H2- Exception Report on Scheme

Update Data
Rs. in Lakh
Sl. No. Division District Block Scheme Name Scheme Category Sub Division Name of AE entrusted Name of JE entrusted Date of Sanction Date of Commencement Target Date of Completion Date Of Updation Work Order Issued FHTCs Sanctioned Cost Payment Physical Progress (in %) Financial Progress (in %)
211 3,020 3,63,383 1,06,331.75 50,912.62   48
1 Jalpaiguri Division JALPAIGURI Dhupguri Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Ambari Tea Garden Piped Water Supply Scheme,SM/06837 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 06/10/2020 23/08/2018 31/03/2025 29/12/2025 10 1,080 61.53 127.39 85 207
2 Jalpaiguri Division JALPAIGURI Jalpaiguri Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Boalmari Piped Water Supply Scheme,SM/06838 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 06/10/2020 15/10/2020 31/05/2025 29/12/2025 7 1,664 92.26 94.17 85 102
3 Jalpaiguri Division JALPAIGURI Maynaguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Kajaldighi Piped Water Supply Scheme,SM/06839 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 06/10/2020 18/11/2020 30/06/2025 29/12/2025 9 1,671 99.99 149.50 80 150
4 Jalpaiguri Division JALPAIGURI Jalpaiguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Aragi Goralbari Piped Water Supply Scheme,SM/06840 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 06/10/2020 18/11/2020 31/05/2025 29/12/2025 11 1,362 74.02 142.26 99 192
5 Jalpaiguri Division JALPAIGURI Matiali Providing Funtional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna including existing LDS under the comand area of Nakhati Tea Garden Piped Water Supply Scheme,SM/06842 Retrofitting Jalpaiguri Sadar Sub-Division Junior Engineer 06/10/2020 09/01/2018 31/08/2025 29/12/2025 2 873 48.73 20.56 84 42
6 Jalpaiguri Division JALPAIGURI Dhupguri Funtional Household Tap Connection (FHTC) under Jaldhara Jal Sapna under command area of Red Bank Garden Piped Water Supply Scheme,SM/06843 Retrofitting Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 06/10/2020 23/11/2020 31/12/2025 29/12/2025 1 925 52.30 15.72 89 30
7 Jalpaiguri Division JALPAIGURI Matiali Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Nagaisuree Tea Garden Area Piped Water Supply Scheme,SM/06844 Retrofitting Jalpaiguri Sadar Sub-Division Junior Engineer 06/10/2020 18/11/2020 30/04/2025 29/12/2025 6 1,082 57.04 111.59 85 196
8 Jalpaiguri Division JALPAIGURI Matiali Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Youngtong Tea Garden Piped Water Supply Scheme,SM/06846 Retrofitting Jalpaiguri Sadar Sub-Division Junior Engineer 06/10/2020 18/11/2020 30/04/2025 29/12/2025 8 632 37.11 80.29 87 216
9 Jalpaiguri Division JALPAIGURI Matiali Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Juranti T.G Area Piped Water Supply Scheme,SM/06847 Retrofitting Jalpaiguri Sadar Sub-Division Junior Engineer 06/10/2020 18/11/2020 30/04/2025 29/12/2025 2 1,019 56.03 89.99 95 161
10 Jalpaiguri Division JALPAIGURI Jalpaiguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Arjimaria Kamlapukuri Piped Water Supply Scheme ,SM/06936 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 03/11/2020 25/11/2020 31/05/2025 29/12/2025 10 2,332 126.48 185.61 88 147
11 Jalpaiguri Division JALPAIGURI Maynaguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Charerbari Piped Water Supply Scheme,SM/06937 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 03/11/2020 18/11/2020 30/06/2025 29/12/2025 11 2,431 129.58 144.65 80 112
12 Jalpaiguri Division JALPAIGURI Nagrakata Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Jiti Tea Garden Piped Water Supply Scheme at Nagrakata Block ,SM/06952 Retrofitting Jalpaiguri Sadar Sub-Division Junior Engineer 03/11/2020 18/12/2020 30/04/2025 29/12/2025 3 1,257 65.98 130.74 80 198
13 Jalpaiguri Division JALPAIGURI Nagrakata Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Hope Tea Garden Area Piped Water Supply Scheme at Nagrakata Block,SM/06953 Retrofitting Jalpaiguri Sadar Sub-Division Junior Engineer 03/11/2020 18/12/2020 30/04/2025 29/12/2025 4 917 48.90 95.76 86 196
14 Jalpaiguri Division JALPAIGURI Nagrakata Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Caron Tea Garden Piped Water Supply Scheme at Nagrakata Block,SM/06954 Retrofitting Jalpaiguri Sadar Sub-Division Junior Engineer 03/11/2020 18/12/2020 31/08/2025 29/12/2025 2 607 34.50 116.82 82 339
15 Jalpaiguri Division JALPAIGURI Nagrakata Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Luksan Bazar Tea Garden Piped Water Supply Scheme at Nagrakata Block,SM/06955 Retrofitting Jalpaiguri Sadar Sub-Division Junior Engineer 03/11/2020 18/12/2020 30/04/2025 29/12/2025 4 1,205 62.52 143.60 85 230
16 Jalpaiguri Division JALPAIGURI Nagrakata Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Nayasaily Tea Garden Piped Water Supply Scheme at Nagrakata Block ,SM/06956 Retrofitting Jalpaiguri Sadar Sub-Division Junior Engineer 03/11/2020 18/12/2020 30/04/2025 29/12/2025 5 1,225 64.77 128.99 88 199
17 Jalpaiguri Division JALPAIGURI Nagrakata Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Hila Tea Garden Area Piped Water Supply Scheme at Nagrakata Block ,SM/06957 Retrofitting Jalpaiguri Sadar Sub-Division Junior Engineer 03/11/2020 18/12/2020 31/08/2025 29/12/2025 3 640 36.00 71.25 85 198
18 Jalpaiguri Division JALPAIGURI Dhupguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Bhandani Piped Water Supply Scheme at Dhupguri Block,SM/06958 Retrofitting 03/11/2020 18/12/2020 31/07/2025 29/12/2025 6 1,745 99.31 234.21 40 236
19 Jalpaiguri Division JALPAIGURI Dhupguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Sajnapara Mouza under Sajnapara Piped Water Supply Scheme ,SM/06959 Retrofitting Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 03/11/2020 18/12/2020 31/12/2025 29/12/2025 5 914 57.13 237.44 90 416
20 Jalpaiguri Division JALPAIGURI Dhupguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Dakshin Dangapara & Dambari Mouza Under Patkidaha Piped Water Supply Scheme ,SM/06961 Retrofitting Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 03/11/2020 18/12/2020 31/05/2025 29/12/2025 2 1,259 75.45 70.26 90 93
