Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
8 1,090.96 100.24 9.19  
1 UTTAR DINAJPUR Islampur Malda Mechanical DHANTOLA PIPED WATER SUPPLY SCHEME AT ISLAMPUR BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/13717 New W.B.S.E.D.C.LTD Quotation charge at P/H No. I of DHANTOLA, Islampur C.C.C in the district of Uttar Dinajpur Under Malda Mechanical Division PHE Dte. Assistant Engineer - I ORD/000984/2023-2024 4003229554 13/09/2023 90 W.B.S.E.D.C.LTD 4.14 4.14 100 100
2 UTTAR DINAJPUR Islampur Raiganj Division DHANTOLA PIPED WATER SUPPLY SCHEME AT ISLAMPUR BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/13717 New Material Requisition To Resource Division RTOR000116/2022-2023 603/RD/PHE 27/02/2023 0 Resource Division 109.00 0.00 0 0
3 UTTAR DINAJPUR Islampur Malda Mechanical DHANTOLA PIPED WATER SUPPLY SCHEME AT ISLAMPUR BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/13717 New Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I , II & III and making compound lighting arrangement at T/W no. I of Dhantola Water Supply Scheme in the District of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (TSM/014170) Assistant Engineer - I Junior Engineer-02 ORD/000493/2023-2024 2494/MLMD 04/08/2023 817 ALOK ENTERPRISE, A UNIT OF SAKET TREXIM PVT. LTD.. 42.27 24.49 57.94 58
4 UTTAR DINAJPUR Islampur Raiganj Division DHANTOLA PIPED WATER SUPPLY SCHEME AT ISLAMPUR BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/13717 New Construction of Boundary Wall with Gate at Head Work Site, 2nd & 3rd Tube-Well Site under DHANTOLA Piped Water Supply Scheme at Islampur Block under Raiganj Division, PHE Dte. in the District of Uttar Dinajpur. Assistant Engineer HQ,Assistant Engineer ISD,Assistant Engineer RWS SD Junior Engineer, ISD ORD/000456/2023-2024 564/RD/PHE 05/03/2024 180 M/S CAMELLIA CONSTRUCTION AND CO. 27.65 25.48 92.15 100
5 UTTAR DINAJPUR Islampur Raiganj Division DHANTOLA PIPED WATER SUPPLY SCHEME AT ISLAMPUR BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/13717 New Implementation of DHANTALA and it's adjoining mouzas Pipe Water Supply Scheme at Islampur Block of Uttar Dinajpur District under Raiganj Division.(Sinking of Tube Well, Laying of Rising Main, Laying Distribution pipe line,Providing Functional house Hold Tap Connections, OHR, Pump House Head Work, 2nd & 3rdTube Well.) Assistant Engineer ISD Junior Engineer, ISD ORD/000331/2022-2023 674/RD/PHE 06/03/2023 757 UNIVERSAL ENGINEERS CO-OPERATIVE SOCIETY LTD. 840.35 46.13 5.49 6
6 UTTAR DINAJPUR Islampur Raiganj Division DHANTOLA PIPED WATER SUPPLY SCHEME AT ISLAMPUR BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/13717 New Construction Of Approach Road at Head Work Site, & 2nd Tube-Well Site under New Scheme of Dhantola PWSS at Islampur Block under Raiganj Division, PHE dte. Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD Junior Engineer, ISD ORD/000166/2024-2025 2894/RD/PHE 25/09/2024 20 SHANKAR SAHA 4.31 0.00 0 0
7 UTTAR DINAJPUR Islampur Raiganj Division DHANTOLA PIPED WATER SUPPLY SCHEME AT ISLAMPUR BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/13717 New Providing FHTC in connection with Dhantaola Pipe Water Supply Scheme at Islampur Block of Uttar Dinajpur District under Raiganj Division.(New PWSS) Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD Junior Engineer, ISD ORD/000507/2024-2025 52/RD/PHE 03/01/2025 45 M/S J.S.B ASSOCIATE CONSTRUCTION NAMEDUTTA@GMAIL.COM 8.23 0.00 0 0
8 UTTAR DINAJPUR Islampur Raiganj Division DHANTOLA PIPED WATER SUPPLY SCHEME AT ISLAMPUR BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/13717 New Laying of Additional pipeline with other ancillary works at different mouzas of DHANTALA PWSS under Islampur Sub-Division P.H.E. Dte. Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD Junior Engineer, ISD ORD/000372/2024-2025 3491/RD/PHE 02/12/2024 45 M/S LOKENATH CONSTRUCTION (SUDARSHANPUR) 55.01 0.00 0 0
Total 1,090.96 100.24 9.19