Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
13 499.82 81.64 16.33  
1 NORTH 24 PARGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Sindrani Zone-I to accommodate FHTC , SM/10375 Augmentation Repairing & Renovation of 02Nos. Pump House and allied works at Sindrani(ZI&II) water supply scheme under Bongaon Sub-Division, P.H.E.Dte. Assistant Engineer Junior Engineer ORD/002939/2021-2022 594/BON 22/12/2021 21 GHOSH CONSTRUCTION. 2.52 2.34 92.86 1
2 NORTH 24 PARGANAS Eastern Mechanical Augmentation of Ground water based piped water supply scheme for Sindrani Zone-I to accommodate FHTC , SM/10375 Augmentation Supply, delivery & installation of Submersible Pumping Machinery alongwith allied electro- mechanical works and chlorinator(in connection with Aug. work related to FHTC) at Pump House No.II(Z-I) under Sindrani W/S Scheme District of 24 Pgs. (N) (Block- Baduria). NIET No.- 15 of EE/EMD of 2022-23 (Sl. No.- 11) ORD/002287/2022-2023 6148 /EMD 14/08/2022 30 DIPALI CONSTRUCTION 15.00 0.00 0 0
3 NORTH 24 PARGANAS Eastern Mechanical Augmentation of Ground water based piped water supply scheme for Sindrani Zone-I to accommodate FHTC , SM/10375 Augmentation Supply, delivery & installation of Submersible Pumping Machinery alongwith allied electro- mechanical works and chlorinator(in connection with Aug. work related to FHTC) at Pump House No.II under Sindrani W/S Scheme District of 24 Pgs. (N) ORD/001898/2022-2023 6148 / EMD 14/08/2022 30 DIPALI CONSTRUCTION 12.81 9.06 70.73 0
4 NORTH 24 PARGANAS Eastern Mechanical Augmentation of Ground water based piped water supply scheme for Sindrani Zone-I to accommodate FHTC , SM/10375 Augmentation Supply, delivery & installation of Submersible Pumping Machinery alongwith allied electro- mechanical works and chlorinator(in connection with Aug. work related to FHTC) at Pump House No.I Z-I under Sindrani W/S Scheme District of 24 Pgs. (N) ORD/001902/2022-2023 6147 / EMD 14/08/2022 30 RAKA ENTERPRISE 12.85 11.96 93.07 1
5 NORTH 24 PARGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Sindrani Zone-I to accommodate FHTC , SM/10375 Augmentation Formal work order for Providing Functional House Hold Tap Connection (FHTC) from existing and new proposed distribution system with in command area at Sindrani (Zone-I) Water Supply Scheme under Bongaon Sub-Division, PHE Dte.(Augmentation). Assistant Engineer Junior Engineer ORD/000010/2022-2023 1210/BD 21/04/2022 90 SRIJAN ECOLOGICAL UPLIFTMENT PVT.LTD. 299.02 42.84 14.33 1
6 NORTH 24 PARGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Sindrani Zone-I to accommodate FHTC , SM/10375 Augmentation Acceptance cum work order for Sinking of 1(one) no. 300mm x 200 mm. dia. Tube well 250 mtr deep by D.R. method with UPVC pipe & UPVC ribbed strainer for Augmentation at Sindrani (Zone-I) water supply scheme (Head Works site) under Bongaon Sub-Division P.H.E.Dte. Assistant Engineer Junior Engineer ORD/000828/2022-2023 3622/BD 12/12/2022 15 NADIA TUBEWELLS 15.06 12.32 81.81 0
7 NORTH 24 PARGANAS Eastern Mechanical Augmentation of Ground water based piped water supply scheme for Sindrani Zone-I to accommodate FHTC , SM/10375 Augmentation Supply, delivery and fitting fixing of change over switch, cable etc. at pump house no. I (Z-I), under Sindrani W/S Scheme in connection with FHTC. Junior Engineer ORD/001184/2023-2024 1773/EMSD-I 10/08/2023 10 RAKA ENTERPRISE 2.39 0.00 0 100
8 NORTH 24 PARGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Sindrani Zone-I to accommodate FHTC , SM/10375 Augmentation Material Requisition To Resource Division RTOR000011/2022-2023 1364/BD 13/05/2022 0 Resource Division 33.31 0.00 0 0
9 NORTH 24 PARGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Sindrani Zone-I to accommodate FHTC , SM/10375 Augmentation Material Requisition To Resource Division RTOR000021/2022-2023 1675/BD 13/06/2022 0 Resource Division 16.72 0.00 0 0
10 NORTH 24 PARGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Sindrani Zone-I to accommodate FHTC , SM/10375 Augmentation Material Requisition To Resource Division RTOR000033/2022-2023 2374/BD 12/08/2022 0 Resource Division 60.89 0.00 0 0
11 NORTH 24 PARGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Sindrani Zone-I to accommodate FHTC , SM/10375 Augmentation Health assessment of existing OHR of Sindrani (Zone-I) PWSS (135 cum) and ancillary structures, Bagdah Block conducting Non-Destructive Test and through visual observation at within the jurisdiction Bongaon Sub-Division under Barasat Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/000012/2024-2025 685/Bon 07/06/2024 15 RISHAN ENGINEERING CONSULTANCY 3.12 3.12 100 100
12 NORTH 24 PARGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Sindrani Zone-I to accommodate FHTC , SM/10375 Augmentation Acceptance cum work order for Providing Functional Household Tap Connection (FHTC) to the uncovered household as well as convert the mouzas into Swajal Gram including laying of UPVC pipe and tube well connection under Augmentation work at Sindrani W/S Scheme (Zone - I) Bagdah block within the jurisdiction of Bongaon Sub-Division under Barasat Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/000085/2024-2025 1766/BD 01/07/2024 15 ONKAR ENTERPRISE. 19.03 0.00 0 100
13 NORTH 24 PARGANAS Barasat Division Augmentation of Ground water based piped water supply scheme for Sindrani Zone-I to accommodate FHTC , SM/10375 Augmentation Acceptance cum work order for Hire and labour charges for staging and scaffolding, bamboo baricading and removal of rubbish for dismantling of existing OHR at Head work Site of Sindrani Zone-I Water Supply Scheme Bagdah Block within the jurisdiction of Bongaon Sub-Division under Barasat Division, P.H.E. Dte. Assistant Engineer ORD/001698/2024-2025 704/BD 06/03/2025 60 ONKAR ENTERPRISE. 7.10 0.00 0 0
Total 499.80 81.63 16.33