Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
25 | 1,227.4 | 263.34 | 21.46 | ||||||||||||||
1 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | OHR MONDAL GHAT | VCH/001247/2021-2022 | BP-2021-22-391 | 17/03/2022 | M/S R.N. TRADERS | 51.64 | 0.00 | 0 | 0 | ||||
2 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | Continuation order for Maintenance of pipe line & others Mise. Work related to pipe line Mtc. Of I.E plant for MondalghatP/ W/S/S under Jalpaiguri Division PHE Dte. Period from 01.07.2021 to 31.12.2021 | Junior Engineer | ORD/000723/2021-2022 | 400/RWS | 30/06/2021 | 180 | UNITED CONSTRUCTION | 2.01 | 0.00 | 0 | 1 | ||
3 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | CONST B-WALL FOR MONDALGHAT PWSS | VCH/001264/2021-2022 | BP-2021-22-495 | 29/03/2022 | M/S UNITED CONSTRUCTION | 3.51 | 0.00 | 0 | 0 | ||||
4 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | CONSTRUCTION 550 M3 AUG MANDALGHAT PWSS | VCH/001306/2021-2022 | BP-2021-22-391 | 17/03/2022 | R.N.TRADER'S | 51.64 | 0.00 | 0 | 0 | ||||
5 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | LDS MONDALGHAT | VCH/001386/2021-2022 | BP-2021-22-514 | 30/03/2022 | M/S SURAJIT DEY AND CO. | 71.57 | 0.00 | 0 | 0 | ||||
6 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | providing drainage system for mondalghat pwss | VCH/000021/2022-2023 | BP-2021-23-7 | 21/04/2022 | M/S RATAN KUMAR DAS GUPTA AND CO | 1.72 | 0.00 | 0 | 0 | ||||
7 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | SOIL TEST FOR MANDALGHAT | VCH/001437/2021-2022 | BP-2021-22 | 22/03/2022 | R.B TESTING | 2.02 | 0.00 | 0 | 0 | ||||
8 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | PROVIDING DRAINAGE SYSTEM FOR MONDALGHAT PWSS | VCH/000057/2022-2023 | BP-2021-22-7 | 21/04/2022 | M/S RATAN KUMAR DAS GUPTA AND CO | 1.72 | 0.00 | 0 | 0 | ||||
9 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | FHTC GRASS MORE | VCH/000061/2022-2023 | BP-2021-22-25 | 26/04/2022 | M/S R.N. TRADERS | 7.08 | 0.00 | 0 | 0 | ||||
10 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | LAYING DISTRIBUTION SYSTEM AND FUNCTIONAL HOUSEHOLD TAP CONNECTION FOR AUGMENTATION OF MONDALGHAT PIPED WATER SUPPLY SCHEME BLOCK SADAR DISTRICT JALPAIGURI (PART-A). | Junior Engineer | ORD/000446/2021-2022 | 342/JD | 03/02/2022 | 90 | M/S R.N. TRADERS | 158.04 | 0.00 | 0 | 1 | ||
11 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | OHR MONDALGHAT | VCH/000251/2022-2023 | BP-2022-23-67 | 04/07/2022 | M/S R.N. TRADERS | 6.02 | 0.00 | 0 | 0 | ||||
12 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | LDS FHTC FOR MONDALGHAT | VCH/000254/2022-2023 | BP-2022-23-62 | 04/07/2022 | M/S R.N. TRADERS | 65.57 | 0.00 | 0 | 0 | ||||
13 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | LAYING DISTRIBUTION SYSTEM AND FUNCTIONAL HOUSEHOLD TAP CONNECTION FOR AUGMENTATION OF MONDALGHAT PIPED WATER SUPPLY SCHEME BLOCK SADAR DISTRICT JALPAIGURI (PART-B). | Junior Engineer | ORD/000465/2021-2022 | 345/JD | 03/02/2022 | 90 | M/S SURAJIT DEY AND CO. | 195.60 | 2.98 | 1.52 | 1 | ||
14 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | Installation of Iron Elimination Plant (IEP) including construction of concrete platform & drain at Head work site for Augmentation Mondalghat piped Water Supply Scheme under Jalpaiguri Division, P.H.E. Dte. | Junior Engineer | ORD/000615/2021-2022 | 402/JD | 11/02/2022 | 45 | M/S R.N. TRADERS | 27.54 | 22.98 | 83.44 | 1 | ||
