Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
12 1,316.81 754.07 57.26  
1 MALDAH Gazole Malda Mechanical ARAZI JALSA PIPED WATER SUPPLY SCHEME. , SM/13734 New W.B.S.E.D.C.LTD Quotation charge at T/W No. I of ARAZI JALSA , Pandua C.C.C in the district of Malda Under Malda Mechanical Division PHE Dte. Assistant Engineer - II Junior Engineer-07 ORD/001899/2023-2024 3004481943 08/11/2023 90 W.B.S.E.D.C.LTD 9.23 9.23 100 100
2 MALDAH Gazole Malda Mechanical ARAZI JALSA PIPED WATER SUPPLY SCHEME. , SM/13734 New W.B.S.E.D.C.LTD Quotation charge at T/W No. II of ARAZI JALSA , Pandua C.C.C in the district of Malda Under Malda Mechanical Division PHE Dte. Assistant Engineer - II Junior Engineer-07 ORD/001900/2023-2024 3004481907 08/11/2023 90 W.B.S.E.D.C.LTD 4.21 4.21 100 100
3 MALDAH Gazole Malda Division ARAZI JALSA PIPED WATER SUPPLY SCHEME. , SM/13734 New Material Requisition To Resource Division RTOR000054/2023-2024 1811/MD 27/04/2023 0 Resource Division 11.31 0.00 0 0
4 MALDAH Gazole Malda Division ARAZI JALSA PIPED WATER SUPPLY SCHEME. , SM/13734 New Continuation work order for Hiring of 1 no diesel vehicle in good condition (traffic worthily) having licensed contract carriage permit from Regional Transport Authority for office of the Superintending Engineer, North Bengal Circle-II, PHE Dte. (Period from 10/05/2024 to 19/06/2024=41 Days). Mr. Prosanta Mandal, Assistant Engineer Mr. Sujit Sarkar, Junior Engineer ORD/000576/2024-2025 2421/MD 09/05/2024 41 TARUN KUMAR BHATTACHARYA 0.19 0.26 136.84 0
5 MALDAH Gazole Malda Division ARAZI JALSA PIPED WATER SUPPLY SCHEME. , SM/13734 New Construction of Boundary Wall at Head Work site of Arazi Jalsa Water Supply Scheme under Gazole Block under Malda Division, PHE Dte. in the district of Malda. Mr. Arnab Giri, Assistant Engineer Amit Karmakar, Junior Engineer ORD/000265/2024-2025 3213/MD 27/06/2024 431 LABANYA ENGINEERS CO-OPERATIVE SOCIETY LTD. 21.89 0.00 0 70
6 MALDAH Gazole Malda Division ARAZI JALSA PIPED WATER SUPPLY SCHEME. , SM/13734 New Material Requisition To Resource Division RTOR000096/2023-2024 29/MD 04/01/2024 0 Resource Division 20.40 0.00 0 0
7 MALDAH Gazole Malda Division ARAZI JALSA PIPED WATER SUPPLY SCHEME. , SM/13734 New Formal work order for the work of Implementation of ARAZI JALSA Water Supply Scheme at Gazole Block of Malda district under Malda Division, PHE Dte., Govt. of West Bengal. Mr. Arnab Giri, Assistant Engineer Amit Karmakar, Junior Engineer ORD/000046/2023-2024 2008/MD 17/05/2023 838 M/S TAPAS KUMAR CHAKRABORTY & CO 1,160.94 738.03 63.57 65
8 MALDAH Gazole Malda Mechanical ARAZI JALSA PIPED WATER SUPPLY SCHEME. , SM/13734 New Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I & II and making compound lighting arrangement at T/W no. I of Arazi Jalsa Water Supply Scheme in the District of Malda under Malda Mechanical Division, PHE Dte. (TSM/013468) Assistant Engineer - II Junior Engineer-07 ORD/000505/2023-2024 2575/MLMD 04/08/2023 756 NIRMAN. 26.75 0.00 0 87
9 MALDAH Gazole Malda Division ARAZI JALSA PIPED WATER SUPPLY SCHEME. , SM/13734 New Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM) at Arazi Jalsa Water Supply Scheme under Gazole Block under Malda Division, PHE Dte. in the district of Malda. Mr. Arnab Giri, Assistant Engineer Amit Karmakar, Junior Engineer ORD/000634/2024-2025 5913/MD 26/11/2024 309 EUREKA UNEMPLOYED ENGINEERS CO-OPERATIVE SOCIETY LTD. 28.74 0.00 0 0
10 MALDAH Gazole Malda Division ARAZI JALSA PIPED WATER SUPPLY SCHEME. , SM/13734 New Hiring of 1 no diesel vehicle in good condition (traffic worthily) having licensed contract carriage permit from Regional Transport Authority for office of the Superintending Engineer, North Bengal Circle-II, PHE Dte. (Period from 20/06/2024 to 16/12/2024=180 Days). Mr. Prosanta Mandal, Assistant Engineer Mr. Sujit Sarkar, Junior Engineer ORD/000577/2024-2025 3108/MD 18/06/2024 180 TARUN KUMAR BHATTACHARYA 0.86 1.41 163.95 0
11 MALDAH Gazole Malda Division ARAZI JALSA PIPED WATER SUPPLY SCHEME. , SM/13734 New Continuation work order for Hiring of 1 no diesel vehicle in good condition (traffic worthily) having licensed contract carriage permit from Regional Transport Authority for office of the Superintending Engineer, North Bengal Circle-II, PHE Dte. (Period from 20/06/2024 to 16/12/2024=180 Days). Vehicle no. WB 65A/4911.Hiring of 1 no diesel vehicle in good condition (traffic worthily) having licensed contract carriage permit from Regional Transport Authority for office of the Superintending Engineer, North Bengal Circle-II, PHE Dte. (Period from 17/12/2024 to 14/06/2025=180 Days). Mr. Prosanta Mandal, Assistant Engineer Mr. Sujit Sarkar, Junior Engineer ORD/000918/2024-2025 6328/MD 16/12/2024 180 USHA ENTERPRISE 0.86 0.93 108.14 0
12 MALDAH Gazole Malda Division ARAZI JALSA PIPED WATER SUPPLY SCHEME. , SM/13734 New Design, Supplying, Fabrication, Erection & Commissioning including 3 (three) months Trial Run of 80m³/hr. capacity Pressure type IRON ELIMINATION Plant with Construction of Blower room & backwash water disposal at head work site of Arazi Jalsha Water Supply Scheme of Gazole Dev. Block under Malda Division P.H.E Dte in the District of Malda. Mr. Arnab Giri, Assistant Engineer Amit Karmakar, Junior Engineer ORD/000133/2025-2026 2507/MD 29/05/2025 135 WIST WATER SOLUTIONS 31.43 0.00 0 0
Total 1,316.81 754.06 57.26