H2- Exception Report on Scheme

Update Data
Rs. in Lakh
Sl. No. Division District Block Scheme Name Scheme Category Sub Division Name of AE entrusted Name of JE entrusted Date of Sanction Date of Commencement Target Date of Completion Date Of Updation Work Order Issued FHTCs Sanctioned Cost Payment Physical Progress (in %) Financial Progress (in %)
63 1,038 98,126 28,867.14 55.93   0
1 Jalpaiguri Division JALPAIGURI Dhupguri Funtional Household Tap Connection (FHTC) under Jaldhara Jal Sapna under command area of Red Bank Garden Piped Water Supply Scheme,SM/06843 Retrofitting Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 06/10/2020 23/11/2020 31/12/2025 27/01/2026 1 925 52.30 0.00 89 0
2 Jalpaiguri Division JALPAIGURI Dhupguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Dakshin Altagram & Paschim Altagram Mouza under Mainatali Piped Water Supply Scheme,SM/06960 Retrofitting Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 03/11/2020 18/12/2020 31/12/2026 27/01/2026 3 1,692 99.43 1.57 90 2
3 Jalpaiguri Division JALPAIGURI Dhupguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Pradhanpara Mouza Under Sajnapara Piped Water Supply Scheme,SM/07302 Retrofitting Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 10/12/2020 18/12/2020 31/12/2026 27/01/2026 0 1,309 75.74 3.50 90 5
4 Jalpaiguri Division JALPAIGURI Rajganj Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Ambari Falakata Piped Water Supply Scheme at Rajganj Block,SM/08036 Retrofitting Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 02/02/2021 13/05/2021 31/05/2025 27/01/2026 24 6,704 349.29 28.42 90 8
5 Jalpaiguri Division JALPAIGURI Jalpaiguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Mahitnagar Piped Water Supply Scheme at Jalpaiguri Block,SM/08037 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 02/02/2021 27/01/2021 31/05/2025 27/01/2026 15 6,385 348.32 22.44 99 6
6 Jalpaiguri Division JALPAIGURI Jalpaiguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Goralbari Piped Water Supply Scheme,SM/08038 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 02/02/2021 27/01/2021 31/05/2025 27/01/2026 43 6,473 396.46 0.00 99 0
7 Jalpaiguri Division JALPAIGURI Matiali Indong Tea Garden Area Piped Water Supply Scheme.,SM/08873 New Jalpaiguri Sadar Sub-Division Junior Engineer 22/09/2021 01/02/2022 31/07/2025 27/01/2026 18 1,236 311.47 0.00 92 0
8 Jalpaiguri Division JALPAIGURI Mal Kumlai Tea Garden Area Piped Water Supply Scheme.,SM/08875 New RWS Jalpaiguri Sub-Division Junior Engineer 22/09/2021 21/01/2022 30/04/2025 27/01/2026 22 991 303.84 0.00 97 0
9 Jalpaiguri Division JALPAIGURI Jalpaiguri Rejuvenation of Goralbari Piped Water Supply Scheme ,SM/09390 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 12/11/2021 07/12/2021 31/12/2025 27/01/2026 34 0 337.55 0.00 98 0
10 Jalpaiguri Division JALPAIGURI Maynaguri Rejuvenation of Madhabdanga piped water supply scheme.,SM/09456 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 27/12/2021 31/05/2025 27/01/2026 22 0 125.38 0.00 85 0
11 Jalpaiguri Division JALPAIGURI Maynaguri Rejuvenation of Kajaldighi piped water supply scheme.,SM/09457 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 27/12/2021 30/04/2025 27/01/2026 13 0 116.90 0.00 95 0
12 Jalpaiguri Division JALPAIGURI Maynaguri Rejuvenation of Charerbari piped water supply scheme.,SM/09458 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 27/12/2021 31/03/2025 27/01/2026 18 0 115.93 0.00 98 0
13 Jalpaiguri Division JALPAIGURI Maynaguri Rejuvenation of Dwarikamari piped water supply scheme.,SM/09459 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 01/02/2022 31/03/2026 27/01/2026 25 0 121.40 0.00 95 0
