H2- Exception Report on Scheme

Update Data
Rs. in Lakh
Sl. No. Division District Block Scheme Name Scheme Category Sub Division Name of AE entrusted Name of JE entrusted Date of Sanction Date of Commencement Target Date of Completion Date Of Updation Work Order Issued FHTCs Sanctioned Cost Payment Physical Progress (in %) Financial Progress (in %)
1 10 5,630 1,693.56 106.01   6
1 Coochbehar Division COOCHBEHAR Mathabhanga - I AUGMENTATION OF SIKARPUR PIPED WATER SUPPLY SCHEME,SM/18757 Augmentation Mathabhanga Sub-Division ASSISTANT ENGINEER, MATHABHANGA SUB-DIVISION JUNIOR ENGINEER, MATHABHANGA SUB-DIVISION 21/08/2023 22/08/2023 21/05/2024 27/09/2023 10 5,630 1,693.56 106.01 81 6
Total 10 5,630 1,693.56 106.01   6