21 Jalpaiguri Division JALPAIGURI Matiali Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Engo Tea Garden Piped Water Supply Scheme at Matiali Block,SM/07301 Retrofitting Jalpaiguri Sadar Sub-Division Junior Engineer 10/12/2020 18/12/2020 31/05/2025 29/12/2025 5 240 30.18 60.24 90 200
22 Jalpaiguri Division JALPAIGURI Dhupguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Patkidaa & Jakhaikona Mouza under Patkidaha Piped Water Supply Scheme,SM/07304 Retrofitting 10/12/2020 18/12/2020 31/05/2025 29/12/2025 3 447 36.39 143.73 83 395
23 Jalpaiguri Division JALPAIGURI Dhupguri Functional Household Tap Connection (FHTC)under Jaldhara Jal Sapna under comand area of Purba Magurmari Piped Water Supply Scheme at Dhupguri Block,SM/07891 Retrofitting Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 19/01/2021 20/01/2021 31/05/2025 29/12/2025 11 4,696 285.66 91.23 35 32
24 Jalpaiguri Division JALPAIGURI Dhupguri Functional Household Tap Connection (FHTC)under Jaldhara Jal Sapna under comand area of Chauhaddi Piped Water Supply Scheme at Dhupguri Block,SM/07893 Retrofitting 19/01/2021 22/01/2021 31/08/2025 29/12/2025 12 2,191 133.21 83.94 50 63
25 Jalpaiguri Division JALPAIGURI Jalpaiguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Porapara Piped Water Supply Scheme at Jalpaiguri Block,SM/08035 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 2 02/02/2021 17/07/2020 31/12/2025 29/12/2025 9 5,856 320.18 133.34 60 42
26 Jalpaiguri Division JALPAIGURI Rajganj Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Ambari Falakata Piped Water Supply Scheme at Rajganj Block,SM/08036 Retrofitting Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 02/02/2021 13/05/2021 31/05/2025 29/12/2025 24 6,704 349.29 313.76 90 90
27 Jalpaiguri Division JALPAIGURI Jalpaiguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Mahitnagar Piped Water Supply Scheme at Jalpaiguri Block,SM/08037 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 02/02/2021 27/01/2021 31/05/2025 29/12/2025 15 6,385 348.32 315.75 99 91
28 Jalpaiguri Division JALPAIGURI Jalpaiguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Goralbari Piped Water Supply Scheme,SM/08038 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 02/02/2021 27/01/2021 31/05/2025 29/12/2025 43 6,473 396.46 407.81 99 103
29 Jalpaiguri Division JALPAIGURI Maynaguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara/Jal Sapna under the command area of Basilardanga Piped Water Supply Scheme,SM/08077 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2021 04/02/2021 31/08/2025 29/12/2025 6 1,080 62.08 81.54 85 131
30 Jalpaiguri Division JALPAIGURI Dhupguri Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara/Jal Sapna under the command area of Madhya Khuttimari piped Water Supply Scheme at Dhupguri Block,SM/08078 Retrofitting Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 04/02/2021 13/05/2021 31/12/2025 29/12/2025 9 2,090 136.18 41.79 30 31
31 Jalpaiguri Division JALPAIGURI Matiali Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Mathachulka Tea Garden Piped Water Supply Scheme at Metiali Block,SM/08284 Retrofitting Jalpaiguri Sadar Sub-Division Junior Engineer 09/02/2021 18/01/2021 31/07/2025 29/12/2025 10 2,315 137.50 19.02 25 14
32 Jalpaiguri Division JALPAIGURI Rajganj Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Sapna for Chakiavita Piped Water Supply Scheme at Rajganj Block,SM/08285 Retrofitting Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 09/02/2021 13/05/2021 31/05/2025 29/12/2025 28 5,069 268.15 291.94 90 109
33 Jalpaiguri Division JALPAIGURI Nagrakata Supply of potable drinking water to Dharanipur Tea Garden in relation with Chaa Sundari Project.,SM/08578 New Jalpaiguri Sadar Sub-Division Junior Engineer 10/02/2021 02/08/2023 02/08/2025 29/12/2025 6 285 150.29 42.87 35 29
34 Jalpaiguri Division JALPAIGURI Dhupguri Supply of potable drinking water to Red Bank Tea Garden in relation with Chaa Sundari Project. ,SM/08581 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 10/02/2021 18/05/2023 31/03/2025 29/12/2025 5 562 172.90 45.12 55 26
35 Jalpaiguri Division JALPAIGURI Nagrakata Ghasmari Piped Water Supply Scheme.,SM/08868 New Northern Mechanical Division Assistant Engineer , Head Quarters , NMD Junior Engineer 20/09/2021 31/03/2022 30/06/2025 29/12/2025 24 779 293.24 159.44 80 54
36 Jalpaiguri Division JALPAIGURI Matiali Indong Tea Garden Area Piped Water Supply Scheme.,SM/08873 New Jalpaiguri Sadar Sub-Division Junior Engineer 22/09/2021 01/02/2022 31/07/2025 29/12/2025 18 1,236 311.47 234.64 92 75
37 Jalpaiguri Division JALPAIGURI Mal Bagrakote Tea Garden Area Piped Water Supply Scheme.,SM/08874 New RWS Jalpaiguri Sub-Division Junior Engineer 22/09/2021 03/02/2022 31/03/2025 29/12/2025 19 4,594 518.37 237.22 55 46
38 Jalpaiguri Division JALPAIGURI Mal Kumlai Tea Garden Area Piped Water Supply Scheme.,SM/08875 New RWS Jalpaiguri Sub-Division Junior Engineer 22/09/2021 21/01/2022 30/04/2025 29/12/2025 22 991 303.84 244.94 97 81
39 Jalpaiguri Division JALPAIGURI Dhupguri Augmentation of Chamurchi Tea Garden (Chamurchi Bazar & Chamurchi Forest Busty & Labor Colony) Piped Water Supply Scheme.,SM/08876 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 22/09/2021 20/04/2022 31/12/2025 29/12/2025 44 3,422 1,136.39 701.05 60 62
40 Jalpaiguri Division JALPAIGURI Water Supply Arrangement for Anganwadi Centre having Electric Power Connection and within the command area of PWSS (Phase-I).,SM/08965 Anganwadi 28/10/2021 12/11/2021 30/06/2025 29/12/2025 28 0 479.35 299.44 50 62
41 Jalpaiguri Division JALPAIGURI Maynaguri PROVIDING FUNCTIONAL HOUSEHOLD TAP CONNECTION (FHTC) WITH RETROFITTING OF UTTAR BHUSKADANGA AND GARTALI JALPESH PIPED WATER SUPPLY SCHEME UNDER JAL SWAPNA UNDER JALPAIGURI DIVISION, PHE DTE.,SM/09099 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 28/10/2021 28/10/2021 31/05/2025 29/12/2025 9 1,369 163.94 113.68 80 69
42 Jalpaiguri Division JALPAIGURI Rajganj Augmentation of Binnaguri Piped Water Supply Scheme,SM/09344 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 12/11/2021 01/02/2022 31/12/2025 29/12/2025 22 2,082 871.08 376.11 65 43
43 Jalpaiguri Division JALPAIGURI Maynaguri Augmentation of Domohani Piped Water Supply Scheme,SM/09345 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 12/11/2021 11/03/2022 31/07/2025 29/12/2025 25 2,548 855.56 617.79 80 72
