D4- Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Clear
Rs. in Lakh
Sl No. Division
Working Divisions
Sub Division
Working Divisions
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
2185 76,772.01 44,977.09  
1 Alipurduar Division New Connection for Toorsa TG Zone-I Phase-II BILL/00032/2022-2023 357/22-23/PFMS 12/12/2022 0 WBSEDCL 1.19 0.00 0
2 Alipurduar Division New Connection for Torsa TG Zone-II Phase-I BILL/00033/2022-2023 358/22-23/PFMS 12/12/2022 0 WBSEDCL 1.19 0.00 0
3 Alipurduar Division New Connection for Torsa TG Zone-II BILL/00034/2022-2023 359/22-23/PFMS 12/12/2022 0 WBSEDCL 1.19 0.00 0
4 Alipurduar Division New Connection for Torsa TG Zone-I Phase-I BILL/00035/2022-2023 360/22-23/PFMS 12/12/2022 0 WBSEDCL 1.19 0.00 0
5 Alipurduar Division NEW CONNECTION FOR TUTURIKHANDA BILL/00044/2022-2023 394/22-23/PFMS 21/12/2022 0 WBSEDCL 0.08 0.00 0
6 Alipurduar Division Procurement of Laptop,Tab .Assemble Deskton Printer VC accessories and Other related accessories Tor all Permanent & contractual JE. all Assistant Engineer and Divisional Staff at Alipurduar PHED. BILL/00098/2024-2025 77/24-25/PFMS 21/06/2024 0 CYBERNET 31.34 0.00 0
7 Alipurduar Division New Connection for Assistant Engineer Alipurduar RWS Sub-Division PHE Reti Forest, Bandapani BILL/00106/2022-2023 444/22-23/PFMS 21/01/2023 0 WBSEDCL 0.10 0.00 0
8 Alipurduar Division Quotation for New Connection for Dangapara, Sishujumra BILL/00107/2022-2023 445/22-23/PFMS 21/01/2023 0 WBSEDCL 0.10 0.00 0
9 Alipurduar Division Quotation for New Connection in Dalgaon BILL/00108/2022-2023 446/22-23/PFMS 21/01/2023 0 WBSEDCL 0.10 0.00 0
10 Alipurduar Division Payment of Net Present value( NPV) against proposal no:FP/WB/Others /443394/2023- Cornpensatory levies {demand rote) againstIn-principal (Stage-l) approval of Water Supply Scheme Buxa forest PWSS {Z-Il} Pampu Basty under,Jal Jeelan Mission at Pampu Basti Forest Village - reg"(Annexure- I) BILL/00155/2024-2025 154/24-25/PFMS 08/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 2.59 0.00 0
11 Alipurduar Division Payment for compensatory afforestation under proposal no FP/WB/others/443394/2023-C0mpenatory Levies(demand note) against In- principal of water supply scheme Buxa forest pwss ( Z-II)Pampu Basty under Jal Jeevan misson at pampu basti forest village - reg as per annexture-2 BILL/00156/2024-2025 153/24-25/PFMS 08/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 2.13 0.00 0
12 Alipurduar Division Payment for boundary demarcation and construction of boundary pillar for the principal ( stage-I) approval for diversion of the forest land of area 0.0232 ha for water supply scheme Buxa forest PWSS(Z-II) Pampu Basty under proposal No :FP/WB/Others/443394/2023 BILL/00157/2024-2025 152/24-25/PFMS 08/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 0.52 0.00 0
13 Alipurduar Division Payment of Net Present value ( NPV) against proposal no : FP/WB/Others/443377/2023- Compensatory levies ( Demand Note ) against In Principal ( Stage-I) approval of water supply scheme for Buxa Forest PWSS ( Z-II)Garo Basty under JJM at Garo Basti Forest Village- reg BILL/00158/2024-2025 157/24-25/PFMS 08/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 17.54 0.00 0
14 Alipurduar Division Payment for compensatory afforestation under proposal no : FP/WB/Others/443377/2023-Compensatory levies ( Demand note) against In - Principal ( Stage-I) approval of Water supply scheme for Buxa Forest PWSS ( Z-II) Garo Basty under jal Jeevan Mission at Garo Basti Forest Village- reg BILL/00159/2024-2025 155/24-25/PFMS 08/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 2.13 0.00 0
15 Alipurduar Division Payment for boundary demarcation and construction of boundary pillar for the principal ( stage-I) approval for diversion of forest land of area 0.157 ha for Buxa forest PwSS ( Z-II ) Garo BastyUnder Proposal No: FP/WB/Others/443377/2023 BILL/00160/2024-2025 156/24-25/PFMS 08/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 0.94 0.00 0
16 Alipurduar Division Payment of Net Present Value ( NPV) against proposal No : FP/WB/Others/ 443397/2023 - Compensatory Levies ( Demand Note) against in- Principal ( Stage-I) approval of water supply Scheme for Buxa Forest PWSS (Z-II) Panijhora under JJM at Panijhora forest village reg BILL/00161/2024-2025 158/24-25/PFMS 09/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 2.59 0.00 0
17 Alipurduar Division Cost of raising and maintenance of the compensatory afforestation for Ca area 0.04 ha ( 100 trees plantation and maintenance for 10 years) against proposed diversion of forrest land for water supply scheme Buxa forest PWSS ( Z-II) panijhora under JJM at panijhora forest Village reg under proposal NO: FP/WB/Others/443397/2023 BILL/00162/2024-2025 159/24-25/PFMS 09/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 2.13 0.00 0
18 Alipurduar Division payment for boundary demarcation and constuction of boundary pillar for the principal ( Stage - I ) approval for diversion of forest land of .0232 ha area for Buxa forest PWSS ( Z-II) Panijhora under JJM at Panijhora forest village - reg under Proposal No: FP/WB/Others /443397/2023 BILL/00163/2024-2025 160/24-25/PFMS 09/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 0.52 0.00 0
19 Alipurduar Division payment against proposal No : FP/WB/Others/443310/2023for boundary demarcation and construction of boundary pillar for diversion of forest land of area 0.0464 ha for 28 and 29 mile basty PWSS ( Z-IV) Garam basty under JJM at garam basty forest Village under BTR ( West) Division under WDPO Range . BILL/00182/2024-2025 144/24-25/PFMS 08/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 0.94 0.00 0
20 Alipurduar Division Payment for NPV for diversion of forest land of 0.0464 ha area against proposal No : FP/WB/Others/443310/2023 for water supply scheme 28 and 29 Mile Basty PWSS ( Z-VI) Garam Basty under JJM Garam Basty Forest Village under BTR(West ) Division under WDPO Range under DPO_9 Compartment BILL/00183/2024-2025 145/24-25/PFMS 08/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 5.18 0.00 0
21 Alipurduar Division Cost of raising and maintenance of the compensatory afforestation ( 100 trees plantation and mtc for 10 years ) against proposed diversion of forest land for 28 and 29 mile basty PWSS (Z-IV) Garam Basty under JJM against Proposal No : FP/WB/Others/443310/2023 BILL/00184/2024-2025 146/24-25/PFMS 08/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 2.13 0.00 0
22 Alipurduar Division Payment against proposal No : FP/WB/Others /442047/2023-compensatory Levies ( Demand Note)against in- principal ( stage-I) approval of Gravity based WSS for boundary demarcation and construction of boundary pillar for Buxa forest PWSS under JJM at Uttar Poro Forest village -reg BILL/00185/2024-2025 149/24-25/PFMS 08/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 0.52 0.00 0
23 Alipurduar Division Payement aginst proposal no : FP/WB/Others/ 442047/2023 of Net Present Value of 0.0232 ha ( As per Annexure-1) forest land for diversion for gravity base water supply scheme for Buxa forest PWSS at Uttor Poro under JJM under BTR(WEST) Diivision under WDPO range Poro7Compartment BILL/00186/2024-2025 150/24-25/PFMS 08/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 2.59 0.00 0
24 Alipurduar Division Payment as per annexure -2 against proposal No : FP/WB/Others/442047/2023 for raising and maintenance of the compensatory afforestation ( 100 trees plantation and maintence for 1o years ) agaist proposed diversion of forest land forgravity based piped water supply scheme for Buxa forest PWSS under JJm at Uttar Poro BILL/00187/2024-2025 151/24-25/PFMS 08/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 2.13 0.00 0
25 Alipurduar Division payment for NPV Demand Note against In-principal (Stage-l) approval of Central Government under Section 2 (1) (ii) of the Van (Sanrakshan Evam Samvardhan) Adhiniyam-1980 for non-forestry use of 0.1458 ha. of forest land in favour of West Bengal Public Health Engineering Directorate for Gravity Based Water Supply Scheme (GBWSS) under Jal Jeevan Mission (JJM) 28 & 29 Mile Basty PWSS under Buxa Tiger Reserve (East) Forest Division. (Proposal No. FPWBIOTHERSI442029/2023). BILL/00188/2024-2025 147/24-25/PFMS 08/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 15.59 0.00 0
26 Alipurduar Division Cost of raising and maintenance of the Compensatory Afforestation demand note against In-principal (Stage-l) approval of Central Government under Section 2 (1) (ü) of the Van (Sanrakshan Evam Samvardhan) Adhiniyam-1980 for Directorate non-forestry use of 0.1458 ha. of forest land in favour of West Bengal Public Health Engineering for Gravity Based Water Supply Scheme (GBWSS) under Jal Jeevan Mission (JJM) 28 & 29 Mile Basty PWSS under Buxa Tiger Reserve (East) Forest Division. (Proposal No. FPWBIOTHERS/442029/2023 BILL/00189/2024-2025 148/24-25/PFMS 08/08/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 2.13 0.00 0
27 Alipurduar Division Hydro Geological investigation about water evaluation availability and quality parameter for both Ground and surface sources at Lankapara central Dooars Tea Estates within Alipurduar District BILL/00215/2024-2025 164/24-25/PFMS 12/08/2024 0 IIT CONSULTATIVE PRACTICE 9.74 0.00 0
28 Alipurduar Division Road Restoration of Volka Road against Brajerkuthi PWSS BILL/00320/2024-2025 189/24-25/PFMS 10/09/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 10.73 0.00 0
29 Alipurduar Division Road Restoration of Volka Road against PURBA CHIKLIGURI PWSS BILL/00321/2024-2025 190/24-25/PFMS 10/09/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 8.85 0.00 0
30 Alipurduar Division Payment against proposal no . FP/ WB/ Others/ 442029/2023- for erection of Boundary pillar at diverted site against In - principal ( stage - I ) approval of water supply scheme for Buxa Forest PWSS uder Jal Jeevan Mission at 28 & 29 Mile Basty , Buxa tiger Reserve ( East) Division - reg BILL/00339/2024-2025 18/09/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 0.21 0.00 0
31 Alipurduar Division New service connection charges for Mujnai Cha Sundori PH NO-VI under NMD-II BILL/00392/2024-2025 20249706 02/12/2024 0 WBSEDCL 8.09 0.00 0
32 Alipurduar Division New Service Connection Charges for Lankapara TG PWSS PH NO-VII ( AT VES-4) Near Chha Sundari BILL/00485/2024-2025 324/24-25/PFMS 22/11/2024 0 WBSEDCL 16.11 0.00 0
33 Alipurduar Division New service connection charges for Dheklapara T.G PWSS P/H no-I (Cha Sundari) BILL/00489/2024-2025 325/24-25/PFMS 02/12/2024 0 WBSEDCL 5.04 0.00 0
34 Alipurduar Division RESTORATION OF PIPELINE DAMAGED DUE TO CONSTRUCTION ACTIVITY WBSRDA BILL/00501/2024-2025 321/24-25/PFMS 14/11/2024 0 EXECUTIVE ENGINEER WBSRDA 64.01 0.00 0
35 Alipurduar Division New Service Connection Charges for Hantapara TG Near GP under NMD-II in the dist of Alipurduar BILL/00505/2024-2025 330/24-25/PFMS 18/02/2025 0 WBSEDCL 5.71 0.00 0
36 Alipurduar Division Payment against proposal no . FP/ WB/ Others/ 442029/2023- for erection of Boundary pillar at diverted site against In - principal ( stage - I ) approval of water supply scheme for Buxa Forest PWSS uder Jal Jeevan Mission at 28 & 29 Mile Basty , Buxa tiger Reserve ( East) Division - reg BILL/00506/2024-2025 329/24-25/PFMS 19/12/2024 0 EXECUTIVE ENGINEER, ALIPURDUAR DIVISION 0.31 0.00 0
37 Alipurduar Division Laying of distribution of UPVC pipeline including FHTC for KHOARDANGA AREA under NARATHALI PWSS under Alipurduar Division, PHE DTE 2743/ALD DT:24/02/2022 BILL/00599/2023-2024 447/23-24/PFMS 30/03/2024 0 HARIDAS GHOSH 1.98 0.00 0
38 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Dakshin Paitkapara Water Supply Scheme under Alipurduar Division P.H.E. Dte. (699/ALD DT:08/06/2022) Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling at H/W site including laying distribution system and providing FHTC for DAKSHIN PAITKAPARA PWSS Under Alipurduar Division PHE DTE(16/ALD DT:01/04/2022) BILL/00600/2023-2024 29/02/2024 0 HARIDAS GHOSH 6.95 0.00 0
39 Alipurduar Division Construction of Pump House ,Boundary Wall and Providing FHTC including Laying of UPVC pipeline and Tube well Boring by ODEX-165 Method of drilling for Bholardabri PWSS under Alipurduar Division PHE DTE.(2382/ALD DT:31/01/2022) Construction of 450cum OHR for Bholardabri water Supply Scheme under Alipurduar Division, PHE Dte. (2187/ALD DT:29/02/2022) BILL/00601/2023-2024 29/02/2024 0 HARIDAS GHOSH 2.68 0.00 0
40 Alipurduar Division Providing FHTC including Rising main and laying distribution system for PUTIMARI Piped Water Supply Scheme Under Alipurduar Division PHE DTE. BILL/00602/2023-2024 29/02/2024 0 HARI CONSTRUCTION 1.21 0.00 0
41 Alipurduar Division New Service Connection Charges for Dashkin Sonapur P/H NO-3 Under NMD-II in the dist. of Alipurduar BILL/00616/2024-2025 332/24-25/PFMS 21/03/2025 0 WBSEDCL 5.71 0.00 0
42 Alipurduar Division New Service Connection Charges for PARERPAR P/H NO-3 in the dist. of Alipurduar Under NMD-II BILL/00617/2024-2025 333/24-25/PFMS 21/03/2025 0 WBSEDCL 2.40 0.00 0
43 Alipurduar Division Hydro-Geologica! investigation aboutWater evaluation, availability and quality parameterfor both ground and surface sources at Lankapara and Gentral Dooars Tea Estate within Alipuduar district. BILL/00683/2023-2024 429/23-24/PFMS 28/03/2024 0 IIT CONSULTATIVE PRACTICE 2.36 0.00 0
44 Alipurduar Division Construction of Pump House ,Boundary Wall and Providing FHTC including Laying of UPVC pipeline and Tube well Boring by ODEX-165 Method of drilling for Bholardabri PWSS under Alipurduar Division PHE DTE.(2382/ALD DT:31/01/2022) Construction of 450cum OHR for Bholardabri water Supply Scheme under Alipurduar Division, PHE Dte. (2187/ALD DT:29/02/2022) BILL/00749/2023-2024 448/23-24/PFMS 30/03/2024 0 HARIDAS GHOSH 1.49 0.00 0
45 Alipurduar Division Construction of Pump House ,Boundary Wall and Providing FHTC including Laying of UPVC pipeline and Tube well Boring by ODEX-165 Method of drilling for Bholardabri PWSS under Alipurduar Division PHE DTE.(2382/ALD DT:31/01/2022) Construction of 450cum OHR for Bholardabri water Supply Scheme under Alipurduar Division, PHE Dte. (2187/ALD DT:29/02/2022) BILL/00750/2023-2024 449/23-24/PFMS 30/03/2024 0 HARIDAS GHOSH 1.19 0.00 0
46 Alipurduar Division Laying of overground distribution system by using HDPE pipes under Augmentation of Totopara PWSS under Alipurduar Division PHE Dte. ORD/000001/2023-2024 04/ALD 04/04/2023 60 DULAL DAS 39.82 39.61 100
47 Alipurduar Division Laying of DI & HDPE Pipe line, Construction of sluice valve chamber, trenchless pipe laying & other works for providing FHTC AT BIRPARA Zone-II Area under BIRPARA PWSS under Alipurduar Division, PHE Laying of DI & HDPE Pipe line, Construction of sluice valve chamber, trenchless pipe laying & other works for providing FHTC AT BIRPARA Zone-II Area under BIRPARA PWSS under Alipurduar Division, PHE DTE.. ORD/000001/2025-2026 111/ALD 16/04/2025 45 RATAN DUTTA 120.16 0.00 0
48 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling including laying distribution system, Rising main and providing FHTC for CHUNIAJHORA TEA GARDEN AREA PWSS under Alipurduar Division PHE DTE ORD/000002/2022-2023 12/ALD 01/04/2022 120 AKANSHA COMMERCIAL PRIVATE LTD. 168.43 168.43 100
49 Alipurduar Division Construction of 200cum OHR as per departmental design and drawing, providing FHTC for 28 and 29 mile Busty PWSS under Alipurduar Division, PHE Dte. ORD/000002/2023-2024 05/ALD 04/04/2023 180 A B TECHNO ENTERPRISE 91.25 0.00 0
50 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling including providing FHTC, laying distribution system and Rising main for Gangutia Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000003/2022-2023 13/ALD 01/04/2022 120 SHREE RANISATI ENTERPRISE 193.63 124.70 67
51 Alipurduar Division Laying HDPE pipeline from Dakshin Sonapur aath mile bazaar to head work site due to widening of NH and providing FHTC at Dakshin Sonapur PWSS Area, Alipurduar-I Block under Alipurduar Division, PHE Dte. ORD/000003/2023-2024 06/ALD 04/04/2023 450 PINTU SAHA 46.56 46.03 80
52 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling including laying distribution system, Rising main and providing FHTC for MECHPARA TEA GARDEN AREA PWSS under Alipurduar Division PHE DTE ORD/000004/2022-2023 14/ALD 01/04/2022 120 SHREE RANISATI ENTERPRISE 224.94 114.03 38
53 Alipurduar Division Tubewell boring by ODEX-165 method of drilling, construction of Pump House, Boundary wall at proposed 4th TW site of Kaijali PWSS under Alipurduar Division, PHE Dte. ORD/000004/2023-2024 07/ALD 04/04/2023 120 PRITAM DAS 17.41 16.17 100
54 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling including providing FHTC and Rising main for SIDHABARI Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000005/2022-2023 15/ALD 01/04/2022 120 BILTU DAS 181.30 116.95 56
55 Alipurduar Division Laying of new UPVC/DI pipeline for replacement of 75mm dia UPVC pipe with 90mm dia pipeline, gap filling and re distribution system along with the others allied works under Jashodanga PWSS under Alipurduar Division, PHE Dte. ORD/000005/2023-2024 26/ALD 06/04/2023 540 HIMALAYAN CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 44.98 20.52 45
56 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling at H/W site including laying distribution system and providing FHTC for DAKSHIN PAITKAPARA PWSS Under Alipurduar Division PHE DTE ORD/000006/2022-2023 16/ALD 01/04/2022 240 HARIDAS GHOSH 230.68 200.30 86
57 Alipurduar Division Construction of concrete platform, pathway and drain along with the repairing of existing boundary wall and drain for effectively stacking the various pipe/ specials items at Alipurduar Sadar Sub-Division Stackyard under the head of augmentation of Bhatibari PWSS under Alipurduar, Division, PHE Dte. ORD/000006/2023-2024 03/ALD 04/04/2023 90 HARIDAS GHOSH 6.38 6.02 100
58 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling at H/W site including laying distribution system and providing FHTC for MATHURA TG AREA PWSS Under Alipurduar Division PHE DTE ORD/000007/2022-2023 17/ALD 01/04/2022 120 M/S SURAJIT DEY & CO 246.10 148.93 69
59 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling at H/W site including laying distribution system and providing FHTC for MADARIHAT TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE ORD/000008/2022-2023 18/ALD 01/04/2022 120 DILIP MAHATO 216.89 197.43 100
60 Alipurduar Division Laying of new HDPE pipeline in the balance portion distribution system of Raydak TG PWSS under Alipurduar Division, PHE Dte. (Part-A) ORD/000008/2023-2024 92/ALD 18/04/2023 60 TILAK SHARMA 12.11 0.00 0
61 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling at H/W site including laying distribution system and providing FHTC for KALCHINI TG ZONE-I PWSS Under Alipurduar Division PHE DTE ORD/000009/2022-2023 3230/ALD. 27/02/2023 240 SHREE RANISATI ENTERPRISE 190.87 119.33 10
62 Alipurduar Division Construction of pump house boundary wall Tubewell boring (by ODEX-165 method of drilling) and rising main for Zone-II 3rd TW site at Augmentation of Birpara PWSS under Alipurduar Division, PHE Dte. ORD/000009/2023-2024 93/ALD 18/04/2023 120 SUBHAK CHIK BARAIK 31.63 9.71 100
63 Alipurduar Division Tube well Boring by ODEX-165 Method of drilling at TUBE WELL site including laying distribution system with new HDPE pipeline ,One nos pump house & boundary wall, providing FHTC and others allied works for Bhutri Forest PWSS Under Alipurduar Division PHE DTE. ORD/000010/2023-2024 94/ALD 18/04/2023 120 FAUDA SINGH CHHETRI 34.70 33.34 100
64 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling at 2nd site including laying distribution system , Rising main and providing FHTC for DAKSHIN PAITKAPARA PWSS under Alipurduar Division PHE DTE ORD/000011/2022-2023 21/ALD 01/04/2022 120 SOUVIK ROY PALADHI 230.70 209.27 55
65 Alipurduar Division Tube well Boring by ODEX-165 Method of drilling at HW, FIRST TUBE WELL site including laying distribution system with new UPVC pipeline , Constructions of 100 Cum OHR as per Departmental Design & drawing including soil investigation works, TWO nos. pump house & boundary wall, providing FHTC and others allied works for UTTAR BARAJHAR FOREST PWSS Under Alipurduar Division PHE DTE. (2nd call) ORD/000011/2023-2024 134/ALD 24/04/2023 180 TAPASH DAS 193.20 32.59 15
66 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling at 2nd site including laying distribution system , Rising main and providing FHTC for MATHURA TG AREA PWSS Under Alipurduar Division PHE DTE ORD/000012/2022-2023 22/ALD 01/04/2022 120 TAPASH KUMAR BHOWMICK 246.44 231.69 65
67 Alipurduar Division Laying of CI/DI/MS Pipe for delivery line, cons. of RCC Pillar with ISMB and balance part of boundary wall of CWR Project Area and earth filling at River Bed site of JDA (JAIGAON DEVELOPMENT AUTHORITY) Area Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000013/2021-2022 405/ALD 17/06/2021 30 DILIP MAHATO 49.78 92.02 67
68 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling at 2nd & 3rd site including laying distribution system , Rising main and providing FHTC for MADARIHAT TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE ORD/000013/2022-2023 23/ALD 01/04/2022 120 DILIP MAHATO 213.90 154.11 84
69 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling at 2nd & 3rd site including laying distribution system , Rising main and providing FHTC for KALCHINI TG ZONE-I PWSS Under Alipurduar Division PHE DTE. ORD/000014/2022-2023 3229/ALD. 27/02/2023 120 SHREE RANISATI ENTERPRISE 143.22 63.43 30
70 Alipurduar Division Construction of pump house boundary wall Tubewell boring (by ODEX-165 method of drilling) and rising main for Zone-III 3rd TW site at Augmentation of Birpara PWSS under Alipurduar Division, PHE Dte. ORD/000014/2023-2024 166/ALD 26/04/2023 480 RATAN DUTTA 31.78 18.23 65
71 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling at 3rd & 4th site including laying distribution system , Rising main and providing FHTC for KALCHINI TG ZONE-II PWSS Under Alipurduar Division PHE DTE. ORD/000015/2022-2023 3227/ALD 27/02/2023 120 SHREE RANISATI ENTERPRISE 179.10 0.00 0
72 Alipurduar Division Laying of distribution system with HDPE/DI pipeline, Providing FHTC and others allied works for Chengmari PWSS Under Alipurduar Division PHE DTE. ORD/000015/2023-2024 233/ALD 04/05/2023 270 HARIDAS GHOSH 248.85 205.79 65
73 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling at H/W site including laying distribution system and providing FHTC fo GOPALPUR TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE. ORD/000016/2022-2023 26/ALD 01/04/2022 1320 ASHIT KUMAR SINGHA 136.46 60.00 95
74 Alipurduar Division Constructions of pump house and Tube well Boring by ODEX-165 Method of drilling at HW site and 2nd site, Laying of distribution system with HDPE/DI pipeline, providing FHTC and others allied works for Dhantali PWSS Under Alipurduar Division PHE DTE. ORD/000016/2023-2024 234/ALD 04/05/2023 240 SOUVIK ROY PALADHI 190.55 131.42 70
75 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling at 2nd site including laying distribution system , Rising main and providing FHTC for GOPALPUR TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE. ORD/000017/2022-2023 27/ALD 01/04/2022 840 M/S DUTTA AND CO 138.71 102.09 90
76 Alipurduar Division Boring of Tube Well by reverse rotary method, Construction of Pump House, Boundary Wall, Laying Of Distribution System and providing FHTC for Parpatlakhawa PWSS under Alipurduar Division, PHE Dte. ORD/000017/2023-2024 235/ALD 04/05/2023 720 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 113.69 70.52 16
77 Alipurduar Division Tube well Boring by ODEX-165 Method of drilling at HW, 2nd TUBE WELL site including two nos. pump house and boundary wall, providing FHTC and others allied works for MALANGI TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE. ORD/000018/2023-2024 236/ALD 04/05/2023 748 RAMESH SHARMA 139.90 21.20 10
78 Alipurduar Division Restoration of pipeline, FHTC and Allied works under Beech Tea Garden PWSS Under Alipurduar Division ,PHE DTE. ORD/000020/2025-2026 71/ALD 09/04/2025 90 PRAPTI DUTTA 0.73 0.00 100
79 Alipurduar Division Constructions of pump house and Tube well Boring by ODEX-165 Method of drilling at HW site and 2nd site , Laying of distribution system with HDPE pipeline including rising main & delivery connection , Constructions of 100 Cum OHR as per Departmental Design & drawing along with the Soil investigation works , providing FHTC and others allied works for Uttar Dhalkar PWSS Under Alipurduar Division PHE DTE. ORD/000021/2023-2024 237/ALD 04/05/2023 720 TAPASH KUMAR BHOWMICK 226.42 153.23 45
80 Alipurduar Division Soil investigation at OHR site, constructions of 300 Cum OHR at HW , distribution line and providing FHTC as per Departmental Design & drawing for Khagenhat PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000022/2023-2024 258/ALD 08/05/2023 180 DILIP MAHATO 217.32 199.14 80
81 Alipurduar Division Cons. of tube wells at 2nd site by Reverse rotary method of drilling, cons. of pump house and boundary wall at 2nd site, rising main, distribution line(C) and providing FHTC as per Departmental Design & drawing for Khagenhat PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000023/2023-2024 257/ALD 08/05/2023 120 PRAMESH LAMA 176.90 61.70 10
82 Alipurduar Division Continuation for the work of Entry of data for house Connection (JJM) of PWSS in website under Alipurduar division, PHE Dte. ORD/000023/2025-2026 343/ALD 29/04/2025 180 TAPASH KUMAR BHOWMICK 4.29 0.00 0
83 Alipurduar Division Extension of pipeline from Santali TG connection line to upper line of Madhu TG area (booster line) under Hasimara TG PWSS at Kalchini Block under Alipurduar Division, PHE Dte. ORD/000024/2022-2023 19/ALD 01/04/2022 60 AASHIRBAD ENTERPRISE 12.61 8.47 49
84 Alipurduar Division Continuation for the work of Collection of house hold details at prescribed format through mobile app/Hard Copy including Geo-reference as directed by the E.I.C. and submission the same to PHE Dte. in soft copy. ORD/000024/2025-2026 344/ALD 29/04/2025 120 TAPASH KUMAR BHOWMICK 4.67 0.00 100
