Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
15 168.15 69.29 41.21  
1 MALDAH Malda Division Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation Acceptance cum formal work order for Sinking of ( 250mm. Dia. x 200mm. Dia ) Big dia Tube Well No - 3 ( 78.00 Mtr. deep ) by D.R. Rig method using P.V.C. pipe & Gravel Filter including supply of Materials at DALLA Water Supply Scheme of Habibpur Block under Malda Division P.H.E Dte in the District of Malda. Mr. Arnab Giri, Assistant Engineer Biswajit Gosh, Junior Engineer,Mukaddar Parvage, Junior Engineer ORD/000770/2022-2023 1428/MD 29/03/2023 30 ABHIJIT PAUL 6.86 5.98 87.17 100
2 MALDAH Malda Division Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation Acceptance cum formal work order for Sinking of ( 250mm. Dia. x 200mm. Dia ) Big dia Tube Well No - 4 ( 78.00 Mtr. deep ) by D.R. Rig method using P.V.C. pipe & Gravel Filter including supply of Materials at DALLA Water Supply Scheme of Habibpur Block under Malda Division P.H.E Dte in the District of Malda. (2nd Call) Mr. Arnab Giri, Assistant Engineer Biswajit Gosh, Junior Engineer,Mukaddar Parvage, Junior Engineer ORD/000771/2022-2023 1429/MD 29/03/2023 30 ABHIJIT PAUL 6.86 6.17 89.94 100
3 MALDAH Malda Mechanical Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation W.B.S.E.D.C.LTD Quotation charge at T/W No. IV of Dalla, Aiho C.C.C in the district of Malda Under Malda Mechanical Division PHE Dte. Assistant Engineer - II ORD/000924/2023-2024 3004413357 05/09/2023 90 W.B.S.E.D.C.LTD 4.77 4.77 100 100
4 MALDAH Malda Division Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation Acceptance cum formal work order for Extension of Pipe line and replacing of damage uPVC pipe line by different dia UPVC pipe for DALLA Piped Water Supply Scheme (Mouza-Dalla, JL No. 54) at Habibpur Dev. Block of Malda District under Malda Division, PHE Dte. Mr. Arnab Giri, Assistant Engineer Ziaur Rahaman, Junior Engineer ORD/000738/2022-2023 1210/MD 21/03/2023 45 TARUN KUMAR DEY 28.46 13.19 46.35 90
5 MALDAH Malda Mechanical Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation W.B.S.E.D.C.LTD Quotation charge at T/W No. III of Dalla, Aiho C.C.C in the district of Malda Under Malda Mechanical Division PHE Dte. BILL/02468/2023-2024 BP-2023-24-401 03/01/2024 W.B.S.E.D.C.LTD 4.25 0.00 0 0
6 MALDAH Malda Mechanical Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation W.B.S.E.D.C.LTD Quotation charge at T/W No. III of Dalla, Aiho C.C.C in the district of Malda Under Malda Mechanical Division PHE Dte. BILL/02468/2023-2024 BP-2023-24-401 03/01/2024 W.B.S.E.D.C.LTD 4.25 0.00 0 0
7 MALDAH Malda Division Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation Acceptance cum formal work order for Construction of 2 (two) Nos 3.60 mtr.X 3.00 mtr Switch Room cum chlorine room with Water Supply and sanitary arrangement in connection with source Augmentation of Dalla Piped Water Supply Scheme at Habibpur Block of Malda District under Malda Division, PHE Dte. Mr. Arnab Giri, Assistant Engineer Ziaur Rahaman, Junior Engineer ORD/000755/2022-2023 1303/MD 23/03/2023 45 M/S BHARATI CONSTRUCTION 8.34 4.16 49.88 100