44 Jalpaiguri Division JALPAIGURI Jalpaiguri Rejuvenation of Goralbari Piped Water Supply Scheme ,SM/09390 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 12/11/2021 07/12/2021 31/12/2025 29/12/2025 34 0 337.55 334.94 98 99
45 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Sajnapara Piped Water Supply Scheme,SM/09391 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 12/11/2021 14/09/2022 31/03/2025 29/12/2025 12 0 92.36 30.72 80 33
46 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Kathalguri Tea Garden Piped water Supply Scheme,SM/09392 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 12/11/2021 03/03/2022 31/12/2025 29/12/2025 17 1,462 290.82 169.98 70 58
47 Jalpaiguri Division JALPAIGURI Maynaguri Rejuvenation of Madhabdanga piped water supply scheme.,SM/09456 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 27/12/2021 31/05/2025 29/12/2025 22 0 125.38 107.18 85 85
48 Jalpaiguri Division JALPAIGURI Maynaguri Rejuvenation of Kajaldighi piped water supply scheme.,SM/09457 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 27/12/2021 30/04/2025 29/12/2025 13 0 116.90 66.48 95 57
49 Jalpaiguri Division JALPAIGURI Maynaguri Rejuvenation of Charerbari piped water supply scheme.,SM/09458 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 27/12/2021 31/03/2025 29/12/2025 18 0 115.93 96.33 98 83
50 Jalpaiguri Division JALPAIGURI Maynaguri Rejuvenation of Basilardanga piped water supply scheme.,SM/09460 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 27/12/2021 31/12/2025 29/12/2025 20 0 115.16 105.01 97 91
51 Jalpaiguri Division JALPAIGURI Jalpaiguri Rejuvenation of Boalmari piped water supply scheme.,SM/09462 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 04/01/2022 31/05/2025 29/12/2025 11 0 113.60 108.26 99 95
52 Jalpaiguri Division JALPAIGURI Jalpaiguri Rejuvenation of Porapara piped water supply scheme.,SM/09463 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 2 19/11/2021 22/02/2022 30/06/2025 29/12/2025 19 0 121.26 103.81 90 86
53 Jalpaiguri Division JALPAIGURI Rajganj Rejuvenation of Chakiavita Piped Water Supply Scheme ,SM/09482 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 19/11/2021 07/12/2021 31/12/2025 29/12/2025 18 0 119.98 110.12 85 92
54 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Madhya Khutttimari Piped Water Supply Scheme,SM/09483 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 19/11/2021 21/01/2022 31/03/2025 29/12/2025 7 0 188.47 29.87 65 16
55 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Chauhaddi Piped Water Supply Scheme,SM/09484 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 19/11/2021 10/12/2021 31/03/2025 29/12/2025 17 0 226.32 166.16 70 73
56 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Mallicksova Piped water Supply Scheme,SM/09485 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 19/11/2021 21/01/2022 31/12/2025 29/12/2025 21 0 178.69 88.01 70 49
57 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Khalaigram Piped Water Supply Scheme,SM/09486 Augmentation Northern Mechanical Division Assistant Engineer , Head Quarters , NMD,Assistant Engineer,HQ Junior Engineer 19/11/2021 21/01/2022 31/03/2025 29/12/2025 9 0 66.14 34.38 80 52
58 Jalpaiguri Division JALPAIGURI Rajganj Rejuvenation of Ambari Falakata Piped Water Supply Scheme,SM/09487 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 19/11/2021 09/03/2022 31/08/2025 29/12/2025 21 0 217.47 92.07 45 42
59 Jalpaiguri Division JALPAIGURI Jalpaiguri Rejuvenation of Araji Maria Kamala Pukhari piped water supply scheme.,SM/09518 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 10/02/2022 31/03/2025 29/12/2025 17 0 114.34 78.18 90 68
60 Jalpaiguri Division JALPAIGURI Jalpaiguri Rejuvenation of Mohitnagar piped water supply scheme.,SM/09519 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/11/2021 25/02/2022 31/05/2025 29/12/2025 31 0 122.19 99.83 99 82
61 Jalpaiguri Division JALPAIGURI Dhupguri Augmentation of Purba Daukimari Piped Water Supply Scheme,SM/09560 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 22/11/2021 02/02/2022 31/03/2025 29/12/2025 18 1,586 545.87 459.48 70 84
62 Jalpaiguri Division JALPAIGURI Mal Augmentation of Dakshin Chak Moulani Piped Water Supply Scheme,SM/09561 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 22/11/2021 24/01/2022 30/04/2025 29/12/2025 21 1,793 681.79 383.49 70 56
63 Jalpaiguri Division JALPAIGURI Jalpaiguri Augmentation of Shikarpur Piped Water Supply Scheme,SM/09562 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 22/11/2021 04/04/2022 31/12/2025 29/12/2025 20 3,418 977.54 309.76 55 32
64 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Mainatali Piped Water Supply Scheme ,SM/09565 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 22/11/2021 21/01/2022 30/06/2025 29/12/2025 11 0 104.11 51.18 60 49
65 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Nagaisuree Tea Garden Area Piped Water Supply Scheme,SM/09858 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 06/12/2021 31/01/2022 31/03/2025 29/12/2025 10 0 171.50 99.67 95 58
66 Jalpaiguri Division JALPAIGURI Nagrakata Rejuvenation of Water Supply Scheme of Caron Tea Garden Mouza,SM/09859 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 06/12/2021 04/04/2022 30/06/2025 29/12/2025 19 0 114.69 55.81 92 49
67 Jalpaiguri Division JALPAIGURI Dhupguri Augmentation of Gairkata Piped Water Supply Scheme,SM/09860 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 06/12/2021 31/01/2022 31/03/2025 29/12/2025 11 1,787 480.53 100.58 40 21
68 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Purbba Salbari Piped Water Supply Scheme,SM/09861 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 06/12/2021 31/01/2022 31/08/2025 29/12/2025 16 2,219 696.59 561.48 85 81
69 Jalpaiguri Division JALPAIGURI Nagrakata Rejuvenation of Water Supply Scheme of HopeTea Garden Mouza,SM/09862 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 06/12/2021 25/07/2022 31/03/2025 29/12/2025 12 0 105.33 83.78 93 80
70 Jalpaiguri Division JALPAIGURI Matiali Augmentation of Purbba Batabari Piped Water Supply Scheme ,SM/09864 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 06/12/2021 04/04/2022 31/08/2025 29/12/2025 34 1,795 810.11 487.21 75 60
