Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
9 21,948.01 116.02 0.53  
1 DARJEELING Phansidewa Siliguri W/S Division PURBBA BANSGAON CHAKLA PIPED WATER SUPPLY SCHEME ( ZONE- I & II ) , SM/15929 New Preparation of Details Project Report (DPR) incl. route survey in connection with proposed Purba Bansgaon Chakla Piped water supply schemes at the uncovered mouzas under Phansidewa Block of Siliguri Sub Division, PHE Dte. Assistant Engineer(Civil) Junior Engineer(Civil) ORD/000330/2022-2023 412/SSD 28/07/2022 20 ENVIROTECH SOLUTIONS 3.69 3.69 100 0
2 DARJEELING Phansidewa Siliguri W/S Division PURBBA BANSGAON CHAKLA PIPED WATER SUPPLY SCHEME ( ZONE- I & II ) , SM/15929 New Material Requisition To Resource Division RTOR000014/2023-2024 212/SWSD 25/04/2023 0 Resource Division 23.82 0.00 0 0
3 DARJEELING Phansidewa Siliguri W/S Division PURBBA BANSGAON CHAKLA PIPED WATER SUPPLY SCHEME ( ZONE- I & II ) , SM/15929 New Material Requisition To Resource Division RTOR000057/2023-2024 83/SWSD 10/01/2024 0 Resource Division 12.11 0.00 0 0
4 DARJEELING Phansidewa Northern Mechanical PURBBA BANSGAON CHAKLA PIPED WATER SUPPLY SCHEME ( ZONE- I & II ) , SM/15929 New Infrastructure Cost for PURBBA BANSGAON CHAKLA T/W No. II, ZONE-I, under BIDHANNAGAR CCC , [APPLICATION NO. 4003326724, Reference ID : 403152618] BILL/02037/2023-2024 BP/23-24/311 21/02/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED 4.12 0.00 0 0
5 DARJEELING Phansidewa Northern Mechanical PURBBA BANSGAON CHAKLA PIPED WATER SUPPLY SCHEME ( ZONE- I & II ) , SM/15929 New Infrastructure Cost for PURBBA BANSGAON CHAKLA T/W No. I, ZONE-I, under BIDHANNAGAR CCC , [APPLICATION NO. 4003326733, Reference ID : 403152619] BILL/02036/2023-2024 BP/23-24/311 21/02/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED 10.64 0.00 0 0
6 DARJEELING Phansidewa Northern Mechanical PURBBA BANSGAON CHAKLA PIPED WATER SUPPLY SCHEME ( ZONE- I & II ) , SM/15929 New Additional Charges for New Service Connection at Purba Bansgaon Chakla PWSS ,Zone-II,TW-II under NMD PHEdte. Ref ID- 860316628 Application ID- 100000122188 BILL/01455/2024-2025 BP/24-25/245 26/11/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED 22.22 0.00 0 0
7 DARJEELING Phansidewa Central Drilling PURBBA BANSGAON CHAKLA PIPED WATER SUPPLY SCHEME ( ZONE- I & II ) , SM/15929 New Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) Assistant Engineer,Driller In Charge Junior Engineer ORD/000001/2023-2024 1415/CDD 21/09/2023 304 JHARGRAM SPV PRIVATE LIMITED 21,339.76 13.47 0.06 11
8 DARJEELING Phansidewa Siliguri W/S Division PURBBA BANSGAON CHAKLA PIPED WATER SUPPLY SCHEME ( ZONE- I & II ) , SM/15929 New Construction of 250 cu.m. capacity R.C.C. Elevated Reservoir, 20 mtrs. Staging Height at the head works site along with distribution system, functional household tap connection, rising main, pump house (2 nos.), IEP, boundary wall and tubewell under Jal Jeevan Mission of PURBA BANSGAON CHAKLA Piped Water Supply Scheme under Phansidewa Block under Siliguri Sub Division, P.H.E. Dte Assistant Engineer(Civil) Junior Engineer(Civil) ORD/000108/2023-2024 1148/SWSD 08/08/2023 420 UNIBRO INFRASERV PRIVATE LIMITED 497.64 76.24 15.32 10
9 DARJEELING Phansidewa Northern Mechanical PURBBA BANSGAON CHAKLA PIPED WATER SUPPLY SCHEME ( ZONE- I & II ) , SM/15929 New Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for PURBBA BANSGAON CHAKLA PIPED WATER SUPPLY SCHEME, (Zone-I) TW No. I,II & (Zone-II) TW-I in the district of Darjeeling under Northern Mechanical Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000754/2023-2024 1582/NMD 08/09/2023 723 M/S SAJAHAN CHOWDHURY 34.01 22.62 66.51 70
Total 21,948.02 116.01 0.53