14 Jalpaiguri Division JALPAIGURI Maynaguri Rejuvenation of Basilardanga piped water supply scheme.,SM/09460 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 27/12/2021 31/12/2025 27/01/2026 20 0 115.16 0.00 97 0
15 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Kilkote Tea Garden Piped Water Supply Scheme.,SM/09461 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 23/08/2018 31/08/2025 27/01/2026 10 930 70.07 0.00 100 0
16 Jalpaiguri Division JALPAIGURI Jalpaiguri Rejuvenation of Boalmari piped water supply scheme.,SM/09462 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 04/01/2022 31/05/2025 27/01/2026 11 0 113.60 0.00 99 0
17 Jalpaiguri Division JALPAIGURI Jalpaiguri Rejuvenation of Porapara piped water supply scheme.,SM/09463 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 2 19/11/2021 22/02/2022 30/06/2025 27/01/2026 19 0 121.26 0.00 90 0
18 Jalpaiguri Division JALPAIGURI Rajganj Rejuvenation of Chakiavita Piped Water Supply Scheme ,SM/09482 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 19/11/2021 07/12/2021 31/12/2025 27/01/2026 18 0 119.98 0.00 85 0
19 Jalpaiguri Division JALPAIGURI Jalpaiguri Rejuvenation of Araji Maria Kamala Pukhari piped water supply scheme.,SM/09518 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 10/02/2022 31/03/2025 27/01/2026 17 0 114.34 0.00 90 0
20 Jalpaiguri Division JALPAIGURI Jalpaiguri Rejuvenation of Mohitnagar piped water supply scheme.,SM/09519 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 25/02/2022 31/05/2025 27/01/2026 31 0 122.19 0.00 99 0
21 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Nagaisuree Tea Garden Area Piped Water Supply Scheme,SM/09858 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 06/12/2021 31/01/2022 31/03/2025 27/01/2026 10 0 171.50 0.00 95 0
22 Jalpaiguri Division JALPAIGURI Nagrakata Rejuvenation of Water Supply Scheme of Caron Tea Garden Mouza,SM/09859 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 06/12/2021 04/04/2022 30/06/2025 27/01/2026 19 0 114.69 0.00 92 0
23 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Purbba Salbari Piped Water Supply Scheme,SM/09861 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 06/12/2021 31/01/2022 31/08/2025 27/01/2026 16 2,219 696.59 0.00 85 0
24 Jalpaiguri Division JALPAIGURI Nagrakata Rejuvenation of Water Supply Scheme of HopeTea Garden Mouza,SM/09862 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 06/12/2021 25/07/2022 31/03/2025 27/01/2026 12 0 105.33 0.00 93 0
25 Jalpaiguri Division JALPAIGURI Rajganj Augmentation of Sannyasikata Piped Water Supply Scheme,SM/09996 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 20/12/2021 01/02/2022 30/05/2025 27/01/2026 43 6,379 2,105.11 0.00 85 0
26 Jalpaiguri Division JALPAIGURI Maynaguri Augmentation of Ramsai Water Supply Scheme.,SM/10033 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/01/2022 24/01/2022 31/05/2025 27/01/2026 21 3,250 976.19 0.00 90 0
27 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Juranti Tea Garden Area Piped Water Supply Scheme,SM/10069 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 27/01/2022 09/11/2016 30/04/2025 27/01/2026 15 0 243.70 0.00 100 0
28 Jalpaiguri Division JALPAIGURI Nagrakata Rejuvenation of Hila Tea Garden area piped water supply scheme,SM/10070 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 27/01/2022 01/02/2022 30/06/2025 27/01/2026 24 0 208.35 0.00 95 0
29 Jalpaiguri Division JALPAIGURI Jalpaiguri Augmentation of Dakshin Berubari Water Supply Scheme.,SM/10086 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 01/02/2022 03/02/2022 30/04/2025 27/01/2026 27 4,905 1,574.27 0.00 85 0
30 Jalpaiguri Division JALPAIGURI Jalpaiguri Augmentation of Mondalghat Water Supply Scheme.,SM/10087 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 01/02/2022 03/02/2022 31/12/2025 27/01/2026 22 3,793 1,095.64 0.00 95 0
