| Sl. No. | Division | District | Block | Scheme Name | Scheme Category | Sub Division | Name of AE entrusted | Name of JE entrusted | Date of Sanction | Date of Commencement | Target Date of Completion | Date Of Updation | Work Order Issued | FHTCs | Sanctioned Cost | Payment | Physical Progress (in %) | Financial Progress (in %) |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 1 | 0 | 199.99 | 107.85 | 54 | |||||||||||||
| 1 | Bolpur Mechanical Division | BIRBHUM | Khoyrasol | Solarisation for NET metering of different PWSS at different Blocks under Bolpur Mechanical Division,PHED,SM/16381 | IOT | Central Mechanical Sub-DivisionIII | Assistant Engineer-III | Junior Engineer | 28/02/2023 | 02/08/2023 | 02/08/2025 | 29/12/2025 | 1 | 0 | 199.99 | 107.85 | 90 | 54 |
| Total | 1 | 0 | 199.99 | 107.85 | 54 | |||||||||||||