Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 656.87 69.49 10.58  
1 HOOGHLY Arambag Electrical GROUND WATER BASED MAYAPUR (ZONE-II) PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY , SM/15790 New Supply, delivery & installation of submersible pumping machinery and other electrical/ mechanical equipments etc. including allied works for Mayapur (Zone-II) water supply scheme, T.W. No. I & II, Block: Arambag, District- Hooghly under Electrical Division, PHE Dte. ORD/000025/2023-2024 1702/ED 18/04/2023 90 NUPUR CHANDRA HALDER 20.80 0.00 0 0
2 HOOGHLY Arambag Hooghly Division GROUND WATER BASED MAYAPUR (ZONE-II) PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY , SM/15790 New Material Requisition To Resource Division RTOR000472/2023-2024 3057/12/Hug 11/10/2023 0 Resource Division 6.12 0.00 0 0
3 HOOGHLY Arambag Hooghly Division GROUND WATER BASED MAYAPUR (ZONE-II) PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY , SM/15790 New Material Requisition To Resource Division RTOR000186/2023-2024 1385/57/Hug 15/05/2023 0 Resource Division 2.68 0.00 0 0
4 HOOGHLY Arambag Hooghly Division GROUND WATER BASED MAYAPUR (ZONE-II) PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY , SM/15790 New Material Requisition To Resource Division RTOR000041/2023-2024 1234/14/Hug 28/04/2023 0 Resource Division 25.34 0.00 0 0
5 HOOGHLY Arambag Hooghly Division GROUND WATER BASED MAYAPUR (ZONE-II) PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY , SM/15790 New MAYAPUR ZONE-II Piped Water Supply Scheme with Sinking of tube-well, LDS, Rising Main, FHTC, Construction of 150 cum capacity RCC OHR with 20.0 mtr. Staging height including soil investigation & construction of switch-room & boundary wall at Proposed TW site under Arambagh Sub-Division of Hooghly Division P.H.E Dte. Block Arambagh, District:- Hooghly [NEW SCHEME] Assistant Engineer Junior Engineer (Civill) ORD/000179/2023-2024 1618/hug 02/06/2023 270 M/S RAJKUMAR KHAN 246.71 56.24 22.8 20
6 HOOGHLY Arambag Hooghly Division GROUND WATER BASED MAYAPUR (ZONE-II) PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY , SM/15790 New Sinking of 3 nos 300 X200 mm dia Tube Well, 210 mtr. Depth by D.R. Rig method using UPVC pipe (CD) and UPVC Deep Well Screen (RDS) at Proposed Tube Well Site of KRISHNANAGAR Zone-II , MAYAPUR , TIROL Zone-I W/S Scheme under Arambagh Sub-Division of Hooghly Division, P.H.E. Dte. ORD/000257/2024-2025 3530/HUG 22/10/2024 45 PADMA ENGINEERING CO. 47.50 0.00 0 0
7 HOOGHLY Arambag Hooghly Division GROUND WATER BASED MAYAPUR (ZONE-II) PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY , SM/15790 New Laying of Additional Pipeline for MAYAPUR Piped Water Supply Scheme under ARAMBAGH SUB DIVISION Block Arambagh. ORD/000230/2024-2025 3439/HUG 03/10/2024 30 DILIP KUMAR GHOSH 54.57 0.00 0 0
8 HOOGHLY Arambag Hooghly Division GROUND WATER BASED MAYAPUR (ZONE-II) PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY , SM/15790 New MAYAPUR ZONE-II Piped Water Supply Scheme with Sinking of tube-well, LDS, Rising Main, FHTC, Construction of 150 cum capacity RCC OHR with 20.0 mtr. Staging height including soil investigation & construction of switch-room & boundary wall at Proposed TW site under Arambagh Sub-Division of Hooghly Division P.H.E Dte. Block Arambagh, District:- Hooghly [NEW SCHEME] Assistant Engineer ORD/000164/2023-2024 1618/Hug 02/06/2023 270 M/S RAJKUMAR KHAN 246.71 13.25 5.37 15
9 HOOGHLY Arambag Electrical GROUND WATER BASED MAYAPUR (ZONE-II) PIPED WATER SUPPLY SCHEME IN ARAMBAG BLOCK UNDER HOOGHLY DIVISION, HOOGHLY , SM/15790 New Quotation for New Service Connection at Mayapur W/S. Sch. Z=II BILL/04611/2023-2024 610 04/01/2024 0 WBSEDCL 6.44 0.00 0 0
Total 656.85 69.50 10.58