Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
13 3,393.64 270.98 7.98  
1 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based RAINA PWSS to accommodate FHTC in Raina-I block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09493 Augmentation Supply of materials for different water supply scheme under Burdwan Division, PHE Dte. VCH/001578/2021-2022 1207/DW 10/03/2022 EXECUTIVE ENGINEER, RESOURCES DIVISION, P.H.E. DTE. 3,005.00 0.00 0 0
2 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based RAINA PWSS to accommodate FHTC in Raina-I block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09493 Augmentation Route Survey & Preparation of DPR for Raina W/S Scheme under Raina-I Block under Burdwan Sub-Division under Burdwan Division PHE Dte. Sl No.12. Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. ORD/000501/2021-2022 187/BSD 31/01/2022 30 RADIANT 2.72 2.71 99.63 1
3 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based RAINA PWSS to accommodate FHTC in Raina-I block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09493 Augmentation Quotation for shifting of 11 KV Raina Local Feeder at Raina PHE under Burdwan South Division, WBSEDCL.[Ref ID-860249099, App ID-100000061079, dt.-22/09/2022] VCH/000558/2022-2023 675/DW/22-23 29/09/2022 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 4.94 0.00 0 0
4 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based RAINA PWSS to accommodate FHTC in Raina-I block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09493 Augmentation Supply of 100 mm dia C.I. Sluice valve (P.N.-I) of Augmentation of Raina water supply scheme of Raina-I under Burdwan sub division, PHE Dte. Gr.C. Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. ORD/000572/2022-2023 1851/BSD 21/10/2022 15 SINHA BROTHERS 0.47 0.47 100 1
5 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based RAINA PWSS to accommodate FHTC in Raina-I block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09493 Augmentation Laying Distribution of 160 mm dia HDPE pipeline for Augmentation of RAINA Piped Water Supply Scheme AT NODE 138 to 135, 135 to 119, 119 to 114, 114 to 110 to 105, 105 to 93 within Burdwan Sub-Division under Burdwan Division, PHE Dte. Gr.B. Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. ORD/000365/2022-2023 1404/BSD 10/08/2022 45 RANADHIR SINHA 4.77 3.53 74 0
6 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based RAINA PWSS to accommodate FHTC in Raina-I block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09493 Augmentation Restoration work at various location at Thanar Danga to Nandipara Kalitala via.Ranapara and Raina Co-Operative Society of Augmentation of Raina Water Supply Scheme at Raina-I Block within under Burdwan Division,PHE Dte. Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. JUNIOR ENGINEER BURDWAN SADAR SUB-DIVISION PHE DTE ORD/000180/2023-2024 1004/BSD 06/06/2023 15 SOUMYAVASH DAS 0.95 0.94 98.95 100
7 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based RAINA PWSS to accommodate FHTC in Raina-I block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09493 Augmentation Sinking of 300 X 200mm dia Tube Well 150 mtr. Depth by D.R. Rig method using UPVC pipe (CD) and UPVC Deep Well Screen (RDS) for Aug. of RAINA W/S Scheme (H.W SITE) under Raina-I Block within Burdwan Sub-Division, PHE Dte. [For 01 No. Tube well]. Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. JUNIOR ENGINEER BURDWAN SADAR SUB-DIVISION PHE DTE ORD/000190/2023-2024 2697/BWD 08/06/2023 30 RANADHIR SINHA 13.20 11.37 86.14 100
8 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based RAINA PWSS to accommodate FHTC in Raina-I block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09493 Augmentation Material Requisition To Resource Division RTOR000060/2021-2022 559/BWD 27/01/2022 Resource Division 12.84 0.00 0 0
9 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based RAINA PWSS to accommodate FHTC in Raina-I block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09493 Augmentation Material Requisition To Resource Division RTOR000095/2021-2022 932/BWD 16/02/2022 Resource Division 23.01 0.00 0 0
10 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based RAINA PWSS to accommodate FHTC in Raina-I block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09493 Augmentation Material Requisition To Resource Division RTOR000217/2021-2022 1540/BWD 15/03/2022 Resource Division 0.37 0.00 0 0
11 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based RAINA PWSS to accommodate FHTC in Raina-I block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09493 Augmentation Quotation for new service connection of Augmentation of Raina water supply scheme.[REF ID-503550762][TW-3] BILL/01691/2023-2024 1367/JJM 20/02/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 3.08 0.00 0 0
12 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based RAINA PWSS to accommodate FHTC in Raina-I block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09493 Augmentation Quotation for new service connection of Augmentation of Raina water supply scheme.[REF ID-503550762][TW-3] BILL/01691/2023-2024 1367/JJM 20/02/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LTD. 3.08 0.00 0 0
13 PURBA BARDHAMAN Burdwan Division Augmentation of ground water based RAINA PWSS to accommodate FHTC in Raina-I block under Burdwan Sub Division of Burdwan Division in Purba Bardhaman District , SM/09493 Augmentation Augmentation of RAINA Piped Water Supply Scheme with LDS, FHTC, Rising Main & Construction of 300 Cum capacity OHR with 20.0 Mtr. Staging height inclusive of soil test under Raina ¿ I Block, District - Purba Bardhaman. Assistant Engineer Burdwan Sadar Sub-Division PHE. DTE. JUNIOR ENGINEER BURDWAN SADAR SUB-DIVISION PHE DTE ORD/000600/2021-2022 1475/BWD 14/03/2022 360 RANADHIR SINHA 319.21 251.96 78.93 100
Total 3,393.62 270.97 7.98