8 MALDAH Malda Division Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation Replacement of ( 200 mm Dia. All through) Tubewell No.-1 (75 M deep) at Head Work Site by D.R Rig. Method using P.V.C. pipe & Gravel Filter including Supply of materials at DALLA Water Supply Scheme of Habibpur Block under Malda Division, P.H.E Dte in the District of Malda. Mr. Arnab Giri, Assistant Engineer Ziaur Rahaman, Junior Engineer ORD/000974/2023-2024 871/MD 27/02/2024 45 A. L. ENGINEERING SOLUTION 7.00 0.00 0 0
9 MALDAH Malda Division Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation Design, Supplying, Fabrication, Erection & Commissioning including 3 (three) months Trial Run of 30m³/hr. capacity Pressure type IRON ELIMINATION Plant for providing FHTC with Construction of Blower room & backwash water disposal at Tubewell no. 4 site of Dalla Water Supply Scheme of Habibpur Block under Malda Division P.H.E Dte in the District of Malda. Mr. Arnab Giri, Assistant Engineer Ziaur Rahaman, Junior Engineer ORD/001009/2023-2024 1185/MD 14/03/2024 180 MERCURY ENGINEERING COMPANY 16.64 0.00 0 0
10 MALDAH Malda Division Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation Design, Supplying, Fabrication, Erection & Commissioning including 3 (three) months Trial Run of 30m³/hr. capacity Pressure type IRON ELIMINATION Plant for providing FHTC with Construction of Blower room & backwash water disposal at Tubewell no. 3 site of Dalla Water Supply Scheme of Habibpur Block under Malda Division P.H.E Dte in the District of Malda. Mr. Arnab Giri, Assistant Engineer Ziaur Rahaman, Junior Engineer ORD/001008/2023-2024 1184/MD 14/03/2024 180 MERCURY ENGINEERING COMPANY 16.64 0.00 0 0
11 MALDAH Malda Division Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation Devlopment of 200 mm dia. (90 Mtr. Deep) Big dia. Tube Well at Head Work Site by using suitable Air compressor at DALLA Piped Water Supply Scheme of Habibpur Block under Malda Division, PHE Dte. Mr. Arnab Giri, Assistant Engineer Ziaur Rahaman, Junior Engineer ORD/000977/2023-2024 456/MD 19/01/2024 7 ABHIJIT PAUL 0.68 0.34 50 100
12 MALDAH Malda Division Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation Construction of Boundary Wall of Tubewell site at Dalla Mouza of Dalla Water Supply Scheme under Habibpur Block under Malda Division, PHE Dte. in the district of Malda. Mr. Arnab Giri, Assistant Engineer Ziaur Rahaman, Junior Engineer ORD/001018/2023-2024 1186/MD 14/03/2024 30 J. M. CONSTRUCTION 11.89 4.96 41.72 0
13 MALDAH Malda Mechanical Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. III & IV of Dalla Water Supply Scheme in the District of Malda under Malda Mechanical Division, PHE Dte. (TSM/016720) Assistant Engineer - II Junior Engineer-03 ORD/000560/2023-2024 2615/MLMD 10/08/2023 180 ANIMA ENTERPRISE 22.09 19.32 87.46 100
14 MALDAH Malda Division Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation Material Requisition To Resource Division RTOR000021/2024-2025 3997/MD 08/08/2024 Resource Division 7.39 0.00 0 0
15 MALDAH Malda Division Source Augmentation of Dalla Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/15079 Augmentation Acceptance cum formal work order for Extension of Pipe line and replacing of damage uPVC pipe line by different dia UPVC pipe for DALLA Piped Water Supply Scheme (Moua-Aragacchhi, JL-No. 57) at Habibpur Dev. Block of Malda District under Malda Division, PHE Dte. Mr. Arnab Giri, Assistant Engineer Ziaur Rahaman, Junior Engineer ORD/000736/2022-2023 1208/MD 21/03/2023 45 EUREKA UNEMPLOYED ENGINEERS CO-OPERATIVE SOCIETY LTD. 22.03 10.40 47.21 90
Total 168.13 69.29 41.21