROUND WATER BASED MADHABPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY DISTRICT , SM/18288 New Hiring of Luxury Car (BS-IV) for the Official use of the Executive Engineer, Electrical Division, PHE Dte. w.e.f. 01.12.2023 to 31.05.2024. Assistant Engineer 1 Junior Engineer5 ORD/001947/2023-2024 876/AE-I/ED 23/11/2023 182 TRIDIP SARKAR 0.87 2.40 275.86 10
5 HOOGHLY Arambag Hooghly Division GROUND WATER BASED MADHABPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY DISTRICT , SM/18288 New Construction of 4 Nos. 3.6 m X 3.0 m Switch Room with Sanitary and Water Supply arrangement, 4 Nos. Boundary Wall in Proposed T.W Site, Laying rising main pipe for inter connection between 4 Nos. T.W & Distribution at SELALPUR (2Nos.), MADHABPUR (2Nos.) W/S Scheme under Arambagh Sub-Division of Hooghly Division, P.H.E. Dte. ORD/000234/2024-2025 3469/HUG 04/10/2024 90 AMWOODO ECO PRODUCTS PRIVATE LIMITED 47.22 0.00 0 0
6 HOOGHLY Arambag Electrical GROUND WATER BASED MADHABPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY DISTRICT , SM/18288 New Supply, delivery & installation of submersible pumping machinery and other electrical / mechanical equipments etc. including allied works for MADHABPUR PIPED W/S SCHEME, T.W. No. III, Block: Arambag, District - Hooghly under JJM Program under Electrical Division PHE Dte. Assistant Engineer Howrah mechanical Sub Division Junior Engineer4 ORD/000134/2024-2025 1159/ED 14/06/2024 90 SANKAR PRASAD DUTTA & CO. 10.91 0.00 0 0
7 HOOGHLY Arambag Hooghly Division GROUND WATER BASED MADHABPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY DISTRICT , SM/18288 New Sinking of 2 nos 300 X200 mm dia Tube Well ,210 mtr. Depth by D.R. Rig method using UPVC pipe (CD) and UPVC Deep Well Screen (RDS) at Proposed Tube Well Siteof MADHABPUR W/S Scheme under Arambagh Sub-Division of Hooghly Division, P.H.E. Dte ORD/000256/2024-2025 3526/HUG 22/10/2024 30 GITA ENTERPRISE 31.35 0.00 0 0
8 HOOGHLY Arambag Hooghly Division GROUND WATER BASED MADHABPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY DISTRICT , SM/18288 New BALUNDI,SELALPUR, MADHABPUR, DAHARKUNDU ZONE-II Piped Water Supply Scheme with T.W, SWITCH ROOM , BOUNDARY WALL, RISING MAIN, LDS, FHTC & Construction of OHR with 20 mtr. staging height including Soil Investigation work at ARAMBAGH Block under ARAMBAGH Sub-Division Under Hooghly Division PHE Dte Assistant Engineer Junior Engineer (Civill) ORD/000556/2023-2024 3191/HUG 31/10/2023 731 S & P ENTERPRISE 2,296.42 294.27 12.81 30
9 HOOGHLY Arambag Hooghly Division GROUND WATER BASED MADHABPUR PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY DISTRICT , SM/18288 New Horizontal Auger boring with water jet system & other ancillary works at Madhabpur Water Suply Scheme under Serampur Sub Division of Hooghly Division PHE Dte, ORD/001837/2024-2025 333/HUG 05/02/2025 60 ARUN SEAL AND CO. 28.35 0.00 0 0
Total 2,444.71 296.67 12.14