85 Alipurduar Division Extension of pipeline from Malangi TW to Bharnobari TG area (booster line) under Hasimara PWSS at Kalchini Block under Alipurduar Division, PHE Dte. ORD/000025/2022-2023 20/ALD 01/04/2022 60 AASHIRBAD ENTERPRISE 14.64 11.92 50
86 Alipurduar Division CONSTRUCTION OF PUMP HOUSE & BOUNDARY WALL FOR ADDITIONAL TUBEWELL FOR PROVIDING FHTC AND CONSTRUCTION OF RIVER BANK PROTECTION WALL WITH WIRE CREATE AND FILLING NEAR HWS AT PARARPAR PWSS WITHIN ALIPURDUAR-I BLOCK UNDER ALIPURDUAR DIVISION, PHE DTE. ORD/000025/2025-2026 434/ALD 30/04/2025 60 SASANKA ROY 21.00 0.00 0
87 Alipurduar Division Laying of UPVC/DI/MS/CI distribution pipe line for gap filling and FHTC connection for Beltali Road and adjoining area of Jateswar PWSS under Alipurduar Division, PHE Dte. ORD/000026/2022-2023 24/ALD 01/04/2022 60 AASHIRBAD ENTERPRISE 12.35 12.33 80
88 Alipurduar Division CONSTRUCTION OF PUMP HOUSE & BOUNDARY WALL FOR ADDITIONAL TUBEWELL FOR PROVIDING FHTC AND LAND DEVELOPMENT AT HW SITE & 2ND SITE FOR AUGMENTATION OF DAKSHIN SONAPUR PWSS. ORD/000026/2025-2026 435/ALD 30/04/2025 300 TAPASH DAS 16.07 0.00 60
89 Alipurduar Division CONS. OF RESERVOIR (100M3), BOUNDARY WALL (80m), PUMP HOUSE (1No.), TUBE WELL (2 Nos.), RISING MAIN AND LAND DEVELOPMENT FOR TORSHA (Hat Khola Line, Naya Line, 3 No. Line (A) AND (B) and Khoyar line) 256 unit CHA SUNDARAI WATER SUPPLY SCHEME UNDER ALIPURDUAR DIVISION PHE DTE. ORD/000028/2022-2023 282/ALD 26/04/2022 150 DILIP MAHATO 104.00 103.66 88
90 Alipurduar Division Sinking of 250 mm x 200 mm x 150 mtr Big dia TW by reverse rotary drilling method at 4th TW site of Purba Chepani PWSS under Alipurduar Division, PHE Dte. ORD/000028/2025-2026 437/ALD 30/04/2025 30 MADHAB SAHA 11.51 0.00 0
91 Alipurduar Division CONS. OF RESERVOIR (100M3), BOUNDARY WALL (80 m), PUMPHOUSE( 1.Nos) ,TUBEWELL (2 Nos.), RISING MAIN AND LAND DEVELOPMENT FOR TORSHA (Sawa Line, Chetri Line, Bancha Line,Gopal Line, Jiten Line)220 unit CHA SUNDARAI WATER SUPPLY SCHEME UNDER ALIPURDUAR DIVISION PHE DTE. ORD/000029/2022-2023 283/ALD 26/04/2022 300 MAHENDRA CHHETRI 100.66 97.34 86
92 Alipurduar Division Boring of TW, Cons. Of Pump House, boundary wall, OHR (400 cum) inclu. Soil investigation works, Laying of rising main, distribution system and providing FHTC for BARIGURI PWSS under Alipurduar Division PHE DTE. (2nd call) ORD/000029/2023-2024 333/ALD 16/05/2023 720 MESSRS A.B.G CONSTRUCTION 592.24 248.77 4
93 Alipurduar Division Sinking of 250 mm x 200 mm x 150 mtr Big dia TW by reverse rotary drilling method at 4th TW site of Salsalabari PWSS under Alipurduar Division, PHE Dte. ORD/000029/2025-2026 438/ALD 30/04/2025 30 MADHAB SAHA 11.51 0.00 0
94 Alipurduar Division CONS. FOR RESERVOIR (200 M3), RISING MAIN AND DISTRIBUTION LINE FOR DHEKLAPARA MAIN DIVISION CHA SUNDARAI WATER SUPPLY SCHEME UNDER ALIPURDUAR DIVISION PHE DTE. ORD/000030/2022-2023 284/ALD 26/04/2022 150 SUBHAS CHANDRA ROY 86.68 70.85 100
95 Alipurduar Division Construction of tube wells (2 nos.) by Reverse rotary method of drilling at HW site and 2nd TW site , Soil investigation at OHR site, constructions of 350 Cum OHR at HW , construction of pump house and boundary wall at H/W and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for MAIRADANGA PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000030/2023-2024 334/ALD 16/05/2023 720 MESSRS A.B.G CONSTRUCTION 653.77 362.94 65
96 Alipurduar Division Laying of new HDPE pipeline for providing FHTC and land filling at Headwork site & 2nd site at Foskadanga PWSS under Alipurduar Division, PHE Dte. ORD/000030/2025-2026 439/ALD 30/04/2025 60 MADHAB SAHA 52.23 0.00 0
97 Alipurduar Division PROVIDING FHTC IN CONNECTION WITH JALDHARA JAL SAPNA FOR AUGMENTATION OF FALAKATA WATER SUPPLY SCHEME UNDER ALIPURDUAR DIVISION, PHE DTE. (COMMAND AREA : OLD OHR) ORD/000031/2021-2022 579/ALD 15/07/2021 45 NARENDRA BHADANI. 21.24 35.05 0
98 Alipurduar Division Laying of new HDPE pile line in the balance portion distribution system at Sanialine & adj. Area of Raydak TG PWSS under Alipurduar Division PHE Dte. ORD/000031/2023-2024 362/ALD 18/05/2023 60 SUMAN CHAKRABORTY 7.99 0.00 0
99 Alipurduar Division Hiring of Diesel Vehicle Maxi Cab (At least 7 seater ) for Executive Engineer, Alipurduar Division, P.H.E. Dte. (from01.05.2025 to 30.04.2026) ORD/000031/2025-2026 419/ALD 30/04/2025 365 APSARI BHOWMICK 4.80 0.00 0
100 Alipurduar Division CONS. OF STORAGE TANK, BOUNDARY WALL, PUMP HOUSE, TUBE WELL (1 No.), RISING MAIN AND LAND DEVELOPMENT FOR NEPANIA MAIN DIVISION (150 Unit) CHA SUNDARAI WATER SUPPLY SCHEME UNDER ALIPURDUAR DIVISION PHE DTE. ORD/000032/2022-2023 296/ALD 27/04/2022 1345 S.N. POLYMERS PRIVATE LIMITED 108.37 0.00 75
101 Alipurduar Division Tubewell boring by ODEX-165 method of drilling, construction of Pump House, Boundary Wall at Proposed 3rd TW site of Raydak TG PWSS under Alipurduar Division, PHE Dte. ORD/000032/2023-2024 363/ALD 18/05/2023 360 POLY CONSTRUCTION 17.71 5.08 3
102 Alipurduar Division Construction of Tubewell by ODEX-165 method of drilling, construction of of pump house and boundary wall for Gopalpur PWSS under Alipurduar Division, PHE Dte. ORD/000033/2023-2024 364/ALD 18/05/2023 775 SWAPAN KUMAR SAHA 24.47 15.02 100
103 Alipurduar Division PROVIDNG HOUSE CONNECTION FOR BHARNOBARI TG AREA NEAR DALSINGPARA AT KALCHINI BLOCK UNDER ALIPURDUAR DIVISION, PHE DTE. ORD/000034/2021-2022 582/ALD 15/07/2021 30 M/S BHOWMICK CONSTRUCTION 20.03 20.03 96
104 Alipurduar Division Construction of pump house & sinking of 250 mm x 200 mm x 150mtr Big dia Tubewell at 2nd site of Bhatibari Zone-IV PWSS under Alipurduar Division, PHE Dte. ORD/000034/2023-2024 365/ALD 18/05/2023 600 MONORAMA ENTERPRISE 22.01 19.10 100
105 Alipurduar Division Restoration of DI pipe crossing near CHOR TORSHA and other repair works in Banshidharpur area under Alipurduar Division, PHE Dte. ORD/000035/2023-2024 366/ALD 18/05/2023 30 NARENDRA BHADANI. 1.42 0.00 100
106 Alipurduar Division Laying of new HDPE pile line in the balance portion distribution system at khuruline & four line of Raydak TG PWSS under Alipurduar Division PHE Dte. ORD/000038/2023-2024 369/ALD 18/05/2023 60 PRAPTI DUTTA 10.00 8.51 80
107 Alipurduar Division Construction of Soak well, Fencing and other works at Madhu TG PWSS under Alipurduar Division, PHE Dte. ORD/000039/2020-2021 516/ALD 20/08/2020 60 TAPASH KUMAR BHOWMICK 3.91 7.82 0
108 Alipurduar Division Tubewell boring by ODEX-165 method of drilling, construction of Pump House, Boundary Wall at Proposed 3rd TW site of Kohinur TG PWSS under Alipurduar Division, PHE Dte. ORD/000039/2023-2024 370/ALD 18/05/2023 120 DILIP MAHATO 17.39 17.27 100
109 Alipurduar Division Construction of Boundary Wall at Dalda Bari of Jaigaon WSS, Zone-II under Alipurduar Division, PHE Dte. ORD/000040/2021-2022 551/ALD 14/07/2021 45 TAPASH DAS 4.90 9.78 0
110 Alipurduar Division Construction of pump house, Boundary Wall, Tube well Boring (by ODEX-165 method of drilling) and Rising main for Zone-I 1st TW site at Augmentation of Birpara PWSS under Alipurduar Division, PHE Dte. ORD/000040/2023-2024 386/ALD 19/05/2023 120 KAJAL KUMAR DE 32.74 20.26 30
111 Alipurduar Division Construction of pump house, Boundary Wall, Tube well Boring (by ODEX-165 method of drilling) and Rising main, laying of DI and UPVC pipeline for Uttar Sishubari PWSS under Alipurduar Division, PHE Dte. ORD/000041/2023-2024 387/ALD 19/05/2023 480 MITHUN DAS 93.44 40.47 62
112 Alipurduar Division Repairing of pump house at headwork site of Bakla PWSS under Alipurduar Division, PHE Dte. ORD/000041/2025-2026 666/ALD 21/05/2025 60 SHYAMAL ROY 1.02 0.00 0
113 Alipurduar Division Laying of DI & HDPE pipeline from Santali TG and Malangi TG to the existing OHR at Hasimara PWSS area, kalchini Block under Alipurduar division, PHE Dte. ORD/000042/2023-2024 388/ALD 19/05/2023 1110 D. K. & SONS 26.33 13.59 100
114 Alipurduar Division Replacement of damaged pipeline in Madarihat Bazar Area PWSS under Alipurduar Division, PHE Dte. ORD/000043/2023-2024 389/ALD 19/05/2023 180 KAMALESH ROY 5.46 4.63 95
115 Alipurduar Division Supply of DI pipe & CI special for Madhya Kamakhyaguri PWSS under Alipurduar Division PHE Dte. ORD/000044/2023-2024 390/ALD 19/05/2023 30 DILIP MAHATO 71.61 68.44 75
116 Alipurduar Division Providing FHTC from existing distribution system as per specification for TOTOPARA PWSS under madarihat - Birpara Block under Alipurduar Division PHE Dte. ORD/000044/2025-2026 669/ALD 21/05/2025 90 DULAL DAS 23.27 0.00 0
117 Alipurduar Division Supply of DI pipe & CI special for Baruipara PWSS under Alipurduar Division PHE Dte. ORD/000045/2023-2024 391/ALD 19/05/2023 30 HARI CONSTRUCTION 34.33 34.27 90
118 Alipurduar Division Supply of DI pipe & CI special for Dakhin Majidkhana PWSS under Alipurduar Division PHE Dte. ORD/000046/2023-2024 392/ALD 19/05/2023 801 TAPASH KUMAR BHOWMICK 40.11 36.65 80
119 Alipurduar Division Collection of house hold details at prescribed format through mobile app/Hard Copy including Geo-reference as directed by the E.I.C. and submission the same (soft copy) to P.H.E. Dte. Part-B ORD/000048/2023-2024 394/ALD 19/05/2023 120 TAPASH KUMAR BHOWMICK 4.67 4.67 0
120 Alipurduar Division Entry of data for house Connection (JJM) of PWSS in website under Alipurduar division, PHE Dte. ORD/000049/2023-2024 395/ALD 19/05/2023 120 TAPASH KUMAR BHOWMICK 4.29 4.29 20
121 Alipurduar Division Cons. of pump house and Tube well Boring by ODEX-165 Method of drilling at HW site and 2nd site, LDS with HDPE pipeline including rising main and delivery connection, Cons. of 100 Cum OHR as per Dept. Design and drawing along with the Soil investigation works, providing FHTC and other allied works for Purba Majherdabri TG PWSS Under Alipurduar Division PHE DTE. ORD/000050/2023-2024 406/ALD 22/05/2023 680 DAS CONSTRUCTION 212.40 155.27 35
122 Alipurduar Division Laying of new UPVC/DI Pipeline for interconnection in the distribution system and bridge/culvert crossing and other allied works in connection with Baruipara PWSS Alipurduar Division, PHE Dte. ORD/000050/2025-2026 675/ALD 21/05/2025 90 TAPAN CHANDA 29.05 0.00 50
123 Alipurduar Division Construction of Fire hydrant, parking area for water collecting vehicles, surface drain and other miscellaneous works for Madhu T.G. P/W/S/S, Under Alipurduar Division P.H.E. Dte. ORD/000051/2020-2021 530/ALD 20/08/2020 60 TAPASH KUMAR BHOWMICK 5.00 10.00 0
124 Alipurduar Division Laying of additional DI & HDPE pipeline, Costruction of Sluice Valve chamber & other works for Providing FHTC at Mairadanga PWSS under Alipurduar Division, PHE Dte. ORD/000051/2025-2026 677/ALD 21/05/2025 90 ANIRBAN DEY SARKAR CONSTRUCTION 44.30 0.00 0
125 Alipurduar Division Continuation for the work of Hiring of Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for inspection and monitoring of Jal Jeevan Mission (JJM) works under Alipurduar Division, P.H.E. Dte.(from 01/05/2023 to 31/07/2023) ORD/000052/2023-2024 180/ALD 27/04/2023 91 NIRANJAN KIRTANIA 0.50 0.50 85
126 Alipurduar Division Restoration of FHTCs and withdrawing and relaying a pipeline (125 mm) at Patotola area at 5th site Samuktala PWSS under Alipurduar Division, PHE Dte. ORD/000052/2025-2026 678/ALD 21/05/2025 45 DULAL DAS 4.50 0.00 0
127 Alipurduar Division Cons. Of tube wells at H/W site by Reverse rotary method of drilling , cons. of pump house and boundary wall at H/W , rising main, distribution line(B) and providing FHTC as per Departmental Design & drawing for Khagenhat PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000053/2023-2024 422/ALD 24/05/2023 1003 MADHAB SAHA 201.45 0.00 50
128 Alipurduar Division Supply and installation of sign board at different PWSS site of Kumargram Block under Alipurduar Division, PHE Dte. ORD/000053/2025-2026 679/ALD 21/05/2025 45 TAPASH DAS 4.69 0.00 100
129 Alipurduar Division Continuation order of Supply of fuel for Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for inspection and monitoring of Jal Jeevan Mission (JJM) works under Alipurduar Division, P.H.E. Dte.(from 01.05.2023 to 31.07.2023) ORD/000054/2023-2024 181/ALD 27/04/2023 91 NIRANJAN KIRTANIA 0.70 0.58 0
130 Alipurduar Division Constructions of pump house and Tube well Boring by ODEX-165 Method of drilling at HW site and 2nd site, Laying of distribution system with HDPE pipeline including rising main and delivery connection, Constructions of 200 Cum OHR as per Departmental Design and drawing along with the Soil investigation works, providing FHTC and others allied works for Chengmari PWSS Under Alipurduar Division PHE DTE. ORD/000055/2023-2024 423/ALD 24/05/2023 678 HARIDAS GHOSH 240.70 143.93 85
131 Alipurduar Division Laying of distribution line with HDPE, UPVC & CI/DI Pipes at Kumarpara & adjoining areas and others allied works for Augmentation of Dakshin Sonapur PWSS within Alipurduar-I Block under Alipurduar Division, PHE DTE. ORD/000055/2025-2026 706/ALD 22/05/2025 75 S.D. PROJECT 150.21 0.00 0
132 Alipurduar Division Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Augmentation of Dakshin Sonapur Water Supply Scheme TW No.-III (Additional) under NMD-II,PHE.Dte,Alipurduar. ORD/000057/2025-2026 785/ALD 30/05/2025 30 DILIP MAHATO (OPC) PRIVATE LIMITED 11.09 0.00 0
133 Alipurduar Division Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Nimti Domohini Water Supply Scheme TW No.-III (Additional) under NMD-II,PHE.Dte,Alipurduar. ORD/000058/2025-2026 786/ALD 30/05/2025 30 MADHAB SAHA. 10.80 0.00 0
134 Alipurduar Division Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Pararpar Water Supply Scheme TW No.-III (Additional) under NMD-II,PHE.Dte,Alipurduar. ORD/000059/2025-2026 787/ALD 30/05/2025 30 SUBODH KUMAR BANIK 11.09 0.00 0
135 Alipurduar Division Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Madhya Khairbari Water Supply Scheme TW No.-IV (Additional) under NMD-II,PHE.Dte,Alipurduar. ORD/000060/2025-2026 788/ALD 30/05/2025 30 M/S. BHOWMIK & CO 10.78 0.00 0
136 Alipurduar Division Constrcution of Pump House with Sanitary & Plumbing arrangement at 2nd Site (Old) of Dalmore Water supply scheme under Alipurduar Division. P.H.E. Dte. ORD/000061/2020-2021 537/ALD 20/08/2020 120 M/S MONORAMA ENTERPRISE 4.75 8.40 0
137 Alipurduar Division Construction of Pump House with Sanitary & Plumbing arrangement at H/W Site (Old) of Dalmore Water supply scheme under Alipurduar Division. P.H.E. Dte. ORD/000062/2020-2021 538/ALD 20/08/2020 120 PRAPTI DUTTA 4.75 8.40 0
138 Alipurduar Division Restoration of damaged FHTCs, Replacement of old damaged pipeline at Bakla PWSS under Alipurduar Division, PHE Dte. ORD/000063/2025-2026 815/ALD 03/06/2025 60 SHYAMAL ROY 6.23 0.00 0
139 Alipurduar Division Extension of pipeline and connection with main line by UPVC, GI, DI pipe and construction of valve chamberand others at Bhutnirghat WSS under Alipurduar Division, PHE Dte. ORD/000065/2022-2023 342/ALD 02/05/2022 45 DILIP MAHATO 25.70 17.56 92
140 Alipurduar Division Gap joint and restoration of HDPE line and repairing of FHTC and allied works at Radharani and Chuapara village under Radharani under Bhutri Forest PWSS within Kalchini Block under Alipurduar Division, PHE Dte. ORD/000065/2025-2026 817/ALD 03/06/2025 150 PRAPTI DUTTA 23.32 0.00 100
141 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling including Rising Main at 3rd site for SALKUMARHAT PWSS Under Alipurduar Division PHE DTE. ORD/000066/2022-2023 338/ALD 02/05/2022 883 SUBRATA DAS 24.16 22.94 8
142 Alipurduar Division Gap filling of distribution line, land development and other allied works for ParpatlaKhawa Piped Water Supply Scheme within Alipurduar Block-I under Alipurduar Division, PHE Dte. ORD/000066/2025-2026 818/ALD 03/06/2025 75 CHITTA RANJAN DEY 20.25 0.00 0
143 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling including Rising Main at 4th site for SALKUMARHAT PWSS Under Alipurduar Division PHE DTE ORD/000067/2022-2023 339/ALD 02/05/2022 980 SHYAMAL ROY 24.17 9.70 100
144 Alipurduar Division Laying Rising Main and delivery main connection along with laying of new UPVC/DI pipeline for interconnection in the distribution system and bridge/culvert crossing and other allied works for Nararthali PWSS adjacent to Purba Narathali WSS under Alipurduar Division, PHE Dte. ORD/000067/2025-2026 819/ALD 03/06/2025 90 NARAYANIMAA EXIM PVT. LTD. 32.53 0.00 0
145 Alipurduar Division Laying of DI / UPVC Pipeline & other Misc. works related to DIMA PWSS under Alipurduar Division PHED. ORD/000068/2020-2021 623/ALD 03/09/2020 120 TILAK SHARMA 29.43 49.30 30
146 Alipurduar Division Laying of additional HDPE pipeline for Gap filling and providing FHTC at Hoasinbad TG under Hoasinbad PWSS under Alipurduar Division, PHE Dte. ORD/000068/2025-2026 966/ALD 12/06/2025 60 SASANKA ROY 26.04 0.00 0
147 Alipurduar Division Balance part of laying of HDPE/DI pipe line alongwith construction of RCC piller at different area of DIMDIMA TG under ALIPURDUAR Division, PHED. ORD/000069/2020-2021 622/ALD 03/09/2020 120 M/S SSB CONSTRUCTION 34.11 59.98 88
148 Alipurduar Division Laying Distribution line with UPVC pipe at PUTIMARI WSS under Alipurduar Division , PHE Dte(Part - III) ORD/000069/2022-2023 434/ALD 13/05/2022 30 HARI CONSTRUCTION 5.02 4.74 93
149 Alipurduar Division 1 Nos TW boring of ODEX-165 for additional T/W for 3rd site of Nimti Domohani PWSS under Alipurduar Division, PHE Dte. ORD/000069/2025-2026 967/ALD 12/06/2025 30 CHINMOY BHATTACHARJEE 8.07 0.00 0
150 Alipurduar Division Laying of HDPE / DI Pipeline at different area of MAKRAPARA PWSS under Alipurduar Division PHED. ORD/000070/2020-2021 624/ALD 03/09/2020 120 DILIP MAHATO 14.63 23.60 84
151 Alipurduar Division Laying of DI pipe of Different Dia and other works For TAPSHIKHATA PWSS at Alipurduar -I Block under Alipurduar Division , PHE Dte. ORD/000070/2022-2023 435/ALD 13/05/2022 30 KAMALESH ROY 4.76 0.00 0
152 Alipurduar Division Gap filling of distribution line river crossing and other allied works for Kalaberia village under Kalaberia PWSS within Alipurduar-I block under Alipurduar Division, PHE Dte. ORD/000070/2025-2026 968/ALD 12/06/2025 90 SASANKA ROY 73.92 0.00 0
153 Alipurduar Division Laying of DI / UPVC Pipeline & other Misc. works for Bhutiya Basti area at PAITKAPARA PWSS under Alipurduar Division PHED. ORD/000071/2020-2021 625/ALD 03/09/2020 120 DAS CONSTRUCTION 16.33 7.80 99
154 Alipurduar Division Repairing of old UPVC pipe line , FHTC and other misc. work related to DHAOLAJHORA PWSS Alipurduar - II Block under Alipurduar Division , PHE Dte ORD/000071/2022-2023 436/ALD 13/05/2022 30 MATARA CONSTRUCTION CO 3.30 3.29 27
155 Alipurduar Division Supply and installation of sign board at different PWSS site of Alipurduar-II Block under Alipurduar Division, PHE Dte. ORD/000071/2025-2026 969/ALD 12/06/2025 45 HARI CONSTRUCTION 4.92 0.00 0
156 Alipurduar Division Loop Connention between West Falakata & Barodoba area via Mujnai River Bridge incl interconnection with the existing BHUTNIRGHAT PWSS under FALAKATA Aug. PWSS under Alipurduar Division PHED. ORD/000072/2020-2021 626/ALD 03/09/2020 120 GOUTAM KUMAR DAS 26.08 42.69 83
157 Alipurduar Division Providing House connection and extension of pipe line for Silbarihat area within PATLAKHAWA PWSS under Alipurduar Division PHE Dte. ORD/000072/2021-2022 879/ALD 03/09/2021 60 TAPASH KUMAR BHOWMICK 45.70 38.27 76
158 Alipurduar Division Repairing of old UPVC pipe line , FHTC and other misc. work related to FALAKATA PWSS FALAKATA Block under Alipurduar Division , PHE Dte ORD/000072/2022-2023 437/ALD 13/05/2022 30 NARENDRA BHADANI. 4.66 3.81 66
159 Alipurduar Division Laying of UPVC Pipeline Distrbutation system, Delivery line connection, Cons. of surface drain, Pathway and Land Development works for 4th site at Paschim Chepani under Purba Chepani PWSS under Alipurduar Division, PHE Dte. ORD/000072/2025-2026 970/ALD 12/06/2025 90 PROGRESSIVE UN EMPLOYED CO OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD 38.43 0.00 0
160 Alipurduar Division Providing FHTC for Bharnobari / Santali TG area including supply of CI materials and other misc. works under Alipurduar Division, P.H.E. Dte. ORD/000073/2021-2022 880/ALD 03/09/2021 60 SOUVIK ROY PALADHI 30.69 19.40 95
161 Alipurduar Division Gap filling of distribution line, land development and others allied works for augmentation of Pararpar PWSS within APD-I Block under Alipurduar Division, PHE Dte. ORD/000073/2025-2026 971/ALD 12/06/2025 90 SASANKA ROY 60.73 0.00 0
162 Alipurduar Division Laying of UPVC/DI/MS/CI Distribution pipe line for Gap filling and FHTC connection at different location of AUG. of Falakata PWSS (ZONE -II & III) under Alipurduar Division , PHE Dte. ORD/000074/2022-2023 439/ALD 13/05/2022 30 SASANKA ROY 4.73 4.75 66
163 Alipurduar Division Restoration of damaged FHTCs of Purba Chepani PWSS under Alipurduar Division, PHE Dte. ORD/000074/2025-2026 972/ALD 12/06/2025 406 KOUSHIK BHOWMICK 2.44 0.00 100
164 Alipurduar Division Construction of boundary wall, repairing of pump house of 3rd T/W site and interconnection between 2nd and 3rd site by using DI pipe with pillar including supply of CI materials at Narathali Water Supply Scheme under Alipurduar Division, P.H.E. Dte. ORD/000075/2021-2022 881/ALD 03/09/2021 60 SREE MAA CONSTRUCTION & CO. 13.19 8.13 71
165 Alipurduar Division Laying Distribution pipe line by DI pipe(with piller ) along the flack of Alipurduar - Bhatibari - Salsalabari Road of Chandijhar WSS under Alipurduar Division , PHE Dte. ORD/000075/2022-2023 440/ALD 13/05/2022 30 SREE MAA CONSTRUCTION 4.59 4.52 9
166 Alipurduar Division Gap Filling of distribution line, land development at Pump House and others allied works for NAOTHOARTARI PWSS within Alipurduar Block-I under Alipuduar Division PHE.Dte. ORD/000075/2025-2026 973/ALD 12/06/2025 90 CHINMOY BHATTACHARJEE 42.38 0.00 0
167 Alipurduar Division Balance work of OHR Construction of PHouse B/Wall Godown & ODEX-165 Tubewell incl. laying of DI/HDPE Pipe for Nayabasti SSB Camp at RADHARANI PWSS under Alipurduar Division PHED. ORD/000076/2020-2021 627/ALD 03/09/2020 120 UMWELT ENGINEER PVT. LTD. 65.53 48.57 92
168 Alipurduar Division Replacement of damaged pipeline with HDPE pipes for Sidhabari PWSS under Alipurduar Division, PHE Dte. ORD/000076/2025-2026 974/ALD 12/06/2025 60 SANKAR ROY 8.53 0.00 0
169 Alipurduar Division Extension and replacement of damaged pipeline under Birpara APD PWSS at Alipurduar-I under Alipurduar Division, P.H.E. Dte. ORD/000077/2021-2022 883/ALD 03/09/2021 45 KAMALESH ROY 15.92 3.32 0
170 Alipurduar Division Construction of valve chamber, dismantling concrete road and other misc works at Malangi TG area within Hasimara W/S/S under Alipurduar Division, PHE Dte. ORD/000077/2022-2023 442/ALD 13/05/2022 30 MADHAB SAHA 4.90 4.55 49
171 Alipurduar Division Laying of UPVC pipeline at opposite flank of Higher dia in the distribution system and const. of culvert at front of HW site at Kayakhata PWSS under Alipurduar Division, PHE Dte. ORD/000077/2025-2026 975/ALD 12/06/2025 90 HARI CONSTRUCTION 22.06 0.00 0
172 Alipurduar Division Extension and replacement of damaged pipeline including new FHTC under Dakshin Chakoakhati mouza (Simlabari area) at Alipurduar-I Block under Alipurduar Division, PHE Dte. ORD/000078/2021-2022 876/ALD 03/09/2021 60 M/S AMIT KUMAR GUPTA 35.43 35.50 75
173 Alipurduar Division Dismantling Concrete road and re -casting the same for providing FHTC at different area of BIRPARA (APD) PWSS AND Alipurduar - I Block under Alipurduar Division , PHE Dte. ORD/000078/2022-2023 441/ALD 13/05/2022 30 R.K.CONSTRUCTION 4.96 4.95 71
174 Alipurduar Division Laying of new HDPE pipeline for interconnection in the distributation system and bridge/culvert crossing and other allied works in connection with Chengmari PWSS under Alipurduar Division, PHE Dte. ORD/000078/2025-2026 976/ALD 12/06/2025 90 HARI CONSTRUCTION 49.29 0.00 0
175 Alipurduar Division Extension and replacement of damaged pipeline including new FHTC under Dakshin Chakoakhati mouza (Sonapur area) at Alipurduar-I Block under Alipurduar Division, PHE Dte. ORD/000079/2021-2022 877/ALD 03/09/2021 60 M/S STAR INDIA CONSTRUCTION 33.42 27.31 73
176 Alipurduar Division Retrofitting of pipeline etc. for "Jal Swapno Program" (FHTC for every house hold) under Purba Chenpani PWSS under Alipurduar-II Block under Alipurduar Division, PHE Dte.(Re-tenter) ORD/000079/2022-2023 443/ALD 13/05/2022 30 MATRI ENTERPRISE 4.20 4.06 10
177 Alipurduar Division Restoration of damaged FHTCs and replacement of Old damaged pipelines at Salsalabari PWSS under Alipurduar Division, PHE Dte. ORD/000079/2025-2026 977/ALD 12/06/2025 409 KOUSHIK BHOWMICK 3.88 0.00 0
178 Alipurduar Division Extension and replacement of damaged pipeline and providing house connection at Dakshin Sonapur Area under Sonapur PWSS under Alipurduar Division, PHE Dte. ORD/000080/2021-2022 976/ALD 13/09/2021 60 MADHAB SAHA 44.48 43.57 17
179 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna for Madarihat-Birpara Block under Alipurduar Division, PHE Dte. (Pin point site of the FHTC will be given at the time of issue of work order) ORD/000080/2025-2026 1048/ALD 17/06/2025 60 MOTI INDUSTRIES 18.14 0.00 0
180 Alipurduar Division Extension and replacement of damaged pipeline and providing house connection at Panchkolguri area under Sonapur PWSS under Alipurduar Division, PHE Dte. ORD/000081/2021-2022 977/ALD 13/09/2021 1355 M/S JHA CONSTRUCTION 43.59 40.35 60
181 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna for Kumargram Block under Alipurduar Division, PHE Dte. (Pin point site of the FHTC will be given at the time of issue of work order) ORD/000081/2025-2026 1049/ALD 17/06/2025 300 MOTI INDUSTRIES 18.14 0.00 15
182 Alipurduar Division Providing House connection for DHEKLAPARA PWSS at MADARIHAT-BIRPARA Block under Alipurduar Division PHED PART 1 ORD/000082/2020-2021 634/ALD 03/09/2020 90 DILIP MAHATO 21.80 33.66 0
183 Alipurduar Division Extension and replacement of damaged pipeline and providing house connection at Salsalabari area under Alipurduar Division, PHE Dte. ORD/000082/2021-2022 978/ALD 13/09/2021 180 HARIDAS GHOSH 17.44 11.69 100