71 Jalpaiguri Division JALPAIGURI Nagrakata Rejuvenation of Water Supply Scheme of Jiti Tea Garden Mouza,SM/09865 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 06/12/2021 31/05/2022 30/09/2025 29/12/2025 18 0 110.47 94.93 70 86
72 Jalpaiguri Division JALPAIGURI Nagrakata Bhagatpur Tea Garden Area Piped Water Supply Scheme.,SM/09975 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 22/09/2021 01/02/2022 31/03/2025 29/12/2025 33 1,906 385.01 225.42 60 59
73 Jalpaiguri Division JALPAIGURI Mal Augmentation of Kranti Piped water supply Scheme,SM/09994 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 20/12/2021 24/01/2022 31/03/2025 29/12/2025 34 5,563 1,755.80 1,000.63 75 57
74 Jalpaiguri Division JALPAIGURI Rajganj Augmentation of Sukani Piped Water Supply Scheme,SM/09995 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 20/12/2021 31/01/2022 31/12/2025 29/12/2025 96 14,294 4,370.14 2,615.13 75 60
75 Jalpaiguri Division JALPAIGURI Rajganj Augmentation of Sannyasikata Piped Water Supply Scheme,SM/09996 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 20/12/2021 01/02/2022 30/05/2025 29/12/2025 43 6,379 2,105.11 1,474.23 85 70
76 Jalpaiguri Division JALPAIGURI Maynaguri Augmentation of Madhya Khagrabari Water Supply Scheme.,SM/10028 Augmentation Northern Mechanical Division Assistant Engineer , Head Quarters , NMD Junior Engineer 17/01/2022 21/01/2022 31/05/2025 29/12/2025 33 3,594 986.41 733.68 80 74
77 Jalpaiguri Division JALPAIGURI Maynaguri Augmentation of Ramsai Water Supply Scheme.,SM/10033 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 19/01/2022 24/01/2022 31/05/2025 29/12/2025 21 3,250 976.19 753.72 90 77
78 Jalpaiguri Division JALPAIGURI Maynaguri Augmentation of Maynaguri Piped Water Supply Scheme. ,SM/10042 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 2 20/01/2022 10/02/2022 31/12/2025 29/12/2025 48 7,191 978.70 564.17 72 58
79 Jalpaiguri Division JALPAIGURI Dhupguri Augmentation of Jalapara Piped Water Supply Scheme,SM/10043 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 20/01/2022 13/07/2023 31/12/2025 29/12/2025 9 1,573 620.86 341.68 60 55
80 Jalpaiguri Division JALPAIGURI Dhupguri Augmentation of Banerhat Bazar Piped Water Supply Scheme,SM/10044 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 20/01/2022 01/03/2023 31/12/2025 29/12/2025 24 3,913 671.77 439.69 75 65
81 Jalpaiguri Division JALPAIGURI Nagrakata Rejuvenation of Hila Tea Garden area piped water supply scheme,SM/10070 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 27/01/2022 01/02/2022 30/06/2025 29/12/2025 24 0 208.35 151.33 95 73
82 Jalpaiguri Division JALPAIGURI Nagrakata AUGMENTATION OF ANGRABHASA PIPED WATER SUPPLY SCHEME.,SM/10071 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 27/01/2022 05/04/2022 31/07/2025 29/12/2025 15 1,235 521.15 296.98 80 57
83 Jalpaiguri Division JALPAIGURI Jalpaiguri Augmentation of Dakshin Berubari Water Supply Scheme.,SM/10086 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 01/02/2022 03/02/2022 30/04/2025 29/12/2025 27 4,905 1,574.27 842.17 85 53
84 Jalpaiguri Division JALPAIGURI Jalpaiguri Augmentation of Mondalghat Water Supply Scheme.,SM/10087 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 01/02/2022 03/02/2022 31/12/2025 29/12/2025 22 3,793 1,095.64 689.74 95 63
85 Jalpaiguri Division JALPAIGURI Jalpaiguri Augmentation of Kharija-Berubari Water Supply Scheme.,SM/10088 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 01/02/2022 02/02/2022 30/04/2025 29/12/2025 25 5,781 2,064.37 1,264.19 87 61
86 Jalpaiguri Division JALPAIGURI Maynaguri Augmentation of Baikur Piped Water Supply Scheme.,SM/10089 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 01/02/2022 01/02/2022 30/05/2025 29/12/2025 42 7,173 1,763.64 1,258.88 82 71
87 Jalpaiguri Division JALPAIGURI Maynaguri Augmentation of Barnes Water Supply Scheme.,SM/10090 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 01/02/2022 02/02/2022 31/08/2025 29/12/2025 39 4,046 1,115.54 968.14 85 87
88 Jalpaiguri Division JALPAIGURI Nagrakata IMPLEMENTATION OF STANDALONE WATER SUPPLY SYSTEM IN THE VILLAGES HAVING LESS THAN 100 HOUSEHOLD UNDER JALPAIGURI DISTRICT,SM/10775 New RWS Jalpaiguri Sub-Division Junior Engineer 23/05/2022 01/06/2022 31/03/2025 29/12/2025 1 783 536.12 74.74 50 14
89 Jalpaiguri Division JALPAIGURI Matiali REJUVENATION OF METELIBAZAR PWSS,SM/11813 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 16/08/2022 26/04/2022 31/05/2025 29/12/2025 25 1,904 721.07 206.11 25 29
90 Jalpaiguri Division JALPAIGURI Nagrakata AUGMENTATION OF LUKSAN BAZAR PWSS,SM/11814 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 16/08/2022 28/02/2022 30/04/2025 29/12/2025 36 1,895 616.25 203.51 48 33
91 Jalpaiguri Division JALPAIGURI Nagrakata Augmentation of Bhatipara Water Supply Scheme,SM/13277 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 19/09/2022 01/03/2023 31/12/2025 29/12/2025 29 5,116 1,483.83 716.59 60 48
92 Jalpaiguri Division JALPAIGURI Mal Augmentation of Lataguri Piped Water Supply Scheme,SM/13278 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 19/09/2022 26/04/2022 31/08/2025 29/12/2025 58 4,977 1,834.70 1,313.97 75 72
93 Jalpaiguri Division JALPAIGURI Dhupguri MADHYA BAROGARI ZONE-I PIPED WATER SUPPLY SCHEME,SM/13681 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 14/11/2022 02/08/2023 02/08/2025 29/12/2025 10 2,185 807.25 234.05 40 29
94 Jalpaiguri Division JALPAIGURI Maynaguri DAKHSIN PUTIMARI PIPED WATER SUPPLY SCHEME,SM/13700 New RWS Jalpaiguri Sub-Division Junior Engineer 14/11/2022 02/08/2023 02/08/2025 29/12/2025 14 1,413 661.12 342.44 55 52
95 Jalpaiguri Division JALPAIGURI Maynaguri GAURGRAM PIPED WATER SUPPLY SCHEME,SM/13701 New RWS Jalpaiguri Sub-Division Junior Engineer 14/11/2022 02/08/2023 02/08/2025 29/12/2025 14 1,472 594.88 386.73 65 65
96 Jalpaiguri Division JALPAIGURI Rajganj MAHANBHITA PIPED WATER SUPPLY SCHEME,SM/13702 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 14/11/2022 26/05/2023 31/03/2025 29/12/2025 16 2,113 868.48 360.91 44 42
97 Jalpaiguri Division JALPAIGURI Matiali BARA DIGHI PIPED WATER SUPPLY SCHEME,SM/13703 New Jalpaiguri Sadar Sub-Division Junior Engineer 14/11/2022 01/03/2023 30/06/2025 29/12/2025 6 210 156.26 84.68 85 54
98 Jalpaiguri Division JALPAIGURI Jalpaiguri SHAKATI PIPED WATER SUPPLY SCHEME,SM/13704 New RWS Jalpaiguri Sub-Division Junior Engineer 14/11/2022 02/08/2023 02/08/2025 29/12/2025 14 2,042 557.70 314.76 75 56
