Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
10 1,508.52 23.86 1.58  
1 PURBA BARDHAMAN Raina-I Burdwan Division GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15235 New Material Requisition To Resource Division RTOR000482/2023-2024 4006/BWD 08/09/2023 0 Resource Division 5.14 0.00 0 0
2 PURBA BARDHAMAN Raina-I Burdwan Division GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15235 New Material Requisition To Resource Division RTOR000197/2023-2024 2155/BWD 10/05/2023 0 Resource Division 12.69 0.00 0 0
3 PURBA BARDHAMAN Raina-I Burdwan Division GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15235 New Material Requisition To Resource Division RTOR000669/2023-2024 5083/BWD 23/11/2023 0 Resource Division 20.46 0.00 0 0
4 PURBA BARDHAMAN Raina-I Central Mechanical GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15235 New New service connection charges for Gopalpur PWSS TW-2 BILL/01528/2023-2024 BP-2023-24-193 11/10/2023 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 3.82 0.00 0 0
5 PURBA BARDHAMAN Raina-I Burdwan Division GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15235 New Restoration of hard shoulder from 0.00 km to 2.918 km of Sagrai Raina Road (MDR) for laying of water supply pipeline of Gopalpur PWSS under Burdwan Division, PHE Dte. BILL/01127/2023-2024 1084/JJM 20/12/2023 0 EXECUTIVE ENGINEER BURDWAN SOUTH HIGHWAY DIVISION P.W. (ROADS) DTE. 4.72 0.00 0 0
6 PURBA BARDHAMAN Raina-I Burdwan Division GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15235 New Field level data validation of FHTC executed by Agencies on the basis of pictorial data with the objective of controlling multiple entry,improving data quality in terms of absolute household by verification through electric connection or any other unique documents and making error free database of GOPALPUR Pipe Water Supply Scheme in Raina-I Block within Burdwan Sub-Division under Burdwan Division,PHE Dte JUNIOR ENGINEER BURDWAN SADAR SUB-DIVISION PHE DTE ORD/000946/2024-2025 2732/BSD 10/12/2024 30 TECHVISION 0.56 0.00 0 0
7 PURBA BARDHAMAN Raina-I Central Mechanical GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15235 New Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Tube well No.-1 & 2 at Gopalpur Water Supply Scheme [ Block- Raina-1 ] under CMD, PHE Dte., Dist.- Purba-Bardhaman. ASSISTANT ENGINEER JUNIOR ENGINEER ORD/000720/2023-2024 4031/CMD 29/08/2023 30 M/S. SWAPAN BANERJEE 28.98 23.86 82.33 100
8 PURBA BARDHAMAN Raina-I Central Mechanical GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15235 New New electric connection for Gopalpur PWSS. BILL/01869/2023-2024 BP-2023-24-344 11/01/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 3.66 0.00 0 0
9 PURBA BARDHAMAN Raina-I Central Mechanical GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15235 New Installation of two tank chlorination system, Yard lighting arrangement & allied works at Bajitpur, Belsar & other water supply scheme under Raina-1 Block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman. ASSISTANT ENGINEER JUNIOR ENGINEER ORD/000117/2024-2025 2589/CMD 27/08/2024 90 DEY ENTERPRISE 74.58 0.00 0 10
10 PURBA BARDHAMAN Raina-I Burdwan Division GOPALPUR PIPED WATER SUPPLY SCHEME , SM/15235 New Balance work [i.e. Extension or parallel Pipeline, Leftout FHTC, Road Restoration work, Sinking of Additional Tube Well with Pump House & Boundary wall, inter Connection of Additional Tube Well, Construction of M.S.Structural bridge, canal Crossing, MS casing with allied work of Bhagabatipur, Machkhara, Udgara, Bantir, Chakpurohit Rasuikhanda, Sankarpur, Gopalpur & Belshar PWSS Block-RAINA- I under Burdwan Sub Division, PHE Dte. within Burdwan Division PHE Dte. Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. JUNIOR ENGINEER BURDWAN SADAR SUB-DIVISION PHE DTE ORD/001103/2024-2025 469/BWD 24/01/2025 366 SK ALIM 1,353.91 0.00 0 25
Total 1,508.51 23.86 1.58