184 Alipurduar Division Construction of pathway with paver block & land development of Loknathpur HW site WSS (Western part of GADA rivert) under Alipurduar Division, PHE Dte. ORD/000082/2022-2023 446/ALD 13/05/2022 30 MATARA CONSTRUCTION CO 4.21 0.00 0
185 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna for Alipurduar-I Block under Alipurduar Division, PHE Dte. (Pin point site of the FHTC will be given at the time of issue of work order) ORD/000082/2025-2026 1050/ALD 17/06/2025 300 MOTI INDUSTRIES 18.14 0.00 15
186 Alipurduar Division Sinking of Big Dia T/Well P/House B/Wall & Rising Main of 3rd T/Well Site at FALAKATA Aug. PWSS under Alipurduar Division PHED. ORD/000083/2020-2021 655/ALD 08/09/2020 120 BILTU DAS 22.65 16.12 82
187 Alipurduar Division Replacement of old existing AC pipeline with UPVC pipe and providing FHTC in connection with Jaldhara/Jal Sapna for Augmentation of Falakata WSS under Alipurduar Division, PHE Dte.( Masterpara, BDO Office and adjacent area.) ORD/000083/2021-2022 979/ALD 13/09/2021 60 MESSRS R N TRADERS 40.51 38.36 67
188 Alipurduar Division Construction of pathway with paver block & land development of Loknathpur HW site & 2nd site WSS (Western part of GADA rivet) under Alipurduar Division, PHE Dte. ORD/000083/2022-2023 447/ALD 13/05/2022 30 AKANSHA COMMERCIAL PRIVATE LTD. 4.19 0.00 0
189 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna for Alipurduar-II Block under Alipurduar Division, PHE Dte. (Pin point site of the FHTC will be given at the time of issue of work order) ORD/000083/2025-2026 1051/ALD 17/06/2025 360 MOTI INDUSTRIES 18.14 0.00 20
190 Alipurduar Division Withdrawing & relaying & laying of pipeline and other misc. works for retrofitting of DHUMCHIPARA PWSS under Alipurduar Division PHED. ORD/000084/2020-2021 688/ALD 16/09/2020 120 MITHUN DAS 24.86 49.21 37
191 Alipurduar Division Restoration of laying distribution system by replacing of damaged AC pipeline with DI and UPVC pipe of Kumargram WSS under Alipurduar Division, PHE Dte. ORD/000084/2021-2022 980/ALD 13/09/2021 60 DILIP MAHATO 48.35 39.41 68
192 Alipurduar Division Construction of balance portion of boundary wall at CWR site under LANKAPARA (TULSHIPARA TG ) WSS under Alipurduar Division PHE Dte . ORD/000084/2022-2023 448/ALD 13/05/2022 30 TAPASH KUMAR BHOWMICK 4.91 4.80 97
193 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna for Kalchini Block under Alipurduar Division, PHE Dte. (Pin point site of the FHTC will be given at the time of issue of work order) ORD/000084/2025-2026 1052/ALD 17/06/2025 60 MOTI INDUSTRIES 18.14 0.00 0
194 Alipurduar Division Construction of Truss roof for office cum Godown Path way at KAIJALI BUSTY WSS under Alipurduar Division PHE Dte. ORD/000085/2022-2023 449/ALD 13/05/2022 30 DAS ENTERPRISE 4.79 0.00 0
195 Alipurduar Division Laying Distribution line of UPVC & Di Pipe , with providing FHTC Connection for the Salkumarhat Water Supply Scheme Under Alipurduar Division PHE DTE (PART-A) ORD/000087/2021-2022 983/ALD 13/09/2021 60 TAPASH DAS 25.25 0.00 97
196 Alipurduar Division Laying Delivary line with M.S FOR Connection of KAIJALI BUSTY WSS under Jainti TG Water Supply Scheme . ORD/000087/2022-2023 451/ALD 13/05/2022 30 TAPASH KUMAR BHOWMICK 4.94 4.86 66
197 Alipurduar Division Restoration of pipe line by providing steel piles at Turturi River for LOKNATHPUR Water Supply Scheme Under Alipurduar Division PHE Dte. ORD/000088/2020-2021 692/ALD 16/09/2020 120 MATARA CONSTRUCTION CO 6.04 5.77 100
198 Alipurduar Division Providing house connection from Bhatibari Water Supply Scheme (Specially for schools & FHTC) under Alipurduar Division P.H.E. Dte.Part-1 ORD/000088/2021-2022 887/ALD 03/09/2021 30 SREE MAA CONSTRUCTION 4.87 4.87 21
199 Alipurduar Division Renovation of Pump house and boundary wall at H/W site of Hantapara TG PWSS under Alipurduar Division, PHE Dte. ORD/000088/2025-2026 1172/ALD 26/06/2025 90 MANI PRADHAN 1.28 0.00 0
200 Alipurduar Division Providing house connection from Bhatibari Water Supply Scheme (Specially for ICDS & FHTC) under Alipurduar Division P.H.E. Dte.Part-2 ORD/000089/2021-2022 888/ALD 03/09/2021 30 SREE MAA CONSTRUCTION 4.86 4.86 20
201 Alipurduar Division Laying of UPVC/DI/MS/CI Distribution pipe line for Gap filling and FHTC connection at different location of AUG. of Falakata PWSS (ZONE - I & III) under Alipurduar Division , PHE Dte. ORD/000089/2022-2023 453/ALD 13/05/2022 30 NARENDRA BHADANI. 5.05 5.04 65
202 Alipurduar Division Renovation of Pump house and boundary wall at 2nd site of Hantapara TG PWSS under Alipurduar Division, PHE Dte ORD/000089/2025-2026 1173/ALD 26/06/2025 90 MANI PRADHAN 1.07 0.00 0
203 Alipurduar Division Providing house connection from Rahimabad Water Supply Scheme (Specially for School & FHTC) under Alipurduar Division P.H.E. Dte.Part-3 ORD/000090/2021-2022 889/ALD 03/09/2021 30 POLY CONSTRUCTION 4.30 8.60 0
204 Alipurduar Division Balance work of construction of RADHARANI GODOWN cum REST SHED at RADHARANI WSS under Alipurduar Division , PHE Dte ( Part - A) ORD/000090/2022-2023 454/ALD 13/05/2022 30 BHAGWATI BHUJEL 5.02 4.79 92
205 Alipurduar Division Renovation of Pump house and boundary wall at 3rd site of Hantapara TG PWSS under Alipurduar Division, PHE Dte ORD/000090/2025-2026 1174/ALD 26/06/2025 90 MANI PRADHAN 1.05 0.00 0
206 Alipurduar Division House connection Providing for MAKRAPARA TG PWSS at MADARIHAT-BIRPARA Block under Alipurduar Division PHED . ORD/000091/2020-2021 697/ALD 16/09/2020 120 DILIP MAHATO 25.73 15.24 0
207 Alipurduar Division Providing house connection from Rahimabad Water Supply Scheme (Specially for School & FHTC) under Alipurduar Division P.H.E. Dte.Part-4 ORD/000091/2021-2022 890/ALD 03/09/2021 30 SOUVIK ROY PALADHI 4.30 3.54 71
208 Alipurduar Division Construction of Approach Road with paver Block at RADHARANI WSS under Alipurduar Division , PHE Dte ORD/000091/2022-2023 455/ALD 13/05/2022 30 BHAGWATI BHUJEL 4.96 4.66 92
209 Alipurduar Division Renovation of Pump house and boundary wall at 3rd Pump house of Dhumchipara TG PWSS under Alipurduar Division, PHE Dte ORD/000091/2025-2026 1175/ALD 26/06/2025 90 MANI PRADHAN 1.05 0.00 0
210 Alipurduar Division Withdrawing & relaying & laying of pipeline and other misc. works for retrofitting of GARGENDA PWSS under Alipurduar Division PHED. ORD/000092/2020-2021 698/ALD 16/09/2020 120 M/S SSB CONSTRUCTION 30.51 51.74 60
211 Alipurduar Division Renovation of Pump house and boundary wall at 2nd Pump house site of Dhumchipara TG PWSS under Alipurduar Division, PHE Dte ORD/000092/2025-2026 1176/ALD 26/06/2025 90 AVNI CONSTRUCTION 1.04 0.00 0
212 Alipurduar Division Construction of Balance boundary wall at CWR under Makrapara WSS under Alipurduar Division PHE Dte. ORD/000093/2021-2022 892/ALD 03/09/2021 45 DILIP MAHATO 4.76 4.90 0
213 Alipurduar Division Plinth protection of office cum GODOWN surface dressing & land development (H/W) at RADHARANI WSS under Alipurduar Division , PHE Dte ORD/000093/2022-2023 457/ALD 13/05/2022 30 DILIP MAHATO 4.39 3.84 82
214 Alipurduar Division Renovation of Pump house and boundary wall at 3rd Pump house site of Gargenda TG PWSS under Alipurduar Division, PHE Dte ORD/000093/2025-2026 1177/ALD 26/06/2025 90 AVNI CONSTRUCTION 1.04 0.00 0
215 Alipurduar Division Construction of Pump House with Sanitary & Plumbing arrangement at 2nd Pump House Site of Dalmore-Ramjhora WSS (Ramjhora Pump House no-2) under Alipurduar Division PHE Dte. ORD/000094/2021-2022 893/ALD 03/09/2021 60 PRAMESH LAMA 4.96 4.97 60
216 Alipurduar Division Carrying of different dia AC pipes from Alipurduar Stackyard and withdrawing CI pipes at Alipurduar Sadar Sub-Division under Alipurduar Division, PHE Dte. ORD/000094/2022-2023 458/ALD 13/05/2022 30 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 0.99 0.00 58
217 Alipurduar Division Renovation of Pump house and boundary wall at 2nd Pump house site of Gargenda TG PWSS under Alipurduar Division, PHE Dte ORD/000094/2025-2026 1178/ALD 26/06/2025 90 AVNI CONSTRUCTION 1.04 0.00 0
218 Alipurduar Division Construction of Pump House with Sanitary & Plumbing arrangement at Headwork Site of Dalmore-Ramjhora WSS (Ramjhora Pump House no-1) under Alipurduar Division PHE Dte. ORD/000095/2021-2022 894/ALD 03/09/2021 60 PRAMESH LAMA 4.96 4.97 0
219 Alipurduar Division Renovation of Pump house and boundary wall at H/W site of Gargenda TG PWSS under Alipurduar Division, PHE Dte ORD/000095/2025-2026 1179/ALD 26/06/2025 90 AVNI CONSTRUCTION 1.30 0.00 0
220 Alipurduar Division Construction of boundary wall at 2nd PH Site of Uttar Sishubari WSS under Alipurduar Division. ORD/000096/2021-2022 895/ALD 03/09/2021 45 MITHUN DAS 4.98 4.99 56
221 Alipurduar Division Installation of rising main with CI/DI pipeline and others misc. works for augmentation of Falakata PWSS (For Old OHR) under Alipurduar Division, PHE Dte. ORD/000096/2022-2023 460/ALD 13/05/2022 30 ASSOCIATE CONSTRUCTION COMPANY 5.02 5.02 100
222 Alipurduar Division Route surveying and revalidation of Household data with digitization of LDS for Lepchakha and Santalebari PWSS under Kalchini Block under Alipurduar Division, PHE Dte. ORD/000096/2025-2026 1180/ALD 26/06/2025 30 GEOTECHNICAL ENGINEERS CONSORTIUM 3.58 0.00 0
223 Alipurduar Division Route surveying and revalidation of Household data with digitization of LDS for Lankapara (Zone-I, Zone-II & Zone-III) PWSS under Madarihat-Birpara Block under Alipurduar Division, PHE Dte. ORD/000097/2025-2026 1181/ALD 26/06/2025 30 GEOTECHNICAL ENGINEERS CONSORTIUM 6.65 0.00 0
224 Alipurduar Division Providing House connection for Tapshikhata water supply scheme at Alipurduar -I Block under Alipuduar Division, P.H.E. Dte. ORD/000098/2020-2021 719/ALD 22/09/2020 30 KAMALESH ROY 4.98 9.96 0
225 Alipurduar Division Route surveying and revalidation of Household data with digitization of LDS for Cha Sundari Cluster-I,, Cluster-II, Cluster-III & Cluster-IV (with 2 options) PWSS under Madarihat-Birpara Block under Alipurduar Division, PHE Dte. ORD/000098/2025-2026 1182/ALD 26/06/2025 30 GEOTECHNICAL ENGINEERS CONSORTIUM 6.40 0.00 0
226 Alipurduar Division Providing House connection for Birpara water supply scheme at Alipurduar -I Block under Alipuduar Division, P.H.E. Dte. ORD/000099/2020-2021 720/ALD 22/09/2020 30 KAMALESH ROY 4.98 9.96 0
227 Alipurduar Division Repairing & renovation of Pump House, Pathway, Boundary wall (2nd site) & laying DI Pipe line at Salkumarhat WSS under Alipurduar Division PHE Dte. ORD/000099/2021-2022 898/ALD 03/09/2021 45 TAPASH DAS 4.82 4.16 62
228 Alipurduar Division Construction of deep TW by ODEX-165 method of drilling for Subhashini TG under Hasimara PWSS under Alipurduar Division, PHE Dte. ORD/000099/2025-2026 1184/ALD 26/06/2025 60 SWARAN ENTERPRISE 8.73 0.00 0
229 Alipurduar Division Providing House connection for Banchukamari piped water supply scheme at Alipurduar -I Block under Alipuduar Division, P.H.E. Dte. ORD/000100/2020-2021 721/ALD 22/09/2020 30 DAS CONSTRUCTION 4.99 9.99 0
230 Alipurduar Division Providing House connection for Munshipara piped water supply scheme at Alipurduar -I Block under Alipuduar Division, P.H.E. Dte. ORD/000101/2020-2021 722/ALD 22/09/2020 30 TAPASH DAS 4.98 9.97 0
231 Alipurduar Division Implementation of MINI PIPED WATER SUPPLY SCHEME IN 4(Four) nos. villages under different blocks having less than 100 household under Alipurduar district in connection with Jal Swapna. ORD/000101/2022-2023 605/ALD 31/05/2022 946 M/S KAMAK ENGINEERS AND CO 159.94 97.37 90
232 Alipurduar Division Laying Rising Main, providing FHTC, Repairing existing Pipe line, Restoration of FHTC at 4th TW site and Gap filing in distribution system at Kaijali Busty PWSS under Alipurduar Division, PHE Dte. ORD/000101/2025-2026 1186/ALD 26/06/2025 75 RAMEN DEY & CO 15.59 0.00 0
233 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Uttar Latabari PWSS under Alipurduar Division, PHE Dte. Part-2 ORD/000102/2022-2023 406/ALD 11/05/2022 45 ASHOK SAPKOTA 24.20 20.74 42
234 Alipurduar Division Restoration of damaged FHTCs of Kaijali Busty PWSS under Alipurduar Division, PHE Dte. ORD/000102/2025-2026 1187/ALD 26/06/2025 45 RAMEN DEY & CO 4.00 0.00 0
235 Alipurduar Division Providing House connection for Bhutia Basty and Jayanti water supply scheme at Kalchini Block under Alipuduar Division, P.H.E. Dte ORD/000103/2020-2021 724/ALD 22/09/2020 30 M/S BHOWMICK CONSTRUCTION 4.99 9.99 0
236 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Uttar Latabari PWSS under Alipurduar Division, PHE Dte. Part-3 ORD/000103/2022-2023 407/ALD 11/05/2022 45 SHIB RATAN BHOWMIK 24.21 8.68 46
237 Alipurduar Division Providing balance FHTC and construction of new sluice valve chamber for controlling water including laying UPVC pipe at leftout area of Chhoto Salkumar PWSS and other allied works adjacent to Augmentation of Salkumarhat PWSS under Alipurduar Division, PHE Dte. ORD/000103/2025-2026 1188/ALD 26/06/2025 90 M/S DUTTA AND CO 26.37 0.00 0
238 Alipurduar Division Providing House connection for Putimari water supply scheme at Alipurduar-II Block under Alipuduar Division, P.H.E. Dte. ORD/000104/2020-2021 725/ALD 22/09/2020 30 HIMALAYAN CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 5.02 10.04 0
239 Alipurduar Division Installation of additional new tube well by ODEX-165 method of drilling for Uttar Kamakhyaguri Water Supply Scheme under Alipurduar Division PHE DTE. ORD/000104/2022-2023 776/ALD 20/06/2022 30 ANUP GUPTA 6.99 5.44 57
240 Alipurduar Division Laying of pipeline distribution system (Parallel and left out Area) and other allied works at Salkumarhat PWSS within APD-I Block under Alipurduar Division, PHE Dte. ORD/000104/2025-2026 1222/ALD 01/07/2025 60 DILIP MAHATO (OPC) PRIVATE LIMITED 53.57 0.00 0
241 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Augmentation of Bholardabri Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000105/2022-2023 697/ALD 08/06/2022 30 KAMALESH ROY 4.84 4.84 63
242 Alipurduar Division Replacement of damaged pipeline with HDPE pipes for Purba Kathalbari Zone-I PWSS under Alipurduar Division, PHE Dte. ORD/000105/2025-2026 1223/ALD 01/07/2025 60 DILIP MAHATO (OPC) PRIVATE LIMITED 5.30 0.00 0
243 Alipurduar Division Construction of Approach road for 2nd TWS & others misc work of Radharani WSS under Alipurduar Division PHE Dte. ORD/000106/2021-2022 904/ALD 03/09/2021 30 SOUVIK ROY PALADHI 4.98 4.04 86
244 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Augmentation of Putimari Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000106/2022-2023 698/ALD 08/06/2022 30 TAPASH DAS 4.83 4.83 93
245 Alipurduar Division Supply and installation of sign board at different PWSS under Birpara Sub-Division, under Alipurduar Division, PHE Dte. ORD/000106/2025-2026 1224/ALD 01/07/2025 30 DILIP MAHATO (OPC) PRIVATE LIMITED 6.89 0.00 100
246 Alipurduar Division Providing House connection for Bakla Piped water supply scheme at Alipurduar-II Block under Alipuduar Division, P.H.E. Dte. ORD/000107/2020-2021 728/ALD 22/09/2020 30 PROGRESSIVE UNEMPLOYED CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 4.98 9.96 0
247 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Dakshin Paitkapara Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000107/2022-2023 699/ALD 08/06/2022 30 HARIDAS GHOSH 4.92 4.92 84
248 Alipurduar Division Distribution line for Barobisha (Zone-III) water Supply Scheme under Alipurduar Division, PHE Dte. (Part-A) ORD/000108/2020-2021 729/ALD 22/09/2020 45 TAPAN CHANDA 4.97 9.27 0
249 Alipurduar Division Preparation of Augmentation D.P.R after investigation For Purba Kathalbari W/S scheme under Alipurduar Division. ORD/000108/2021-2022 911/ALD 06/09/2021 30 BHAGWATI BHUJEL 2.14 4.28 0
250 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Augmentation of Narathali Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000108/2022-2023 700/ALD 08/06/2022 30 M/S SHIB RATAN BHOWMICK & CO 4.88 4.88 70
251 Alipurduar Division Distribution line for Barobisha (Zone-III) water Supply Scheme under Alipurduar Division, PHE Dte. (Part-B) ORD/000109/2020-2021 730/ALD 22/09/2020 45 TAPAN CHANDA 5.00 9.94 0
252 Alipurduar Division Preparation of Agumentation D.P.R after investigation For Kumargram W/Sscheme under Alipurduar Division. ORD/000109/2021-2022 912/ALD 06/09/2021 30 BHAGWATI BHUJEL 2.77 5.54 0
253 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Augmentation of Uttar Majherdabri Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000109/2022-2023 701/ALD 08/06/2022 30 HARIDAS GHOSH 4.96 4.96 73
254 Alipurduar Division Preparation of Augmentation D.P.R after investigation For Bhatibari W/S scheme under Alipurduar Division. ORD/000110/2021-2022 913/ALD 06/09/2021 30 BHAGWATI BHUJEL 2.62 5.25 0
255 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Augmentation of Kaijali Basti Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000110/2022-2023 702/ALD 08/06/2022 30 NARENDRA BHADANI. 4.98 4.98 66
256 Alipurduar Division Preparation of Augmentation D.P.R after investigation For Jateswar W/S scheme under Alipurduar Division. ORD/000111/2021-2022 914/ALD 06/09/2021 30 BHAGWATI BHUJEL 2.31 2.31 0
257 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Augmentation of Hasimara Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000111/2022-2023 703/ALD 08/06/2022 30 MADHAB SAHA 4.84 4.84 50
258 Alipurduar Division Preparation of Augmentation D.P.R after investigation For SamuktalaW/S scheme under Alipurduar Division. ORD/000112/2021-2022 915/ALD 06/09/2021 30 BHAGWATI BHUJEL 2.81 5.61 0
259 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Augmentation of Totpara Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000112/2022-2023 704/ALD 08/06/2022 30 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 4.92 4.92 99
260 Alipurduar Division Supply and installation of scheme information board at different PWSS site of Kalchini Block under Alipurduar Division, PHE Dte. ORD/000112/2025-2026 1394/ALD 16/07/2025 60 M/S SARKAR & CO 3.64 0.00 100
261 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Mathura Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000113/2022-2023 705/ALD 08/06/2022 30 SASANKA ROY 4.79 4.79 65
262 Alipurduar Division Expenditure for different PWSS land registration and subsequent mutation process as compliance for PHED and Land commissioner authorise to overcome the stalemate and initiation of due diligence process in Kalchini Block under Alipurduar Division, PHE Dte. ORD/000113/2025-2026 1395/ALD 16/07/2025 300 M/S SARKAR & CO 2.00 0.00 60
263 Alipurduar Division Preparation of Augmentation D.P.R after investigation For Dalimpur W/S scheme under Alipurduar Division. ORD/000114/2021-2022 920/ALD 06/09/2021 30 BHAGWATI BHUJEL 2.18 4.37 0
264 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Augmentation of Uttar Kamakhyaguri Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000114/2022-2023 706/ALD 08/06/2022 30 DEBAJYOTI SUTRADHAR 4.95 4.95 57
265 Alipurduar Division Preparation of Augmentation D.P.R after investigation For Salkumarhat W/S scheme under Alipurduar Division. ORD/000115/2021-2022 921/ALD 06/09/2021 30 BHAGWATI BHUJEL 1.08 2.15 0
266 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Gangutia Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000115/2022-2023 707/ALD 08/06/2022 30 DAS CONSTRUCTION 4.89 4.89 68
267 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Mechpara Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000116/2022-2023 708/ALD 08/06/2022 30 TAPASH KUMAR BHOWMICK 4.89 4.89 40
268 Alipurduar Division Supply of 250 mm dia CI Sluice Valve for Augmentation of Bhutnirghat Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000117/2022-2023 709/ALD 08/06/2022 30 DILIP MAHATO 4.93 4.93 98
269 Alipurduar Division Laying of Distribution Line (by using metal Pipes) of Zone-I for JDA (Jaigaon Development Authority) Area Water Supply Scheme under Alipurduar District. ORD/000118/2020-2021 789/ALD 01/10/2020 150 M/S SSB CONSTRUCTION CO. 185.60 295.06 65
270 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Jateswar PWSS under Alipurduar Division, PHE Dte. Part-4 ORD/000118/2022-2023 411/ALD 11/05/2022 45 SOUVIK ROY PALADHI 24.47 10.14 63
271 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Jateswar PWSS under Alipurduar Division, PHE Dte. Part-5 ORD/000119/2022-2023 412/ALD 11/05/2022 45 AASHIRBAD ENTERPRISE 24.10 0.00 65
272 Alipurduar Division Laying of Different Dia pipeline And providing FHTC For Uttar Simlabari and adjoing area under Patlakhowa PWSS at Alipurduar-I Block under Alipurduar Division, PHE Dte. ORD/000121/2022-2023 1491/ALD 05/09/2022 766 SHREE RANISATI ENTERPRISE 100.02 0.00 30
273 Alipurduar Division Extension of pipeline to Bharnabari TG area under Hasimara PWSS for providing at Kalchini Block under Alipurduar Division, P.H.E. Dte.(Part-A) ORD/000122/2020-2021 794/ALD 01/10/2020 60 TAPASH KUMAR BHOWMICK 40.85 64.49 98
274 Alipurduar Division Laying of Different Dia pipeline And providing FHTC For Patlakhowa and Adjoining area under Patlakhowa PWSS at Alipurduar-I Block under Alipurduar Division, PHE Dte. ORD/000122/2022-2023 919/ALD 07/07/2022 45 M/S DUTTA AND CO 72.26 47.54 70
275 Alipurduar Division Extension of pipeline for Jainti TG including connection from Reservoir-2 under Jainti TG Water Supply Scheme (Part-A). ORD/000123/2020-2021 795/ALD 01/10/2020 60 CALCON CONSTRUCTIONS 40.62 64.59 90
276 Alipurduar Division Laying of HDPE pipeline and interconnection of other different dia pipe line with CIDF Specials & Providing house connection (FHTC) at Uttar Madarihat WSS under Alipurduar Division PHE Dte. ORD/000127/2021-2022 1241/ALD 27/09/2021 60 M/S SURAJIT DEY & CO 47.32 22.91 96
277 Alipurduar Division Laying of additional HDPE pipeline at Ramjhora TG under Ranjhora WSS under Alipurduar Division, PHE Dte. ORD/000128/2025-2026 1536/ALD 29/07/2025 45 SUNIL HAJANG THAKUR 13.14 0.00 0
278 Alipurduar Division Repair of Gate, Drainage System & Rest Shed infront of Office cum Godown building at H/W Site of Birpara WSS under Alipuduar Division, P.H.E. Dte. ORD/000129/2020-2021 875/ALD 14/10/2020 45 DILIP MAHATO 4.97 9.61 0
279 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna for Falakata Block under Alipurduar Division, PHE Dte. (Pin point site of the FHTC will be given at the time of issue of work order) ORD/000130/2025-2026 1629/ALD 04/08/2025 60 NARENDRA BHADANI. 18.13 0.00 0
280 Alipurduar Division Repair of Pump House with additional Toilet at 2nd Pump House site of Madarihat WSS under Alipuduar Division, P.H.E. ORD/000131/2020-2021 877/ALD 14/10/2020 45 DILIP MAHATO 2.13 1.86 91
281 Alipurduar Division Laying Distribution line of UPVC & Di Pipe , with providing FHTC Connection for the Salkumarhat Water Supply Scheme Under Alipurduar Division PHE DTE (PART-A) ORD/000131/2021-2022 1242/ALD 27/09/2021 60 KAMALESH ROY 25.25 20.28 9
282 Alipurduar Division Soil investigation work for proposed overhead reservoir, cons. Of 150cum OHR at Dalmore, 2nos. Of TW boring by ODEX-165 method of drilling at Dalmore and Ramjhora, cons. of pump house and boundary wall at both TW site, LDS as per Departmental Design & drawing for DALMORE & RAMJHORA TG PWSS under Birpara Sub-Division, Alipurduar Division PHE DTE. ORD/000131/2023-2024 638/ALD 06/06/2023 180 SUKAMAL GHOSH 158.82 0.00 0
283 Alipurduar Division Laying of 90 mm HDPE pipeline in uncovered area and construction of excess work of boundary wall and 3 m span open foundation culvert with boulder protection works and other allied works at 2nd site of Shrinathpur TG PWSS under alipurduar Division, PHE Dte. ORD/000131/2025-2026 1628/ALD 04/08/2025 75 PRAPTI DUTTA 11.82 0.00 0
284 Alipurduar Division Extension of Distribution line with UPVC pipe line (From B.Ed College to Pulin Biswas House) under Dalimpur Water Supply Scheme under Alipurduar Division,PHE Dte. ORD/000132/2020-2021 878/ALD 14/10/2020 30 NARAYAN CHANDRA SAHA 3.14 5.95 0
285 Alipurduar Division Cons of PH AND TW Boring by ODEX-165 drilling at HW site and 2nd site , LDS with HDPE P/LINE INCL RM and delivery connection , CONS of 100 Cum OHR along with the Soil investigation works , providing FHTC and others for Jayanti Tea Garden-II PWSS Under Alipurduar Division PHE DTE. ORD/000132/2023-2024 637/ALD 06/06/2023 901 ACHINTA SAHA 170.77 85.86 70
286 Alipurduar Division Laying of HDPE pipeline (parallel and balance line ) at Khagenhat PWSS under Alipurduar Division, PHE Dte. ORD/000132/2025-2026 1627/ALD 04/08/2025 75 DILIP MAHATO 77.79 0.00 0
287 Alipurduar Division Extension of Distribution line with UPVC pipe line (From Pulin Biswas House to Bipul Islam House) under Dalimpur Water Supply Scheme under Alipurduar Division,PHE Dte. ORD/000133/2020-2021 879/ALD 14/10/2020 30 PARAMJYOTI ENTERPRISE 3.14 5.94 0
288 Alipurduar Division Laying Distribution line of UPVC & Di Pipe , with providing FHTC Connection for the Salkumar Water Supply Scheme Under Alipurduar Division PHE DTE (PART-A) ORD/000133/2021-2022 1243/ALD 27/09/2021 60 TAPASH DAS 25.25 22.51 78
289 Alipurduar Division Laying of HDPE pipeline (left out ) at Dhanirampur PWSS under Alipurduar Division, PHE Dte. ORD/000133/2025-2026 1626/ALD 04/08/2025 60 DILIP MAHATO 30.28 0.00 0
290 Alipurduar Division Extension of Distribution line with UPVC pipe line near Narendra Nath Sishu Siksha Kendra under Jateswar Water Supply Scheme under Alipurduar Division,PHE Dte. ORD/000134/2020-2021 880/ALD 14/10/2020 30 NARAYAN CHANDRA SAHA 2.02 3.71 0
291 Alipurduar Division Laying of HDPE pipeline (new and Parallel ) at Malsagaon PWSS under Alipurduar Division, PHE Dte. ORD/000134/2025-2026 1625/ALD 04/08/2025 75 DILIP MAHATO 65.97 0.00 0
292 Alipurduar Division Construction of 150cum. OHR for Bandapani ZONE-II Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000137/2022-2023 974/ALD 15/07/2022 540 MITHUN DAS 49.89 43.12 86
293 Alipurduar Division Construction of 250cum. OHR for Newlands TG Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000138/2022-2023 975/ALD 15/07/2022 1143 TAPASH KUMAR BHOWMICK 57.61 41.99 75