31 Jalpaiguri Division JALPAIGURI Jalpaiguri Augmentation of Kharija-Berubari Water Supply Scheme.,SM/10088 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 01/02/2022 02/02/2022 30/04/2025 27/01/2026 25 5,781 2,064.37 0.00 87 0
32 Jalpaiguri Division JALPAIGURI Maynaguri Augmentation of Baikur Piped Water Supply Scheme.,SM/10089 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 01/02/2022 01/02/2022 30/05/2025 27/01/2026 42 7,173 1,763.64 0.00 82 0
33 Jalpaiguri Division JALPAIGURI Maynaguri Augmentation of Barnes Water Supply Scheme.,SM/10090 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 01/02/2022 02/02/2022 31/08/2025 27/01/2026 39 4,046 1,115.54 0.00 85 0
34 Jalpaiguri Division JALPAIGURI Dhupguri REJUVENATION OF DEBPARA TEA GARDEN PIPED WATER SUPPLY SCHEME,SM/11812 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 16/08/2022 14/09/2022 30/04/2026 27/01/2026 8 1,206 94.73 0.00 95 0
35 Jalpaiguri Division JALPAIGURI Matiali BARA DIGHI PIPED WATER SUPPLY SCHEME,SM/13703 New Jalpaiguri Sadar Sub-Division Junior Engineer 14/11/2022 01/03/2023 30/06/2025 27/01/2026 6 210 156.26 0.00 85 0
36 Jalpaiguri Division JALPAIGURI Mal Augmentation of Odlabari Piped Water Supply Scheme,SM/13790 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 21/10/2022 05/04/2022 31/12/2025 27/01/2026 29 3,348 1,003.52 0.00 90 0
37 Jalpaiguri Division JALPAIGURI Dhupguri MADHYA DAUKIMARI PIPED WATER SUPPLY SCHEME ,SM/13898 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 25/11/2022 10/04/2023 31/03/2027 27/01/2026 15 1,809 906.72 0.00 90 0
38 Jalpaiguri Division JALPAIGURI Nagrakata PIPE WATER SUPPLY SCHEME FOR UPPER TENDU FOREST,SM/13989 New Jalpaiguri Sadar Sub-Division Junior Engineer 01/12/2022 16/03/2023 31/05/2025 27/01/2026 9 360 143.56 0.00 90 0
39 Jalpaiguri Division JALPAIGURI Rajganj SIMULGURI PIPED WATER SUPPLY SCHEME,SM/14240 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 16/01/2023 30/03/2023 30/06/2025 27/01/2026 15 2,948 1,172.27 0.00 85 0
40 Jalpaiguri Division JALPAIGURI Dhupguri GAIRKHATA TEA GARDEN (D) PIPED WATER SUPPLY SCHEME ,SM/14664 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 31/01/2023 06/03/2023 30/04/2025 27/01/2026 12 2,319 870.88 0.00 95 0
41 Jalpaiguri Division JALPAIGURI Dhupguri GENDRAPARA TEA GARDEN PIPED WATER SUPPLY SCHEME,SM/14666 New Northern Mechanical Division Assistant Engineer , Head Quarters , NMD,Assistant Engineer,HQ Junior Engineer 31/01/2023 02/08/2023 02/08/2025 27/01/2026 15 2,390 852.43 0.00 90 0
42 Jalpaiguri Division JALPAIGURI Mal KANTADIGHI KUMARPARA TEA GARDEN,SM/14879 New Jalpaiguri Sadar Sub-Division Junior Engineer 03/02/2023 10/05/2023 30/04/2026 27/01/2026 16 2,481 841.22 0.00 91 0
43 Jalpaiguri Division JALPAIGURI Mal RANICHERA TEA GARDEN PIPED WATER SUPPLY SCHEME ,SM/14885 New Jalpaiguri Sadar Sub-Division Junior Engineer 03/02/2023 28/07/2023 31/12/2025 27/01/2026 17 2,665 913.53 0.00 90 0
44 Jalpaiguri Division JALPAIGURI Jalpaiguri REJUVENATION OF ARJI GARALBARI PWSS,SM/15030 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2023 29/03/2023 30/06/2025 27/01/2026 15 0 172.44 0.00 95 0
45 Jalpaiguri Division JALPAIGURI Maynaguri REJUVENATION OF HASLURDANGA PIPED WATER SUPPLY SCHEME,SM/15031 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2023 16/03/2023 31/12/2025 27/01/2026 9 0 161.99 0.00 90 0
46 Jalpaiguri Division JALPAIGURI Maynaguri Rejuvenation of Bhangarhat Piped Water Supply Scheme,SM/15032 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 04/02/2023 24/05/2023 31/03/2025 27/01/2026 7 0 178.30 0.00 95 0
