Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 7,354.28 131.74 1.79  
1 UTTAR DINAJPUR Chopra Raiganj Division BARA DOPAHARU Piped Water Supply Scheme , SM/12396 New Material Requisition To Resource Division RTOR000004/2023-2024 1036/RD/PHE 04/04/2023 0 Resource Division 25.91 0.00 0 0
2 UTTAR DINAJPUR Chopra Malda Mechanical BARA DOPAHARU Piped Water Supply Scheme , SM/12396 New Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I & II and making compound lighting arrangement at T/W no. I of Bara Dopaharu Water Supply Scheme in the District of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (TSM/014803) Assistant Engineer - I Junior Engineer-02 ORD/000454/2023-2024 2478/MLMD 04/08/2023 802 ANIMA ENTERPRISE 28.34 21.02 74.17 74
3 UTTAR DINAJPUR Chopra Malda Mechanical BARA DOPAHARU Piped Water Supply Scheme , SM/12396 New Quotation for new service connection at BARA DOPAHARU PH-I (Chopra ccc) in the district of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (SM/12396) BILL/01086/2024-2025 BP-2024-25-307 05/06/2024 0 W.B.S.E.D.C.LTD 18.64 0.00 0 0
4 UTTAR DINAJPUR Chopra Raiganj Division BARA DOPAHARU Piped Water Supply Scheme , SM/12396 New Laying of additional pipeline for improving FHTC with ancillary works at different mouzas at BARA DOPAHARU PWSS Of CHOPRA Block under Islampur Sub-Division P.H.E. Dte. (2nd Call) Assistant Engineer HQ,Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD ORD/000385/2025-2026 2097/RD/PHE 15/07/2025 180 M/S SACHIN KUMAR 43.32 0.00 0 0
5 UTTAR DINAJPUR Chopra Raiganj Division BARA DOPAHARU Piped Water Supply Scheme , SM/12396 New Providing FHTC in connection with Bara Dopaharu Pipe Water Supply Scheme at Chopra Block of Uttar Dinajpur District under Raiganj Division.(New PWSS) (2nd Call) Assistant Engineer HQ,Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD ORD/000389/2025-2026 2174/RD/PHE 25/07/2025 90 M/S SHIB ENTERPRISE 5.40 0.00 0 0
6 UTTAR DINAJPUR Chopra Raiganj Division BARA DOPAHARU Piped Water Supply Scheme , SM/12396 New Sinking of Tube Well, laying of rising main & distribution system, providing FHTC ,construction of Over Head Reservoir over Pile / Raft Foundation including subsoil investigation, construction of Pump House, Chlorine room, Boundary Wall & Approach Road and allied works for 19 nos. Piped water supply Schemes within CHOPRA Dev. Block of Uttar Dinajpur District under Raiganj Division PHE Dte. Assistant Engineer ISD Junior Engineer, ISD ORD/000372/2023-2024 2567/RD/PHE 01/09/2023 805 ROY ENGINEERS. (PATNA) 7,213.93 110.72 1.53 30
7 UTTAR DINAJPUR Chopra Raiganj Division BARA DOPAHARU Piped Water Supply Scheme , SM/12396 New Designing, Supplying, Febrication, Erection on suitable RCC foundation, commissioning with 3(three) months Trial Run (including cost of routine testing of water sample and flow/hr for performance evaluation) of pressure type Iron Removal Plant as per design norms of CPHEEO(latest) with necessary accessories for Bara Dopaharu Water Supply Scheme at Chopra Block under Raiganj Division, P.H.E. Dte. Dist:- Uttar Dinajpur, Capacity- 40 M3/hr. Assistant Engineer HQ,Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD ORD/000310/2025-2026 1978/RD/PHE 03/07/2025 180 MONDAL PRECISION PRIVATE LIMITED 18.74 0.00 0 0
Total 7,354.29 131.74 1.79