294 Alipurduar Division Reparing of Pump House at 2nd site of MADHU TG PWSS Under Alipurduar Division PHE DTE. ORD/000138/2025-2026 1575/ALD 31/07/2025 60 NARENDRA BHADANI. 0.94 0.00 0
295 Alipurduar Division Construction of 250cum. OHR for Kumargram TG Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000139/2022-2023 976/ALD 15/07/2022 180 HARIDAS GHOSH 57.62 47.61 100
296 Alipurduar Division Reparing of Pump House at 3rd site of MADHU TG PWSS Under Alipurduar Division PHE DTE. ORD/000139/2025-2026 1576/ALD 31/07/2025 60 NARENDRA BHADANI. 0.78 0.00 0
297 Alipurduar Division Construction of 250cum. OHR for Sankosh TG Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000140/2022-2023 977/ALD 15/07/2022 180 SOUVIK ROY PALADHI 57.62 39.52 80
298 Alipurduar Division Reparing of Pump House at Headwork site of MADHU TG PWSS Under Alipurduar Division PHE DTE. ORD/000140/2025-2026 1577/ALD 31/07/2025 60 NARENDRA BHADANI. 0.94 0.00 0
299 Alipurduar Division Providing House connection for KUMARGRAM water supply scheme at KUMARGRAM Block under Alipuduar Division, P.H.E. Dte. ORD/000141/2020-2021 857/ALD 14/10/2020 30 ASHIM KUMAR CHAKRABORTY 4.98 4.98 8
300 Alipurduar Division Laying of different dia. Pipeline and providing FHTC for Northern side of Purba Kathalbari Zone (II) PWSS and surrounding areas at Alipurduar-I Block under Alipurduar Division, PHE Dte. ORD/000141/2022-2023 978/ALD 15/07/2022 60 DILIP MAHATO 99.77 76.96 15
301 Alipurduar Division Reparing of Pump House at 2nd site of Dima TG PWSS Under Alipurduar Division PHE DTE. ORD/000141/2025-2026 1578/ALD 31/07/2025 60 TAPASH DAS 0.99 0.00 0
302 Alipurduar Division Providing House connection for BAROBISHA ZONE- I water supply scheme at KUMARGRAM Block under Alipuduar Division, P.H.E. Dte. ORD/000142/2020-2021 858/ALD 14/10/2020 30 TAPAN CHANDA 4.98 9.97 0
303 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling including Rising Main at H/W site and 2nd site for Purba Kathalbari Zone-II PWSS Under Alipurduar Division PHE DTE. ORD/000142/2022-2023 979/ALD 15/07/2022 1081 JYOTI CHHETRI 45.88 38.27 61
304 Alipurduar Division Reparing of Pump House at Headwork site of Dima TG PWSS Under Alipurduar Division PHE DTE. ORD/000142/2025-2026 1579/ALD 31/07/2025 60 TAPASH DAS 0.79 0.00 0
305 Alipurduar Division Providing House connection for BAROBISHA ZONE- II water supply scheme at KUMARGRAM Block under Alipuduar Division, P.H.E. Dte. ORD/000143/2020-2021 859/ALD 14/10/2020 30 AKANSHA COMMERCIAL PRIVATE LTD. 4.98 9.96 0
306 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling including Rising Main at H/W site and 2nd site for Purba Kathalbari Zone-IV PWSS Under Alipurduar Division PHE DTE. ORD/000143/2022-2023 980/ALD 15/07/2022 720 MAHENDRA CHHETRI 46.09 27.06 98
307 Alipurduar Division Withdrawing and relaying and laying of UPVC/DI/MS/CI Distribution pipe line and other misc. work for retrofitting of Mujnai PWSS under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000144/2020-2021 943/ALD 19/10/2020 60 VEDATRAYEE AND CO 29.81 58.89 92
308 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Purba Kathalbari PWSS under Alipurduar Division, PHE Dte. Part-3 ORD/000144/2022-2023 981/ALD 15/07/2022 45 MAHENDRA CHHETRI 24.20 7.33 26
309 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for PurbaKathalbari PWSS under Alipurduar Division, PHE Dte. Part-4 ORD/000145/2022-2023 982/ALD 15/07/2022 45 DAS CONSTRUCTION 24.14 0.00 27
310 Alipurduar Division Withdrawing and relaying of UPVC and DI pipeline due to damaged during bitumen road construction and other misc works at Tapshikhata PWSS under Alipurduar Division, PHE Dte. ORD/000146/2020-2021 941/ALD 19/10/2020 60 KAMALESH ROY 10.81 17.28 77
311 Alipurduar Division Providing FHTC at Kumargram WSS under Alipurduar Division, PHE Dte. Part-3 ORD/000146/2022-2023 1001/ALD 15/07/2022 30 DILIP MAHATO 5.04 0.00 0
312 Alipurduar Division Construction of 150cum. OHR for KUMARGRAM ZONE-IV Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000147/2022-2023 983/ALD 15/07/2022 180 MATRI ENTERPRISE 50.41 0.00 0
313 Alipurduar Division Providing House connection for BAROBISHA ZONE- III water supply scheme at KUMARGRAM Block under Alipuduar Division, P.H.E. Dte. ORD/000148/2020-2021 860/ALD 14/10/2020 30 AKANSHA COMMERCIAL PRIVATE LTD. 4.98 4.98 79
314 Alipurduar Division Providing House Connection (FHTC) at Kumargram WSS under Alipurduar Division, PHE Dte. Part-4 ORD/000148/2022-2023 1002/ALD 15/07/2022 30 DILIP MAHATO 5.04 0.00 43
315 Alipurduar Division Providing House connection for KAMAKHYAGURI water supply scheme at KUMARGRAM Block under Alipuduar Division, P.H.E. Dte. ORD/000149/2020-2021 861/ALD 14/10/2020 30 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 4.94 4.94 98
316 Alipurduar Division Construction of 150cum. OHR for PURBA KATHALBARI ZONE-IV Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000149/2022-2023 984/ALD 15/07/2022 720 MAHENDRA CHHETRI 50.44 38.98 52
317 Alipurduar Division Providing House connection for KAIJALI BASTYI water supply scheme at KUMARGRAM Block under Alipuduar Division, P.H.E. Dte. ORD/000150/2020-2021 862/ALD 14/10/2020 30 DAS ENTERPRISE 4.96 4.96 68
318 Alipurduar Division Providing House Connection (FHTC) at Kumargram WSS under Alipurduar Division, PHE Dte. Part-5 ORD/000150/2022-2023 1003/ALD 15/07/2022 30 DILIP MAHATO 5.04 0.00 42
319 Alipurduar Division Providing House connection for LOKNATHPUR water supply scheme at KUMARGRAM Block under Alipuduar Division, P.H.E. Dte. ORD/000152/2020-2021 864/ALD 14/10/2020 30 MATARA CONSTRUCTION CO 4.98 9.97 0
320 Alipurduar Division Construction of OHR 200cum for PURBA KATHALBARI ZONE-III Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000152/2022-2023 986/ALD 15/07/2022 180 MADHAB SAHA 55.36 45.63 51
321 Alipurduar Division Providing House connection for BHUTNIRGHAT water supply scheme at FALAKATA Block under Alipuduar Division, P.H.E. Dte. ORD/000153/2020-2021 865/ALD 14/10/2020 30 GOUTAM KUMAR DAS 4.98 6.28 0
322 Alipurduar Division Restoration of Laying distribution system by replacing of Damaged AC pipeline with UPVC pipe of Kumargram WSS under Alipurduar Division, PHE Dte. ORD/000153/2022-2023 1004/ALD 15/07/2022 30 DILIP MAHATO 4.92 4.65 8
323 Alipurduar Division Repairing of Pump House no1 at HW site of SAMUKTALA PWSS Under Alipurduar Division PHE DTE. ORD/000153/2025-2026 1590/ALD 31/07/2025 60 PRITAM DAS 0.97 0.00 0
324 Alipurduar Division Providing House connection for DALIMPUR water supply scheme at FALAKATA Block under Alipuduar Division, P.H.E. Dte. ORD/000154/2020-2021 866/ALD 14/10/2020 30 SANJIT SAHA 4.93 4.93 88
325 Alipurduar Division Repairing of Pump House at 2nd TW site of BAKLA PWSS Under Alipurduar Division PHE DTE. ORD/000154/2025-2026 1591/ALD 31/07/2025 60 SHYAMAL ROY 0.95 0.00 0
326 Alipurduar Division Providing House connection for JATESWAR water supply scheme at FALAKATA Block under Alipuduar Division, P.H.E. Dte. PART-1 ORD/000155/2020-2021 867/ALD 14/10/2020 30 PARAMJYOTI ENTERPRISE 4.93 9.87 0
327 Alipurduar Division Construction of 250cum OHR for PURBA KATHALBARI ZONE-I Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000155/2022-2023 987/ALD 15/07/2022 180 NEOGI ENTERPRISE 57.61 38.03 35
328 Alipurduar Division Providing House connection for JATESWAR water supply scheme at FALAKATA Block under Alipuduar Division, P.H.E. Dte. PART-2 ORD/000156/2020-2021 868/ALD 14/10/2020 30 NARAYAN CHANDRA SAHA & SONS 4.93 9.87 0
329 Alipurduar Division Soil investigation work at 4 different places of Kumargram within Alipurduar District under Alipurduar Division PHE Dte. ORD/000156/2022-2023 1005/ALD 15/07/2022 30 MOYTEC 4.88 0.00 0
330 Alipurduar Division Soil investigation work at 4 different places of Purba Kanthalbari within Alipurduar District under Alipurduar Division PHE Dte. ORD/000157/2022-2023 1006/ALD 15/07/2022 30 MABCO CONSULTANT, 4.87 4.87 27
331 Alipurduar Division Laying Distribution of pipeline with DI and UPVC pipeline along with FHTC Connection for Purba Kathalbari area, Purba Kathalbari WSS under Alipurduar Division, PHE Dte. ORD/000158/2022-2023 988/ALD 15/07/2022 60 NEOGI ENTERPRISE 98.79 80.10 30
332 Alipurduar Division Construction of pump house, Boundary Wall, Tube well Boring (by ODEX-165 method of drilling) and Rising main for Zone-II 1st TW site at Augmentation of Birpara PWSS under Alipurduar Division, PHE Dte. ORD/000158/2023-2024 663/ALD 07/06/2023 480 BRAJA GOPAL SAHA 31.58 22.36 20
333 Alipurduar Division Laying of pipeline distribution system (Parallel and left out Area) and other allied works at Purba Kathalbari Zone-II PWSS within APD-I Block under Alipurduar Division, PHE Dte. ORD/000158/2025-2026 1743/ALD 13/08/2025 60 ANIRBAN DEY SARKAR CONSTRUCTION 41.04 0.00 0
334 Alipurduar Division Providing House connection for PASCHIM KHAYERBARI water supply scheme at MADARIHAT-BIRPARA Block under Alipuduar Division, P.H.E. Dte. ORD/000159/2020-2021 871/ALD 14/10/2020 30 NARENDRA BHADANI. 4.98 8.97 93
335 Alipurduar Division Laying Distribution of pipeline with DI and UPVC pipeline along with FHTC Connection at Jogendranagar area, Purba Kathalbari WSS under Alipurduar Division, PHE Dte. ORD/000159/2022-2023 989/ALD 15/07/2022 60 UTTAM KUMAR DUTTA 98.45 87.43 27
336 Alipurduar Division Repairing of Pump house at 3rd site of Chhoto Salkumar adjacent to Augmentation of Salkumarhat PWSS under Alipurduar Division, PHE Dte. ORD/000159/2025-2026 1744/ALD 13/08/2025 60 ANIRBAN DEY SARKAR CONSTRUCTION 2.31 0.00 0
337 Alipurduar Division Soil investigation work at 3 different places of Dalimpur within Alipurduar District under Alipurduar Division PHE Dte. ORD/000160/2023-2024 965/ALD 12/07/2023 30 CITY ENGINEERING & TESTING LABORATORY 3.67 3.67 100
338 Alipurduar Division Providing House connection for BHUTNIRGHAT water supply scheme at FALAKATA Block under Alipuduar Division, P.H.E. Dte.(PART-2) ORD/000161/2020-2021 905/ALD 16/10/2020 30 GOUTAM KUMAR DAS 4.98 9.97 0
339 Alipurduar Division Providing FHTC and other allied works at Munshipara WSS under Alipurduar Division, PHE Dte. ORD/000161/2021-2022 1303/ALD 05/10/2021 60 BENGAL YOUTH UN EMPLOYED ENGINEERS CO OPERATIVE SOCIETY LIMITED 44.94 39.27 82
340 Alipurduar Division Construction of OHR 200cum for PURBA KATHALBARI ZONE-II Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000161/2022-2023 991/ALD 15/07/2022 1175 MS DEYS CONSTRUCTION 55.50 25.00 55
341 Alipurduar Division Construction of 400cum OHR for DALIMPUR ZONE-I Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000161/2023-2024 968/ALD 12/07/2023 900 NARAYAN CHANDRA SAHA 77.28 28.26 60
342 Alipurduar Division Providing FHTC of Uttar Kamakhyaguri WSS under Alipurduar Division, PHE Dte. (Part-4) ORD/000162/2021-2022 1304/ALD 05/10/2021 60 DULAL MAJUMDER 34.38 32.66 76
343 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Dalimpur PWSS under Alipurduar Division, PHE Dte. Part-3 ORD/000162/2023-2024 966/ALD 12/07/2023 180 TAPASH DAS 34.77 4.52 15
344 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe along with FHTC Connection surrounding Sirubari area, Purba Kathalbari WSS under Alipurduar Division, PHE Dte. ORD/000163/2022-2023 993/ALD 15/07/2022 783 MS DEYS CONSTRUCTION 99.93 69.73 85
345 Alipurduar Division Construction of 1no Pump house, boundary wall and other allied works at 3rd TW Site of Nimti Domohani PWSS under Alipurduar Division, PHE Dte. ORD/000163/2025-2026 1771/ALD 18/08/2025 120 SATYABRATA BHATTACHERJEE 21.28 0.00 0
346 Alipurduar Division Providing House connection for PURBA KATHALBARI water supply scheme at ALIPURDUAR-I Block under Alipuduar Division, P.H.E. Dte. ORD/000164/2020-2021 908/ALD 16/10/2020 30 SREE MAA CONSTRUCTION & CO. 4.98 6.89 0
347 Alipurduar Division Retrofitting of pipeline for the 'Jal Sapno' programme and providing FHTC Connection under Chandirjhar WSS under Alipurduar Division, PHE Dte. ORD/000164/2021-2022 1305/ALD 05/10/2021 60 SASANKA ROY 50.06 49.72 36
348 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe along with FHTC Connection surrounding Palashbari area, Purba Kathalbari WSS under Alipurduar Division, PHE Dte. ORD/000164/2022-2023 994/ALD 15/07/2022 180 BENGAL YOUTH UN EMPLOYED ENGINEERS CO OPERATIVE SOCIETY LIMITED 87.56 53.26 28
349 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling including Rising Main at H/W site and 2nd site for Dalimpur Zone-III PWSS Under Alipurduar Division PHE DTE. ORD/000164/2023-2024 967/ALD 12/07/2023 750 NARENDRA BHADANI. 45.90 44.65 100
350 Alipurduar Division Repairing of pump house at 2nd TW site of Bholardabri PWSS under Alipurduar Division, PHE Dte. ORD/000164/2025-2026 1772/ALD 18/08/2025 30 TAPASH DAS 1.01 0.00 0
351 Alipurduar Division Providing House connection for CHANDIRJHAR water supply scheme at ALIPURDUAR-II Block under Alipuduar Division, P.H.E. Dte. ORD/000165/2020-2021 909/ALD 16/10/2020 30 SREE MAA CONSTRUCTION & CO. 4.98 9.96 0
352 Alipurduar Division Laying of different dia. Pipeline and providing FHTC for Purba Kathalbari Zone(IV) PWSS area and surrounding, Alipurduar-I Block under Alipurduar Division, PHE Dte.(Part-A) ORD/000165/2022-2023 995/ALD 15/07/2022 60 DAS ENTERPRISE 99.06 67.23 27
353 Alipurduar Division Laying of distribution of UPVC/DI/GI pipeline including FHTC for DALIMPUR PWSS under Alipurduar Division, PHE DTE. PART-2 ORD/000165/2023-2024 970/ALD 12/07/2023 480 MITHUN DAS 67.93 63.74 65
354 Alipurduar Division Providing House connection for SALSALABARI water supply scheme at ALIPURDUAR-II Block under Alipuduar Division, P.H.E. Dte. ORD/000166/2020-2021 910/ALD 16/10/2020 30 M/S BHOWMICK CONSTRUCTION 4.96 9.91 0
355 Alipurduar Division Laying of different dia. Pipeline and providing FHTC for Purba Kathalbari Zone(IV) PWSS area and surrounding area of NH-31D at Alipurduar-I Block under Alipurduar Division, PHE Dte.(Part-B) ORD/000166/2022-2023 996/ALD 15/07/2022 60 NARAYAN CHANDRA SAHA 99.18 75.08 76
356 Alipurduar Division Providing House connection for BAROBISHA ZONE- I water supply scheme at KUMARGRAM Block under Alipuduar Division, P.H.E. Dte.(PART-2) ORD/000167/2020-2021 911/ALD 16/10/2020 30 TAPAN CHANDA 4.98 9.97 0
357 Alipurduar Division Restoration of laying distribution system by replacing of damaged AC pipeline with UPVC pipeline of Uttar Kamakhyaguri WSS under Alipurduar Division, PHE Dte.(Part-A) ORD/000167/2021-2022 1306/ALD 05/10/2021 60 GOUTAM KUMAR DAS 25.34 21.65 74
358 Alipurduar Division Laying of different dia. Pipeline and providing FHTC for Southern side of Purba Kathalbari Zone (II) PWSS and surrounding areas at Alipurduar-I Block under Alipurduar Division, PHE Dte. ORD/000167/2022-2023 997/ALD 15/07/2022 60 M/S JHA CONSTRUCTION 99.69 76.99 27
359 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling including Rising Main at H/W site and 2nd site along with repairing of office godown for Dalimpur Zone-I PWSS Under Alipurduar Division PHE DTE. ORD/000167/2023-2024 973/ALD 12/07/2023 360 NARAYAN CHANDRA SAHA 48.31 48.23 65
360 Alipurduar Division Providing House connection for BAROBISHA ZONE- II water supply scheme at KUMARGRAM Block under Alipuduar Division, P.H.E. Dte.(PART-2) ORD/000168/2020-2021 912/ALD 16/10/2020 30 AKANSHA COMMERCIAL PRIVATE LTD. 4.98 9.97 0
361 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling including Rising Main at H/W site and 2nd site for Purba Kathalbari Zone-III PWSS Under Alipurduar Division PHE DTE. ORD/000168/2022-2023 1008/ALD 15/07/2022 90 MADHAB SAHA 45.90 39.60 86
362 Alipurduar Division Providing House connection for KAIJALI BUSTY water supply scheme at KUMARGRAM Block under Alipuduar Division, P.H.E. Dte.(PART-2) ORD/000169/2020-2021 913/ALD 16/10/2020 30 DAS ENTERPRISE 4.96 4.96 67
363 Alipurduar Division Laying Distribution line of UPVC, DI Pipe (with pillar) and cons. Of new toilet, repairing of pump house (2nd site), Land Development at Barobisa Zone-I Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000169/2021-2022 1319/ALD 05/10/2021 60 M/S SURAJIT DEY & CO 81.49 48.46 70
364 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling including Rising Main at H/W site and 2nd site along with repairing of 1 no. pump house for Purba Kathalbari Zone-I PWSS Under Alipurduar Division PHE DTE. ORD/000169/2022-2023 1007/ALD 15/07/2022 90 SAMIRON PODDER 43.06 40.49 0
365 Alipurduar Division Construction of 150cum. OHR for DALIMPUR ZONE-III Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000169/2023-2024 972/ALD 12/07/2023 360 UJJWAL ROY 50.43 40.91 100
366 Alipurduar Division Repairing and relaying of 90 mm dia damaged HDPE pipeline (from node-33 to 32 to 29 to 25) for Kartika PWSS under Alipurduar Division, PHE Dte. ORD/000169/2025-2026 1777/ALD 18/08/2025 45 TAPASH DAS 1.40 0.00 0
367 Alipurduar Division Laying of UPVC & DI (with pillar) pipeline for Barobisha Zone-III Water Supply Scheme under Alipurduar Division, PHE Dte. (Part-A) ORD/000170/2021-2022 1320/ALD 05/10/2021 60 AKANSHA COMMERCIAL PRIVATE LTD. 79.02 73.66 66
368 Alipurduar Division Extension and replacement of damaged pipeline and providing FHTC at surrounding area of Kumargram PWSS, Kumargram Block under Alipurduar Division, PHE Dte. ORD/000170/2022-2023 1009/ALD 15/07/2022 60 DILIP MAHATO 43.79 13.32 6
369 Alipurduar Division Construction of tube wells (2 nos.) by Reverse rotary method of drilling at HW site and 2nd TW site , constructions of 200 Cum OHR at HW including soil investigation, construction of pump house and boundary wall at H/W and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Tasti Tea Garden PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE.(2nd call) ORD/000170/2023-2024 975/ALD 12/07/2023 994 MADHAB SAHA 298.87 95.05 15
370 Alipurduar Division Laying rising main line from 2nd side to HW Site of Bholardabri WSS and construction of different dia valve chamber and restoration of damaged FHTC connection and other allied work at Bholardabri PWSS under JJM Programme under Alipurduar Division, PHE Dte. ORD/000170/2025-2026 1778/ALD 18/08/2025 60 TAPASH DAS 2.88 0.00 0
371 Alipurduar Division Construction of pump house, Boundary Wall, Tube well Boring (by ODEX-165 method of drilling) and Rising main for Zone-III 2nd TW site at Augmentation of Birpara PWSS under Alipurduar Division, PHE Dte. ORD/000171/2023-2024 962/ALD 12/07/2023 120 SUBIR GHOSH 32.45 0.00 0
372 Alipurduar Division Providing House connection for JAYANTI water supply scheme at KALCHINI Block under Alipuduar Division, P.H.E. Dte.(PART-2) ORD/000172/2020-2021 916/ALD 16/10/2020 30 M/S BHOWMICK CONSTRUCTION 4.95 9.90 0
373 Alipurduar Division Construction of tubewells (2 nos.) by Reverse rotary method of drilling , soil investigation at OHR site, constructions of 450 Cum OHR at HW , construction of pump house and boundary wall at HW site and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Uttar Deogaon PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000172/2023-2024 1046/ALD 20/07/2023 661 DILIP MAHATO 539.38 351.12 61
374 Alipurduar Division Providing House connection for KAMAKHYAGURI water supply scheme at KUMARGRAM Block under Alipuduar Division, P.H.E. Dte.(PART-2) ORD/000173/2020-2021 917/ALD 16/10/2020 30 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 4.98 4.90 57
375 Alipurduar Division Construction of tubewells (2 nos.) by Reverse rotary method of drilling at HW site and 2nd TW site , Soil investigation at OHR site, constructions of 350 Cum OHR at HW , construction of pump house and boundary wall at H/W and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Paschim Deogaon PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000173/2023-2024 1047/ALD 20/07/2023 986 SOUVIK ROY PALADHI 547.06 239.02 45
376 Alipurduar Division Extension of Distribution line with UPVC pipe line (From Bhaben Biswas House to Ghughurertala Hridoy Barman's House) at Deodanga under Dalimpur Water Supply Scheme under Alipurduar Division,PHE Dte. ORD/000174/2020-2021 918/ALD 16/10/2020 30 PARAMJYOTI ENTERPRISE 3.16 5.96 0
377 Alipurduar Division Construction of tube wells (2 nos.) by Reverse rotary method of drilling at HW site and 2nd TW site , Soil investigation at OHR site, constructions of 400 Cum OHR at HW , construction of pump house and boundary wall at H/W and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Narasingpur PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000174/2023-2024 1048/ALD 20/07/2023 672 DILIP MAHATO 567.48 496.14 90
378 Alipurduar Division Extension of Distribution line with UPVC pipe line (From Bamoner Bhangha Nagesh barman's House to Kashikanta Biswas House) near Bulet Club under Dalimpur Water Supply Scheme under Alipurduar Division,PHE Dte. ORD/000175/2020-2021 919/ALD 16/10/2020 30 NARAYAN CHANDRA SAHA & SONS 3.16 5.99 0
379 Alipurduar Division Constructions of 300 Cum OHR as per Departmental Design & drawing, including laying distribution system with new HDPE pipeline , Rising Main, Soil Investigation work and others allied works for MALANGI TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE. ORD/000175/2023-2024 1049/ALD 20/07/2023 720 CAPITAL ENGINEERS 201.31 52.22 45
380 Alipurduar Division Repairing of pump house at headwork site of Chandirjhar PWSS under Alipurduar Division, PHE Dte. ORD/000175/2025-2026 1857/ALD 26/08/2025 60 HARI CONSTRUCTION 1.01 0.00 0
381 Alipurduar Division Cons. 4 nos Tube well boring by ODEX-165 Method of drilling at HW site including distribution system with new HDPE pipeline, Cons. of 250 cum OHR as per Departmental Design & drawing, Pump House , Boundary Wall, Path way, Providing FHTC, Soil Testing and other allied works for BUXA FOREST(RAJA BHATKHAWA) PIPED WATER SUPPLY SCHEME under Alipurduar Division, PHE Dte. ORD/000176/2023-2024 1112/ALD 28/07/2023 644 CAPITAL ENGINEERS 518.60 103.94 30
382 Alipurduar Division Constructions of 250 Cum OHR as per Departmental Design & drawing including laying distribution system with new HDPE pipeline, RISING MAIN, Construction of 2(TWO) NOS of BOUNDARY WALL, 3(THREE) NOS ODEX-165 TUBE WELL, 3(THREE) NOS PUMP HOUSE, Soil Investigation work, providing FHTC and others allied works for UTTAR MANDABARI PWSS(ZONE-I+ZONE-II), Alipurduar Division, PHE DTE. ORD/000177/2023-2024 1113/ALD 28/07/2023 720 MAHENDRA CHHETRI 736.75 575.12 77
383 Alipurduar Division Extension and replacement of damaged pipeline and providing FHTC at Alipurduar Birpara Bazar Chowpathi and surrounding area under Birpara PWSS under Alipurduar Division, PHE Dte. ORD/000178/2021-2022 1308/ALD 05/10/2021 60 DAS CONSTRUCTION 43.41 36.36 99
384 Alipurduar Division Supply of fuel for Diesel Vehicle Maxi Cab(At least 7 seater ) (Preferably TUV) for Assistant Engineer, Alipurduar Sadar Sub-Division, P.H.E. Dte.(from 08/08/2022 to 31.12.2022) ORD/000178/2022-2023 1184/ALD 05/08/2022 153 MATRI ENTERPRISE 1.27 0.00 0
385 Alipurduar Division Construction of tube wells (2 nos.) by Reverse rotary method of drilling at HW site and 2nd TW site , soil investigation at OHR site, constructions of 400 Cum OHR at HW , construction of pump house and boundary wall at H/W and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Bengkandi PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000178/2023-2024 1114/ALD 28/07/2023 977 M/S ELITE CONSTRUCTION 655.41 402.25 51
386 Alipurduar Division Repairing of 2 nos. P/H with toilet block (PH-1 and 2) and Replacement of old existing AC p/l with UPVC pipe and providing FHTC in connection with Jaldhara/Jal Sapna for Uttar Sishubari WSS under Alipurduar Division, PHE Dte. (Sishubari High School and adjacent area) ORD/000179/2021-2022 1309/ALD 05/10/2021 60 MITHUN DAS 45.40 35.57 100
387 Alipurduar Division Laying of HDPE/DI pipe line at different area of flank of Dheklapara Bandapani under Alipurduar Division, PHE Dte. ORD/000180/2020-2021 1005/ALD 12/11/2020 60 M/S PALIT ENTERPRISE 11.75 41.37 48
388 Alipurduar Division Restoration of laying distribution system by replacing of damaged AC pipeline with UPVC pipeline of Uttar Kamakhyaguri WSS under Alipurduar Division, PHE Dte.(Part-A) ORD/000180/2021-2022 1307/ALD 05/10/2021 60 TAPASH DAS 25.34 17.32 76
389 Alipurduar Division Sinking of Rig Bore Tube well by Odex-165 method of drilling and installation of Raising Main and laying of DI/MS/HDPE pipe line for the Tulshipara and Lankapara Water Supply Scheme. ORD/000181/2020-2021 1006/ALD 12/11/2020 60 UMWELT ENGINEER PVT. LTD. 32.34 60.90 97
390 Alipurduar Division Supply of fuel for Diesel Vehicle Maxi Cab(At least 7 seater) (Preferably Scorpio) for Executive Engineer, Alipurduar Division, P.H.E. Dte.(from 08.08.2022 to 31.12.2022) ORD/000181/2022-2023 1187/ALD 05/08/2022 153 MITHU DAS 1.16 1.09 100
391 Alipurduar Division Laying of HDPE (PN-6) bring crossing work including land development and allied work at Bhatkhawa Tea Garden Piped Water Supply Scheme Alipurduar Division, PHE Dte. ORD/000181/2025-2026 1884/ALD 27/08/2025 90 PRITAM DAS 21.91 0.00 0
392 Alipurduar Division Laying of HDPE/DI pipe line at different area of flank of Lankapara road/village road and Lankapara Bazar Area under Alipurduar Division, PHE Dte. ORD/000182/2020-2021 1007/ALD 12/11/2020 60 MADHAB SAHA 33.79 27.07 99
393 Alipurduar Division Restoration of Laying distribution system by replacing of damaged AC pipeline with UPVC pipeline & constructon of boundary wall, new toilet, repairing of pump house (H/W site) at Bhatibari Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000182/2021-2022 1311/ALD 05/10/2021 60 DEBAJYOTI SUTRADHAR 14.02 12.00 21
394 Alipurduar Division Constructions of 2(TWO) NOS 150 Cum OHR as per Departmental Design & drawing including laying distribution system with new HDPE pipeline, RISING MAIN, Construction of BOUNDARY WALL, 4(FOUR) NOS ODEX-165 TUBE WELL, 4(FOUR) NOS PUMP HOUSE, Soil Investigation work, providing FHTC and others allied works for RANGAMATI TEA GAEDEN PWSS(ZONE-I+ZONE-II), Alipurduar Division, PHE DTE. ORD/000182/2023-2024 1171/ALD 03/08/2023 720 M/S RADHASWAMI ENTERPRISE 440.20 89.83 40
395 Alipurduar Division Extension and Replacement of damaged pipeline under Patlakhawa PWSS under Alipurduar Division, P.H.E. Dte.(Part-C) ORD/000183/2020-2021 1008/ALD 12/11/2020 60 JAI BHARAT COMMERCIAL CORPORATION 14.40 26.93 100