99 Jalpaiguri Division JALPAIGURI Maynaguri BRAHMAPUR PIPED WATER SUPPLY SCHEME,SM/13705 New RWS Jalpaiguri Sub-Division Junior Engineer 14/11/2022 02/08/2023 02/08/2025 29/12/2025 14 2,545 988.14 320.51 40 32
100 Jalpaiguri Division JALPAIGURI Mal Augmentation of Odlabari Piped Water Supply Scheme,SM/13790 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 21/10/2022 05/04/2022 31/12/2025 29/12/2025 29 3,348 1,003.52 573.10 90 57
101 Jalpaiguri Division JALPAIGURI Dhupguri UTTAR ALTAGRAM PIPED WATER SUPPLY SCHEME ,SM/13899 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 25/11/2022 24/05/2023 31/03/2025 29/12/2025 13 1,798 772.86 530.07 65 69
102 Jalpaiguri Division JALPAIGURI Matiali CHHAOAPHALI PIPED WATER SUPPLY SCHEME ,SM/13901 New Jalpaiguri Sadar Sub-Division Junior Engineer 25/11/2022 28/04/2023 31/12/2025 29/12/2025 10 462 236.73 113.69 70 48
103 Jalpaiguri Division JALPAIGURI Matiali PIPE WATER SUPPLY SCHEME FOR UTTAR DHUPJHORA ,SM/13988 New Jalpaiguri Sadar Sub-Division Junior Engineer 01/12/2022 20/03/2023 31/07/2025 29/12/2025 16 1,157 355.60 260.78 80 73
104 Jalpaiguri Division JALPAIGURI Nagrakata PIPE WATER SUPPLY SCHEME FOR UPPER TENDU FOREST,SM/13989 New Jalpaiguri Sadar Sub-Division Junior Engineer 01/12/2022 16/03/2023 31/05/2025 29/12/2025 9 360 143.56 95.71 90 67
105 Jalpaiguri Division JALPAIGURI Nagrakata PIPE WATER SUPPLY SCHEME FOR TANDU ,SM/13990 New Jalpaiguri Sadar Sub-Division Junior Engineer 01/12/2022 24/03/2023 31/07/2025 29/12/2025 10 396 177.66 86.27 80 49
106 Jalpaiguri Division JALPAIGURI Dhupguri NIRANJANPAT WATER SUPPLY SCHEME,SM/13991 New 01/12/2022 02/08/2023 02/08/2025 29/12/2025 12 866 543.63 140.44 35 26
107 Jalpaiguri Division JALPAIGURI Jalpaiguri BINNAGURI PIPED WATER SUPPLY SCHEME ,SM/14198 New RWS Jalpaiguri Sub-Division Junior Engineer 10/01/2023 02/08/2023 02/08/2025 29/12/2025 11 1,553 409.19 197.82 70 48
108 Jalpaiguri Division JALPAIGURI Maynaguri KAOAGAP PIPED WATER SUPPLY SCHEME,SM/14199 New RWS Jalpaiguri Sub-Division Junior Engineer 10/01/2023 02/08/2023 02/08/2025 29/12/2025 15 984 647.34 299.00 65 46
109 Jalpaiguri Division JALPAIGURI Rajganj SAMAR NAGAR PIPED WATER SUPPLY SCHEME,SM/14200 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 10/01/2023 02/08/2023 02/08/2025 29/12/2025 10 2,644 779.10 334.15 80 43
110 Jalpaiguri Division JALPAIGURI Rajganj SIMULGURI PIPED WATER SUPPLY SCHEME,SM/14240 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 16/01/2023 30/03/2023 30/06/2025 29/12/2025 15 2,948 1,172.27 763.15 85 65
111 Jalpaiguri Division JALPAIGURI Rajganj PANI KAURI PIPED WATER SUPPLY SCHEME,SM/14241 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 16/01/2023 02/08/2023 02/08/2025 29/12/2025 23 3,891 1,381.36 409.42 35 30
112 Jalpaiguri Division JALPAIGURI Rajganj CHHOTA FAPRI WATER SUPPLY SCHEME,SM/14494 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 20/01/2023 03/05/2023 30/09/2025 29/12/2025 7 758 304.33 79.47 25 26
113 Jalpaiguri Division JALPAIGURI Dhupguri UTTAR KHUTTIMARI PIPED WATER SUPPLY SCHEME ,SM/14660 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 31/01/2023 06/06/2023 31/12/2025 29/12/2025 10 1,074 520.46 208.11 70 40
114 Jalpaiguri Division JALPAIGURI Dhupguri GAIRKHATA TEA GARDEN (D) PIPED WATER SUPPLY SCHEME ,SM/14664 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 31/01/2023 06/03/2023 30/04/2025 29/12/2025 12 2,319 870.88 530.37 95 61
115 Jalpaiguri Division JALPAIGURI Dhupguri GADANG PRATHAM KHANDA PIPED WATER SUPPLY SCHEME,SM/14665 New 31/01/2023 02/08/2023 02/08/2025 29/12/2025 9 425 417.67 170.84 60 41
116 Jalpaiguri Division JALPAIGURI Dhupguri GENDRAPARA TEA GARDEN PIPED WATER SUPPLY SCHEME,SM/14666 New Northern Mechanical Division Assistant Engineer , Head Quarters , NMD,Assistant Engineer,HQ Junior Engineer 31/01/2023 02/08/2023 02/08/2025 29/12/2025 15 2,390 852.43 436.35 90 51
117 Jalpaiguri Division JALPAIGURI Maynaguri PASCHIM BARAGILA PIPED WATER SUPPLY SCHEME,SM/14667 New RWS Jalpaiguri Sub-Division Junior Engineer 31/01/2023 02/08/2023 02/08/2025 29/12/2025 15 469 464.69 210.19 64 45
118 Jalpaiguri Division JALPAIGURI Maynaguri DHARMMAPUR ZONE-I PIPED WATER SUPPLY SCHEME,SM/14826 New RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2023 25/04/2023 31/12/2025 29/12/2025 15 1,067 551.68 218.78 60 40
119 Jalpaiguri Division JALPAIGURI Mal RANGAMATI TEA GARDEN PIPED WATER SUPPLY SCHEME,SM/14880 New Jalpaiguri Sadar Sub-Division Junior Engineer 03/02/2023 08/08/2023 31/12/2025 29/12/2025 13 2,050 732.10 111.46 22 15
120 Jalpaiguri Division JALPAIGURI Mal PURBA DOLAIGAON PIPED WATER SUPPLY SCHEME,SM/14881 New Jalpaiguri Sadar Sub-Division Junior Engineer 03/02/2023 24/05/2023 31/12/2025 29/12/2025 14 2,106 681.26 158.80 62 23
121 Jalpaiguri Division JALPAIGURI Maynaguri DHARMMAPUR ZONE-II PIPED WATER SUPPLY SCHEME,SM/14882 New RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2023 25/04/2023 30/06/2025 29/12/2025 14 1,110 558.05 199.48 63 36
122 Jalpaiguri Division JALPAIGURI Mal TUNBARI TEA GARDEN (P) PIPED WATER SUPPLY SCHEME ,SM/14883 New Jalpaiguri Sadar Sub-Division Junior Engineer 03/02/2023 10/05/2023 31/08/2025 29/12/2025 14 1,611 544.31 112.95 80 21
123 Jalpaiguri Division JALPAIGURI Mal RANICHERA TEA GARDEN PIPED WATER SUPPLY SCHEME ,SM/14885 New Jalpaiguri Sadar Sub-Division Junior Engineer 03/02/2023 28/07/2023 31/12/2025 29/12/2025 17 2,665 913.53 708.32 90 78
124 Jalpaiguri Division JALPAIGURI Mal WASHABARI TEA GARDEN PIPED WATER SUPPLY SCHEME ,SM/14886 New Jalpaiguri Sadar Sub-Division Junior Engineer 03/02/2023 05/06/2023 31/03/2025 29/12/2025 11 1,312 525.39 53.69 25 10
125 Jalpaiguri Division JALPAIGURI Maynaguri DAKSHIN DANGAPARA ZONE-I PIPED WATER SUPPLY SCHEME,SM/14887 New RWS Jalpaiguri Sub-Division Junior Engineer 03/02/2023 30/05/2023 30/06/2025 29/12/2025 12 1,619 641.10 288.43 75 45
126 Jalpaiguri Division JALPAIGURI Mal KHAS JANGAL PIPED WATER SUPPLY SCHEME,SM/14907 New Jalpaiguri Sadar Sub-Division Junior Engineer 03/02/2023 08/08/2023 31/12/2025 29/12/2025 6 456 245.77 13.04 20 5
127 Jalpaiguri Division JALPAIGURI Mal DAKSHIN KANTADIGHI KUMARPARA PIPED WATER SUPPLY SCHEME,SM/14908 New Jalpaiguri Sadar Sub-Division Junior Engineer 03/02/2023 24/03/2023 31/03/2025 29/12/2025 11 428 248.15 91.71 68 37
