Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
10 2,373.56 1,196.02 50.39  
1 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Kalitala and adjoining mouzas , SM/14153 Augmentation Material Requisition To Resource Division RTOR000254/2022-2023 925/BD 22/03/2023 Resource Division 280.28 0.00 0 0
2 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Kalitala and adjoining mouzas , SM/14153 Augmentation Formal work order for Construction of 250 Cum capacity 20 mtr staging height R.C.C Over Head water Reservoir as per Departmental design, drawing and specification including bored pile & pile cap for Augmentation of Kalitala (Zone-I) water supply scheme, Hingalganj Block under Hasnabad Sub-Division, PHE Dte. Assistant Engineer ORD/000205/2023-2024 1730/BD 08/06/2023 360 M/S PROGATI ENTERPRISE. 141.21 0.00 0 0
3 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Kalitala and adjoining mouzas , SM/14153 Augmentation Formal work order for Construction of 250 Cum capacity 20 mtr staging height R.C.C Over Head water Reservoir as per Departmental design, drawing and specification including bored pile & pile cap for Augmentation of Kalitala (Zone-I) water supply scheme, Hingalganj Block under Hasnabad Sub-Division, PHE Dte. Assistant Engineer ORD/000216/2023-2024 1731/BD 08/06/2023 360 M/S PROGATI ENTERPRISE. 141.21 0.00 0 0
4 NORTH 24 PARAGANAS Eastern Mechanical Augmentation of ground water based piped water supply scheme for Kalitala and adjoining mouzas , SM/14153 Augmentation Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.I, II, III, IV & V under Kalitala W/S Scheme District of 24 Pgs. (N) ORD/001171/2023-2024 4799/EMD 09/08/2023 30 ASHUTOSH DAS & CO. 54.35 0.00 0 0
5 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Kalitala and adjoining mouzas , SM/14153 Augmentation Material Requisition To Resource Division RTOR000162/2023-2024 4509/BD 28/11/2023 Resource Division 17.23 0.00 0 0
6 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Kalitala and adjoining mouzas , SM/14153 Augmentation Acceptance cum work order for Sinking of 2 nos. 300 mm. x 200 mm. dia. 360 mtr deep Tubewell by D.R. Rig method at PH No.-3 & 4 with PVC pipe & strainer having 300mm dia 48 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Augmentation of Kalitala w/s scheme (Z-I), Hingalganj block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer ORD/000726/2023-2024 2476/BD 18/08/2023 30 M/S DATTA ENTERPRISE. 63.24 23.51 37.18 98
7 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Kalitala and adjoining mouzas , SM/14153 Augmentation Formal work order for Laying of DI rising main, DI/UPVC distribution pipe line and providing Functional Household Tap Connection in connection with Augmentation of Kalitala water supply scheme (Zone-I), Hingalganj Block under Hasnabad Sub-Division, PHE Dte. Assistant Engineer Junior Engineer ORD/001148/2022-2023 654/BD 28/02/2023 90 SUPRITI ENTERPRISE. 610.10 522.73 85.68 60
8 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Kalitala and adjoining mouzas , SM/14153 Augmentation Acceptance cum work order for Sinking of 2 nos. 300 mm. x 200 mm. dia. 360 mtr deep Tubewell by D.R. Rig method at PH No.-3 & 4 with PVC pipe & strainer having 300mm dia 48 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Augmentation of Kalitala w/s scheme (Z-II), Hingalganj block under Hasnabad Sub-Division, P.H.E. Dte. Assistant Engineer ORD/000728/2023-2024 2477/BD 18/08/2023 30 M/S PROGATI ENTERPRISE. 63.27 43.87 69.34 71
9 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Kalitala and adjoining mouzas , SM/14153 Augmentation Formal work order for Laying of DI rising main, DI/UPVC distribution pipe line and providing Functional Household Tap Connection in connection with Augmentation of Kalitala water supply scheme (Zone-II), Hingalganj Block under Hasnabad Sub-Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000008/2023-2024 1151/BD 13/04/2023 90 UMWELT ENGINEER PVT.LTD. 851.89 605.91 71.13 100
10 NORTH 24 PARAGANAS Barasat Division Augmentation of ground water based piped water supply scheme for Kalitala and adjoining mouzas , SM/14153 Augmentation Formal work order for Construction of 300 Cum capacity 20 mtr staging height R.C.C Over Head water Reservoir as per Departmental design, drawing and specification including bored pile & pile cap for Augmentation of Kalitala (Zone-II) water supply scheme, Hingalganj Block under Hasnabad Sub-Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000218/2023-2024 1733/BD 08/06/2023 365 M/S NIRMAN CONSTRUCTION. 150.78 0.00 0 35
Total 2,373.57 1,196.04 50.39