396 Alipurduar Division Restoration of Laying distribution system by replacing of damaged AC pipeline with UPVC pipeline and constructon of boundary wall, toilet and repairing of pump house (2nd site) at Narathali Water Supply Scheme under Alipurduar Division, PHE Dte ORD/000183/2021-2022 1312/ALD 05/10/2021 60 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 11.97 3.92 69
397 Alipurduar Division Construction of tubewells (2 nos.) by Reverse rotary method of drilling at HW site and 2nd TW site , soil investigation at OHR site, constructions of 300 Cum OHR at HW , construction of pump house and boundary wall at H/W and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Lachhimandabri PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000183/2023-2024 1172/ALD 03/08/2023 1080 M/S T M CONSTRUCTION 433.46 174.73 35
398 Alipurduar Division Extension and Replacement of damaged pipeline under Patlakhawa PWSS under Alipurduar Division, P.H.E. Dte.(Part-C) ORD/000184/2020-2021 1009/ALD 12/11/2020 60 M/S PALIT ENTERPRISE 14.40 26.95 70
399 Alipurduar Division Repairing and renovation of 2 nos. P/H, cons. Of 2 nos. Toilet (for 1st and 2nd site) and laying of UPVC pipe line with providing House connection at Bholardabri WSS under Alipurduar Division, PHE Dte. ORD/000184/2021-2022 1313/ALD 05/10/2021 60 HARI CONSTRUCTION 33.81 33.47 64
400 Alipurduar Division Preparation of operation and maintenance DPR booklet in connection to 92 no's piped water supply scheme under Alipurduar Division P.H.E Dte ORD/000184/2023-2024 1202/ALD 07/08/2023 30 ANIK BHATTACHARJEE 0.78 0.78 100
401 Alipurduar Division Extension of pipeline to Bharnabari TG area under Hasimara PWSS for providing at Kalchini Block under Alipurduar Division, P.H.E. Dte.(Part-B) ORD/000185/2020-2021 1010/ALD 12/11/2020 60 ASHIT KUMAR SINGHA 39.34 49.96 0
402 Alipurduar Division Preparation of detailed Additional cost Requirement D.P.R. booklets in connection to various PWSS under Alipurduar-I and Alipurduar- II Block under Alipurduar Division P.H.E Dte. ORD/000185/2023-2024 1203/ALD 07/08/2023 30 ANIK BHATTACHARJEE 0.78 0.78 100
403 Alipurduar Division Replacement of old existing AC pipeline with UPVC pipe and providing FHTC in connection with Jaldhara/Jal Sapna for Augmentation of Falakata WSS under Alipurduar Division, PHE Dte.( Subhaspally and adjacent area.) ORD/000186/2021-2022 1314/ALD 05/10/2021 60 SOUVIK ROY PALADHI 41.30 34.95 67
404 Alipurduar Division Balance work of Radharani Godown cum rest shed under Radharani WSS under Alipurduar Division, PHE Dte. (Part-B) ORD/000186/2022-2023 1020/ALD 21/07/2022 30 ASHOK PRADHAN 2.82 2.77 89
405 Alipurduar Division Preparation of detailed Additional cost Requirement D.P.R. booklets in connection to various PWSS under Kumargram and Kalchini Block under Alipurduar Division P.H.E Dte. ORD/000186/2023-2024 1204/ALD 07/08/2023 30 ANIK BHATTACHARJEE 0.78 0.78 100
406 Alipurduar Division Laying of DI/UPVC pipeline along with PMGSY Road and other misc. works related to Munshipara PWSS under Alipurduar Division PHE DTE. ORD/000187/2020-2021 1012/ALD 12/11/2020 60 TAPASH DAS 35.88 56.28 83
407 Alipurduar Division Preparation of detailed Additional cost Requirement D.P.R. booklets in connection to various PWSS under Block Faakata & Madarihat Block under Alipurduar Division P.H.E Dte. ORD/000187/2023-2024 1205/ALD 07/08/2023 30 ANIK BHATTACHARJEE 0.78 0.78 100
408 Alipurduar Division Construction of boundary wall, pump house, tubewell, rising main for (Mouza- Lankapara TG, JL No. 30, Sheet No. 5, Plot No. 704) 327 units Cha Sundori Water Supply Scheme under Alipurduar Division PHE DTE. ORD/000189/2023-2024 1280/ALD 11/08/2023 827 ASHOK PRADHAN 57.36 15.93 35
409 Alipurduar Division Construction of boundary wall, pump house, tubewell, rising main for (Mouza- Lankapara TG, JL NO. 30, Sheet No. 8, Plot No. 1052) 117 units Cha Sundori Water Supply Scheme under Alipurduar Division PHE DTE. ORD/000190/2023-2024 1460/ALD 14/08/2023 540 SUDDHYA SING LAMA 39.38 11.24 61
410 Alipurduar Division Hiring of Diesel vehicle maxi cab (at least 7 seater) for Executive Engineer, Alipurduar Division.(01.09.2020 to 31.03.2021) ORD/000191/2020-2021 600/ALD 31/08/2020 212 APSARI BHOWMICK 1.25 1.70 0
411 Alipurduar Division Providing House connection and construction of different dia. sluice valve chamber including supply of CI materials for Jashodanga WSS under Alipurduar Division, PHE Dte. ORD/000192/2021-2022 1316/ALD 05/10/2021 45 HARI CONSTRUCTION 12.88 12.83 99
412 Alipurduar Division Gap filling of distribution line with DI/CI/UPVC pipe at Nurpur WSS under Alipurduar Division, PHE Dte. ORD/000192/2023-2024 1468/ALD 16/08/2023 60 BENGAL YOUTH UN EMPLOYED ENGINEERS CO OPERATIVE SOCIETY LIMITED 20.69 17.31 70
413 Alipurduar Division New Laying of UPVC/DI pipeline, Providing FHTC and other allied works for Augmentation of Purba Chepani PWSS under Alipurduar Division, PHE Dte. ORD/000193/2022-2023 1220/ALD 10/08/2022 60 SREE MAA CONSTRUCTION 21.55 20.42 94
414 Alipurduar Division Laying distribution system with new HDPE pipeline for providing FHTC in the Command area of Shrinathpur TG PWSS under Alipurduar Division, PHE Dte. ORD/000193/2023-2024 1469/ALD 16/08/2023 60 CHANDAN KIRTONIA 13.00 13.00 100
415 Alipurduar Division PROVIDING HOUSE CONNECTION FOR DIMDIMA Z-I PWSS AT MADARIHAT-BIRPARA BLOCK UNDER ALIPURDUAR DIVISION, PHE DTE. PART-2 ORD/000194/2020-2021 1025/ALD 18/11/2020 60 DILIP MAHATO 28.87 44.59 0
416 Alipurduar Division New Laying of UPVC/DI pipeline, Providing FHTC and other allied works for Augmentation of Putimari PWSS under Alipurduar Division, PHE Dte. ORD/000194/2022-2023 1221/ALD 10/08/2022 1020 HARI CONSTRUCTION 38.90 25.91 100
417 Alipurduar Division Construction of pathway, surface drain and chatal, land development, along with other allied works at Shrinathpur PWSS under Alipurduar Division, PHE Dte. ORD/000194/2023-2024 1470/ALD 16/08/2023 420 KAMALESH ROY 12.83 4.56 50
418 Alipurduar Division Laying of HDPE pipeline (parallel and balance line ) at Umacharanpur PWSS under Alipurduar Division, PHE Dte. ORD/000194/2025-2026 2077/ALD 19/09/2025 75 TAPASH KUMAR BHOWMICK 80.25 0.00 0
419 Alipurduar Division PROVIDING HOUSE CONNECTION FOR DIMDIMA Z-II PWSS AT MADARIHAT-BIRPARA BLOCK UNDER ALIPURDUAR DIVISION, PHE DTE. PART-2 ORD/000195/2020-2021 1026/ALD 18/11/2020 60 ASHIT KUMAR SINGHA 19.61 30.28 0
420 Alipurduar Division Laying of UPVC/DI distribution pipeline including road and culvert crossing of different area for augmentation of Jateswar Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000195/2022-2023 1225/ALD 10/08/2022 60 SOUVIK ROY PALADHI 41.01 39.23 63
421 Alipurduar Division Laying distribution system with new HDPE/DI pipeline and other allied works for providing FHTC in connection with the Shrinathpur TG PWSS under Alipurduar Division, PHE Dte. ORD/000195/2023-2024 1471/ALD 16/08/2023 420 KAMALESH ROY 32.95 30.78 100
422 Alipurduar Division PROVIDING HOUSE CONNECTION FOR RADHARANI PWSS AT KALCHINI BLOCK UNDER ALIPURDUAR DIVISION, PHE DTE. PART-1 ORD/000196/2020-2021 1027/ALD 18/11/2020 60 UMWELT ENGINEER PVT. LTD. 37.24 22.54 92
423 Alipurduar Division Laying Distribution line of UPVC and DI with providing FHTC Connection for the Salkumar and Munshipara Water Supply Scheme Area under Alipurduar Division, PHE Dte. ORD/000196/2021-2022 1317/ALD 05/10/2021 1679 DILIP MAHATO 58.07 39.35 85
424 Alipurduar Division Laying of HDPE pipeline including Providing FHTC at Jaigaon Development Area Zone-II from Krishna Pradhan house to Geeta Chhetri house within Kalchini Block under Alipurduar Division, PHE Dte. ORD/000196/2022-2023 1222/ALD 10/08/2022 60 MAHENDRA CHHETRI 36.35 36.20 67
425 Alipurduar Division Construction of boundary wall, pump house, tubewell, rising main and land development for (Mouza- Lankapara TG, JL No. 30, Sheet No. 7, Plot No. 920,921, 922 & 923 ) 375 units Cha Sundori Water Supply Scheme under Alipurduar Division PHE DTE. ORD/000196/2023-2024 1486/ALD 16/08/2023 120 SUBIR GHOSH 55.70 0.00 0
426 Alipurduar Division Construction of 250cum OHR as per Departmental Design, laying of rising main & delivery connection . Supply of CIDF Specials and others allied works for Bhatibari Z-III PWSS Under Alipurduar Division PHE Dte. ORD/000196/2024-2025 1766/ALD 07/06/2024 573 HARIDAS GHOSH 103.38 37.39 50
427 Alipurduar Division Restoration of pipeline and FHTC and allied works at Madhu TG under Augmentation of Hasimara PWSS under Alipurduar Division, PHE Dte. ORD/000196/2025-2026 2103/ALD 23/09/2025 60 NARENDRA BHADANI. 6.46 0.00 0
428 Alipurduar Division PROVIDING HOUSE CONNECTION FOR RADHARANI PWSS AT KALCHINI BLOCK UNDER ALIPURDUAR DIVISION, PHE DTE. PART-2 ORD/000197/2020-2021 1028/ALD 18/11/2020 60 UMWELT ENGINEER PVT. LTD. 37.24 32.53 91
429 Alipurduar Division Laying Distribution line of UPVC and DI with providing FHTC Connection for the Salkumar Water Supply Scheme Area under Alipurduar Division, PHE Dte. ORD/000197/2021-2022 1318/ALD 05/10/2021 60 TAPASH KUMAR BHOWMICK 35.38 31.38 85
430 Alipurduar Division Extension of UPVC pipeline for augmentation of Uttar Majherdabri Water Supply Scheme under Alipurduar Division, PHE Dte. (Part-A) ORD/000197/2022-2023 1223/ALD 10/08/2022 960 DILIP MAHATO 56.93 54.35 100
431 Alipurduar Division Construction of pathway, surface drain and chatal, installation of paver block, land development along with the others allied works at Samuktala Zone-I head work site PWSS under Alipurduar Division, PHE Dte. ORD/000197/2023-2024 1495/ALD 16/08/2023 60 DIPAK DAS 13.04 5.10 25
432 Alipurduar Division Soil investigation at OHR site and construction of 450cum OHR at Uttar Sishubari under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000197/2024-2025 1767/ALD 07/06/2024 300 BISWAJIT DUTTA 118.67 0.00 0
433 Alipurduar Division Painting of Old OHR of 300 cum at Madhu under Augmentation of Hasimara PWSS under Alipurduar Division, PHE Dte. ORD/000197/2025-2026 2104/ALD 23/09/2025 60 NARENDRA BHADANI. 3.39 0.00 0
434 Alipurduar Division Retrofitting work of pipeline of Dalmore PWSS under Alipurduar Division, PHE Dte. ORD/000198/2021-2022 971/ALD 13/09/2021 30 MS DEYS CONSTRUCTION 5.04 5.04 59
435 Alipurduar Division Extension of UPVC pipeline for augmentation of Uttar Majherdabri Water Supply Scheme under Alipurduar Division, PHE Dte. (Part-B) ORD/000198/2022-2023 1224/ALD 10/08/2022 60 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 46.73 40.43 70
436 Alipurduar Division Continuation work order for the work of "Construction of tube wells (2 nos.) by Reverse rotary method of drilling , soil investigation at OHR site, constructions of 450 Cum OHR at HW , construction of pump house and boundary wall at HW site and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Uttar Deogaon PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE." (As per approval of SE NBC-I P.H.E. Dte. vide e-file no-DPHE-33014/4/2024-EE(ALI_D) SEC-DPHE (Computer No-973240)) ORD/000198/2024-2025 1912/ALD 26/06/2024 60 DILIP MAHATO 21.25 0.00 100
437 Alipurduar Division Painting of Old OHR (350 cum) at Chhoto Salkumar adjacent to Augmentation of Salkumarhat PWSS under Alipurduar Division, PHE Dte. ORD/000198/2025-2026 2105/ALD 23/09/2025 60 NARENDRA BHADANI. 3.04 0.00 0
438 Alipurduar Division Retrofitting work of pipeline of Madarihat PWSS under Alipurduar Division, PHE Dte. ORD/000199/2021-2022 972/ALD 13/09/2021 30 MS DEYS CONSTRUCTION 4.99 4.99 99
439 Alipurduar Division Continuation work order for the work of "Sinking of Rig bore T/W (4nos.) by Reverse Rotary method of drilling, cons. of 100 cum. OHR (2nos), cons. of P/H and B/W, Rising main, distribution line and providing FHTC at H/W and 2nd site inclu. Soil testing for KADAMBINI TG PWSS (ZONE-I and ZONE-II) under Birpara Sub-Division, Alipurduar Division, PHE Dte." (As per approval of SE NBC-I P.H.E. Dte. vide e-file no-DPHE-33014/5/2024-EE(ALI_D) SEC-DPHE (Computer No-973264)) ORD/000199/2024-2025 1913/ALD 26/06/2024 60 DILIP MAHATO 14.57 14.37 90
440 Alipurduar Division Hiring of Diesel Vehicle Maxi Cab(At least 7 seater ) for Executive Engineer, Alipurduar Division, P.H.E. Dte.(from 01.08.2022 to 31.12.2022) ORD/000200/2022-2023 1121/ALD 29/07/2022 153 MITHU DAS 0.84 0.84 100
441 Alipurduar Division Continuation work order of the work of "Boring of TW, Cons. Of Pump House, boundary wall, OHR (300 cum) inclu. Soil investigation works, Laying of rising main, distribution system and providing FHTC for MADHYA KHAIRBARI PWSS under Alipurduar Division PHE DTE." (As per approval of SE NBC-I P.H.E. Dte. vide e-file no-DPHE-33014/10/2024-EE(ALI_D) SEC-DPHE (Computer No-974292)) ORD/000200/2024-2025 1914/ALD 26/06/2024 60 DILIP MAHATO 26.54 26.16 90
442 Alipurduar Division Hiring of Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for inspection and monitoring of Jal Jeevan Mission (JJM) works under Alipurduar Division, P.H.E. Dte.(from 01.08.2022 to 31.10.2022) ORD/000201/2022-2023 1122/ALD 29/07/2022 92 NIRANJAN KIRTANIA 0.50 0.50 100
443 Alipurduar Division Continuation work order for the work of 'Tube well Boring by ODEX-165 Method of drilling at HW, FIRST TUBE WELL site including laying distribution system with new UPVC pipeline , Constructions of 250 Cum OHR as per Departmental Design & drawing including soil investigation works , 2nos pump house & boundary wall, providing FHTC and others allied works for ATIABARI TEA GARDEN PWSS Under Alipurduar Division PHE DTE." (As per approval of SE NBC-I P.H.E. Dte. vide e-file no-DPHE-33014/9/2024-EE(ALI_D) SEC-DPHE (Computer No-974282)) ORD/000201/2024-2025 1915/ALD 26/06/2024 60 SOUVIK ROY PALADHI 15.17 0.00 0
444 Alipurduar Division Laying balance portion pipeline and providing house connection at Jayanti Water Supply Scheme and Bhutiya Busty Area under Alipurduar Division, PHE Dte. ORD/000202/2021-2022 975/ALD 13/09/2021 30 GHOSH & SAHA CONSTRUCTION 5.04 5.03 54
445 Alipurduar Division Laying of UPVC/DI distribution pipeline including road and culvert crossing of different area for augmentation of Jateswar Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000202/2022-2023 1226/ALD 10/08/2022 120 TAPASH DAS 41.01 38.71 63
446 Alipurduar Division Construction of 300 cum OHR as per Departmental Design, laying of rising main & delivery connection . Supply of CIDF Specials and others allied works for Bhatibari Z-IPWSS Under Alipurduar Division PHE Dte. ORD/000202/2024-2025 1931/ALD 28/06/2024 300 TAPASH KUMAR BHOWMICK 114.70 17.27 45
447 Alipurduar Division Providing House connection for Birpara water supply scheme at Alipurduar -I Block under Alipuduar Division, P.H.E. Dte. Part-II ORD/000203/2020-2021 1157/ALD 15/12/2020 60 DAS CONSTRUCTION 29.90 29.90 97
448 Alipurduar Division Providing House Connection of Bholardabri WSS under Alipurduar Division, PHE Dte.Part-7 ORD/000203/2021-2022 991/ALD 13/09/2021 30 MANORAMA ENTERPRISE 4.30 3.00 63
449 Alipurduar Division Land development and laying of UPVC pipeline at additional TW Site of Uttar Kamakhyaguri PWSS under Alipurduar Division, PHE Dte. ORD/000203/2023-2024 1556/ALD 23/08/2023 60 SREE MAA CONSTRUCTION 8.60 8.54 100
450 Alipurduar Division Supply of DIDF pipes and specials and Sluice Valve for Uttar Mendabari Water Supply (SM/16539) Scheme OF Kalchini Block under Alipurduar Division P.H.E. Dte. ORD/000203/2024-2025 1952/ALD 02/07/2024 30 KAMALA VALVES AND ENGINEERING PRIVATE LIMITED 16.50 0.00 85
451 Alipurduar Division Providing House connection for Munshipara piped water supply scheme at Alipurduar-I Block under Alipuduar Division, P.H.E. Dte.Part-II ORD/000204/2020-2021 1158/ALD 15/12/2020 60 TAPASH DAS 19.93 27.63 82
452 Alipurduar Division Restoration of laying distribution system by replacing of Damaged AC pipeline with UPVC pipeline of Bholardabri WSS under Alipurduar Division, PHE Dte. ORD/000204/2021-2022 992/ALD 13/09/2021 30 MANORAMA ENTERPRISE 4.89 4.62 65
453 Alipurduar Division Supply of DIDF pipes and specials and Sluice Valve for Beech TG Water Supply Scheme (SM/14214) under Alipurduar Division P.H.E. Dte. ORD/000204/2024-2025 1953/ALD 02/07/2024 30 KAMALA VALVES AND ENGINEERING PRIVATE LIMITED 15.43 8.46 85
454 Alipurduar Division Providing House connection for Jashodanga water supply scheme at Alipurduar -II Block under Alipuduar Division, P.H.E. Dte. Part-II ORD/000205/2020-2021 1159/ALD 15/12/2020 60 TAPASH KUMAR BHOWMICK 29.89 42.61 98
455 Alipurduar Division Sinking of 1no. Tube Well for replacement and another 1no. new Tube Well near factory line by ODEX-195 method of drilling at Lankapara Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000205/2021-2022 1345/ALD 08/10/2021 30 SASANKA ROY 33.00 32.32 96
456 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling at H/W site including laying distribution system and providing FHTC for KUMARGRAM TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE. ORD/000205/2022-2023 1304/ALD 22/08/2022 120 GOUTAM KUMAR DAS 94.63 57.55 80
457 Alipurduar Division Providing balance FHTC for Putimari PWSS under Alipurduar Division, PHE Dte. ORD/000205/2023-2024 1558/ALD 23/08/2023 30 HARI CONSTRUCTION 3.35 0.00 0
458 Alipurduar Division Laying of rising main line with HDPE PN10, horizontal boring by HDD method , bridge and culvert crossing, left out portion of household connection with HDPE pipe, providing balance FHTC, construction of pathway, surface drain and chatal, installation of paver block, land development along with the other allied works at DHAOLAJHORA (SM/07191) 3rd TW site PWSS of Alipurduar Sadar Sub-Division under Alipurduar Division, PHE Dte. ORD/000205/2024-2025 1954/ALD 02/07/2024 270 CHANDAN KIRTONIA 33.15 7.50 70
459 Alipurduar Division Repairing of pump house at 2nd site of Dakshin Sonapur PWSS under Alipurduar Division, PHE Dte. ORD/000205/2025-2026 2352/ALD 10/11/2025 60 DIPAK DAS 2.29 0.00 0
460 Alipurduar Division Providing House connection for BAROBISHA Zone-I water supply scheme at Kumargram Block under Alipuduar Division, P.H.E. Dte. Part-III ORD/000206/2020-2021 1160/ALD 15/12/2020 60 M/S SURAJIT DEY & CO 29.98 47.09 69
461 Alipurduar Division Construction of Pump House,Boundary Wall, Tube well Boring by ODEX-165 Method of drilling at H/W site including laying distribution system and providing FHTC for NEWLANDS TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE. ORD/000206/2022-2023 1275/ALD 17/08/2022 501 TAPASH KUMAR BHOWMICK 96.78 90.66 95
462 Alipurduar Division Providing balance FHTC for Bakla PWSSunder Alipurduar Division, PHE Dte. ORD/000206/2023-2024 1560/ALD 23/08/2023 30 PROGRESSIVE UNEMPLOYED CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 2.47 2.44 99
463 Alipurduar Division Providing House connection for BAROBISHA Zone-II water supply scheme at Kumargram Block under Alipuduar Division, P.H.E. Dte. Part-III ORD/000207/2020-2021 1161/ALD 15/12/2020 60 TAPAN CHANDA 29.90 59.81 0
464 Alipurduar Division Construction of Pump House,Boundary Wall, Tube well Boring by ODEX-165 Method of drilling at H/W site including laying distribution system and providing FHTC for SANKOSH TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE. ORD/000207/2022-2023 1276/ALD 17/08/2022 120 SOUVIK ROY PALADHI 96.66 90.94 50
465 Alipurduar Division Providing balance FHTC for Raydak TG PWSS under Alipurduar Division, PHE Dte. ORD/000207/2023-2024 1561/ALD 23/08/2023 45 BRAJA GOPAL SAHA 6.69 0.00 0
466 Alipurduar Division Gap filling of distribution pipeline and other allied works for Satkodali and adjoining area under Banchukamari PWSS within Alipurduar-I Block under Alipurduar Division, PHE Dte. ORD/000207/2025-2026 2351/ALD 10/11/2025 75 DAS CONSTRUCTION 68.41 0.00 0
467 Alipurduar Division Providing House connection for BAROBISHA Zone-III water supply scheme at Kumargram Block under Alipuduar Division, P.H.E. Dte. Part-II ORD/000208/2020-2021 1162/ALD 15/12/2020 60 AKANSHA COMMERCIAL PRIVATE LTD. 19.93 19.93 77
468 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling at 2nd site including laying distribution system , Rising main and providing FHTC for SANKOSH TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE. ORD/000208/2022-2023 1277/ALD 17/08/2022 120 SOUVIK ROY PALADHI 83.75 73.88 70
469 Alipurduar Division Providing balance FHTC for Chhoto Daldali PWSS under Alipurduar Division, PHE Dte. ORD/000208/2023-2024 1562/ALD 23/08/2023 30 DAS CONSTRUCTION 3.35 0.00 0
470 Alipurduar Division Laying of new UPVC p/l, bridge and culvert crossing, construction of pathway, surface drain and chatal, instalation of paver block, land development along with the other allied works, chhoto Daldali PWSS under Alipurduar Division, PHE Dte. ORD/000208/2025-2026 2350/ALD 10/11/2025 90 DAS CONSTRUCTION 86.28 0.00 0
471 Alipurduar Division Providing House connection for KAMAKHYAGURI water supply scheme at Kumargram Block under Alipuduar Division, P.H.E. Dte. Part-III ORD/000209/2020-2021 1163/ALD 15/12/2020 60 TAPASH DAS 19.94 26.48 77
472 Alipurduar Division Laying distribution system along with the other allied works at Santalabari under Augmentation of Jainti Wter Supply Scheme under Alipurduar Division PHE DTE. ORD/000209/2022-2023 1278/ALD 17/08/2022 60 ASHOK SAPKOTA 22.72 22.51 63
473 Alipurduar Division Providing balance FHTC for Brajerkuthi PWSS under Alipurduar Division, PHE Dte. ORD/000209/2023-2024 1563/ALD 23/08/2023 508 TAPASH KUMAR BHOWMICK 6.25 0.00 0
474 Alipurduar Division Making arrangement for pumping test with suitable pump and required column pipes etc. including all charges at 6 locations. ORD/000209/2024-2025 1825/ALD 14/06/2024 360 EFFLUENT AND WATERTREATMENT ENGINEERS PVT LTD 15.96 0.00 30
475 Alipurduar Division Providing House connection for KAIJALI BUSTY water supply scheme at Kumargram Block under Alipuduar Division, P.H.E. Dte. Part-III ORD/000210/2020-2021 1164/ALD 15/12/2020 60 GHOSH & SAHA CONSTRUCTION 19.93 19.34 68
476 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling at 2nd site including laying distribution system , Rising main and providing FHTC for KUMARGRAM TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE. ORD/000210/2022-2023 1305/ALD 22/08/2022 720 HARIDAS GHOSH 81.11 60.75 90
477 Alipurduar Division Providing balance FHTC for Dakshin Majidkhana PWSS under Alipurduar Division, PHE Dte. ORD/000210/2023-2024 1564/ALD 23/08/2023 45 HARI CONSTRUCTION 6.77 0.00 0
478 Alipurduar Division Laying of rising main DI (K7), interconnection work with HDPE pipe , Construction of sluice valve chamber for Umacharanpur PWSS under Birpara Sub- Division ,Alipurduar Division PHE Dte. under North Bengal Circle-I PHE DTE. ORD/000210/2024-2025 2061/ALD 12/07/2024 300 TAPASH KUMAR BHOWMICK 101.24 93.17 90
479 Alipurduar Division Providing House connection for PURBA CHEPANI water supply scheme at Alipurduar-II Block under Alipuduar Division, P.H.E. Dte. Part-II ORD/000211/2020-2021 1165/ALD 15/12/2020 60 TAPAN CHANDA 23.90 23.90 94
480 Alipurduar Division New Laying of UPVC/DI Pipe Line, Providing FHTC & Other allied works at Uttar Kamakhyaguri PWSS Under Alipurduar Division, PHE DTE. ORD/000211/2022-2023 1306/ALD 22/08/2022 60 DILIP MAHATO 28.04 21.00 57
481 Alipurduar Division Providing balance FHTC for Baruipara PWSS under Alipurduar Division, PHE Dte. ORD/000211/2023-2024 1565/ALD 24/08/2023 30 RAMEN DEY & CO 4.89 0.00 0
482 Alipurduar Division Laying of pipeline distribution system (Parallel and left out Area) and other allied works at Purba Kathalbari Zone-I PWSS within APD-I Block under Alipurduar Division, PHE Dte. ORD/000211/2025-2026 2414/ALD 18/11/2025 60 ANIRBAN DEY SARKAR CONSTRUCTION 54.38 0.00 0
483 Alipurduar Division Providing House connection for Purba Chepani water supply scheme at Alipurduar -II Block under Alipuduar Division, P.H.E. Dte.(Part-IV ORD/000212/2020-2021 1132/ALD 10/12/2020 30 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 4.93 9.86 0
484 Alipurduar Division Providing balance FHTC for PAKRIGURI PWSSunder Alipurduar Division, PHE Dte. ORD/000212/2023-2024 1566/ALD 23/08/2023 30 SREE MAA CONSTRUCTION 3.43 0.00 15
485 Alipurduar Division Providing House connection for Paschim Khayerbari water supply scheme at Madarihat-Birpara Block under Alipuduar Division, P.H.E. Dte.(Part-III) ORD/000213/2020-2021 1133/ALD 10/12/2020 30 NARENDRA BHADANI. 4.98 4.98 92
486 Alipurduar Division Construction of Pump House,Boundary Wall, Tube well Boring by ODEX-165 Method of drilling at 2nd site including laying distribution system , Rising main and providing FHTC for NEWLANDS TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE. ORD/000213/2022-2023 1307/ALD 22/08/2022 120 MADHAB SAHA 97.20 91.59 94
487 Alipurduar Division Providing balance FHTC for UTTAR MAJIDKHANA PWSSunder Alipurduar Division, PHE Dte. ORD/000213/2023-2024 1567/ALD 23/08/2023 225 TAPASH KUMAR BHOWMICK 9.36 0.00 0
488 Alipurduar Division Providing House connection for Dalimpur water supply scheme at Falakata Block under Alipuduar Division, P.H.E. Dte.(Part-II) ORD/000214/2020-2021 1134/ALD 10/12/2020 30 PARAMJYOTI ENTERPRISE 4.98 4.98 85
489 Alipurduar Division Providing balance FHTC for CHALNIPAK PWSS under Alipurduar Division, PHE Dte. ORD/000214/2023-2024 1568/ALD 23/08/2023 45 SOUVIK ROY PALADHI 9.97 0.00 0
490 Alipurduar Division Providing House connection for PURBA CHEPANI water supply scheme at Alipurduar-II Block under Alipuduar Division, P.H.E. Dte. Part-III ORD/000215/2020-2021 1166/ALD 15/12/2020 60 AKANSHA COMMERCIAL PRIVATE LTD. 23.91 23.91 95
491 Alipurduar Division Construction of HP Culvert for drainage purpose with 900 mm dia humepipe and construction of screening and inspection chamber at Hasimara PWSS HWS under Alipurduar Division PHE Dte.,Part-B ORD/000215/2022-2023 1105/ALD 29/07/2022 30 ALATYA CONSTRUCTION & CO. 3.60 3.59 100
492 Alipurduar Division Providing balance FHTC for MARAKHATA PWSS under Alipurduar Division, PHE Dte. ORD/000215/2023-2024 1569/ALD 23/08/2023 30 HARI CONSTRUCTION 4.69 0.00 0
