Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
22 | 620.2 | 436.19 | 70.33 | ||||||||||||||
1 | HOOGHLY | Hooghly Division | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Preparation of DPR for Augmentation of RAJHATO Piped Water Supply Scheme Under Arambagh Sub-Division of Hooghly Division P.H.E Dte. [Block-Khanakul-II]. | Assistant Engineer | Junior Engineer (Civill) | ORD/000382/2021-2022 | 613/Arg | 31/12/2021 | 30 | SRIJAN ECOLOGICAL UPLIFTMENT PVT. LTD. | 3.79 | 3.78 | 99.74 | 100 | |
2 | HOOGHLY | Central Drilling | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | CONTINGENCY BILL | VCH/000150/2022-2023 | BP-2022-23-41 | 15/07/2022 | ASHUTOSH PAL | 0.29 | 0.00 | 0 | 0 | ||||
3 | HOOGHLY | Central Drilling | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | CONTINGENCY BILL | VCH/000151/2022-2023 | BP-2022-23-40 | 15/07/2022 | SUJATA BHOWMICK | 0.14 | 0.00 | 0 | 0 | ||||
4 | HOOGHLY | Central Drilling | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | HIRING OF DIESEL DRIVEN MOTOR CAB (BS-III & ABOVE) (NON AC) HAVING CONTRACT CARRIAGE PERMIT ALONG WITH FOR THE OFFICE OF THE CALCUTTA MECHANICAL SUB DIVISION-I, PHE DTE. | ORD/000217/2021-2022 | 67/CMSD-I (D) | 22/03/2022 | 7 | SUJATA BHOWMICK | 0.87 | 0.00 | 0 | 66.67 | |||
5 | HOOGHLY | Central Drilling | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | SUPPLY AND DELIVERY OF TENT FOR DRILLING WORK AT RAJHATO PWSS UNDER CDD, PHE DTE. | ORD/000190/2022-2023 | 255/CMSD-I | 23/06/2022 | 15 | M/S S.K.GHOSH & CO. | 4.56 | 0.00 | 0 | 100 | |||
6 | HOOGHLY | Central Drilling | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | MISCELLANEOUS REPAIRING OF MUD PUMP ATTACHED WITH RIG MACHINE NO. KORES/DR/1000 UNDER CMSD-II (D), CDD, PHE DTE. | ORD/000241/2021-2022 | 634/CMSD-II (D) | 23/12/2021 | 15 | M/S B.P.TRADING CORPORATION | 3.28 | 3.22 | 98.17 | 100 | |||
7 | HOOGHLY | Central Drilling | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Supply & Delivery of Tent for Drilling work at Rajhato PWSS, Dist Hooghly and other PWSS under CDD, PHE Dte. | ORD/000306/2022-2023 | 336/CMSD-I(D) | 18/07/2022 | 15 | M/S S.K.GHOSH & CO. | 4.37 | 4.37 | 100 | 100 | |||
8 | HOOGHLY | Central Drilling | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | HIRING OF DIESEL DRIVEN MOTOR CAB (BS-IV & ABOVE) HAVING CONTRACT CARRIAGE PERMIT ALONG WITH DRIVER FOR THE OFFICE OF THE DRILLER-IN-CHARGE, CMSD-II (D), CDD, PHE DTE. | ORD/000216/2021-2022 | 55/CMSD-II (D) | 31/01/2022 | 7 | ASHUTOSH PAL | 0.86 | 0.00 | 0 | 64 | |||
9 | HOOGHLY | Hooghly Division | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Augmentation of RAJHATO Water Supply Scheme with LDS, Switch room, Boundary wall,Rising Main,FHTC Work, of existing Switch Rooms& Boundary Wall at Khanakul-II Block. | Assistant Engineer | Junior Engineer (Civill) | ORD/000190/2022-2023 | 826//Hug | 20/04/2022 | 180 | M/S PRADYUT KUMAR HAZRA | 404.28 | 365.14 | 90.32 | 80 | |
10 | HOOGHLY | Electrical | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Quotation bill for New Service connection of Rajhato w/s scheme,TW-I | BILL/00731/2023-2024 | 20 | 04/05/2023 | WBSEDCL | 2.22 | 0.00 | 0 | 0 | ||||
11 | HOOGHLY | Central Drilling | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | PROVIDING DRILLING CREW AND OTHER ALLIED WORKS FOR CONSTRUCTION OF TUBE WELL (250MM X 200MM X 240 MTRS DEPTH) BY UTILISING DEPARTMENTAL MACHINERIES FOR AUGMENTATION OF MIDNAPORE MEDICAL COLLEGE & HOSPITAL W/S SCHEME (TW0II) UNDER PASCHIM MIDNAPORE DISTRICT, CDD, PHE DTE. | ORD/000393/2022-2023 | 1077/CDD | 28/10/2022 | 30 | PADMA ENGINEERING & CO. | 16.51 | 4.28 | 25.92 | 0 | |||
12 | HOOGHLY | Hooghly Division | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Material Requisition To Resource Division | RTOR000142/2023-2024 | 1385/14/Hug | 15/05/2023 | Resource Division | 0.20 | 0.00 | 0 | 0 | ||||