128 Jalpaiguri Division JALPAIGURI Mal NIDAM JHORA TEA GARDEN PIPED WATER SUPPLY SCHEME,SM/14911 New Jalpaiguri Sadar Sub-Division Junior Engineer 03/02/2023 08/08/2023 30/04/2025 29/12/2025 11 590 274.41 107.09 47 39
129 Jalpaiguri Division JALPAIGURI Maynaguri UTTAR MAUAMARI PIPED WATER SUPPLY SCHEME,SM/14914 New RWS Jalpaiguri Sub-Division Junior Engineer 03/02/2023 13/07/2023 30/05/2025 29/12/2025 13 2,374 478.22 239.08 55 50
130 Jalpaiguri Division JALPAIGURI Maynaguri UTTAR MARICHBARI PIPED WATER SUPPLY SCHEME,SM/14919 New RWS Jalpaiguri Sub-Division Junior Engineer 03/02/2023 27/03/2023 30/06/2025 29/12/2025 13 2,306 366.08 166.58 80 46
131 Jalpaiguri Division JALPAIGURI Jalpaiguri REJUVENATION OF ARJI GARALBARI PWSS,SM/15030 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2023 29/03/2023 30/06/2025 29/12/2025 15 0 172.44 83.32 95 48
132 Jalpaiguri Division JALPAIGURI Maynaguri REJUVENATION OF HASLURDANGA PIPED WATER SUPPLY SCHEME,SM/15031 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2023 16/03/2023 31/12/2025 29/12/2025 9 0 161.99 102.58 90 63
133 Jalpaiguri Division JALPAIGURI Maynaguri Rejuvenation of Bhangarhat Piped Water Supply Scheme,SM/15032 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 04/02/2023 24/05/2023 31/03/2025 29/12/2025 7 0 178.30 37.96 95 21
134 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Chauhaddi Piped Water Supply Scheme ,SM/15033 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 04/02/2023 24/05/2023 31/12/2025 29/12/2025 5 0 198.79 59.42 80 30
135 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Baradighi Tea Garden Area Piped Water Supply Scheme,SM/15059 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 04/02/2023 09/03/2023 30/06/2025 29/12/2025 11 0 127.24 62.04 45 49
136 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Nagaisuree Tea Garden Area Piped Water Supply Scheme,SM/15060 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 04/02/2023 22/05/2023 30/06/2025 29/12/2025 8 0 285.02 90.77 20 32
137 Jalpaiguri Division JALPAIGURI Mal REJUVENATION OF JOGESH CHANDRA TEA GARDEN AREA PWSS,SM/15068 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2023 14/07/2023 31/08/2025 29/12/2025 6 0 70.86 37.19 82 52
138 Jalpaiguri Division JALPAIGURI Jalpaiguri REJUVENATION OF RAIPUR TEA GARDEN AREA PWSS,SM/15071 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2023 01/06/2023 31/12/2025 29/12/2025 5 1,015 177.04 53.99 90 30
139 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Mogalkata Tea Garden Area Piped Water Supply Scheme,SM/15075 Augmentation RWS Jalpaiguri Sub-Division Assistant Engineer Junior Engineer 04/02/2023 01/03/2023 31/12/2025 29/12/2025 8 0 158.29 48.19 80 30
140 Jalpaiguri Division JALPAIGURI Maynaguri REJUVENATION OF PASCHIM SALBARI PWSS,SM/15076 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 2 04/02/2023 01/03/2023 31/12/2025 29/12/2025 11 2,840 399.40 46.34 25 12
141 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Uttar Danga Para & Dakshin Sakojhora Piped Water Supply Scheme,SM/15078 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 04/02/2023 22/05/2023 30/05/2025 29/12/2025 10 0 157.06 25.79 65 16
142 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation for Patkidaha Piped Water Supply Scheme,SM/15085 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 04/02/2023 01/03/2023 31/12/2025 29/12/2025 13 0 145.15 66.90 80 46
143 Jalpaiguri Division JALPAIGURI Dhupguri REJUVENATION OF DAKSHIN SALBARI PWSS,SM/15087 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 2 04/02/2023 02/03/2023 31/05/2025 29/12/2025 10 2,129 246.25 29.94 85 12
144 Jalpaiguri Division JALPAIGURI Rajganj REJUVENATION OF AMBARI FALAKATA PIPED WATER SUPPLY SCHEME,SM/15089 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 04/02/2023 08/06/2023 31/12/2025 29/12/2025 4 0 151.59 33.40 35 22
145 Jalpaiguri Division JALPAIGURI Dhupguri REJUVENATION OF BHANDANI PIPED WATER SUPPLY SCHEME,SM/15094 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 04/02/2023 13/07/2023 30/05/2025 29/12/2025 8 0 125.87 35.91 50 29
146 Jalpaiguri Division JALPAIGURI Maynaguri REJUVENATION OF BHANGAMALI PIPED WATER SUPPLY SCHEME,SM/15096 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 04/02/2023 06/02/2023 31/07/2025 29/12/2025 6 0 119.10 24.12 95 20
147 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Mathachulka Piped Water Supply Scheme,SM/15098 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 04/02/2023 13/07/2023 04/06/2025 29/12/2025 11 0 175.20 90.65 60 52
148 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Palasbari Tea Garden Area Piped Water Supply Scheme,SM/15099 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 04/02/2023 06/02/2023 31/07/2025 29/12/2025 6 0 150.59 38.96 70 26
149 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvanation of Riabari Tea Garden Area Piped Water Supply Scheme,SM/15103 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 04/02/2023 30/05/2023 31/12/2025 29/12/2025 6 0 149.74 77.07 80 51
150 Jalpaiguri Division JALPAIGURI Maynaguri REJUVENATION OF JABRAMALI PIPED WATER SUPPLY SCHEME,SM/15109 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2023 02/08/2023 02/08/2025 29/12/2025 8 0 182.13 48.72 44 27
151 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Chilouni Tea Garden Area Piped Water Supply Scheme,SM/15114 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 04/02/2023 01/03/2023 31/12/2025 29/12/2025 12 0 255.47 177.47 78 69
152 Jalpaiguri Division JALPAIGURI Mal NEORA NADI TEA GARDEN PIPED WATER SUPPLY SCHEME,SM/15115 New Jalpaiguri Sadar Sub-Division Junior Engineer 04/02/2023 08/05/2023 31/03/2025 29/12/2025 14 1,368 560.37 300.03 98 54
153 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Nakhati Tea Garden Area Piped Water Supply Scheme ,SM/15116 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 04/02/2023 25/05/2023 31/12/2025 29/12/2025 9 0 194.43 110.93 85 57
154 Jalpaiguri Division JALPAIGURI Mal Rejuvenation of Syli Tea Garden Area Piped Water Supply Scheme,SM/15117 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 04/02/2023 01/03/2023 30/04/2025 29/12/2025 10 0 196.67 162.46 98 83