493 Alipurduar Division Supply of DIDF pipes and DI specials and CI Jeffy Coupling for Nimtijhora Domohoni Water Supply Scheme (SM/13244) of Kalchini Block under Alipurduar Division P.H.E. Dte. ORD/000215/2024-2025 2067/ALD 12/07/2024 30 MANSAROVAR CASTING 9.63 9.63 100
494 Alipurduar Division Providing House connection for BHUTNIRGHAT water supply scheme at Falakata Block under Alipuduar Division, P.H.E. Dte. Part-III ORD/000216/2020-2021 1167/ALD 15/12/2020 60 GOUTAM KUMAR DAS 19.91 39.83 0
495 Alipurduar Division Construction of HP Culvert for drainage purpose with 900 mm dia humepipe and construction of screening and inspection chamber at Hasimara PWSS HWS under Alipurduar Division PHE Dte., Part-C ORD/000216/2022-2023 1106/ALD 29/07/2022 30 ALATYA CONSTRUCTION & CO. 4.08 4.08 100
496 Alipurduar Division Providing balance FHTC for TELIPARA PWSS under Alipurduar Division, PHE Dte. ORD/000216/2023-2024 1570/ALD 23/08/2023 30 DHANENDRA SARKAR 4.32 0.00 0
497 Alipurduar Division Supply of DIDF Pipes and DI Special and CI Jeffy Coupling for Bairiguri Water Supply(SM/13246) of Alipurduar-I Block Scheme under Alipurduar Division P.H.E. Dte. ORD/000216/2024-2025 2068/ALD 12/07/2024 30 BARMAN ENTERPRISE 11.35 10.11 100
498 Alipurduar Division Providing House connection for JOGENDRAPUR water supply scheme at Falakata Block under Alipuduar Division, P.H.E. Dte. Part-III ORD/000217/2020-2021 1168/ALD 15/12/2020 60 SASANKA ROY 29.90 36.44 67
499 Alipurduar Division Providing balance FHTC for TURTURI PWSS under Alipurduar Division, PHE Dte. ORD/000217/2023-2024 1571/ALD 23/08/2023 496 TAPASH KUMAR BHOWMICK 6.81 0.00 0
500 Alipurduar Division Supply of DIDF Pipes and DI Special and CI Jeffy Coupling for Purba Majherdabri TG Water Supply Scheme (SM/18157) of Alipurduar-II Block under Alipurduar Division P.H.E. Dte. ORD/000217/2024-2025 2069/ALD 12/07/2024 30 GUHA ENTERPRISE 8.02 8.02 100
501 Alipurduar Division Providing House connection for CHOTO SALKUMAR water supply scheme at Falakata Block under Alipuduar Division, P.H.E. Dte. Part-III ORD/000218/2020-2021 1169/ALD 15/12/2020 60 SASANKA ROY 29.90 51.79 70
502 Alipurduar Division Carrying of AC pipe and DI pipe and specials from Bhutnirghat PWSS to Falakata Stackyard due to widening PWD Road under Alipurduar Division, PHE Dte. ORD/000218/2022-2023 1108/ALD 29/07/2022 30 SASANKA ROY 0.92 0.92 67
503 Alipurduar Division Providing balance FHTC for Jashodanga PWSSunder Alipurduar Division, PHE Dte. ORD/000218/2023-2024 1559/ALD 23/08/2023 30 JUGAL CHOUDHURY 1.67 0.00 0
504 Alipurduar Division Providing House connection for PASCHIM KHAYERBARI water supply scheme at Madarihat-Birpara Block under Alipuduar Division, P.H.E. Dte. Part-II ORD/000219/2020-2021 1170/ALD 15/12/2020 60 MITHUN DAS 29.88 29.88 91
505 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Turturi Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000219/2023-2024 1579/ALD 24/08/2023 30 TAPASH KUMAR BHOWMICK 11.27 11.27 85
506 Alipurduar Division Laying of pipeline distribution system (Parallel and left out area) and other allied works at Paschim khairbari PWSS under Madarihat-Birpara Block under Alipurduar Division, PHE Dte. ORD/000219/2025-2026 2921/ALD 29/01/2026 75 GIRIRAJ ENTERPRISE 24.60 0.00 0
507 Alipurduar Division Laying of DI pipe and connection with Tubewell, Construction of Pathway, Fencing work and other works at Malangi TG Pump House under Alipurduar Division, PHE Dte. ORD/000220/2022-2023 1110/ALD 29/07/2022 990 MAHENDRA CHHETRI 4.99 0.00 100
508 Alipurduar Division Cons. Of balance portion of pump house, boundary wall, rising main, laying of DI and UPVC pipeline for Aug. of Banchukamari PWSS under Alipurduar Division, PHE Dte. ORD/000220/2023-2024 1580/ALD 24/08/2023 120 HITANGSHU CHOUDHURY 20.36 8.25 35
509 Alipurduar Division Land development works, Construction of surface drain, pathway, and other allied works at Kaijali Busty 4th tube well site with the Augmentation of Kaijali Busty PWSS Under Alipurduar Sadar Sub-Division, under Alipurduar Division PHE DTE.(SM/11958) ORD/000220/2024-2025 2273/ALD 05/08/2024 180 RAMEN DEY & CO 4.28 4.24 100
510 Alipurduar Division Providing House connection for PATLAKHAWA water supply scheme at Alipurduar-I Block under Alipuduar Division, P.H.E. Dte. Part-IV ORD/000221/2020-2021 1172/ALD 15/12/2020 60 SOUVIK ROY PALADHI 23.92 12.68 79
511 Alipurduar Division Laying of remaining Distribution Line and providing FHTC at different areas under Torsha FOREST PWSS under Alipurduar Division, PHE Dte ORD/000221/2023-2024 1581/ALD 24/08/2023 60 KAMALESH ROY 10.84 10.84 100
512 Alipurduar Division Land development works, Construction of surface drain, pathway, and other allied works at Kaijali Busty 3rd tube well site with the Augmentation of Kaijili Busty PWSS Alipurduar Sadar Sub-Division, under Alipurduar Division PHE DTE.(SM/11958) ORD/000221/2024-2025 2274/ALD 05/08/2024 60 KAMALESH ROY 3.84 0.18 50
513 Alipurduar Division Providing House connection for PURBA KATHALBARI water supply scheme at Alipurduar -I Block under Alipuduar Division, P.H.E. Dte. Part-II ORD/000222/2020-2021 1173/ALD 15/12/2020 60 MADHAB SAHA 19.93 39.87 0
514 Alipurduar Division Extension pipeline (HDPE) for providing FHTC at Santalbari area under Jainti Water Supply Scheme, Alipurduar Division, PHE Dte. ORD/000222/2021-2022 1619/ALD 23/11/2021 60 M/S BHOWMICK CONSTRUCTION 24.53 23.54 60
515 Alipurduar Division Cons. Of Rising line, pathway, surface drain, laying of DI and UPVC pipeline and restoration of FHTC at Salkumarhat PWSS under Alipurduar Division, PHE Dte. ORD/000222/2023-2024 1582/ALD 24/08/2023 90 TAPASH DAS 18.46 14.21 5
516 Alipurduar Division Laying of new UPVC/DI pipeline for filling of left out portion in the distribution system and other allied works in connection with the Augmentation of Bhatibari (Zone-III) PWSS Alipurduar Sadar Sub-Division, under Alipurduar Division PHE DTE. .(SM/14096) ORD/000222/2024-2025 2275/ALD 05/08/2024 360 HARI CONSTRUCTION 37.43 0.00 65
517 Alipurduar Division Providing House connection for CHANDIRJHAR water supply scheme at Alipurduar -II Block under Alipuduar Division, P.H.E. Dte. Part-II ORD/000223/2020-2021 1174/ALD 15/12/2020 60 TAPASH KUMAR BHOWMICK 19.93 19.93 0
518 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Kartika TG WSS Under Alipurduar Division P.H.E Dte. ORD/000223/2023-2024 1594/ALD 25/08/2023 30 JUGAL CHOUDHURY 6.76 5.59 68
519 Alipurduar Division Laying of new UPVC/DI pipeline for interconnection in the distribution system and bridge/ culvert crossing , Land developement works , Constructions of surface drain , pathway and others allied works in connection with the Chalnipak PWSS Alipurduar Sadar Sub-Division, under Alipurduar Division PHE DTE. .(SM/15534) ORD/000223/2024-2025 2276/ALD 05/08/2024 60 SOUVIK ROY PALADHI 77.22 0.00 0
520 Alipurduar Division Extension pipeline (HDPE) for providing FHTC at 28th and 29th mile busty area under Jainti Water Supply Scheme, Alipurduar Division, PHE Dte. ORD/000224/2021-2022 1576/ALD 22/11/2021 60 DEBAJYOTI SUTRADHAR 25.75 25.23 69
521 Alipurduar Division Repairing of boundary wall with Gate and pump house at 2nd Tubewell site of Dhumchipara WSS under Alipurduar Division, PHE Dte. ORD/000224/2022-2023 1114/ALD 29/07/2022 30 KAMALESH ROY 2.58 1.66 37
522 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Raydak TG WSS Under Alipurduar Division P.H.E Dte. ORD/000224/2023-2024 1595/ALD 25/08/2023 30 DAS CONSTRUCTION 6.76 6.74 95
523 Alipurduar Division Constructions of pump house, Boundary wall, laying of UPVC pipeline & Rising main connection for Purba Barachouki area under Bhatibari PWSS proposed Alipurduar Sadar Sub-Division, under Alipurduar Division PHE DTE. .(SM/14096) ORD/000224/2024-2025 2277/ALD 05/08/2024 360 HARI CONSTRUCTION 32.72 0.00 35
524 Alipurduar Division Laying of UPVC and DI (with pillar) pipeline Barobisa Zone-III Water Supply Scheme under Alipurduar Division, PHE Dte. (Part-B) ORD/000225/2021-2022 1575/ALD 22/11/2021 90 TAPAN CHANDA 75.74 70.03 69
525 Alipurduar Division Laying of water Supply pipeline due to widening of Road at industrial park by JDA (Jaigaon Development Authority Area) at Jaigaon Zone-2 WSS under Alipurduar District. ORD/000225/2022-2023 1115/ALD 29/07/2022 30 D. K. & SONS 4.84 0.00 0
526 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Marakhata WSS Under Alipurduar Division P.H.E Dte. ORD/000225/2023-2024 1598/ALD 25/08/2023 30 HARI CONSTRUCTION 6.76 6.76 100
527 Alipurduar Division Constructions of balance portion of Boundary Wall ,path way, Surface drain and chatal, Land development, laying of Rising main line & delivery line connection( for direct supply of water) along with the others allied works at Bhatibari Zone-II PWSS Alipurduar Sadar Sub-Division, under Alipurduar Division PHE DTE. .(SM/14096) ORD/000225/2024-2025 2278/ALD 05/08/2024 360 DULAL DAS 16.03 0.00 100
528 Alipurduar Division Providing House connection for Tapshikatha water supply scheme at Alipurduar-I Block under Alipuduar Division, P.H.E. Dte.(Part-III) ORD/000226/2020-2021 1136/ALD 10/12/2020 30 KAMALESH ROY 4.98 9.95 0
529 Alipurduar Division Restoration of laying distribution system by replacing of damaged AC pipeline with UPVC pipeline and Providing House Connection of Uttar Kamakhyaguri Water Supply Scheme under Alipurduar Division, PHE Dte. (Part-B) ORD/000226/2021-2022 1574/ALD 22/11/2021 60 M/S PALIT ENTERPRISE 48.63 36.42 78
530 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Purba Chikliguri WSS Under Alipurduar Division P.H.E Dte. ORD/000226/2023-2024 1603/ALD 25/08/2023 541 SOUVIK ROY PALADHI 6.76 0.00 100
531 Alipurduar Division Laying of new UPVC/DI pipeline for interconnection in the distribution system and bridge/culvert crossing, Construction of surface drain, pathway other allied works in connection with the Madhya Kamakhyaguri PWSS Alipurduar Sadar Sub-Division, under Alipurduar Division PHE DTE. .(SM/15517) ORD/000226/2024-2025 2279/ALD 05/08/2024 180 GHOSH & SAHA CONSTRUCTION 61.08 0.00 70
532 Alipurduar Division "Providing House connection for Bakla water supply scheme at Alipurduar-II Block under Alipuduar Division, P.H.E. Dte. (Part-II)" ORD/000227/2020-2021 1137/ALD 10/12/2020 30 PROGRESSIVE UNEMPLOYED CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 4.98 9.96 0
533 Alipurduar Division Restoration of laying distribution system of Totpara PWSS by replacing of damaged AC pipeline with UPVC and DI pipeline including interconnection with Bakla Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000227/2021-2022 1573/ALD 22/11/2021 120 HARIDAS GHOSH 55.38 46.41 100
534 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Uttar Majidkhana WSS Under Alipurduar Division P.H.E Dte. ORD/000227/2023-2024 1606/ALD 25/08/2023 30 TAPASH KUMAR BHOWMICK 7.89 7.88 100
535 Alipurduar Division Laying of HDPE/DI pipe line near Dangi Bazar area for interconnection in the distribution system and bridge /culvert crossing under KOHINUR TEA GARDEN PWSS , Alipurduar Sadar Sub-Division, under Alipurduar Division PHE DTE. (SM/12113) ORD/000227/2024-2025 2280/ALD 05/08/2024 240 JAYDAB ADHIKARI 26.67 0.00 85
536 Alipurduar Division Laying distribution system for Putimari PWSS under Alipurduar Division, PHE Dte. ORD/000228/2022-2023 1104/ALD 29/07/2022 30 HARIDAS GHOSH 2.92 2.92 95
537 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Dakshin Majidkhana WSS Under Alipurduar Division P.H.E Dte. ORD/000228/2023-2024 1605/ALD 25/08/2023 640 HARI CONSTRUCTION 6.76 0.00 80
538 Alipurduar Division Construction of excess work of Boundary wall & 3m Span open Foundation Culvert with Boulder Protection works and other alied works at 2nd Site of Samuktala PWSS Zone-I PWSS Alipurduar Sadar Sub-Division, under Alipurduar Division PHE DTE. (SM/12561) ORD/000228/2024-2025 2281/ALD 05/08/2024 240 PRITAM DAS 12.58 3.29 100
539 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Purba Khalshamari WSS Under Alipurduar Division P.H.E Dte. ORD/000229/2023-2024 1604/ALD 25/08/2023 30 HARI CONSTRUCTION 6.76 0.00 100
540 Alipurduar Division Laying of HDPE/DI pipe line near kohinur TG factory area for interconnection in the distribution system and bridge /culvert crossing , Construction of Pump House, Boundary Wall at Head work site of KOHINUR TEA GARDEN PWSS Alipurduar Sadar Sub-Division, under Alipurduar Division PHE DTE. (SM/12113). ORD/000229/2024-2025 2282/ALD 05/08/2024 240 DILIP MAHATO 60.91 13.08 95
541 Alipurduar Division Laying of HDPE pipe line for the Birpara Water Supply Scheme under Alipurduar Division,PHE Dte.(Part-2) ORD/000230/2021-2022 1571/ALD 22/11/2021 60 PRAMESH LAMA 51.34 44.47 7
542 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Brajerkuti WSS Under Alipurduar Division P.H.E Dte. ORD/000230/2023-2024 1602/ALD 25/08/2023 30 TAPASH KUMAR BHOWMICK 6.76 6.76 99
543 Alipurduar Division Laying of different dia DI,UPVC pipeline, bridge and culvert crossing and other works for providing FHTC at Jogendrapur and Satpukuri mouza at Augmentation of Jogendrapur PWSS under Birpara Sub-Division under Alipurduar Division, PHE Dte. (SM/10678) ORD/000230/2024-2025 2283/ALD 05/08/2024 60 MONORAMA ENTERPRISE 21.88 0.00 0
544 Alipurduar Division Withdrawing and relaying and laying of UPVC/DI/MS Distribution pipe line and other misc. work for retrofitting of Paschim Khayerbari WSS under Birpara Sub-Division, Alipurduar Division, PHE Dte.(Part-II) ORD/000231/2020-2021 1177/ALD 15/12/2020 60 MATARA CONSTRUCTION CO 45.10 63.92 92
545 Alipurduar Division Laying of HDPE pipe line for the Birpara Water Supply Scheme under Alipurduar Division,PHE Dte.(Part-3) ORD/000231/2021-2022 1570/ALD 22/11/2021 420 SOUVIK ROY PALADHI 37.07 29.87 61
546 Alipurduar Division New Laying of UPVC/DI pipeline,and other allied works including filling of gap in the distribution system for Augmentation of Chandirjhar PWSS under Alipurduar Division, PHE Dte. ORD/000231/2022-2023 1228/ALD 10/08/2022 30 MATRI ENTERPRISE 3.21 2.87 8
547 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Kohinur TG WSS Under Alipurduar Division P.H.E Dte. ORD/000231/2023-2024 1600/ALD 25/08/2023 541 DILIP MAHATO 6.76 0.00 85
548 Alipurduar Division Continuation for the work of hiring of additional Diesel vehicle maxi cab (At least 7 seater) for Assistant Engineer, Birpara Sub-Division, P.H.E. Dte. (from 01.01.2026 to 31.03.2026) ORD/000231/2025-2026 2745/ALD 30/12/2025 90 PARITOSH SUTRADHAR 1.20 0.00 0
549 Alipurduar Division Laying of UPVC/DI/MS Distribution pipe line and FHTC in connection with Jaldhara Jal Sapna and other misc work for Dalimpur WSS under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000232/2020-2021 1178/ALD 15/12/2020 60 M/S PALIT ENTERPRISE 45.48 54.37 86
550 Alipurduar Division Construction of Piller and Repairing of pipeline with GI Pipe near the house of Durga Oraon, kamal Roy & Banchukamari 1No. BFP School for Banchukamari WSS unedr Alipurduar Division, PHE Dte ORD/000232/2022-2023 1229/ALD 10/08/2022 30 TAPASH DAS 3.07 0.00 80
551 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Srinathpur TG WSS Under Alipurduar Division P.H.E Dte. ORD/000232/2023-2024 1599/ALD 25/08/2023 30 GIRIRAJ ENTERPRISE 6.70 6.56 98
552 Alipurduar Division Supply of MSREW Pipe for modified DTH - ODEX of drilling at Site no. 01 of GARGENDA TE of RWS SUB-Division under Alipurduar Division, PHE Dte.(SM/16824) ORD/000232/2024-2025 2292/ALD 06/08/2024 30 EFFLUENT AND WATERTREATMENT ENGINEERS PVT LTD 8.77 7.43 100
553 Alipurduar Division Continuation of Hiring of Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for inspection and monitoring of Jal Jeevan Mission (JJM) works under Alipurduar Division, P.H.E. Dte..(from 01.02.2026 to 30.04.2026) ORD/000232/2025-2026 2933/ALD 29/01/2026 90 CHANDAN KIRTONIA 1.20 0.00 0
554 Alipurduar Division Supply Installation Commissioning and Trial Operation of Electro Mechanical components at Bandapani TG Hindi High School within Madarihat-Birpara Block under Alipurduar Division, PHE Dte. (Part-1) ORD/000233/2022-2023 1230/ALD 10/08/2022 30 BHAGWATI BHUJEL 3.92 3.88 25
555 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Paschim Chegmari WSS Under Alipurduar Division P.H.E Dte. ORD/000233/2023-2024 1597/ALD 25/08/2023 30 M/S SSB CONSTRUCTION CO. 6.77 0.00 0
556 Alipurduar Division Supply of MSREW Pipe for modified DTH - ODEX of drilling at 2 different locations under Madarihat-Birpara Block of RWS SUB-Division under Alipurduar Division, PHE Dte.(SM/16824) ORD/000233/2024-2025 2293/ALD 06/08/2024 30 EFFLUENT AND WATERTREATMENT ENGINEERS PVT LTD 14.15 8.09 100
557 Alipurduar Division Laying of UPVC/DI/MS Distribution pipe line and FHTC in connection with Jaldhara Jal Sapna and other misc work for Dalimpur WSS under Birpara Sub-Division, Alipurduar Division, PHE Dte.(under Jateswar-I GP area) ORD/000234/2020-2021 1179/ALD 15/12/2020 60 NARAYAN CHANDRA SAHA 45.66 35.45 0
558 Alipurduar Division Supply Installation Commissioning and Trial Operation of Electro Mechanical components at Bandapani TG Hindi High School withing Madarihat-Birpara Block under Alipurduar Division, PHE Dte. (Part-2) ORD/000234/2022-2023 1231/ALD 10/08/2022 30 BHAGWATI BHUJEL 3.80 3.30 24
559 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Phashawa TG WSS Under Alipurduar Division P.H.E Dte. ORD/000234/2023-2024 1596/ALD 25/08/2023 542 DILIP MAHATO 5.64 0.00 85
560 Alipurduar Division Sinking of Big dia Tube Well (250 x 200 mm dia) by R.C. drilling for Aug. of Pararpar PWSS within Alipurduar-I Block of RWS SUB-Division under Alipurduar Division, PHE Dte.(SM/14209) ORD/000234/2024-2025 2294/ALD 07/08/2024 30 EFFLUENT AND WATERTREATMENT ENGINEERS PVT LTD 20.72 0.00 100
561 Alipurduar Division Laying of pipeline distribution system (Parallel and left out Area) and other allied works at Munshipara PWSS within APD-I Block under Alipurduar Division, PHE Dte. ORD/000234/2025-2026 3180/ALD 11/03/2026 75 TAPASH DAS 65.71 0.00 0
562 Alipurduar Division Restotation of pipeline by providing steel piles for JJM at Paschim Khairbari WSS under Alipurduar Division, PHE Dte. ORD/000235/2022-2023 1227/ALD 10/08/2022 30 MATARA CONSTRUCTION CO 1.30 1.26 62
563 Alipurduar Division Sinking of Big dia Tube Well (250 x 200 mm dia) by R.C. drilling for Aug. of Dakshin Sonapur PWSS within Alipurduar-I Block of RWS SUB-Division under Alipurduar Division, PHE Dte.(SM/11970) ORD/000235/2024-2025 2295/ALD 07/08/2024 207 EFFLUENT AND WATERTREATMENT ENGINEERS PVT LTD 20.72 0.00 100
564 Alipurduar Division Gap filling by Laying of HDPE pipeline (Parallel and left out) at Madhya Khairbari PWSS under Alipurduar Division, PHE Dte. ORD/000235/2025-2026 3181/ALD 11/03/2026 75 MITHUN DAS 60.29 0.00 0
565 Alipurduar Division Withdrawing and relaying and laying of UPVC/DI/MS/CI Distribution pipe line and other misc work for retrofitting of PASCHIM KHAYERBAR WSS under Birpara Sub-Division, Alipurduar Division,PHE Dte. Part-I ORD/000236/2020-2021 1181/ALD 15/12/2020 60 SANJIT SAHA 43.88 31.11 100
566 Alipurduar Division Replacement of old existing AC pipeline with UPVC pipe and providing FHTC in connection with Jaldhara/Jal Sapna for Uttar Sishubari WSS under Alipurduar Division, PHE Dte. (Opposite of Rail line area) ORD/000236/2021-2022 1577/ALD 22/11/2021 60 ASHOK SAPKOTA 22.55 20.81 54
567 Alipurduar Division Land development of 3rd Tubewell site at Chandirjhar WSS under Alipurduar Division, PHE Dte. ORD/000236/2022-2023 1232/ALD 10/08/2022 30 DULAL DAS 1.36 1.26 9
568 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Sankos TG WSS Under Alipurduar Division P.H.E Dte. ORD/000236/2023-2024 1592/ALD 25/08/2023 541 SOUVIK ROY PALADHI 6.76 5.24 100
569 Alipurduar Division Sinking of Big dia Tube Well (250 x 200 x 150 mm dia) by Modified DTH - ODEX of drilling for Aug. of Totopara PWSS within Madarihat-Birpara Block of RWS SUB-Division under Alipurduar Division, PHE Dte.(SM/11765) ORD/000236/2024-2025 2296/ALD 07/08/2024 270 EFFLUENT AND WATERTREATMENT ENGINEERS PVT LTD 27.04 0.00 100
570 Alipurduar Division Gap Filling, Replacement of damaged distribution line & FHTCs, land development of 3rd Pump House and others allied works for TAPASHIKHATA PWSS within Alipurduar Block-I under Alipuduar Division PHE.Dte. ORD/000236/2025-2026 3182/ALD 11/03/2026 90 TAPASH DAS 91.62 0.00 0
571 Alipurduar Division Replacement of old existing AC pipeline with UPVC pipe and providing FHTC in connection with Jaldhara/Jal Sapna for Uttar Sishubari WSS under Alipurduar Division, PHE Dte. (Opposite of Rail line area) ORD/000237/2021-2022 1578/ALD 22/11/2021 60 KAMALESH ROY 22.55 20.81 55
572 Alipurduar Division Construction of Boundary Wall and pathway for Dakshin Paitkapara PWSS under Alipurduar Division PHE DTE. ORD/000237/2022-2023 1329/ALD 24/08/2022 1064 M/S BASU CONSTRUCTION AND CO 36.21 10.83 82
573 Alipurduar Division Supply of CIDF & CISS Pipes and specials for NURPUR WSS Under Alipurduar Division P.H.E Dte. ORD/000237/2023-2024 1591/ALD 25/08/2023 30 BENGAL YOUTH UN EMPLOYED ENGINEERS CO OPERATIVE SOCIETY LIMITED 6.76 0.00 0
574 Alipurduar Division Sinking of Big dia Tube Well (250 x 200 x 150 mm dia) by Modified DTH - ODEX of drilling at Madhya Khairbari PWSS within Madarihat-Birpara Block of RWS SUB-Division under Alipurduar Division, PHE Dte. (SM/13248) ORD/000237/2024-2025 2297/ALD 07/08/2024 30 EFFLUENT AND WATERTREATMENT ENGINEERS PVT LTD 18.06 0.00 80
575 Alipurduar Division Laying of different dia DI, UPVC pipeline, & other works for Uttar Sishubari PWSS, under Alipurduar Division P.H.E. DTE. ORD/000237/2025-2026 3183/ALD 11/03/2026 90 MITHUN DAS 35.76 0.00 0
576 Alipurduar Division Repairing and renovation of 2 nos. pump house, boundary wall (H/W Site, 2nd site), Pathway, Cons. Of 2 nos New Toilet and restoration of laying distribution system by replacing of damaged AC pipeline with UPVC pipe at Totpara Water Supply Scheme under Alipurduatr Division, PHE Dte. ORD/000238/2021-2022 1579/ALD 22/11/2021 1200 NARENDRA BHADANI. 22.78 19.70 100
577 Alipurduar Division Laying of HDPE pipeline for providing FHTC at Uttar Latabari PWSS area, Kalchini Block under Alipurduar Division PHE DTE. ORD/000238/2022-2023 1330/ALD 24/08/2022 60 DIPANKAR DUTTA 47.46 47.24 46
578 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Chalnipak WSS Under Alipurduar Division P.H.E Dte. ORD/000238/2023-2024 1607/ALD 25/08/2023 30 SOUVIK ROY PALADHI 7.89 0.00 0
579 Alipurduar Division Laying of UPVC/DI/MS Distribution pipe line and FHTC in connection with Jaldhara Jal Sapna and other misc. work for Jateswar WSS under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000239/2020-2021 1180/ALD 15/12/2020 60 SANJIT SAHA 41.94 61.91 96
580 Alipurduar Division Repairing and renovation of 2 nos. pump house, boundary wall (H/W Site, 2nd site), Pathway, Cons. Of 2 nos New Toilet and restoration of laying distribution system by replacing of damaged AC pipeline with UPVC pipe at Totpara Water Supply Scheme under Alipurduatr Division, PHE Dte. ORD/000239/2021-2022 1580/ALD 22/11/2021 1200 SASANKA ROY 22.78 20.11 100
581 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( Reverse Rotary Method) and Rising Main for Additional T/W of Patlakhawa Piped Water Supply Scheme ORD/000239/2022-2023 1331/ALD 24/08/2022 60 UTTAM SAHA 29.37 28.52 97
582 Alipurduar Division Supply of CIDF special for Kumargram TG Pwss Under Alipurduar Division PHE Dte. ORD/000239/2023-2024 1608/ALD 25/08/2023 30 HARI CONSTRUCTION 7.67 7.65 95
583 Alipurduar Division Supply of CIDF & CISS Pipes and specials for Kayakhata WSS Under Alipurduar Division P.H.E Dte. ORD/000240/2023-2024 1775/ALD 28/08/2023 30 HARI CONSTRUCTION 6.76 6.76 100
584 Alipurduar Division Cons. Of balance portion of pump house, boundary wall, rising main, laying of DI and HDPE pipeline for 3rd site of Dakshin Paitkapara PWSS under Alipurduar Division, PHE Dte. ORD/000241/2023-2024 1787/ALD 29/08/2023 120 ANUP GUPTA 22.82 0.00 40
585 Alipurduar Division Repairing of Old OHR at Banchukamari PWSS under Alipurduar Division, PHE Dte. ORD/000241/2025-2026 3200/ALD 12/03/2026 90 DAS CONSTRUCTION 11.32 0.00 0
586 Alipurduar Division Providing House connection for UTTAR LATABARI piped water supply scheme under Alipuduar Division, P.H.E. Dte. Part-1 ORD/000242/2020-2021 1244/ALD 28/12/2020 60 SHIB RATAN BHOWMIK 9.97 9.97 0
587 Alipurduar Division Supply & delivery of Desktop CPU-AMD Ryzen5 2400, H320 Gigabyte Mother Board, 8GB DDR4 Ram, ATX Cabinet, SMPS 450 Watt,240 GB SSD,1 TB HDD & Epson printer L-1100 for the use at office of the Assistant Engineer, Alipurduar RWS Sub-Division, P.H.E. Dte. ORD/000242/2022-2023 1152/ALD 02/08/2022 7 CYBER NET 0.99 0.99 94
588 Alipurduar Division Providing balance FHTC for KAYAKHATA PWSS under Alipurduar Division, PHE Dte. ORD/000242/2023-2024 1788/ALD 29/08/2023 60 HARI CONSTRUCTION 11.22 0.00 0
589 Alipurduar Division Laying of DI & HDPE pipeline, River and Road crossing, construction of valve chamber and other misc. workss for Purba Majherdabri TG PWSS under Alipurduar Division P.H.E. DTE. ORD/000242/2025-2026 3201/ALD 12/03/2026 75 DAS CONSTRUCTION 16.37 0.00 0
590 Alipurduar Division Providing balance FHTC for KOHINUR TG PWSS (PART-II) under Alipurduar Division, PHE Dte. ORD/000243/2023-2024 1789/ALD 29/08/2023 60 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 16.73 0.00 0
591 Alipurduar Division Providing balance FHTC for SANKOSH TG PWSS under Alipurduar Division, PHE Dte. ORD/000244/2023-2024 1790/ALD 29/08/2023 533 SOUVIK ROY PALADHI 12.27 0.00 75
592 Alipurduar Division Providing balance FHTC for KUMARGRAM TG PWSS under Alipurduar Division, PHE Dte. ORD/000245/2023-2024 1791/ALD 29/08/2023 360 HARI CONSTRUCTION 13.16 11.10 81
593 Alipurduar Division Providing House connection for FALAKATA AUG. piped water supply scheme (Falakata-Dhupguri Road) under Alipuduar Division, P.H.E. Dte. Part-4 ORD/000246/2020-2021 1246/ALD 28/12/2020 60 TAPASH KUMAR BHOWMICK 30.04 54.27 67
594 Alipurduar Division Providing balance FHTC for NEWLAND TG PWSS under Alipurduar Division, PHE Dte. ORD/000246/2023-2024 1792/ALD 29/08/2023 60 SUBHAK CHIK BARAIK 13.39 0.00 0
595 Alipurduar Division Providing House connection for BANGSHIDHARPUR piped water supply scheme under Alipuduar Division, P.H.E. Dte. Part-1 ORD/000247/2020-2021 1247/ALD 28/12/2020 60 MESSRS R N TRADERS 40.06 80.12 0