47 Jalpaiguri Division JALPAIGURI Mal REJUVENATION OF JOGESH CHANDRA TEA GARDEN AREA PWSS,SM/15068 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2023 14/07/2023 31/08/2025 27/01/2026 6 0 70.86 0.00 82 0
48 Jalpaiguri Division JALPAIGURI Jalpaiguri REJUVENATION OF RAIPUR TEA GARDEN AREA PWSS,SM/15071 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2023 01/06/2023 31/12/2025 27/01/2026 5 1,015 177.04 0.00 90 0
49 Jalpaiguri Division JALPAIGURI Dhupguri REJUVENATION OF DAKSHIN SALBARI PWSS,SM/15087 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 2 04/02/2023 02/03/2023 31/05/2025 27/01/2026 10 2,129 246.25 0.00 85 0
50 Jalpaiguri Division JALPAIGURI Maynaguri REJUVENATION OF BHANGAMALI PIPED WATER SUPPLY SCHEME,SM/15096 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 04/02/2023 06/02/2023 31/07/2025 27/01/2026 6 0 119.10 0.00 95 0
51 Jalpaiguri Division JALPAIGURI Mal NEORA NADI TEA GARDEN PIPED WATER SUPPLY SCHEME,SM/15115 New Jalpaiguri Sadar Sub-Division Junior Engineer 04/02/2023 08/05/2023 31/03/2025 27/01/2026 14 1,368 560.37 0.00 98 0
52 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Nakhati Tea Garden Area Piped Water Supply Scheme ,SM/15116 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 04/02/2023 25/05/2023 31/12/2025 27/01/2026 9 0 194.43 0.00 85 0
53 Jalpaiguri Division JALPAIGURI Mal Rejuvenation of Syli Tea Garden Area Piped Water Supply Scheme,SM/15117 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 04/02/2023 01/03/2023 30/04/2025 27/01/2026 10 0 196.67 0.00 98 0
54 Jalpaiguri Division JALPAIGURI Jalpaiguri RETROFITTING OF MAHITNAGAR PWSS,SM/15131 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2023 08/06/2023 31/12/2025 27/01/2026 2 0 180.43 0.00 98 0
55 Jalpaiguri Division JALPAIGURI Dhupguri LAKSHMI PARA TEA GARDEN PIPED WATER SUPPLY SCHEME,SM/15262 New Northern Mechanical Division Assistant Engineer , Head Quarters , NMD,Assistant Engineer,HQ Junior Engineer 08/02/2023 02/08/2023 02/08/2025 27/01/2026 14 1,408 635.17 0.00 90 0
56 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Karbala Tea Garden Piped Water Supply Scheme,SM/15298 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 09/02/2023 13/04/2023 30/04/2025 27/01/2026 5 0 241.44 0.00 90 0
57 Jalpaiguri Division JALPAIGURI Nagrakata Rejuvenation of Nagrakata Tea Garden Area Piped Water Supply Scheme,SM/15300 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 09/02/2023 08/06/2023 30/05/2025 27/01/2026 11 0 159.96 0.00 85 0
58 Jalpaiguri Division JALPAIGURI Matiali REJUVENATION OF BATABARI TEA GARDEN AREA PIPED WATER SUPPLY SCHEME,SM/16773 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 13/03/2023 02/08/2023 02/08/2025 27/01/2026 6 527 171.57 0.00 86 0
59 Jalpaiguri Division JALPAIGURI Maynaguri REJUVENATION OF UTTAR BHUSKADANGA AND GARTALI JALPESH PWSS,SM/16937 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 16/03/2023 06/06/2023 30/06/2025 27/01/2026 6 0 161.99 0.00 95 0
60 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Aibhil Tea Garden Area Piped Water Supply Scheme,SM/17185 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 15/03/2023 26/05/2023 31/03/2025 27/01/2026 7 940 180.04 0.00 99 0
61 Jalpaiguri Division JALPAIGURI Dhupguri BARAGHARIA Piped Water Supply Scheme.,SM/17649 New Northern Mechanical Division Assistant Engineer , Head Quarters , NMD,Assistant Engineer,HQ Junior Engineer 22/03/2023 24/05/2023 31/07/2025 27/01/2026 8 2,063 613.18 0.00 90 0
62 Jalpaiguri Division JALPAIGURI Mal ODLABARI TEA GARDEN PIPED WATER SUPPLY SCHEME,SM/18356 New 11/07/2023 24/07/2023 30/04/2026 27/01/2026 52 2,798 1,140.38 0.00 88 0
63 Jalpaiguri Division JALPAIGURI Mal DAMDIM TEA GARDEN PIPED WATER SUPPLY SCHEME,SM/18711 New 04/08/2023 02/08/2023 02/08/2025 27/01/2026 15 1,951 584.88 0.00 90 0
Total 1,038 98,126 28,867.14 55.93   0