Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 553.44 184.45 33.33  
1 UTTAR DINAJPUR Raiganj Malda Mechanical KULIARA ANANTAPUR PWSS IN RAIGANJ BLOCK IN UTTAR DINAJPUR , SM/11821 New W.B.S.E.D.C.LTD Quotation charge at T/W No.I of Kuliara Anantapur PWSS , Raiganj C.C.C in the district of Uttar Dinajpur Under Malda Mechanical Division PHE Dte. Assistant Engineer - I Junior Engineer-07 ORD/001884/2023-2024 4003203670 02/08/2023 90 W.B.S.E.D.C.LTD 8.31 8.31 100 100
2 UTTAR DINAJPUR Raiganj Raiganj Division KULIARA ANANTAPUR PWSS IN RAIGANJ BLOCK IN UTTAR DINAJPUR , SM/11821 New Material Requisition To Resource Division RTOR000076/2022-2023 521/RD/PHE 20/02/2023 0 Resource Division 33.03 0.00 0 0
3 UTTAR DINAJPUR Raiganj Raiganj Division KULIARA ANANTAPUR PWSS IN RAIGANJ BLOCK IN UTTAR DINAJPUR , SM/11821 New Material Requisition To Resource Division RTOR000097/2022-2023 521/RD/PHE 20/02/2023 0 Resource Division 32.76 0.00 0 0
4 UTTAR DINAJPUR Raiganj Malda Mechanical KULIARA ANANTAPUR PWSS IN RAIGANJ BLOCK IN UTTAR DINAJPUR , SM/11821 New W.B.S.E.D.C.LTD Quotation charge at T/W No. II of KULIARA ANANTAPUR PWSS ,Raiganj C.C.C in the district of Uttar Dinajpur Under Malda Mechanical Division PHE Dte. BILL/02584/2023-2024 BP-2023-24-465 26/01/2024 0 W.B.S.E.D.C.LTD 0.45 0.00 0 0
5 UTTAR DINAJPUR Raiganj Malda Mechanical KULIARA ANANTAPUR PWSS IN RAIGANJ BLOCK IN UTTAR DINAJPUR , SM/11821 New Modified Quotation Charge at TW No- II of Kuliara Anantapur, Raiganj CCC in the dist of Uttar Dinajpur Under Malda Mechanical Division PHE Dte. BILL/00237/2024-2025 BP-2024-25-98 16/04/2024 0 W.B.S.E.D.C.LTD 7.84 0.00 0 0
6 UTTAR DINAJPUR Raiganj Raiganj Division KULIARA ANANTAPUR PWSS IN RAIGANJ BLOCK IN UTTAR DINAJPUR , SM/11821 New Implementation of KULIARA ANANTAPUR and it's adjoining mouzas Pipe Water Supply Scheme at Raiganj Block of Uttar Dinajpur District under Raiganj Division, PHE Dte. (2nd Call) Assistant Engineer RSD Junior Engineer, RSD ,Junior Engineer, RWS ORD/000218/2022-2023 96/RD/PHE 19/01/2023 1078 UNIVERSAL ENGINEERS CO-OPERATIVE SOCIETY LTD. 369.00 144.38 39.13 45
7 UTTAR DINAJPUR Raiganj Raiganj Division KULIARA ANANTAPUR PWSS IN RAIGANJ BLOCK IN UTTAR DINAJPUR , SM/11821 New Construction of Pump House & Boundary Wall at Kuliara Anantapur Pipe Water Supply Scheme at Raiganj Block of Uttar Dinajpur District under Raiganj Division.( Pump House at Head Work, 2nd Tube Well and Boundary Wall at Head work Site and 2nd Tube-Well. ) Assistant Engineer RSD Junior Engineer, RSD ORD/000255/2022-2023 382/RD/PHE 08/02/2023 781 M/S. BANGARAJ ASHOKLALRNJ@GMAIL.COM 36.13 13.57 37.56 70
8 UTTAR DINAJPUR Raiganj Malda Mechanical KULIARA ANANTAPUR PWSS IN RAIGANJ BLOCK IN UTTAR DINAJPUR , SM/11821 New Supply, installation, commissioning and trial operation of electro-mechanical components of T/W no. I & II and making compound lighting arrangement at T/W no. I of Kuliara Anantapur Water Supply Scheme in the District of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (TSM/011943) Assistant Engineer - I Junior Engineer-07 ORD/001802/2023-2024 3689/MLMD 29/11/2023 655 MANIK CHANDRA SAHA. 25.33 18.19 71.81 78
9 UTTAR DINAJPUR Raiganj Raiganj Division KULIARA ANANTAPUR PWSS IN RAIGANJ BLOCK IN UTTAR DINAJPUR , SM/11821 New Balance pipe line for providing functional household tap connection (FHTC), approach road with land development of headwork site & 2nd tubewell site and road restoration of Kuliara Anantapur PWSS at Raiganj Block under Raiganj Division, PHE Dte., Uttar Dinajpur. Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD Junior Engineer, RSD ORD/000438/2024-2025 3750/RD/PHED 18/12/2024 135 M/S LOKENATH CONSTRUCTION (SUDARSHANPUR) 40.59 0.00 0 0
Total 553.45 184.45 33.33