596 Alipurduar Division Providing balance FHTC for Purba Chepani PWSS under Alipurduar Division, PHE Dte. ORD/000247/2023-2024 1589/ALD 25/08/2023 30 ANIRBAN KAR 3.32 0.00 0
597 Alipurduar Division Providing House connection for FALAKATA AUG. piped water supply scheme (Subhaspally area, right side of NH) under Alipuduar Division, P.H.E. Dte. Part-5 ORD/000248/2020-2021 1248/ALD 28/12/2020 60 BILTU DAS 29.59 29.59 82
598 Alipurduar Division Providing balance FHTC for PASCHIM CHENGMARI PWSS under Alipurduar Division, PHE Dte. ORD/000248/2023-2024 1590/ALD 25/08/2023 90 ANKIT SARKAR 1.66 1.49 90
599 Alipurduar Division Providing House connection for BAROBISHA ZONE-II piped water supply scheme under Alipuduar Division, P.H.E. Dte. Part-4 ORD/000249/2020-2021 1249/ALD 28/12/2020 60 TAPAN CHANDA 39.91 79.82 0
600 Alipurduar Division Providing Functional Tap Connection from existing pipeline to the schools, AWC, Community centres, Govt. Office Buildings and Households at Southern Part of Uttar Latabari Area under Uttar Latabari PWSS under Alipurduar Division, PHE Dte. ORD/000249/2021-2022 1594/ALD 22/11/2021 30 M/S SHIB RATAN BHOWMICK & CO 4.99 4.99 76
601 Alipurduar Division Providing balance FHTC for MADHYA KAMAKHYAGURI PWSS under Alipurduar Division, PHE Dte. ORD/000249/2023-2024 1850/ALD 04/09/2023 45 MONORAMA ENTERPRISE 5.85 0.00 0
602 Alipurduar Division Providing Functional Tap Connection from existing pipeline to the schools, AWC, Community centres, Govt. Office Buildings and Households at Northern Part of Uttar Latabari Area under Uttar Latabari PWSS under Alipurduar Division, PHE Dte. ORD/000250/2021-2022 1595/ALD 22/11/2021 30 M/S SHIB RATAN BHOWMICK & CO 4.99 4.99 75
603 Alipurduar Division Providing balance FHTC for KOHINUR TG PWSS (PART-I) under Alipurduar Division, PHE Dte. ORD/000250/2023-2024 1852/ALD 04/09/2023 60 TAPASH DAS 16.73 13.52 81
604 Alipurduar Division Balance work of construction of boundary wall of 2nd Site at Bhatibari WSS under Alipurduar Division PHE Dte. ORD/000251/2021-2022 1598/ALD 22/11/2021 45 SREE MAA CONSTRUCTION 4.79 4.77 19
605 Alipurduar Division Preparation of DPR after investigation for Tasti Tea Garden, Dalgaon Tea Garden and Dalmoney Tea Garden Piped Water Supply Scheme under Falakata Block, Alipurduar Division, PHE Dte. ORD/000251/2022-2023 1392/ALD 29/08/2022 30 M/S SOBHA AND CO 6.51 6.51 100
606 Alipurduar Division Construction of tubewells (2 nos.) by Reverse rotary method of drilling at HW site and 2nd TW site, Soil investigation at OHR site, constructions of 500 Cum OHR at HW, construction of pump house and boundary wall at H/W and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Uma Charanpur PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000251/2023-2024 1873/ALD 07/09/2023 270 TAPASH KUMAR BHOWMICK 608.41 242.55 37
607 Alipurduar Division Providing House connection for FALAKATA AUG. piped water supply (Masalapatty area, left side of NH)under Alipuduar Division, P.H.E. Dte. Part-6 ORD/000252/2020-2021 1252/ALD 28/12/2020 60 SOUVIK ROY PALADHI 30.05 57.06 60
608 Alipurduar Division Construction of tubewells (2 nos.) by Reverse rotary method of drilling at HW site and 2nd TW site, soil investigation at HW site, constructions of 350 Cum OHR at HW, construction of pump house and boundary wall at H/W and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Malsagaon PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000252/2023-2024 1874/ALD 07/09/2023 991 DILIP MAHATO 517.30 494.44 90
609 Alipurduar Division Gap filling by UPVC/DI pipe for Bhutnirghat WSS under Alipurduar Division, PHE Dte. ORD/000253/2021-2022 1600/ALD 22/11/2021 30 GOUTAM KUMAR DAS 4.99 4.99 98
610 Alipurduar Division Continuation order of Supply of fuel for Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for inspection and monitoring of Jal Jeevan Mission (JJM) works under Alipurduar Division, P.H.E. Dte.(from 01.08.2023 to 31.10.2023) ORD/000253/2023-2024 1109/ALD 28/07/2023 92 NIRANJAN KIRTANIA 0.70 0.51 0
611 Alipurduar Division Continuation for the work of Hiring of Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for inspection and monitoring of Jal Jeevan Mission (JJM) works under Alipurduar Division, P.H.E. Dte.(from 01/08/2023 to 31/10/2023) ORD/000254/2023-2024 1108/ALD 28/07/2023 92 NIRANJAN KIRTANIA 0.50 0.50 0
612 Alipurduar Division Laying of new UPVC/DI pipeline for filling of left out portion in the distribution system and other allied works in connection with the Augmentation of Bhatibari (Zone-I) PWSS Alipurduar Sadar Sub-Division, under Alipurduar Division PHE DTE. .(SM/14096) ORD/000254/2024-2025 3117/ALD 30/08/2024 530 M/S MAA ELECTRIC ELECTRONIC 6.45 0.00 70
613 Alipurduar Division Construction of 150cum. OHR for KUMARGRAM ZONE-IV Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000255/2022-2023 1486/ALD 05/09/2022 180 MATRI ENTERPRISE 50.41 46.14 100
614 Alipurduar Division Continuation for the work of Collection of house hold details at prescribed format through mobile app/Hard Copy including Geo-reference as directed by the E.I.C. and submission the same (soft copy) to P.H.E. Dte. Part-B ORD/000255/2023-2024 1107/ALD 28/07/2023 120 TAPASH KUMAR BHOWMICK 4.67 4.67 100
615 Alipurduar Division Gap filling by UPVC/DI pipe and bridge crossing near Hat Khola Bazar Area for Augmenttion of Falakata WSS under Alipurduar Division, PHE Dte. ORD/000256/2021-2022 1603/ALD 22/11/2021 30 NARENDRA BHADANI. 5.00 4.82 67
616 Alipurduar Division Construction of OHR 200cum for KUMARGRAM ZONE-II Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000256/2022-2023 1487/ALD 05/09/2022 180 S.G ENTERPRISE 55.09 46.61 100
617 Alipurduar Division Gap filling by UPVC/DI pipe at Parangerpar (near rail gate) of Augmenttion of Falakata WSS under Alipurduar Division, PHE Dte. ORD/000257/2021-2022 1604/ALD 22/11/2021 30 ASSOCIATE CONSTRUCTION COMPANY 4.98 5.00 61
618 Alipurduar Division Construction of OHR 200cum for KUMARGRAM ZONE-III Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000257/2022-2023 1488/ALD 05/09/2022 720 UNIVERSAL ENTERPRISES 55.33 47.63 100
619 Alipurduar Division Providing FHTC from existing distribution system as per specification for Gopalpur TG PWSS under Alipurduar Division, PHE Dte. ORD/000257/2023-2024 1875/ALD 07/09/2023 300 NARENDRA BHADANI. 7.03 6.15 90
620 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/Jal Swapna (Schools, AWC and others) for Bhutnirghat PWSS under Birpara Sub-Division under Alipurduar Division, PHE Dte. Part-4 ORD/000258/2021-2022 1605/ALD 22/11/2021 30 GOUTAM KUMAR DAS 5.04 5.04 95
621 Alipurduar Division Construction of 250cum OHR for KUMARGRAM ZONE-I Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000258/2022-2023 1489/ALD 05/09/2022 720 GOUTAM KUMAR DAS 57.30 52.88 95
622 Alipurduar Division Providing FHTC from existing distribution system as per specification for Ballalguri PWSS under Alipurduar Division, PHE Dte. ORD/000258/2023-2024 1876/ALD 07/09/2023 30 RATAN DUTTA 4.38 0.00 0
623 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/Jal Swapna for Bhutnirghat PWSS under Birpara Sub-Division under Alipurduar Division, PHE Dte. Part-5 ORD/000259/2021-2022 1606/ALD 22/11/2021 30 GOUTAM KUMAR DAS 5.04 0.00 97
624 Alipurduar Division Providing FHTC from existing distribution system as per specification for Bariguri PWSS under Alipurduar Division, PHE Dte. ORD/000259/2023-2024 1877/ALD 07/09/2023 30 DAS CONSTRUCTION 8.10 0.00 0
625 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Uttar Sishubari PWSS under Alipurduar Division, PHE Dte. Part-4 ORD/000260/2022-2023 1492/ALD 05/09/2022 90 MITHUN DAS 24.32 0.00 0
626 Alipurduar Division Providing FHTC from existing distribution system as per specification for Ethelbari PWSS under Alipurduar Division, PHE Dte. ORD/000260/2023-2024 1878/ALD 07/09/2023 805 NARENDRA BHADANI. 3.87 0.00 100
627 Alipurduar Division Development of rig Bore TW by ODEX-165 method of drilling at Lankapara WSS under Alipurduar Division, PHE Dte. ORD/000261/2021-2022 1608/ALD 22/11/2021 20 DILIP MAHATO 0.66 0.50 99
628 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Dakshin Sonapur PWSS under Alipurduar Division, PHE Dte. Part-1 ORD/000261/2022-2023 1493/ALD 05/09/2022 945 MADHAB SAHA 34.59 0.00 27
629 Alipurduar Division Providing FHTC from existing distribution system as per specification for Paschim Satali PWSS under Alipurduar Division, PHE Dte. ORD/000261/2023-2024 1879/ALD 07/09/2023 270 SATYABRATA BHATTACHERJEE 7.02 0.00 1
630 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Dakshin Sonapur PWSS under Alipurduar Division, PHE Dte. Part-2 ORD/000262/2022-2023 1494/ALD 05/09/2022 1080 KAJAL KUMAR DE 34.44 0.00 15
631 Alipurduar Division Providing FHTC from existing distribution system as per specification for Rangamati TG PWSS under Alipurduar Division, PHE Dte. ORD/000262/2023-2024 1880/ALD 07/09/2023 30 ASHOK PRADHAN 9.49 0.00 0
632 Alipurduar Division Providing House connection for FALAKATA AUG. piped water supply scheme (Barodoba Area) under Alipuduar Division, P.H.E. Dte. Part-1 ORD/000263/2020-2021 1254/ALD 28/12/2020 60 HARIDAS GHOSH 43.86 74.64 66
633 Alipurduar Division Providing FHTC connection for AWC, School, Health Centre etc. of Salkumarhat WSS under Alipurduar Division, PHE Dte. Part-C ORD/000263/2021-2022 1596/ALD 22/11/2021 30 DEBABRATA DUTTA 4.92 3.03 98
634 Alipurduar Division Construction of 700cum OHR for Augmentation of DAKSHIN SONAPUR Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000263/2022-2023 1495/ALD 05/09/2022 1080 SHREE RANISATI ENTERPRISE 123.17 52.09 5
635 Alipurduar Division Providing FHTC from existing distribution system as per specification for Atiabari TG PWSS under Alipurduar Division, PHE Dte. ORD/000263/2023-2024 1881/ALD 07/09/2023 30 SOUVIK ROY PALADHI 9.84 0.00 0
636 Alipurduar Division Extension/Merging of Distribution pipeline (UPVC/DI/MS/CI) from Paschim Khairbari WSS to Uttar Sishubari WSS and others misc. work under Alipurduar Division, PHE Dte. ORD/000264/2020-2021 1255/ALD 28/12/2020 60 MITHUN DAS 45.83 45.48 80
637 Alipurduar Division Construction of Culvert at Hasimara WSS Head Work Site within Alipurduar Division, PHE Dte. ORD/000264/2021-2022 1597/ALD 22/11/2021 45 ALATYA CONSTRUCTION & CO. 4.92 4.54 98
638 Alipurduar Division Soil investigation work at 4 different places of Kumargram within Alipurduar District under Alipurduar Division PHE Dte. ORD/000264/2022-2023 1502/ALD 05/09/2022 30 MOYTEC 4.88 4.88 7
639 Alipurduar Division Providing FHTC from existing distribution system as per specification for Nimtijhora TG PWSS under Alipurduar Division, PHE Dte. ORD/000264/2023-2024 1882/ALD 07/09/2023 537 M/S A. B. ENTERPRISE 7.09 6.74 100
640 Alipurduar Division Providing House connection for FALAKATA AUG. piped water supply scheme (College Para Area) under Alipuduar Division, P.H.E. Dte. Part-2 ORD/000265/2020-2021 1256/ALD 28/12/2020 60 BILTU DAS 43.41 78.80 62
641 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna for Govt office and other Institution under Madarihat WSS under Alipurduar Division, PHE Dte. ORD/000265/2021-2022 1830/ALD 10/12/2021 30 BHAGWATI BHUJEL 5.04 5.04 61
642 Alipurduar Division Construction of 100cum. OHR for SAMUKTALA ZONE-III Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000265/2022-2023 1658/ALD 19/09/2022 1140 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 43.90 28.97 100
643 Alipurduar Division Providing FHTC from existing distribution system as per specification for Bhatkhawa TG PWSS under Alipurduar Division, PHE Dte. ORD/000265/2023-2024 1883/ALD 07/09/2023 240 PRANAB GHOSH 7.16 7.10 100
644 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna for AWC and school under Madarihat WSS under Alipurduar Division, PHE Dte. ORD/000266/2021-2022 1831/ALD 10/12/2021 30 RATAN DUTTA 5.04 5.04 59
645 Alipurduar Division Soil investigation work at 3 different places of Samuktala within Alipurduar District under Alipurduar Division PHE Dte. ORD/000266/2022-2023 1657/ALD 19/09/2022 30 ASIS ENTERPRISE 3.65 3.65 50
646 Alipurduar Division Providing FHTC from existing distribution system as per specification for Rajabhat TG PWSS under Alipurduar Division, PHE Dte. ORD/000266/2023-2024 1884/ALD 07/09/2023 300 PRITAM DAS 7.83 7.82 100
647 Alipurduar Division Retrofitting of pipeline etc. for the "Jal Swapno" Programme (FHTC for every house hold) under SALSALABARI PWSS, Block- Alipurduar-II, Dist-Alipurduar. ORD/000267/2020-2021 1279/ALD 05/01/2021 60 MATRI ENTERPRISE 45.43 67.93 97
648 Alipurduar Division Repairing of drainage system & painting of office cum Godown building at Head Work site of Falakata WSS (OLD) under Alipurduar Division, PHE Dte. ORD/000267/2021-2022 1832/ALD 10/12/2021 60 NARENDRA BHADANI. 4.47 4.36 63
649 Alipurduar Division Construction of Boundary wall at 3rd TW site of Samuktalata PWSS under Alipurduar Division, PHE Dte. ORD/000267/2022-2023 1666/ALD 19/09/2022 30 PRITAM DAS 4.74 4.74 47
650 Alipurduar Division Providing FHTC from existing distribution system as per specification for Nimti Domohani PWSS under Alipurduar Division, PHE Dte. ORD/000267/2023-2024 1885/ALD 07/09/2023 30 DEBAJYOTI SUTRADHAR 5.22 0.00 0
651 Alipurduar Division Laying of proposed Rising main (Length- 1085 mtr, 4817 mtr & 1320 mtr.) of Cha-Sundori Project (JJM- SM/10054) within Lankapara Tea Garden Area Piped Water Supply Scheme, Madarihat-Birpara block of Birpara Sub-Division under Alipurduar Division, PHE Dte.[As per new DPR guided by Planning Circle-II, PHE Dte.] ORD/000267/2024-2025 3116/ALD 30/08/2024 45 DILIP MAHATO (OPC) PRIVATE LIMITED 36.54 5.51 28
652 Alipurduar Division Laying of DI/MS/HDPE Distribution pipe line for the LANKAPARA WSS (TULSHIPARA TG) under Alipurduar Division, PHE Dte. Dist-Alipurduar. ORD/000268/2020-2021 1280/ALD 05/01/2021 60 UMWELT ENGINEER PVT. LTD. 30.90 51.11 98
653 Alipurduar Division Construction of RCC boundary wall for Uttar Latabari WSS Pump House (rabindra nagar) at Uttar Latabari PWSS under Alipurduar Division, PHE Dte. ORD/000268/2021-2022 1834/ALD 10/12/2021 45 SHIB RATAN BHOWMIK 4.90 4.48 75
654 Alipurduar Division Construction of Boundary wall at 5th TW site of Samuktalata PWSS under Alipurduar Division, PHE Dte. ORD/000268/2022-2023 1668/ALD 19/09/2022 270 ROY & PANDIT CONSTRUCTIONS 4.76 4.71 100
655 Alipurduar Division Providing FHTC from existing distribution system as per specification for Torsha Cha Sundari PWSS PWSS under Alipurduar Division, PHE Dte. ORD/000268/2023-2024 1886/ALD 07/09/2023 880 D. K. & SONS 1.01 0.00 100
656 Alipurduar Division Retrofitting of pipeline etc. for the "Jal Swapno" Programme (FHTC for every house hold) under PURBA CHEPANI PWSS, Block- Alipurduar-II, Dist-Alipurduar. ORD/000269/2020-2021 1281/ALD 05/01/2021 60 MATRI ENTERPRISE 37.84 52.65 94
657 Alipurduar Division Repairing of damaged pipe line, arrangement of water supply pipe line on emergency basis and other works due to widening and strengthening of PWD road at Sonapur PWSS under Alipurduar Division, PHE Dte. ORD/000269/2021-2022 1835/ALD 10/12/2021 30 HARI CONSTRUCTION 2.56 2.56 97
658 Alipurduar Division Construction of Pump House at 1st TW site of Samuktalata PWSS under Alipurduar Division, PHE Dte. ORD/000269/2022-2023 1669/ALD 19/09/2022 60 KOUSHIK BHOWMICK 4.77 4.77 95
659 Alipurduar Division Bridge Crossing and Laying of DI/MS/HDPE Distribution pipe line for the LANKAPARA WSS under Alipurduar Division, PHE Dte. Dist-Alipurduar. ORD/000270/2020-2021 1282/ALD 05/01/2021 726 GHOSH & SAHA CONSTRUCTION 23.75 12.06 100
660 Alipurduar Division Road crossing (by NP3 Hume pipe) at Dhupguri Road under under Zone-II of augmentation of Falakata WSS due to widening of PWD Road under Alipurduar Division, PHE Dte. (3 nos) ORD/000270/2021-2022 1836/ALD 10/12/2021 45 SASANKA ROY 2.49 2.49 67
661 Alipurduar Division Construction of Pump House at 3rd TW site of Samuktalata PWSS under Alipurduar Division, PHE Dte. ORD/000270/2022-2023 1671/ALD 19/09/2022 60 SWADESH DEV 4.75 4.65 100
662 Alipurduar Division Providing FHTC from existing distribution system as per specification for Uttar Barajhar PWSS PWSS under Alipurduar Division, PHE Dte. ORD/000270/2023-2024 1887/ALD 07/09/2023 30 TAPASH DAS 4.24 0.00 0
663 Alipurduar Division Retrofitting of pipeline etc. for the "Jal Swapno" Programme (FHTC for every house hold) under BAKLA PWSS, Block- Alipurduar-II, Dist-Alipurduar. ORD/000271/2020-2021 1283/ALD 05/01/2021 60 PROGRESSIVE UNEMPLOYED CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 45.19 64.21 74
664 Alipurduar Division Construction of Pump House at 4th TW site of Samuktalata PWSS under Alipurduar Division, PHE Dte. ORD/000271/2022-2023 1672/ALD 19/09/2022 60 PROJIT HALDER 4.77 0.00 0
665 Alipurduar Division Construction of pathway, surface drain and chatal, land development, along with the other allied works at Bhatibari Zone-II PWSS under Alipurduar Division PHE DTE. ORD/000271/2023-2024 1948/ALD 12/09/2023 60 SWAPAN MALAKAR 13.00 0.00 100
666 Alipurduar Division Retrofitting of pipeline etc. for the "Jal Swapno" Programme (FHTC for every house hold) under JHOSHODANGA PWSS, Block- Alipurduar-II, Dist-Alipurduar. ORD/000272/2020-2021 1284/ALD 05/01/2021 60 MADHAB SAHA 24.66 42.78 99
667 Alipurduar Division Laying HDPE pipe , Road crossing and other misc woks related to Radharani WSS under Alipurduar Division PHE Dte. ORD/000272/2021-2022 1838/ALD 10/12/2021 45 UMWELT ENGINEER PVT. LTD. 3.01 2.35 91
668 Alipurduar Division Construction of Pump House at 5th TW site of Samuktalata PWSS under Alipurduar Division, PHE Dte. ORD/000272/2022-2023 1673/ALD 19/09/2022 60 CHITTA RANJAN DEY 4.75 4.70 100
669 Alipurduar Division Providing FHTC from existing distribution system as per specification for Foskadanga PWSS PWSS under Alipurduar Division, PHE Dte. ORD/000272/2023-2024 1888/ALD 07/09/2023 30 MADHAB SAHA 7.00 4.77 70
670 Alipurduar Division Retrofitting of pipeline for UTTAR LATABARAI PWSS (Rabindranagar & surroundings) area at Kalchini Block under Alipurduar Division, PHE Dte. Part-A ORD/000273/2020-2021 1285/ALD 05/01/2021 60 ASHOK SAPKOTA 22.45 41.56 46
671 Alipurduar Division Balance work of office cum Godown at Radharani WSS under Alipurduar Division PHE Dte. ORD/000273/2021-2022 1839/ALD 10/12/2021 60 UMWELT ENGINEER PVT. LTD. 4.97 5.18 92
672 Alipurduar Division Construction of Boundary wall at 4th TW site of Samuktalata PWSS under Alipurduar Division, PHE Dte. ORD/000273/2022-2023 1667/ALD 19/09/2022 45 DHANENDRA SARKAR 4.77 4.74 100
673 Alipurduar Division Construction of pathway, surface drain and chatal, land development, along with the other allied works at Bhatibari Zone-III PWSS under Alipurduar Division PHE DTE. ORD/000273/2023-2024 1949/ALD 12/09/2023 60 CREATIVE UN EMPLOYED ENGINEERSCO OPER SOCYLIMITED 9.75 0.00 0
674 Alipurduar Division Retrofitting of pipeline for UTTAR LATABARAI PWSS (Rabindranagar & surroundings) area at Kalchini Block under Alipurduar Division, PHE Dte. Part-B ORD/000274/2020-2021 1286/ALD 05/01/2021 60 ASHOK SAPKOTA 19.09 6.87 45
675 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Bholardabri WSS under Alipurduar Division, PHE Dte. Part-8 ORD/000274/2021-2022 1840/ALD 10/12/2021 30 HARI CONSTRUCTION 5.00 4.72 66
676 Alipurduar Division Construction of 400cum OHR for SAMUKTALA ZONE-I Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000274/2022-2023 1659/ALD 19/09/2022 180 DILIP MAHATO 77.32 77.29 100
677 Alipurduar Division Construction of boundary wall (H/W) Site, Toilet, Repairing of Pump House & 125 nos. house connection of Uttar Majherdabri Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000275/2020-2021 1287/ALD 05/01/2021 60 TAPASH KUMAR BHOWMICK 20.49 12.70 73
678 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Bholardabri WSS under Alipurduar Division, PHE Dte. Part-9 ORD/000275/2021-2022 1841/ALD 10/12/2021 30 HARI CONSTRUCTION 5.04 4.42 65
679 Alipurduar Division Construction of 350cum OHR for SAMUKTALA ZONE-II Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000275/2022-2023 1661/ALD 19/09/2022 180 MATARA CONSTRUCTION CO 71.41 69.83 100
680 Alipurduar Division Providing FHTC from existing distribution system as per specification for Pararpar PWSS PWSS under Alipurduar Division, PHE Dte. ORD/000275/2023-2024 1889/ALD 07/09/2023 30 INDRAYOODH BHOWAL 8.26 0.00 0
681 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Bholardabri WSS under Alipurduar Division, PHE Dte. Part-10 ORD/000276/2021-2022 1842/ALD 10/12/2021 30 HARIDAS GHOSH 5.02 4.39 63
682 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe of SAMUKTALA ZONE-II WSS under Alipurduar Division, PHE Dte. (Part-A) ORD/000276/2022-2023 1662/ALD 19/09/2022 180 M/S SSB CONSTRUCTION CO. 100.42 92.48 48
683 Alipurduar Division Providing FHTC from existing distribution system as per specification for Kalaberia PWSS PWSS under Alipurduar Division, PHE Dte. ORD/000276/2023-2024 1890/ALD 07/09/2023 30 SASANKA ROY 7.46 0.00 0
684 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Banchukamari WSS under Alipurduar Division, PHE Dte. Part-4 ORD/000277/2021-2022 1844/ALD 10/12/2021 30 HIMALAYAN CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 5.04 2.96 87
685 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe of SAMUKTALA ZONE-II WSS under Alipurduar Division, PHE Dte. (Part-B) ORD/000277/2022-2023 1663/ALD 19/09/2022 180 MATARA CONSTRUCTION CO 101.06 92.43 100
686 Alipurduar Division Supply of CIDF & CISS Pipes and specials for New Land TG WSS Under Alipurduar Division P.H.E Dte. ORD/000277/2023-2024 1593/ALD 25/08/2023 631 MADHAB SAHA 6.76 0.00 100
687 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Munshipara WSS under Alipurduar Division, PHE Dte. Part-5 ORD/000278/2021-2022 1845/ALD 10/12/2021 30 RATAN DUTTA 4.35 2.57 82
688 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe of Baniadabri and Samuktala Bazar Area under SAMUKTALA WSS under Alipurduar Division, PHE Dte. ORD/000278/2022-2023 1664/ALD 19/09/2022 180 DILIP MAHATO 100.58 92.15 46
689 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Munshipara WSS under Alipurduar Division, PHE Dte. Part-6 ORD/000279/2021-2022 1846/ALD 10/12/2021 30 AASHIRBAD ENTERPRISE 4.34 2.47 80
690 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe of Baniadabri and Garokhota Area under SAMUKTALA WSS under Alipurduar Division, PHE Dte. ORD/000279/2022-2023 1665/ALD 19/09/2022 180 GOUTAM KUMAR DAS 101.20 95.10 47
691 Alipurduar Division Construction of pathway, surface drain and chatal, land development, along with the other allied works at Bhatibari Zone-I PWSS under Alipurduar Division PHE DTE. ORD/000279/2023-2024 1947/ALD 12/09/2023 60 SAHA ENTERPRISE 12.40 0.00 0
692 Alipurduar Division Construction of gasious chlorine room for Zone-IIIB of JDA water supply scheme Alipurduar Division PHE Dte. ORD/000280/2020-2021 1330/ALD 11/01/2021 90 MAHENDRA CHHETRI 5.00 9.01 67
693 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Banchukamari WSS under Alipurduar Division, PHE Dte. Part-3 ORD/000280/2021-2022 1843/ALD 10/12/2021 1422 PROJIT HALDER 5.02 2.18 87
694 Alipurduar Division Laying distribution pipeline with UPVC pipe of Samuktala Zone-III Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000280/2022-2023 1660/ALD 19/09/2022 60 LONGLAST PIPES (INDIA)PVT.LTD. 97.26 95.08 50
695 Alipurduar Division Construction of pathway, surface drain and chatal, land development, along with the other allied works at Bhatibari Zone-IV PWSS under Alipurduar Division PHE DTE. ORD/000280/2023-2024 1950/ALD 12/09/2023 60 CREATIVE UN EMPLOYED ENGINEERSCO OPER SOCYLIMITED 13.54 0.00 0
696 Alipurduar Division Construction of gasious chlorine room for Zone-IV of JDA water supply scheme Alipurduar Division PHE Dte. ORD/000281/2020-2021 1331/ALD 11/01/2021 90 MAHENDRA CHHETRI 5.00 9.01 60
697 Alipurduar Division Construction of 200 cum OHR as per Departmental Design and drawing in headwork site, Tube well Boring by ODEX-165 method of drilling 2nos. respectively at Headwork site and 2nd Tubewell site, Rising Main and distribution line (Part-1) for HOASINBAD TG AREA PWSS under Birpara Sub-Division, Alipurduar Division, PHE Dte ORD/000281/2022-2023 1635/ALD 19/09/2022 929 SASANKA ROY 96.32 75.58 95
698 Alipurduar Division Providing balance FHTC from existing distribution system as per specification for UTTAR MANDABARI PWSS under Alipurduar Division, PHE Dte. ORD/000281/2023-2024 1988/ALD 15/09/2023 60 SHYAMAL ROY 11.35 0.00 0
699 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Loknathpur WSS under Alipurduar Division, PHE Dte. Part-5 ORD/000282/2021-2022 1851/ALD 13/12/2021 30 GOUTAM KUMAR DAS 5.04 4.86 63
700 Alipurduar Division Construction of 2nos. Pump house, 2nos. Boundary wall at headwork site and 2nd Tubewell site including providing FHTC for HOASINBAD TG AREA PWSS under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000282/2022-2023 1636/ALD 19/09/2022 954 RATAN DUTTA 37.70 30.66 80
701 Alipurduar Division Providing balance FHTC from existing distribution system as per specification for MALANGI TG PWSS under Alipurduar Division, PHE Dte. ORD/000282/2023-2024 1989/ALD 15/09/2023 60 KAMALESH ROY 10.86 0.00 0
702 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Totpara WSS under Alipurduar Division, PHE Dte. ORD/000283/2021-2022 1852/ALD 13/12/2021 30 HARI CONSTRUCTION 5.04 5.04 96
703 Alipurduar Division Laying of distribution system (Part-2) and providing FHTC for HOASINBAD TG AREA PWSS under Alipurduar Division, PHE Dte. ORD/000283/2022-2023 1637/ALD 19/09/2022 345 SASANKA ROY 81.64 75.12 92
704 Alipurduar Division Providing balance FHTC from existing distribution system as per specification for HASIMARA PWSS under Alipurduar Division, PHE Dte. ORD/000283/2023-2024 1990/ALD 15/09/2023 90 BRAJA GOPAL SAHA 73.90 0.00 0
705 Alipurduar Division Repairing of office Quarter and construction of attached toilet for Assistant Engineer Chamber of Birpara Sub-Division Office under Alipurduar Division PHE Dte. ORD/000284/2021-2022 1853/ALD 13/12/2021 45 DAS ENTERPRISE 4.91 4.75 97