155 Jalpaiguri Division JALPAIGURI Nagrakata Rejuvenation of Grassmore Tea Garden Area Piped Water Supply Scheme,SM/15130 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 04/02/2023 01/03/2023 31/12/2025 29/12/2025 9 1,315 182.74 46.18 70 25
156 Jalpaiguri Division JALPAIGURI Jalpaiguri RETROFITTING OF MAHITNAGAR PWSS,SM/15131 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2023 08/06/2023 31/12/2025 29/12/2025 2 0 180.43 75.34 98 42
157 Jalpaiguri Division JALPAIGURI Jalpaiguri RETROFITTING OF ARJI MARIA KAMALA PUKHARI PIPED WATER SUPPLY SCHEME,SM/15132 Retrofitting RWS Jalpaiguri Sub-Division Junior Engineer 04/02/2023 08/06/2023 31/12/2025 29/12/2025 3 0 189.88 83.59 70 44
158 Jalpaiguri Division JALPAIGURI Dhupguri DIANA TEA GARDEN (D) PIPED WATER SUPPLY SCHEME,SM/15261 New Northern Mechanical Division Assistant Engineer , Head Quarters , NMD,Assistant Engineer,HQ Junior Engineer 08/02/2023 02/08/2023 02/08/2025 29/12/2025 15 966 545.43 167.09 65 31
159 Jalpaiguri Division JALPAIGURI Dhupguri LAKSHMI PARA TEA GARDEN PIPED WATER SUPPLY SCHEME,SM/15262 New Northern Mechanical Division Assistant Engineer , Head Quarters , NMD,Assistant Engineer,HQ Junior Engineer 08/02/2023 02/08/2023 02/08/2025 29/12/2025 14 1,408 635.17 285.29 90 45
160 Jalpaiguri Division JALPAIGURI Rajganj KHOLACHAND FAPRI PIPED WATER SUPPLY SCHEME,SM/15263 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 07/02/2023 10/05/2023 30/06/2025 29/12/2025 8 1,212 399.34 61.06 25 15
161 Jalpaiguri Division JALPAIGURI Matiali CHALSA TEA GARDEN PIPED WATER SUPPLY SCHEME ,SM/15264 New Jalpaiguri Sadar Sub-Division Junior Engineer 07/02/2023 25/01/2022 30/06/2025 29/12/2025 13 1,080 345.92 163.74 80 47
162 Jalpaiguri Division JALPAIGURI Mal NIPUCHHAPUR TEA GARDEN PIPED WATER SUPPLY SCHEME ,SM/15296 New Jalpaiguri Sadar Sub-Division Junior Engineer 09/02/2023 08/05/2023 31/03/2025 29/12/2025 12 1,832 604.63 263.98 70 44
163 Jalpaiguri Division JALPAIGURI Mal GAJALDOBA TEA GARDEN PIPED WATER SUPPLY SCHEME ,SM/15297 New Jalpaiguri Sadar Sub-Division Junior Engineer 09/02/2023 07/06/2023 31/12/2025 29/12/2025 16 1,991 724.23 165.38 60 23
164 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Karbala Tea Garden Piped Water Supply Scheme,SM/15298 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 09/02/2023 13/04/2023 30/04/2025 29/12/2025 5 0 241.44 149.23 90 62
165 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Yongtong Tea Garden Area Pipe Water Supply Scheme,SM/15299 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 09/02/2023 09/03/2023 31/03/2025 29/12/2025 11 0 139.34 77.61 72 56
166 Jalpaiguri Division JALPAIGURI Nagrakata Rejuvenation of Nagrakata Tea Garden Area Piped Water Supply Scheme,SM/15300 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 09/02/2023 08/06/2023 30/05/2025 29/12/2025 11 0 159.96 140.78 85 88
167 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Samsing Tea Garden Area Piped Water Supply Scheme,SM/15301 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 09/02/2023 13/07/2023 30/05/2025 29/12/2025 9 0 391.48 92.62 30 24
168 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Purba Duramari Piped Water Supply Scheme,SM/15326 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 09/02/2023 22/05/2023 30/06/2025 29/12/2025 5 1,409 206.58 51.40 70 25
169 Jalpaiguri Division JALPAIGURI Mal DAKSHIN HANSKHALI PIPED WATER SUPPLY SCHEME,SM/15335 New Northern Mechanical Division Assistant Engineer , Head Quarters , NMD Junior Engineer 09/02/2023 24/07/2023 30/05/2025 29/12/2025 18 2,792 850.70 260.63 72 31
170 Jalpaiguri Division JALPAIGURI Nagrakata Rejuvenation of ANGRABHASA WATER SUPPLY SCHEME,SM/15338 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 09/02/2023 02/08/2023 02/08/2025 29/12/2025 4 0 121.26 77.57 80 64
171 Jalpaiguri Division JALPAIGURI Jalpaiguri PATKATA ZONE-I PIPED WATER SUPPLY SCHEME,SM/15339 New RWS Jalpaiguri Sub-Division Junior Engineer 09/02/2023 02/08/2023 02/08/2025 29/12/2025 15 4,224 980.45 236.45 60 24
172 Jalpaiguri Division JALPAIGURI Dhupguri JHAR SHALBARI PIPED WATER SUPPLY SCHEME,SM/15742 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 20/02/2023 28/04/2023 31/03/2025 29/12/2025 11 1,391 678.84 205.35 35 30
173 Jalpaiguri Division JALPAIGURI Dhupguri PASCHIM SALBARI ZONE-I PIPED WATER SUPPLY SCHEME ,SM/15915 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 22/02/2023 08/05/2023 31/12/2025 29/12/2025 12 878 427.23 82.17 25 19
174 Jalpaiguri Division JALPAIGURI Dhupguri KHUKLUNG PIPED WATER SUPPLY SCHEME,SM/15953 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 22/02/2023 02/08/2023 02/08/2025 29/12/2025 3 118 119.09 34.97 60 29
175 Jalpaiguri Division JALPAIGURI Nagrakata CHHAR TANDU PIPED WATER SUPPLY SCHEME,SM/15964 New Northern Mechanical Division Assistant Engineer , Head Quarters , NMD Junior Engineer 22/02/2023 02/08/2023 02/08/2025 29/12/2025 9 573 330.17 64.40 10 20
176 Jalpaiguri Division JALPAIGURI Mal BARA GHARIA PIPED WATER SUPPLY SCHEME,SM/15967 New Jalpaiguri Sadar Sub-Division Junior Engineer 22/02/2023 25/04/2023 30/06/2025 29/12/2025 15 1,304 703.70 271.68 60 39
177 Jalpaiguri Division JALPAIGURI Mal TESIMALA PIPED WATER SUPPLY SCHEME,SM/15970 New Northern Mechanical Division Assistant Engineer , Head Quarters , NMD Junior Engineer 22/02/2023 08/08/2023 31/12/2025 29/12/2025 7 1,140 391.74 145.94 55 37
178 Jalpaiguri Division JALPAIGURI Mal PATHARJOHRA TEA GARDEN PIPED WATER SUPPLY SCHEME ,SM/15978 New Jalpaiguri Sadar Sub-Division Junior Engineer 22/02/2023 23/05/2023 01/04/2025 29/12/2025 16 988 391.48 213.77 45 55
179 Jalpaiguri Division JALPAIGURI Mal ELLENBURY TEA GARDEN PIPED WATER SUPPLY SCHEME,SM/15980 New 22/02/2023 08/08/2023 31/03/2025 29/12/2025 12 694 350.20 66.56 37 19
180 Jalpaiguri Division JALPAIGURI Mal MENGLASS TEA GARDEN PIPED WATER SUPPLY SCHEME ,SM/15990 New Northern Mechanical Division Assistant Engineer , Head Quarters , NMD Junior Engineer 22/02/2023 13/04/2023 31/03/2025 29/12/2025 13 1,096 406.46 176.65 70 43
181 Jalpaiguri Division JALPAIGURI Dhupguri CHAR CHARABARI PIPED WATER SUPPLY SCHEME ,SM/16042 New Northern Mechanical Division Assistant Engineer , Head Quarters , NMD 22/02/2023 08/05/2023 31/08/2025 29/12/2025 11 1,370 568.49 251.61 70 44
