Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
4 62.98 5.25 8.34  
1 DAKSHIN DINAJPUR Balurghat Division Providing Functional House Hold Tap Connection (part)Under Jal Swapna Programme and Prepartion of DPR in connection with Augmentation for K.D Trimohini Piped Water Supply Scheme Zone II at Hili Block in the District of Dakshin Dinajpur under Balurghat , SM/09780 Augmentation Providing Functional House Hold Tap Connection Under Jal Swapna Programme under Augmentation for K. D. Trimohini Zone II Piped Water Supply Scheme at Hili Block in the District of Dakshin Dinajpur under Balurghat Division P.H.Engineering Dte. (Phase- I) [Work Order No. 1919/BSSD Dated :- 01/12/2021 & Tender No. 414 of 2021-2022] VCH/000163/2022-2023 BP-2022-23-21 16/04/2022 APURBA KUMAR SARKAR 3.52 0.00 0 0
2 DAKSHIN DINAJPUR Balurghat Division Providing Functional House Hold Tap Connection (part)Under Jal Swapna Programme and Prepartion of DPR in connection with Augmentation for K.D Trimohini Piped Water Supply Scheme Zone II at Hili Block in the District of Dakshin Dinajpur under Balurghat , SM/09780 Augmentation Conducting Route Survey, investigation of existing scheme, Design of distribution Network and Prepartion of DPR to provide FHTC in connection with Augmentation of K.D Trimohini Piped Water Supply Scheme (Zone - II) at Hili Block in the District of Dakshin Dinajpur under Balurghat Division P.H.Engineering Dte. Junior Engineer Hili ORD/000537/2021-2022 549/RWS 03/12/2021 15 M/S. SOBHA & CO. 4.31 4.31 100 1
3 DAKSHIN DINAJPUR Balurghat Division Providing Functional House Hold Tap Connection (part)Under Jal Swapna Programme and Prepartion of DPR in connection with Augmentation for K.D Trimohini Piped Water Supply Scheme Zone II at Hili Block in the District of Dakshin Dinajpur under Balurghat , SM/09780 Augmentation Providing Functional House Hold Tap Connection in connection with Retrofitting for K.D. Trimohini Zone-II Piped Water Supply Scheme at Hili Block in the District of Dakshin Dinajpur under Balurghat Division, P.H.Engineering Dte. Assistant Engineer RWS Junior Engineer Hili ORD/000252/2022-2023 3942/BD 31/03/2023 45 SAPTADIP CONSTRUCTION 50.30 0.00 0 0
4 DAKSHIN DINAJPUR Balurghat Division Providing Functional House Hold Tap Connection (part)Under Jal Swapna Programme and Prepartion of DPR in connection with Augmentation for K.D Trimohini Piped Water Supply Scheme Zone II at Hili Block in the District of Dakshin Dinajpur under Balurghat , SM/09780 Augmentation Acceptance cum work order for the work of Providing Functional House Hold Tap Connection Under Jal Swapna Programme under Augmentation for K. D. Trimohini Zone II Piped Water Supply Scheme at Hili Block in the District of Dakshin Dinajpur under Balurghat Division P.H.Engineering Dte. (Phase- I) Assistant Engineer RWS Junior Engineer Hili ORD/000339/2021-2022 1919/BSSD 01/12/2021 25 APURBA KUMAR SARKAR 4.85 0.94 19.38 0
Total 62.97 5.25 8.34