Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
10 583.59 151.11 25.89  
1 DARJEELING Siliguri W/S Division AUGMENTATION OF BUDHARUGAON PIPED WATER SUPPLY SCHEME , SM/13467 Augmentation PREPARATION OF DETAILS PROJECT REPORT (DPR) INCLUDING ROUTE SURVEY IN CONNECTION WITH AUGMENTATION OF BUDHARUGAON PIPED WATER SUPPLY SCHEME UNDER PHANSIDEWA BLOCK, SILIGURI SUB DIVISION, P.H.E. DTE Assistant Engineer(Civil) Junior Engineer (Civil) ORD/000051/2023-2024 244/SSD 05/06/2023 10 ENVIROTECH SOLUTIONS 4.02 3.99 99.25 100
2 DARJEELING Siliguri W/S Division AUGMENTATION OF BUDHARUGAON PIPED WATER SUPPLY SCHEME , SM/13467 Augmentation Material Requisition To Resource Division RTOR000068/2022-2023 2047/SWSD 16/12/2022 0 Resource Division 26.07 0.00 0 0
3 DARJEELING Siliguri W/S Division AUGMENTATION OF BUDHARUGAON PIPED WATER SUPPLY SCHEME , SM/13467 Augmentation Wall writing on smooth, durable wall surface (preferably of Govt. premises/Boundary wall) by cleaning the surface thoroughly, removing old paints, preparing with one coat good quality exterior primer and writing the surface with best quality synthetic enamel paint of approved shed and writing IEC message along with logo, picture etc of multiple colour sample as will be supplied by PHE Dte. by engaging skilled artist and helper artist in different location within 328 Villages in Different Block( Matigara,Phansidewa, KharibarI,Naxalbari Block) under Siliguri W/S Division all complete as per direction of EIC.In Each Villge in 4 Locations tentatively, In Each Location (8 X 5= 40 Sq.Ft) Writing Area Required or as per the Dimension given by PHE Dte.), Writing area should be Geo Tagged in appropriate portal as guided by PHE Department Assistant Engineer(Civil) Junior Engineer (Civil),Junior Engineer(Civil) ORD/000288/2023-2024 382/SWSD 15/02/2024 30 PHANSIDEWA SOCIAL & RURAL WELFARE SOCIETY 21.57 5.33 24.71 50
4 DARJEELING Northern Mechanical AUGMENTATION OF BUDHARUGAON PIPED WATER SUPPLY SCHEME , SM/13467 Augmentation Infrastructure Cost for BUDHARUGAON T/W No. II, ZONE-I, under BIDHANNAGAR CCC , [APPLICATION NO. 4003322531, Reference ID : 403149186] BILL/02026/2023-2024 BP/23-24/311 21/02/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED 4.85 0.00 0 0
5 DARJEELING Northern Mechanical AUGMENTATION OF BUDHARUGAON PIPED WATER SUPPLY SCHEME , SM/13467 Augmentation Infrastructure Cost for BUDHARUGAON T/W No. II, ZONE-III, under BIDHANNAGAR CCC , [APPLICATION NO. 4003322541, Reference ID : 403149161] BILL/02027/2023-2024 BP/23-24/311 21/02/2024 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED 5.00 0.00 0 0
6 DARJEELING Siliguri W/S Division AUGMENTATION OF BUDHARUGAON PIPED WATER SUPPLY SCHEME , SM/13467 Augmentation Construction of Pump House 2 Nos. (5.4 X 3.6) with toilet (2.1 X 1.2), Rig bore 2 Nos. Big Dia T/W by Odex-165 method, Boundary Walls, Laying distribution system (HDPE pipe), Rising Main, Providing FHTC & Supplying Fabrication on suitable RCC foundation & commissioning with 3 (three) months trial run IEP (25 cu.m./hr. for Zone-II & 50 cu.m./hr. for Zone-III), all repair works Zone-I and allied works at Augmentation of BUDHARUGAON PWSS at Phansidewa block under Siliguri Sub Division, P.H.E. Dte. Assistant Engineer(Civil) Junior Engineer (Civil) ORD/000045/2023-2024 655/SWSD 15/06/2023 1125 NETWAY SOLUTION 371.47 141.79 38.17 16
7 DARJEELING Northern Mechanical AUGMENTATION OF BUDHARUGAON PIPED WATER SUPPLY SCHEME , SM/13467 Augmentation Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for AUGMENTATION OF BUDHARUGAON PIPED WATER SUPPLY SCHEME , TW No I (Zone-II) and TW No. I (Zone-III) in the district of Darjeeling under Northern Mechanical Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000439/2023-2024 1378/NMD 09/08/2023 721 NIRMAN 23.67 0.00 0 30
8 DARJEELING Northern Mechanical AUGMENTATION OF BUDHARUGAON PIPED WATER SUPPLY SCHEME , SM/13467 Augmentation Yard lighting arrangement at Head Work Site for Different PWSS under JJM in the BLOCK: PHANSIDEWA, DISTRICT: DARJEELING under Northern Mechanical Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001071/2024-2025 39/NMD 06/01/2025 30 M/S P.P. ELECTRICALS 15.34 0.00 0 0
9 DARJEELING Northern Mechanical AUGMENTATION OF BUDHARUGAON PIPED WATER SUPPLY SCHEME , SM/13467 Augmentation Yard lighting arrangement at Head Work Site for Different PWSS under JJM in the BLOCK: PHANSIDEWA, DISTRICT: DARJEELING under Northern Mechanical Division, P.H.E. Dte. Assistant Engineer Junior Engineer ORD/001072/2024-2025 40/NMD 06/01/2025 30 B.B. CONCERNED 15.33 0.00 0 0
10 DARJEELING Northern Mechanical AUGMENTATION OF BUDHARUGAON PIPED WATER SUPPLY SCHEME , SM/13467 Augmentation Implementation of Affordable IoT-Enabled Water Service Delivery Measurement and Monitoring Sensing System for Rural Deployment in the Proposed Villages under Different Water Supply Schemes at Different Block of Darjeeling District in West Bengal. Assistant Engineer Junior Engineer ORD/000092/2025-2026 1114/NMD 19/05/2025 180 WEBEL TECHNOLOGY LIMITED 96.27 0.00 0 0
Total 583.59 151.11 25.89