182 Jalpaiguri Division JALPAIGURI Maynaguri DAKSHIN DANGAPARA ZONE-II PIPED WATER SUPPLY SCHEME,SM/16181 New RWS Jalpaiguri Sub-Division Junior Engineer 22/02/2023 15/05/2023 31/12/2025 29/12/2025 13 1,385 613.74 266.62 60 43
183 Jalpaiguri Division JALPAIGURI Nagrakata PIPE WATER SUPPLY SCHEME FOR KURTI TEA GARDEN ,SM/16492 New Jalpaiguri Sadar Sub-Division Junior Engineer 02/03/2023 10/05/2023 31/12/2025 29/12/2025 7 1,078 461.81 65.98 5 14
184 Jalpaiguri Division JALPAIGURI Dhupguri BHEMTIA PIPED WATER SUPPLY SCHEME ,SM/16676 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 14/03/2023 06/04/2023 31/12/2025 29/12/2025 7 667 414.83 54.36 60 13
185 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Haritalguri Tea Garden Area Piped Water Supply Scheme,SM/16772 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 13/03/2023 07/06/2023 31/07/2025 29/12/2025 7 1,459 156.25 31.17 80 20
186 Jalpaiguri Division JALPAIGURI Matiali REJUVENATION OF BATABARI TEA GARDEN AREA PIPED WATER SUPPLY SCHEME,SM/16773 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 13/03/2023 02/08/2023 02/08/2025 29/12/2025 6 527 171.57 98.44 86 57
187 Jalpaiguri Division JALPAIGURI Maynaguri PURBA DOBBARI PIPED WATER SUPPLY SCHEME,SM/16776 New RWS Jalpaiguri Sub-Division Junior Engineer 13/03/2023 08/08/2023 30/06/2025 29/12/2025 4 30 89.03 9.13 65 10
188 Jalpaiguri Division JALPAIGURI Jalpaiguri PAHARPUR ZONE-II PIPED WATER SUPPLY SCHEME,SM/16779 New Northern Mechanical Division Assistant Engineer , Head Quarters , NMD Junior Engineer 13/03/2023 28/04/2023 31/03/2025 29/12/2025 13 2,238 709.31 169.61 38 24
189 Jalpaiguri Division JALPAIGURI Mal HAIHAIPATHAR PWSS,SM/16852 New Jalpaiguri Sadar Sub-Division Junior Engineer 13/03/2023 08/06/2023 31/12/2025 29/12/2025 12 2,306 741.68 302.33 60 41
190 Jalpaiguri Division JALPAIGURI Maynaguri REJUVENATION OF UTTAR BHUSKADANGA AND GARTALI JALPESH PWSS,SM/16937 Augmentation RWS Jalpaiguri Sub-Division Junior Engineer 16/03/2023 06/06/2023 30/06/2025 29/12/2025 6 0 161.99 51.79 95 32
191 Jalpaiguri Division JALPAIGURI Nagrakata Rejuvenation of Gatia Tea Garden Area Piped Water supply Scheme,SM/17181 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 15/03/2023 15/05/2023 31/12/2025 29/12/2025 3 1,317 201.66 7.59 5 4
192 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Aibhil Tea Garden Area Piped Water Supply Scheme,SM/17185 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 15/03/2023 26/05/2023 31/03/2025 29/12/2025 7 940 180.04 107.71 99 60
193 Jalpaiguri Division JALPAIGURI Dhupguri BARAGHARIA Piped Water Supply Scheme.,SM/17649 New Northern Mechanical Division Assistant Engineer , Head Quarters , NMD,Assistant Engineer,HQ Junior Engineer 22/03/2023 24/05/2023 31/07/2025 29/12/2025 8 2,063 613.18 271.50 90 44
194 Jalpaiguri Division JALPAIGURI Matiali REJUVENATION OF ENGO TEA GARDEN AREA PIPED WATER SUPPLY SCHEME,SM/17681 Augmentation Jalpaiguri Sadar Sub-Division Junior Engineer 17/03/2023 08/06/2023 31/12/2025 29/12/2025 6 240 116.16 70.27 70 60
195 Jalpaiguri Division JALPAIGURI Dhupguri Rejuvenation of Mainatali Piped Water Supply Scheme Phase-II,SM/18094 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 27/03/2023 06/06/2023 31/12/2025 29/12/2025 3 0 185.13 41.82 45 23
196 Jalpaiguri Division JALPAIGURI Rajganj REJUVENATION OF DABGRAM-II PIPED WATER SUPPLY SCHEME,SM/18283 Augmentation Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 23/06/2023 08/08/2023 31/12/2025 29/12/2025 38 19,720 2,862.78 629.00 40 22
197 Jalpaiguri Division JALPAIGURI Mal CHENGMARIHAT PIPED WATER SUPPLY SCHEME,SM/18358 New 11/07/2023 28/07/2023 30/05/2025 29/12/2025 14 3,607 1,399.31 523.62 50 37
198 Jalpaiguri Division JALPAIGURI Mal BASUSUBA PIPED WATER SUPPLY SCHEME,SM/18359 New 11/07/2023 28/07/2023 30/05/2025 29/12/2025 16 2,822 1,257.66 314.16 35 25
199 Jalpaiguri Division JALPAIGURI Jalpaiguri PATKATA ZONE-II PIPED WATER SUPPLY SCHEME,SM/18360 New 11/07/2023 02/08/2023 02/08/2025 29/12/2025 13 4,224 1,152.06 320.29 60 28
200 Jalpaiguri Division JALPAIGURI Maynaguri Kumarpara Piped Water Supply Scheme.,SM/18491 New 24/07/2023 08/08/2023 30/05/2025 29/12/2025 13 2,400 845.25 376.45 47 45
201 Jalpaiguri Division JALPAIGURI Maynaguri Chapgar Piped Water Supply Scheme.,SM/18492 New 24/07/2023 08/08/2023 30/05/2025 29/12/2025 18 0 757.75 128.76 40 17
202 Jalpaiguri Division JALPAIGURI Rajganj NOWAPARA PIPED WATER SUPPLY SCHEME,SM/18503 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 26/07/2023 02/08/2023 02/08/2025 29/12/2025 16 3,633 1,060.21 60.47 10 6
203 Jalpaiguri Division JALPAIGURI Rajganj SALUGARA PIPED WATER SUPPLY SCHEME,SM/18625 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 31/07/2023 02/08/2023 02/08/2025 29/12/2025 16 5,286 1,182.82 313.11 30 26
204 Jalpaiguri Division JALPAIGURI Mal DAMDIM TEA GARDEN PIPED WATER SUPPLY SCHEME,SM/18711 New 04/08/2023 02/08/2023 02/08/2025 29/12/2025 15 1,951 584.88 228.76 90 39
205 Jalpaiguri Division JALPAIGURI Matiali Rejuvenation of Sathkaya Tea Garden Area Piped Water Supply Scheme,SM/18713 Augmentation 04/08/2023 02/08/2023 02/08/2025 29/12/2025 9 1,019 213.69 35.32 38 17
206 Jalpaiguri Division JALPAIGURI Maynaguri Saptibari Piped Water Supply Scheme.,SM/18759 New RWS Jalpaiguri Sub-Division Assistant Engineer Junior Engineer 23/08/2023 02/08/2023 02/08/2025 29/12/2025 23 663 2,026.68 993.08 80 49
207 Jalpaiguri Division JALPAIGURI Jalpaiguri Satkhamar Piped Water Supply Scheme.,SM/18760 New 23/08/2023 02/08/2023 02/08/2025 29/12/2025 21 7,058 2,137.78 588.35 45 28
208 Jalpaiguri Division JALPAIGURI Maynaguri Singimari Piped Water Supply Scheme.,SM/18761 New 23/08/2023 02/08/2023 02/08/2025 29/12/2025 10 2,814 1,138.97 281.65 40 25
209 Jalpaiguri Division JALPAIGURI Dhupguri Dakshin Jharalta Piped Water Supply Scheme.,SM/18835 New Jalpaiguri Division Assistant Engineer,HQ Junior Engineer 21/09/2023 23/10/2023 31/12/2025 29/12/2025 7 3,531 1,190.83 448.44 50 38
210 Jalpaiguri Division JALPAIGURI Jalpaiguri PAHARPUR ZONE-I PIPED WATER SUPPLY SCHEME,SM/19097 New 08/12/2023 14/12/2023 31/12/2025 29/12/2025 13 3,357 1,000.22 264.79 60 26
211 Jalpaiguri Division JALPAIGURI Nagrakata AUGMENTATION OF CHENGMARI TEA GARDEN PIPED WATER SUPPLY SCHEME,SM/19175 Augmentation 15/02/2024 28/02/2024 31/12/2025 29/12/2025 3 2,814 1,266.28 59.85 5 5
Total 3,020 3,63,383 1,06,331.75 50,912.62   48