Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 276.8 98.56 35.61  
1 NADIA Eastern Mechanical Providing FHTC by augmentation for Madhugari water supply scheme with in Karimpur-I Block in Nadia District under Nadia Division P.H.E. Dte. (Phase-II) , SM/10084 Augmentation Providing, installation and commissioning of submersible pumping machinery along with allied Electro-Mechanical works for Augmentation Tube Well in connection to Accommodate FHTC at Pump House No.-I, (Phase-II) under Madhugari ground water based water supply scheme under Block_ Karimpur-I Dist. - Nadia under EMD, PHE Dte. ORD/001772/2023-2024 6396/EMD 30/10/2023 30 S.P. ENTERPRISE (KOLKATA) 16.32 0.00 0 0
2 NADIA Nadia Division Providing FHTC by augmentation for Madhugari water supply scheme with in Karimpur-I Block in Nadia District under Nadia Division P.H.E. Dte. (Phase-II) , SM/10084 Augmentation Material Requisition To Resource Division RTOR000006/2023-2024 1577/ND 06/04/2023 0 Resource Division 0.41 0.00 0 0
3 NADIA Nadia Division Providing FHTC by augmentation for Madhugari water supply scheme with in Karimpur-I Block in Nadia District under Nadia Division P.H.E. Dte. (Phase-II) , SM/10084 Augmentation Material Requisition To Resource Division RTOR000064/2023-2024 2307/ND 29/05/2023 0 Resource Division 0.62 0.00 0 0
4 NADIA Nadia Division Providing FHTC by augmentation for Madhugari water supply scheme with in Karimpur-I Block in Nadia District under Nadia Division P.H.E. Dte. (Phase-II) , SM/10084 Augmentation Laying of Distribution System including specials, valves & pipe carrying structure all complete and Providing FHTC including supplying, laying, fitting, fixing of 15mm NB PVC (schedule 80)/20mm OD HDPE (PE100, PN16) pipe with all necessary specials, saddle piece etc. all complete for Augmentation of Ground Based Water Supply Scheme at Madhugari to accommodate FHTC within Karimpur-I block under RWS Sub-Division under Nadia Division, PHE Dte. Assistant Engineer Junior Engineer Karimpur- II Block ORD/000294/2022-2023 5334/ND 21/12/2022 75 SANJIB DEY 74.59 68.34 91.62 60
5 NADIA Eastern Mechanical Providing FHTC by augmentation for Madhugari water supply scheme with in Karimpur-I Block in Nadia District under Nadia Division P.H.E. Dte. (Phase-II) , SM/10084 Augmentation Repairing rectification of electro-mechanical works related to installation of submersible pump sets and others accessories in connection with JJM under Madhugari PWSS, Block- Karimpur-I, under EMSD-III, PHE Dte. Assistant Engineer Junior Engineer ORD/000113/2024-2025 1220/EMSD-III 28/06/2024 30 SMILE 2.42 2.41 99.59 100
6 NADIA Nadia Division Providing FHTC by augmentation for Madhugari water supply scheme with in Karimpur-I Block in Nadia District under Nadia Division P.H.E. Dte. (Phase-II) , SM/10084 Augmentation Additional work of providing FHTC and additional work of Laying Distribution System in connection with Augmentation of Madhugari PWSS within Karimpur-I Block under RWS Sub-Division under Nadia Division, PHE Dte. Assistant Engineer Junior Engineer Karimpur- II Block,Junior Engineer Tehatta - II Block ORD/000725/2023-2024 1254/ND 22/02/2024 495 S.S. ENTERPRISE 19.88 17.32 87.12 100
7 NADIA Nadia Division Providing FHTC by augmentation for Madhugari water supply scheme with in Karimpur-I Block in Nadia District under Nadia Division P.H.E. Dte. (Phase-II) , SM/10084 Augmentation Conversion of IEP to AIRP of capacity 38 Cu.m/hr at Madhugari Water Supply Scheme within Karimpur-I block under RWS Nadia Sub-Divn under Nadia Divn, PHE Dte. Assistant Engineer Junior Engineer Karimpur- II Block ORD/000799/2023-2024 1911/ND 15/03/2024 600 MONDAL PRECISION PRIVATE LIMITED 140.38 0.00 0 65
8 NADIA Nadia Division Providing FHTC by augmentation for Madhugari water supply scheme with in Karimpur-I Block in Nadia District under Nadia Division P.H.E. Dte. (Phase-II) , SM/10084 Augmentation Repairing Works (existing OHR, Pump House, Boundary wall etc.) of Madhugari Water Supply Scheme, Karimpur-I Block Under R.W.S. Nadia Sub-Division P.H.E. Dte. Assistant Engineer Junior Engineer Karimpur- II Block ORD/000030/2024-2025 3431/ND 19/06/2024 360 M/S DURGA SECURITIES & SERVICES 22.18 10.49 47.29 100
Total 276.80 98.56 35.61