Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
9 | 341.63 | 151.12 | 44.23 | ||||||||||||||
1 | MALDAH | Harischandrapur - I | Malda Division | Ground Water Based for Tulshihatta Zone-I Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/11590 | New | Acceptance cum formal work order for Route survey, design and preparation of DPR of Tulshihatta Zone-I Piped Water Supply Scheme at Harishchandrapur-I Dev. Block under Malda Division, PHE Dte. | Mr. Sumit Kumar Ghosh, Assistant Engineer | Mr. Tilok Roy, Junior Engineer | ORD/000689/2021-2022 | 654/MD | 22/03/2022 | 15 | M/S SOBHA & CO. | 3.42 | 3.42 | 100 | 1 |
2 | MALDAH | Harischandrapur - I | Malda Division | Ground Water Based for Tulshihatta Zone-I Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/11590 | New | Material Requisition To Resource Division | RTOR000057/2023-2024 | 1811/MD | 27/04/2023 | Resource Division | 17.88 | 0.00 | 0 | 0 | |||
3 | MALDAH | Harischandrapur - I | Malda Division | Ground Water Based for Tulshihatta Zone-I Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/11590 | New | Formal work order for the work of Laying Distribution pipe line for TULSHIHATA (ZONE-I) & its adjoining mouzas Piped Water Supply at Harishchandrapur-I Block in the District Malda under Malda Division, PHE Dte. (2nd Call). | Mr. Sumit Kumar Ghosh, Assistant Engineer | Mr. Tilok Roy, Junior Engineer | ORD/000271/2022-2023 | 2129/MD | 16/09/2022 | 60 | BANIK BROTHERS | 168.65 | 101.34 | 60.09 | 36 |
4 | MALDAH | Harischandrapur - I | Malda Mechanical | Ground Water Based for Tulshihatta Zone-I Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/11590 | New | Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I, II of Tulshihata (zone-I) Water Supply Scheme in the District of Malda under Malda Mechanical Division, PHE Dte. (TSM/011266) | Assistant Engineer - II | Junior Engineer-05 | ORD/000698/2023-2024 | 2773/MLMD | 14/08/2023 | 180 | SUDIP DEY | 25.60 | 10.34 | 40.39 | 0 |
5 | MALDAH | Harischandrapur - I | Malda Division | Ground Water Based for Tulshihatta Zone-I Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/11590 | New | Material Requisition To Resource Division | RTOR000015/2022-2023 | 1874/MD | 16/08/2022 | Resource Division | 18.81 | 0.00 | 0 | 0 | |||
6 | MALDAH | Harischandrapur - I | Malda Division | Ground Water Based for Tulshihatta Zone-I Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/11590 | New | Material Requisition To Resource Division | RTOR000103/2023-2024 | 33/MD | 04/01/2024 | Resource Division | 12.32 | 0.00 | 0 | 0 | |||
7 | MALDAH | Harischandrapur - I | Malda Division | Ground Water Based for Tulshihatta Zone-I Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/11590 | New | Acceptance cum formal work order for Emergent Laying of pipe line along NH-81 for restoring drinking water supply towards Rarial Village from TULSHIHATTA Piped Water Supply Scheme, Harishchandrapur I Block, under Malda Division, PHE Dte. in the District of Malda. | Mr. Sumit Kumar Ghosh, Assistant Engineer | Mr. Sanjit Sarkar, Junior Engineer | ORD/000076/2023-2024 | 2075/MD | 30/05/2023 | 15 | S. N. CONSTRUCTION | 10.18 | 0.00 | 0 | 100 |
8 | MALDAH | Harischandrapur - I | Malda Division | Ground Water Based for Tulshihatta Zone-I Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/11590 | New | Material Requisition To Resource Division | RTOR000009/2024-2025 | 3921/MD | 06/08/2024 | Resource Division | 4.31 | 0.00 | 0 | 0 | |||
9 | MALDAH | Harischandrapur - I | Malda Division | Ground Water Based for Tulshihatta Zone-I Piped Water Supply Scheme under Malda Division, PHE Dte. , SM/11590 | New | Providing Functional Household Tap Connection (FHTC) in connection with Jal Jeevan Mission (JJM) under command area of Tulshihatta Zone-I Water Supply Scheme at Harishchandrapur-I Dev. Block under Malda Division, PHE Dte. in the district of Malda. | Mr. Sumit Kumar Ghosh, Assistant Engineer | Mr. Sanjit Sarkar, Junior Engineer | ORD/000455/2023-2024 | 3372/MD | 29/08/2023 | 45 | M/S SABANA CONSTRUCTION | 80.46 | 36.02 | 44.77 | 85 |
Total | 341.65 | 151.13 | 44.23 |