Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 166.84 86.46 51.82  
1 COOCHBEHAR Coochbehar Division Rejuvenation of NAGARERBARI Piped Water Supply Scheme , SM/10219 Augmentation Sinking of 250mm x 200 mm Big dia. Tube well with UPVC Pipes & Strainer at 3rd Site of NAGARERBARI ZONE I & II PWSS under Cooch Behar Division PHE Dte. ASSISTANT ENGINEER, HEAD QUARTER,COOCHBEHAR DIVISION JUNIOR ENGINEER, HEAD QUARTER, COOCH BEHAR DIVISION ORD/000456/2021-2022 1443/CD 10/03/2022 30 MS DD ENTERPRISE 21.40 20.06 93.74 1
2 COOCHBEHAR Coochbehar Division Rejuvenation of NAGARERBARI Piped Water Supply Scheme , SM/10219 Augmentation Laying of Pipe line at controllerhat under NAGARERBARI Zone-I PWSS under Cooch Behar Division, PHED ASSISTANT ENGINEER, HEAD QUARTER,COOCHBEHAR DIVISION JUNIOR ENGINEER, HEAD QUARTER, COOCH BEHAR DIVISION ORD/000402/2021-2022 1460/CD 10/03/2022 30 KARTICK CH SEAL 6.25 6.25 100 1
3 COOCHBEHAR Coochbehar Division Rejuvenation of NAGARERBARI Piped Water Supply Scheme , SM/10219 Augmentation Providing FHTC Laying Of Pipe Line And Construction Of Boundary Wall And Pump House at 3rd Site of NAGARERBARI (ZONE-I) PWSS under JAL JEEVAN MISSION ASSISTANT ENGINEER, HEAD QUARTER,COOCHBEHAR DIVISION JUNIOR ENGINEER, HEAD QUARTER, COOCH BEHAR DIVISION ORD/000199/2022-2023 674/CD 23/08/2022 60 GOUTAM KUMAR DAS 67.90 55.38 81.56 1
4 COOCHBEHAR Coochbehar Division Rejuvenation of NAGARERBARI Piped Water Supply Scheme , SM/10219 Augmentation Laying of pipe line at Controllerhat under Nagarerbari Zone-I PWSS under Cooch Behar Division, PHE Dte. ASSISTANT ENGINEER, HEAD QUARTER,COOCHBEHAR DIVISION JUNIOR ENGINEER, HEAD QUARTER, COOCH BEHAR DIVISION ORD/000390/2022-2023 77/SD 13/05/2022 30 KARTICK CH SEAL 4.93 4.77 96.75 1
5 COOCHBEHAR Coochbehar Division Rejuvenation of NAGARERBARI Piped Water Supply Scheme , SM/10219 Augmentation Execution of different works related to RAKHALMARI PWSS under JAL JEEVAN MISSION ORD/000080/2024-2025 1188/CD 18/06/2024 90 NEW GOLDEN COOPARATIVE LAB CONT & CONSTN SOCY .LTD 32.46 0.00 0 0
6 COOCHBEHAR Coochbehar Division Rejuvenation of NAGARERBARI Piped Water Supply Scheme , SM/10219 Augmentation Execution of different works (Within the area of LAWCHAPRA) related to NAGARERBARI PWSS under JAL JEEVAN MISSION PART D. ASSISTANT ENGINEER, COOCHBEHAR SADAR SUB-DIVISION JUNIOR ENGINEER, COOCH BEHAR SADAR SUB-DIVISION ORD/000531/2023-2024 326/CD 09/02/2024 60 BIJOY ROY 33.90 0.00 0 90
Total 166.83 86.45 51.82