Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
9 | 1,694.1 | 575.14 | 33.95 | ||||||||||||||
1 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Dakshin Bhebia Zone-II to accommodate FHTC , SM/12277 | Augmentation | Material Requisition To Resource Division | RTOR000239/2022-2023 | 912/BD | 22/03/2023 | Resource Division | 163.73 | 0.00 | 0 | 0 | ||||
2 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Dakshin Bhebia Zone-II to accommodate FHTC , SM/12277 | Augmentation | Material Requisition To Resource Division | RTOR000119/2023-2024 | 4173/BD | 30/10/2023 | Resource Division | 37.95 | 0.00 | 0 | 0 | ||||
3 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Dakshin Bhebia Zone-II to accommodate FHTC , SM/12277 | Augmentation | Material Requisition To Resource Division | RTOR000166/2023-2024 | 4559/BD | 01/12/2023 | Resource Division | 74.49 | 0.00 | 0 | 0 | ||||
4 | NORTH 24 PARAGANAS | Eastern Mechanical | Augmentation of ground water based piped water supply scheme for Dakshin Bhebia Zone-II to accommodate FHTC , SM/12277 | Augmentation | Supply, Delivery & Installation of Submersible Pumping Machinery alongwith allied Electro-Mechanical works, Voltage Stabilizer and Automatic Chlorinator (in connection with Aug. work related to FHTC) at Pump House No.III (Chimta)(Rep.) and IV(New) (Zone-II) under Dakshin Bhebia W/S Scheme District of 24 Pgs. (N) | ORD/001291/2023-2024 | 4941/EMD | 18/08/2023 | 30 | ESENCE ENGINEERING CONCERN | 26.47 | 0.00 | 0 | 0 | |||
5 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Dakshin Bhebia Zone-II to accommodate FHTC , SM/12277 | Augmentation | Acceptance cum work order for Restoration of 225 mm dia. UPVC pipe line due to construction of drain at Kharampur more within Dakshin Bhebia W/S Scheme (Z-II), Hasnabad block under Hasnasbad Sub-Division, P.H.E.Dte. | Assistant Engineer | Junior Engineer | ORD/001298/2023-2024 | 1420/HSD | 06/11/2023 | 7 | SARKAR ENTERPRISE | 0.92 | 0.00 | 0 | 100 | |
6 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Dakshin Bhebia Zone-II to accommodate FHTC , SM/12277 | Augmentation | Damage of road namely Kharampur Uttar Amtala More Bhabhanipur Dakshin Chimta bhabanipur Ghat (Strenthening & improvement of RIDF road from Ghuni Banstala to Bailani Bazar | BILL/00851/2024-2025 | BP-2024-25-267 | 13/09/2024 | EXECUTIVE ENGINEER (HPIU), WBSRDA ,BARASAT DIVISION | 35.17 | 0.00 | 0 | 0 | ||||
7 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Dakshin Bhebia Zone-II to accommodate FHTC , SM/12277 | Augmentation | Acceptance cum work order for Sinking of 3 nos. 300 mm. x 200 mm. dia. 360 mtr deep Tubewell by D.R. Rig method at Ph No.-1, 2 & 4 with PVC pipe & strainer having 300mm dia 48 mtr. long housing pipe & 200mm dia 30 mtr. long filter for Augmentation of Dakshin Bhebia w/s scheme (Z-II), Hasnabad block under Hasnabad Sub-Division, P.H.E. Dte. | Assistant Engineer | ORD/001023/2024-2025 | 3582/BD | 18/12/2024 | 90 | JOY GURU ENTERPRISE | 77.61 | 0.00 | 0 | 0 | ||
8 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Dakshin Bhebia Zone-II to accommodate FHTC , SM/12277 | Augmentation | Formal work order for Additional Laying of UPVC distribution pipe line and Providing Functional Household Tap Connection for the leftout portion with protection work in connection with Augmentation of Dakshin Bhebia water supply scheme (Z-II), Hasnabad Block under Hasnabad Sub-Division, PHE Dte. | Assistant Engineer | ORD/001032/2024-2025 | 3623/BD | 20/12/2024 | 90 | H.I.ENTERPRISE. | 178.87 | 0.00 | 0 | 0 | ||
9 | NORTH 24 PARAGANAS | Barasat Division | Augmentation of ground water based piped water supply scheme for Dakshin Bhebia Zone-II to accommodate FHTC , SM/12277 | Augmentation | Formal work order for Laying of DI rising main, DI/UPVC distribution pipe line, Construction of 700 cum capacity 20 mtr. staging height R.C.C. Over Head Water Reservoir as per Departmental design, drawing and specification including bored pile & pile cap and providing Functional Household Tap Connection in connection with Augmentaion of Dakshin Bhebia water supply scheme (Zone-II), Hasnabad Block under Hasnabad Sub-Division, P.H.E. Dte. | Assistant Engineer | Junior Engineer | ORD/000780/2023-2024 | 2592/BD | 28/08/2023 | 360 | H.I.ENTERPRISE. | 1,098.89 | 575.14 | 52.34 | 80 | |
Total | 1,694.09 | 575.14 | 33.95 |