13 | HOOGHLY | Electrical | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Quotation for New Service Connection of Rajhato(Aug) w/s Scheme, PH No-2 District-Hooghly Under Electrical division PHE Dte | BILL/01162/2023-2024 | 84 | 10/07/2023 | WBSEDCL | 2.57 | 0.00 | 0 | 0 | ||||
14 | HOOGHLY | Hooghly Division | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Sinking of Two Nos Big Dia Tube Well (300 mm X 200 mm) with supply of UPVC pipes & Strainer having depth upto150 Mtr at RAJHATO PWSS of ARAMBAGH Sub-Division under Hooghly Division, PHE Dte. | Assistant Engineer | Junior Engineer (Civill) | ORD/000455/2022-2023 | 2506/HUG | 22/11/2022 | 45 | OSMAN SEKH | 22.53 | 22.24 | 98.71 | 100 | |
15 | HOOGHLY | Central Drilling | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Providing drilling crew and other allied works for construction of Tube Well (300mm x 200mm x 150mtrs Depth ) by utilising Departmental Machineries for Rajhato W/S Scheme ,Arambag Block under hooghly District ,CDD,PHE Dte. | Driller In Charge | Junior Engineer | ORD/000005/2023-2024 | 61/CDD | 06/04/2023 | 30 | UNIVERSAL ENTERPRISES | 11.38 | 10.14 | 89.1 | 100 | |
16 | HOOGHLY | Hooghly Division | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Material Requisition To Resource Division | RTOR000161/2021-2022 | 424/2/Hug | 07/03/2022 | Resource Division | 36.05 | 0.00 | 0 | 0 | ||||
17 | HOOGHLY | Hooghly Division | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Material Requisition To Resource Division | RTOR000045/2022-2023 | 1590/Hug | 03/08/2022 | Resource Division | 24.64 | 0.00 | 0 | 0 | ||||
18 | HOOGHLY | Hooghly Division | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Material Requisition To Resource Division | RTOR000075/2022-2023 | 1773/9/Hug | 29/08/2022 | Resource Division | 0.69 | 0.00 | 0 | 0 | ||||
19 | HOOGHLY | Hooghly Division | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Supply of UPVC Pipe for TW-III of RAJHATO Water Supply Scheme under Arambagh Sub-Division, of Hooghly Division P.H.E. Dte. [Block-Khanakul-II] | Assistant Engineer | ORD/000910/2022-2023 | 209/Arg | 31/03/2023 | 15 | OSMAN SEKH | 0.69 | 0.35 | 50.72 | 100 | ||
20 | HOOGHLY | Hooghly Division | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Sinking of 3 nos. 300 X200 mm dia Tube Well 210 mtr. Depth by D.R. Rig method using UPVC pipe (CD) and UPVC Deep Well Screen (RDS) For AUGMENTATION Of Gobindapur, Rajhato & Kamarpukur W/S Scheme under Arambagh Sub-Division of Hooghly Division, P.H.E. Dte. | Assistant Engineer | Junior Engineer (Civill) | ORD/000226/2023-2024 | 2038/HUG | 13/07/2023 | 30 | SPG ENTERPRISES | 48.51 | 6.87 | 14.16 | 70 | |
21 | HOOGHLY | Electrical | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Supply, delivery & installation of submersible pumping machinery and other electrical/ mechanical equipments etc. including allied works for Augmentation of Rajhato water supply scheme, T.W. No.- I & II, Block: Khanakul-II, District- Hooghly under Electrical Division, PHE Dte. | Assistant Engineer 2 | Junior Engineer4 | ORD/000289/2022-2023 | 939/ED | 22/02/2023 | 90 | MAA KALI ENTERPRISE | 21.48 | 10.66 | 49.63 | 60 | |
22 | HOOGHLY | Hooghly Division | AUGMENTATION OF GROUND WATER BASED PIPED WATER SUPPLY SCHEME FOR RAJHATO. , SM/09693 | Augmentation | Construction of 3.6 m X 3.0 m Switch Room with Sanitary and Water Supply & Sanitation arrangement , Boundary Wall in Proposed T.W Site,Laying rising main pipe for inter connection between T.W & Distribution For Augmentation of RAJHATO Piped Water Supply Scheme under Arambagh Sub-Division of Hooghly Division P.HE Dte. within Khanakul-II Block. | Assistant Engineer | Junior Engineer (Civill) | ORD/000124/2023-2024 | 1458/HUG | 18/05/2023 | 30 | BENGAL TRADERS | 10.29 | 5.14 | 49.95 | 100 | |
Total | 620.21 | 436.19 | 70.33 |