15 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | Construction of 550 m3 capacity 20 Mtr. Staging height RCC Over Head Reservoir as per Departmental Design & drawing including pipe connection and cost of pipes, specials for AUGMENTATION OF MANDALGHAT PWSS, Block- Jalpaiguri, District : Jalpaiguri, under Jalpaiguri Division P.H.E. Dte. | Junior Engineer | ORD/000447/2021-2022 | 336/JD | 02/02/2022 | 120 | M/S R.N. TRADERS | 110.23 | 52.52 | 47.65 | 1 | ||
16 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | Construction of boundary wall with drain for 3rd site of Mondal ghat piped water supply scheme under Jalpaiguri Division, P.H.E. Dte. | ORD/000283/2022-2023 | 648/RWS | 21/10/2022 | 30 | ALICK DUTTA | 4.84 | 4.81 | 99.38 | 100 | |||
17 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | LAYING DISTRIBUTION SYSTEM AND FUNCTIONAL HOUSEHOLD TAP CONNECTION FOR AUGMENTATION OF MONDALGHAT PIPED WATER SUPPLY SCHEME BLOCK SADAR DISTRICT JALPAIGURI (PART-D). | Junior Engineer | ORD/000460/2021-2022 | 339/JD | 03/02/2022 | 90 | BISWANATH GHOSH | 150.63 | 91.81 | 60.95 | 60 | ||
18 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | Material Requisition To Resource Division | RTOR000014/2021-2022 | 550/JD | 01/03/2022 | Resource Division | 60.75 | 0.00 | 0 | 0 | ||||
19 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | Construction of valve chember & Blower room(3.60MX3.00M ) Size for Iron Elimination Plant at Head Work Site of Mondalghat piped Water Supply Scheme under Jalpaiguri Division, P.H.E. Dte. | Assistant Engineer | Junior Engineer | ORD/000043/2023-2024 | 390/RWS | 25/04/2023 | 14 | SWAPAN SAHA | 4.80 | 2.25 | 46.88 | 100 | |
20 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | Repair work of Pump house , bath room of H/W site & ancilliary works at Mondalghat PWSS under Jalpaiguri Division. | Assistant Engineer | Junior Engineer | ORD/000487/2022-2023 | 285/RWS | 29/03/2023 | 14 | M/S UNITED CONSTRUCTION | 1.53 | 0.73 | 47.71 | 100 | |
21 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | Construction of Boundary wall and land development at Head Work Site for Mandalghat Water Supply Scheme under Jalpaiguri Division P.H.E. Dte | ORD/000136/2021-2022 | 1442/JD | 09/09/2021 | 30 | M/S UNITED CONSTRUCTION | 10.53 | 3.51 | 33.33 | 100 | |||
22 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | Sinking of 250mm x 150mm dia tubewell by Reverse Rotary method of drilling for Augmentation of Mandolghat PWSS under JJM work at Jalpaiguri sadar Block under PHE Dte., Jalpaiguri Division | Assistant Engineer | Junior Engineer | ORD/000334/2023-2024 | 1082/RWS | 19/09/2023 | 30 | TIRTHANKAR CHOWDHURY | 9.24 | 4.51 | 48.81 | 100 | |
23 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | LAYING DISTRIBUTION SYSTEM AND FUNCTIONAL HOUSEHOLD TAP CONNECTION FOR AUGMENTATION OF MONDALGHAT PIPED WATER SUPPLY SCHEME BLOCK SADAR DISTRICT JALPAIGURI (PART-C). | Assistant Engineer | Junior Engineer | ORD/000459/2021-2022 | 338/JD | 03/02/2022 | 90 | SIBU DEY | 212.74 | 69.43 | 32.64 | 75 | |
24 | JALPAIGURI | Jalpaiguri Division | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | Reparing of pump houses & construction of Boundary wall at 2nd site for Mandalghat W/S/S under Jalpaiguri Division , P.H.E Dte | Assistant Engineer | Junior Engineer | ORD/000278/2021-2022 | 820/RWS | 30/11/2021 | 30 | ALICK DUTTA | 4.83 | 2.30 | 47.62 | 99 | |
25 | JALPAIGURI | Northern Mechanical | Augmentation of Mondalghat Water Supply Scheme. , SM/10087 | Augmentation | Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for AUGMENTATION OF MANDALGHAT PWSS, TW NO I in the district of Jalpaiguri under Northern Mechanical Division, PHE Dte. | Assistant Engineer | Junior Engineer | ORD/000235/2023-2024 | 1250/NMD | 31/07/2023 | 30 | M/S ANJALI ENTERPRISE | 11.60 | 5.51 | 47.5 | 90 | |
Total | 1,227.39 | 263.34 | 21.46 |