706 Alipurduar Division New Laying of UPVC/DI Pipe line, dismantling concrete road and recasting same and other allied works at Salsalabari PWSS under Alipurduar Division, PHE Dte. ORD/000284/2022-2023 1638/ALD 19/09/2022 1291 NARENDRA BHADANI. 30.82 29.60 98
707 Alipurduar Division Providing FHTC from existing distribution system as per specification for UTTAR SISHUBARI PWSS under Alipurduar Division, PHE Dte. ORD/000284/2023-2024 1991/ALD 15/09/2023 90 MITHUN DAS 57.24 0.00 0
708 Alipurduar Division Tube well Boring by ODEX-165 method of drilling at Head work site, Construction of 1 no. Pump house and Boundary wall at headwork site, Rising Main and Distribution line with FHTC (Part-1) for BANDAPANI TG AREA PWSS (ZONE-I) under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000285/2022-2023 1639/ALD 19/09/2022 775 PRAMESH LAMA 43.08 20.04 50
709 Alipurduar Division Providing FHTC from existing distribution system as per specification for MADHYA KHAIRBARI PWSS under Alipurduar Division, PHE Dte. ORD/000285/2023-2024 1992/ALD 15/09/2023 360 DINABANDHU RAY 16.91 0.00 0
710 Alipurduar Division Providing House connection for Jogijhora water supply scheme at Falakata Block under Alipuduar Division, P.H.E. Dte.(Part-I) ORD/000286/2020-2021 1334/ALD 11/01/2021 30 BHAGWATI BHUJEL 4.98 9.96 0
711 Alipurduar Division Laying of DI pipeline, painting, plastering, land development and other misc works related to Patlakhawa OHR under Patlakhawa PWSS at Alipurduar-I Block, under Alipurduar Division, PHE Dte. ORD/000286/2021-2022 1855/ALD 13/12/2021 45 TAPAN CHANDA 4.26 4.27 77
712 Alipurduar Division Laying distribution system with new HDPE pipeline (Part- B) and providing FHTC and others allied works for SHRINATHPUR TG AREA PWSS under Alipurduar Division, PHE Dte. ORD/000286/2022-2023 1640/ALD 19/09/2022 60 TAPASH KUMAR BHOWMICK 55.91 45.38 50
713 Alipurduar Division Providing FHTC from existing distribution system as per specification for JAGIJHORA PWSS under Alipurduar Division, PHE Dte. ORD/000286/2023-2024 1993/ALD 15/09/2023 60 BENGAL YOUTH UN EMPLOYED ENGINEERS CO OPERATIVE SOCIETY LIMITED 33.81 0.00 0
714 Alipurduar Division Laying distribution system with new HDPE pipeline (Part- C) and providing FHTC and others allied works for SHRINATHPUR TG AREA PWSS under Alipurduar Division, PHE Dte ORD/000287/2022-2023 1641/ALD 19/09/2022 960 DAS CONSTRUCTION 58.40 54.08 45
715 Alipurduar Division Providing FHTC from existing distribution system as per specification for DALIMPUR PWSS under Alipurduar Division, PHE Dte. ORD/000287/2023-2024 1995/ALD 15/09/2023 780 SREE MAA CONSTRUCTION 28.80 9.96 45
716 Alipurduar Division Laying distribution system with new HDPE pipeline (Part- D) and providing FHTC and others allied works for SHRINATHPUR TG AREA PWSS under Alipurduar Division, PHE Dte. ORD/000288/2022-2023 1642/ALD 19/09/2022 900 KAMALESH ROY 45.33 31.15 100
717 Alipurduar Division Providing FHTC from existing distribution system as per specification for PURBA KATHALBARI PWSS under Alipurduar Division, PHE Dte. ORD/000288/2023-2024 1996/ALD 15/09/2023 60 M/S SIBU DEY AND CO 24.20 0.00 0
718 Alipurduar Division Laying distribution system with new HDPE pipeline (Part- E) and providing FHTC and others allied works for SHRINATHPUR TG AREA PWSS under Alipurduar Division, PHE Dte. ORD/000289/2022-2023 1643/ALD 19/09/2022 60 BENGAL YOUTH UN EMPLOYED ENGINEERS CO OPERATIVE SOCIETY LIMITED 55.49 49.11 45
719 Alipurduar Division Construction of boundary wall (remaining portion) at Headwork site under Samuktala Zone-III PWSS under Alipurduar Division, PHE Dte. ORD/000289/2023-2024 1903/ALD 07/09/2023 360 SWAPAN MALAKAR 6.00 5.93 100
720 Alipurduar Division Laying distribution system with new HDPE pipeline (Part-F) with Rising Main and delivery line connection, providing FHTC and other allied works for SHRINATHPUR TG AREA PWSS under Alipurduar Division, PHE Dte ORD/000290/2022-2023 1644/ALD 19/09/2022 60 TAPAN CHANDA 49.13 35.12 44
721 Alipurduar Division Land Development, paver block installation and laying of distribution of UPVC Pipeline at 2nd Pump House site and adjacent area of Shrinathpur TG Area PWSS under Alipurduar Division, PHE Dte. ORD/000290/2023-2024 2014/ALD 15/09/2023 60 SAMIR SARKAR 6.97 2.97 100
722 Alipurduar Division Laying distribution system with new HDPE pipeline (Part- G) with Rising Main and delivery line connection for SHRINATHPUR TG AREA PWSS under Alipurduar Division, PHE Dte. ORD/000291/2022-2023 1645/ALD 19/09/2022 360 DEBAJYOTI SUTRADHAR 62.99 61.30 45
723 Alipurduar Division Laying distribution system with new HDPE pipeline (Part-H) with Rising Main and delivery line connection for SHRINATHPUR TG AREA PWSS under Alipurduar Division, PHE Dte. ORD/000292/2022-2023 1646/ALD 19/09/2022 60 MADHAB SAHA 56.38 54.16 45
724 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( ODEX-165 Method of drilling) and Rising Main for Additional T/W of DIMA TG Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000293/2021-2022 1991/ALD 27/12/2021 90 GOBINDA BAGCHI 20.87 6.00 72
725 Alipurduar Division Construction of Pump House at 2nd TW site of Samuktalata PWSS under Alipurduar Division, PHE Dte. ORD/000293/2022-2023 1670/ALD 19/09/2022 60 M/S SADHAN SAHA & CO. 4.76 4.60 100
726 Alipurduar Division Providing FHTC from existing distribution system as per specification for DALMORE RAMJHORA PWSS under Alipurduar Division, PHE Dte. ORD/000293/2023-2024 2024/ALD 19/09/2023 60 SUDDHYA SING LAMA 23.76 0.00 0
727 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( ODEX-165 Method of drilling) and Rising Main for Additional T/W of HASIMARA Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000294/2021-2022 1992/ALD 27/12/2021 90 MAHENDRA CHHETRI 42.03 42.02 49
728 Alipurduar Division Laying of DI and HDPE pipeline from Kalchini BDO Office towards Hamiltonganj Bazar at Uttar Latabari PWSS area under Alipurduar Division, PHE Dte. ORD/000294/2022-2023 1685/ALD 20/09/2022 60 SUNDAR SING LAMA 24.01 23.09 45
729 Alipurduar Division Providing balance FHTC from existing distribution system as per specification for 28 and 29 MILE BASTY PWSS under Alipurduar Division, PHE Dte. ORD/000294/2023-2024 2103/ALD 29/09/2023 60 EVEREST INFRATECH INC 47.79 0.00 0
730 Alipurduar Division Extension and replacement of damaged pipeline of Birpara PWSS, Alipurduar-I Block under Alipurduar Division, PHE Dte. ORD/000295/2022-2023 1686/ALD 20/09/2022 60 KAMALESH ROY 5.01 0.00 0
731 Alipurduar Division Providing balance FHTC from existing distribution system as per specification for UTTAR LATABARI PWSS under Alipurduar Division, PHE Dte. ORD/000295/2023-2024 2104/ALD 29/09/2023 90 DIPANKAR DUTTA 65.07 0.00 0
732 Alipurduar Division Construction of boulder apron and land development at Patlakhawa WSS (Pump House no-2) under Alipurduar Division, PHE Dte. ORD/000296/2020-2021 1339/ALD 11/01/2021 30 SHIBA ENTERPRISE 4.98 9.95 0
733 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( ODEX-165 Method of drilling) and Rising Main for Additional T/W of PAITKAPARA Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000296/2021-2022 1994/ALD 27/12/2021 90 ANUP GUPTA 20.99 16.51 80
734 Alipurduar Division Construction of 1 no. Pump House, 1 no. Boundary wall at headwork site, distribution of pipeline and providing FHTC for BANDAPANI TG AREA PWSS (ZONE-II) under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000296/2022-2023 1687/ALD 20/09/2022 720 MITHUN DAS 53.39 46.70 78
735 Alipurduar Division Providing FHTC from existing distribution system as per specification for BIRPARA PWSS under Alipurduar Division, PHE Dte. ORD/000296/2023-2024 2105/ALD 29/09/2023 60 GIRIRAJ ENTERPRISE 34.39 0.00 0
736 Alipurduar Division Laying of CIDF, Rising Main, Delivery line, Hydraulic Testing, disinfection of UPVC pipeline and other allied works at Bhutnirghat WSS under Alipurduar Division, PHE Dte. ORD/000297/2022-2023 1688/ALD 20/09/2022 60 DILIP MAHATO 5.82 0.00 0
737 Alipurduar Division Withdrawing and relaying and laying of UPVC/DI/MS/CI Distribution pipe line for retrofitting and providing functional household tap connection (FHTC) in connection with Jaldhara Jal Sapno of Chhoto Salkumar PWSS under Alipurduar Division, PHE Dte. ORD/000298/2020-2021 1378/ALD 19/01/2021 45 M/S PALIT ENTERPRISE 43.75 63.73 68
738 Alipurduar Division Construction of Pump House, Boundary wall, Tube well boring (ODEX- 165 Method) Rising main of 4th T/W site of Radharani TG WSS under Alipurduar Division, PHE Dte. ORD/000298/2022-2023 1689/ALD 20/09/2022 120 BHAGWATI BHUJEL 20.53 19.48 100
739 Alipurduar Division Withdrawing and relaying and laying of UPVC/DI/MS/CI Distribution pipe line and other misc. work for retrofitting at Chhoto Salkumar PWSS under Alipurduar Division, PHE Dte. ORD/000299/2020-2021 1379/ALD 19/01/2021 45 SASANKA ROY 17.09 6.38 100
740 Alipurduar Division Supply, delivery and Installation of split type Air Conditioner for Chamber of Assistant Engineer, Alipurduar, Sadar Sub-Division, P.H.E Dte. ORD/000301/2022-2023 1731/ALD 22/09/2022 7 M/S BADAL CHANDRA SAHA 0.64 0.64 20
741 Alipurduar Division Withdrawing and relaying and laying of UPVC/DI/MS/CI Distribution pipe line and other misc. work for interconnection between Jogendrapur and Augmentation of Falakata PWSS under Alipurduar Division, PHE Dte.(Part-II) ORD/000302/2020-2021 1382/ALD 19/01/2021 45 SASANKA ROY 15.06 15.06 100
742 Alipurduar Division Supply, delivery and Installation of split type Air Conditioner for Junior Engineer Section of Alipurduar, Sadar Sub-Division, P.H.E Dte. ORD/000302/2022-2023 1732/ALD 22/09/2022 7 M/S BADAL CHANDRA SAHA 0.64 0.64 20
743 Alipurduar Division Supply delivery & installation of various machineries at Alipurduar Division Office & allied Sub-Division Offices and laboratories under Alipurduar Division, PHE Dte. ORD/000303/2021-2022 1287/ALD 01/10/2021 15 MATRI ENTERPRISE 1.75 1.75 97
744 Alipurduar Division Providing FHTC from existing distribution system as per specification for Dakshin Rangalibazna PWSS under Alipurduar Division, PHE Dte. ORD/000303/2023-2024 2134/ALD 03/10/2023 30 MANI PRADHAN 3.25 0.00 0
745 Alipurduar Division Providing FHTC from existing distribution system as per specification for Uttar Rangalibazna PWSS under Alipurduar Division, PHE Dte. ORD/000304/2023-2024 2135/ALD 03/10/2023 30 MANI PRADHAN 1.08 0.00 0
746 Alipurduar Division Drilling Rigbore tube well (ODEX-115 method) at Modakpara, Paschim Bholardabri under Alipurduar Division, PHE Dte. ORD/000305/2022-2023 1943/ALD 17/10/2022 30 HARIDAS GHOSH 2.77 0.00 0
747 Alipurduar Division Providing FHTC from existing distribution system as per specification for Khagenhat PWSS under Alipurduar Division, PHE Dte. ORD/000305/2023-2024 2170/ALD 06/10/2023 60 TAPASH DAS 5.58 0.00 0
748 Alipurduar Division Hiring of Diesel Vehicle Maxi Cab(At least 7 seater ) (Preferably TUV) for Assistant Engineer, Alipurduar Sadar Sub-Division, P.H.E. Dte.(from 01.01.2022 to 31.12.2022) ORD/000306/2021-2022 2013/ALD 29/12/2021 365 MATRI ENTERPRISE 1.76 0.00 0
749 Alipurduar Division Repairing and renovation of pump house, boundary wall and construction of new toilet of 2nd T/W site at Kumargram Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000306/2022-2023 1944/ALD 17/10/2022 60 TAPASH DAS 4.73 3.99 8
750 Alipurduar Division Hiring of Diesel Vehicle Maxi Cab(At least 7 seater ) (Preferably TUV) for Assistant Engineer, Alipurduar RWS Sub-Division, P.H.E. Dte.(from 01.01.2022 to 31.12.2022) ORD/000307/2021-2022 2014/ALD 29/12/2021 365 KAMALESH ROY 1.76 1.49 61
751 Alipurduar Division Providing extension of distribution line, repair of water pipeline in 10/142 booth at Khoardanga 2 G.P from the commissioned NARATHALI PWSS (UID-APD-166) UNDER ALIPURDUAR DIVISION PHE DTE. ORD/000309/2020-2021 1483/ALD 27/01/2021 60 TAPASH DAS 15.73 29.83 70
752 Alipurduar Division Soil investigation works at head works site for HOASINBAD TG AREA PWSS under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000309/2022-2023 2133/ALD 10/11/2022 30 MOYTEC 0.70 0.64 0
753 Alipurduar Division Supply of drinking water through tanker by hired vehicle to mitigate drinking water crisis at Huntapara TG, Dhumchipara TG and Gargenda TG and lankapara TG under Madarihat-Birpara Block under Alipurduar Division, PHE Dte. ORD/000309/2023-2024 2174/ALD 06/10/2023 45 BHAGWATI BHUJEL 9.82 9.82 100
754 Alipurduar Division Construction of 450cum OHR for Bhutnirghat Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000310/2021-2022 2186/ALD 11/01/2022 180 DILIP MAHATO 87.59 87.56 80
755 Alipurduar Division Soil investigation works at head works site for BANDAPANI TG AREA PWSS (ZONE-I) under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000310/2022-2023 2134/ALD 10/11/2022 30 MOYTEC 0.70 0.64 0
756 Alipurduar Division Supply of drinking water through tanker by hired vehicle to mitigate drinking water crisis at Bandapani TG under Madarihat-Birpara Block under Alipurduar Division, PHE Dte. ORD/000310/2023-2024 2175/ALD 06/10/2023 45 NARENDRA BHADANI. 3.48 3.48 100
757 Alipurduar Division Construction of 450cum OHR for Bholardabri water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000311/2021-2022 2187/ALD 11/01/2022 180 HARIDAS GHOSH 87.58 86.43 63
758 Alipurduar Division Soil investigation works at head works site for SRINATHPUR TG AREA PWSS under Alipurduar Division, PHE Dte. ORD/000311/2022-2023 2135/ALD 10/11/2022 30 MOYTEC 0.70 0.70 100
759 Alipurduar Division Construction of 350cum OHR for Putimari TG Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000312/2021-2022 2188/ALD 11/01/2022 429 TAPASH KUMAR BHOWMICK 71.40 53.44 95
760 Alipurduar Division Soil investigation works at head works site for BANDAPANI TG AREA PWSS (ZONE-2) under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000312/2022-2023 2136/ALD/ 10/11/2022 30 MOYTEC 0.66 0.61 0
761 Alipurduar Division Construction of 350cum OHR for Madhya Parokata Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000313/2021-2022 2189/ALD 11/01/2022 180 SOUVIK ROY PALADHI 71.40 32.00 96
762 Alipurduar Division Soil investigation works for proposed overhead reservoir of RAYDAK TG PWSS under Alipurduar Division, PHE Dte. ORD/000313/2022-2023 2222/ALD 21/11/2022 30 K S GROUP 0.65 0.65 0
763 Alipurduar Division Special repairing of road for providing of FHTC at Northen side of Hasimara PWSS under Alipurduar, Division, PHE Dte. ORD/000313/2023-2024 2178/ALD 06/10/2023 30 SHIB RATAN BHOWMIK 0.93 0.00 0
764 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( Reverse Rotary Method)and Rising Main for Additional T/W of BAKLA Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000314/2021-2022 2190/ALD 11/01/2022 1081 SHYAMAL ROY 21.81 10.18 100
765 Alipurduar Division Soil investigation works for proposed overhead reservoir of KOHINUR TG PWSS under Alipurduar Division, PHE Dte. ORD/000314/2022-2023 2223/ALD 21/11/2022 30 K S GROUP 0.65 0.65 16
766 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( Reverse Rotary Method) and Rising Main for Additional T/W of BANCHUKAMARI Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000315/2021-2022 2191/ALD 11/01/2022 90 HITANGSHU CHOUDHURY 21.92 19.14 56
767 Alipurduar Division Soil investigation works for proposed overhead reservoir of KARTIKA TG PWSS under Alipurduar Division, PHE Dte. ORD/000315/2022-2023 2224/ALD 21/11/2022 30 K S GROUP 0.65 0.65 0
768 Alipurduar Division Providing balance FHTC from existing distribution system as per specification for BHATPARA TG PWSS under Alipurduar Division, PHE Dte. ORD/000315/2023-2024 2185/ALD 06/10/2023 60 MAHENDRA CHHETRI 17.77 0.00 0
769 Alipurduar Division Retrofitting of pipeline for Ramjhora TG PWSS area at Madarihat-Birpara Block under Alipurduar Division, P.H.E. Dte. ORD/000316/2020-2021 1447/ALD 25/01/2021 45 ASHIT KUMAR SINGHA 16.96 3.58 58
770 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( Reverse Rotary Method) and Rising Main for Additional T/W of BIRPARA Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000316/2021-2022 2192/ALD 11/01/2022 90 DAS CONSTRUCTION 22.03 15.94 65
771 Alipurduar Division Soil investigation works for proposed overhead reservoir of PHASKHAWA TG PWSS under Alipurduar Division, PHE Dte. ORD/000316/2022-2023 2225/ALD 21/11/2022 30 K S GROUP 0.65 0.65 0
772 Alipurduar Division Providing balance FHTC from existing distribution system as per specification for BEECH TG PWSS under Alipurduar Division, PHE Dte. ORD/000316/2023-2024 2184/ALD 06/10/2023 300 D. K. & SONS 16.37 16.32 100
773 Alipurduar Division Providing House connection for JAIGAON piped water supply scheme (Old scheme Area) under Alipuduar Division, P.H.E. Dte. Part-1 ORD/000317/2020-2021 1449/ALD 25/01/2021 45 MAHENDRA CHHETRI 43.86 43.86 67
774 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( Reverse Rotary Method) and Rising Main for Additional T/W of CHANDIRJHAR Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000317/2021-2022 2193/ALD 11/01/2022 90 DULAL DAS 21.92 21.92 100
775 Alipurduar Division Gap filling in laying distribution system by making culvert crossing and laying of DI and UPVC pipes under Narathali Water Supply Scheme under Alipurduar Division, PHE Dte. (Part-A) ORD/000317/2022-2023 2226/ALD 21/11/2022 45 MADHAB SAHA 4.65 0.00 0
776 Alipurduar Division Providing House connection for JAIGAON piped water supply scheme (Old scheme Area) under Alipuduar Division, P.H.E. Dte. Part-2 ORD/000318/2020-2021 1451/ALD 25/01/2021 45 AQUEDUCT PLASTICS PVT. LTD. 43.86 43.86 90
777 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( Reverse Rotary Method) and Rising Main for Additional T/W of CHHOTO SALKUMAR Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000318/2021-2022 2194/ALD 11/01/2022 90 KAJAL KUMAR DE 21.92 19.88 46
778 Alipurduar Division Gap filling in laying distribution system by making culvert crossing and laying of DI and UPVC pipes under Narathali Water Supply Scheme under Alipurduar Division, PHE Dte. (Part-B) ORD/000318/2022-2023 2227./ALD 21/11/2022 45 HARI CONSTRUCTION 3.45 0.00 0
779 Alipurduar Division Laying of new UPVC/DI pipeline for filling of Gap in the distribution system and laying of delivery line connection, supply of CIDF specials, land development works, construction of surface drain, pathway at 3rd TW site and other allied works in connection with the Augmentation of Bholardabri PWSS under Alipurduarn Division, PHE Dte. ORD/000318/2023-2024 2410/ALD 09/11/2023 450 HARI CONSTRUCTION 30.30 16.52 100
780 Alipurduar Division Laying of DI/MS/HDPE pipe line from Nepali School (H.S.) towards Birpara Boro Houda WSS providing Functional Household Tap connection (FHTC) in connection with Jaldhara/Jal Sapna for the Birpara Boro Houda WSS under Alipurduar Division, PHE Dte.(Phase-I) ORD/000319/2020-2021 1452/ALD 25/01/2021 45 GOUTAM KUMAR DAS 43.73 42.53 87
781 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( ODEX-165 Method of drilling) and Rising Main for Additional T/W of LOKNATHPUR Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000319/2021-2022 2195/ALD 11/01/2022 90 GOUTAM KUMAR DAS 20.89 0.00 0
782 Alipurduar Division Construction of Pump House at Head Work site and providing FHTC and other allied works for Phaskhawa TG PWSS under Alipurduar Division, PHE Dte. ORD/000319/2022-2023 2228/ALD 21/11/2022 360 PRITAM DAS 9.88 6.80 51
783 Alipurduar Division Laying of Rising Main, road and culvert crossing and distribution pipeline in DALIMPUR PWSS (Zone-III) under Alipurduar Division, PHE Dte ORD/000319/2023-2024 2411/ALD 09/11/2023 240 NARENDRA BHADANI. 17.66 16.47 10
784 Alipurduar Division Laying of DI/MS/HDPE pipe line and providing Functional Household Tap connection (FHTC) in connection with Jaldhara/Jal Sapna for the Birpara Boro Houda WSS under Alipurduar Division, PHE Dte.(Phase-II) ORD/000320/2020-2021 1453/ALD 25/01/2021 45 PRAMESH LAMA 33.97 38.81 100
785 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( ODEX-165 Method of drilling) and Rising Main for Additional T/W of MADHU TG Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000320/2021-2022 2196/ALD 11/01/2022 90 NARENDRA BHADANI. 20.88 21.06 50
786 Alipurduar Division Laying of new HDPE pipe line, Construction of Pump House at Head Work Site and providing FHTC and other allied works for Raydak TG PWSS under Alipurduar Division, PHE Dte. ORD/000320/2022-2023 2229/ALD 21/11/2022 120 CREATIVE UN EMPLOYED ENGINEERSCO OPER SOCYLIMITED 13.78 6.35 61
787 Alipurduar Division Construction of platform for FHTC laying of different dia. UPVC and DI pipe line at Dakshin Sonapur PWSS and adjoining mouzas under Alipurduar Division, PHE Dte. ORD/000320/2023-2024 2415/ALD 09/11/2023 60 MADHAB SAHA 31.16 6.37 15
788 Alipurduar Division Providing House connection for BHOLARDABRI water supply scheme at ALIPURDUAR-I Block under Alipuduar Division, P.H.E. Dte.(Part-2) ORD/000321/2020-2021 1462/ALD 25/01/2021 30 HARI CONSTRUCTION 5.01 10.02 0
789 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( Reverse Rotary Method) and Rising Main for Additional T/W of TAPSHIKHATA Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000321/2021-2022 2197/ALD 11/01/2022 1116 DEBABRATA DUTTA 21.58 4.43 69
790 Alipurduar Division Laying distribution system with new UPVC pipeline and others allied works for providing functional household Tap Connection(FHTC) in connection with the Augmentation of Bakla PWSS under Alipurduar Division, PHE Dte. ORD/000321/2022-2023 2230/ALD 21/11/2022 840 PROGRESSIVE UNEMPLOYED CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 42.04 40.79 23
791 Alipurduar Division Providing balance FHTC from existing distribution system as per specification for BUXA FOREST (RAJABHATKHAWA) PWSS under Alipurduar Division, PHE Dte. ORD/000321/2023-2024 2416/ALD 09/11/2023 60 SHIB RATAN BHOWMIK 17.96 0.00 0
792 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( ODEX-165 Method of drilling) and Rising Main for Additional T/W of UTTAR MADARIHAT Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000322/2021-2022 2198/ALD 11/01/2022 90 DILIP MAHATO 20.99 15.11 72
793 Alipurduar Division Laying distribution system with new HDPE and DI pipeline, Supply of necessary specials, construction of sluice valve chamber, boundary wall at Head work site of Phaskhawa TG AREA PWSS under Alipurduar Division, PHE Dte. ORD/000322/2022-2023 2231/ALD 21/11/2022 90 SANKAR ROY 13.56 10.82 65
794 Alipurduar Division Rising Main, Laying of DI (K7), gap filling of HDPE pipe, construction of sluice valve chamber for washout purpose in the command area of NARASINGPUR PWSS under Alipurduar Division, PHE Dte. ORD/000322/2023-2024 2417/ALD 09/11/2023 60 DILIP MAHATO 36.67 35.44 80
795 Alipurduar Division Laying distribution system with new HDPE and DI pipeline, Supply of necessary specials, construction of sluice valve chamber, boundary wall at 2nd site of RAYDAK TG AREA PWSS under Alipurduar Division, PHE Dte. ORD/000323/2022-2023 2232/ALD 21/11/2022 90 ALATYA CONSTRUCTION & CO. 13.65 0.00 0
796 Alipurduar Division Tube well boring by ODEX-165 Method of drilling, Construction of Pump House, Boundary wall at proposed 3rd site of Turturi under Alipurduar Division, PHE Dte ORD/000323/2023-2024 2420/ALD 09/11/2023 431 TAPASH KUMAR BHOWMICK 17.40 11.80 70
797 Alipurduar Division Laying of balance DI/MS/HDPE pipeline for the Dalmore-Ramjhora WSS under Alipurduar Division, PHE Dte. ORD/000324/2020-2021 1456/ALD 25/01/2021 45 ASHIT KUMAR SINGHA 21.28 4.28 59
798 Alipurduar Division Laying distribution system with new HDPE and DI pipeline, Supply of necessary specials, construction of sluice valve chamber, boundary wall at 2nd site of Phaskhawa TG AREA PWSS under Alipurduar Division, PHE Dte. ORD/000324/2022-2023 2233/ALD 21/11/2022 90 RAMEN DEY & CO 9.70 9.17 94
799 Alipurduar Division Tube well boring by ODEX-165 Method of drilling, Construction of Pump House, Boundary wall at proposed 6th site of SAMUKTALA PWSS under Alipurduar Division, PHE Dte. ORD/000324/2023-2024 2421/ALD 09/11/2023 360 DULAL DAS 17.57 17.48 100
800 Alipurduar Division Laying of balance DI/MS/HDPE pipeline for Makrapara WSS under Alipurduar Division, PHE Dte. ORD/000325/2020-2021 1457/ALD 25/01/2021 45 DILIP MAHATO 13.65 19.94 85
801 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( ODEX-165 Method of drilling) and Rising Main for Additional T/W of DHAOLAJHORA TG Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000325/2021-2022 2226/ALD 14/01/2022 90 MADHAB SAHA 20.99 17.04 100
802 Alipurduar Division Laying distribution system with new HDPE and DI pipeline, Supply of necessary specials, construction of sluice valve chamber, boundary wall at Head work site of RAYDAK TG AREA PWSS under Alipurduar Division, PHE Dte. ORD/000325/2022-2023 2234/ALD 21/11/2022 90 HITANGSHU CHOUDHURY 15.63 3.73 61
803 Alipurduar Division Gap filling of HDPE pipeline at Nepania Division area under Alipurduar Division, PHE Dte. ORD/000325/2023-2024 2422/ALD 09/11/2023 60 BHAGWATI BHUJEL 5.01 5.01 100
804 Alipurduar Division Construction of Pump House ,Boundary Wall , Tube well Boring ( Reverse Rotary Method) and Rising Main for Additional T/W of MUNSHIPARA Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000326/2021-2022 2227/ALD 14/01/2022 90 TAPASH DAS 21.92 13.85 25
805 Alipurduar Division Tube well Boring by ODEX-165 method of drilling at 2nd TW site, Construction of Pump house and Boundary wall at 2nd site, Laying of Rising and delivery line connection, Providing FHTC and other allied works for KOHINUR TG PWSS under Alipurduar Division, PHE Dte. ORD/000326/2022-2023 2235/ALD 21/11/2022 120 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 96.96 53.89 56
806 Alipurduar Division Providing FHTC from existing distribution system as per specification for Dekhlapara PWSS. ORD/000326/2023-2024 2423/ALD 09/11/2023 60 SHYAMAL ROY 7.21 0.00 0
807 Alipurduar Division Providing House connection for KALCHINI water supply scheme at KALCHINI Block under Alipuduar Division, P.H.E. Dte.(Part-3) ORD/000327/2020-2021 1463/ALD 25/01/2021 30 HARI CONSTRUCTION 4.98 7.82 97
808 Alipurduar Division Extension and replacement of damaged pipeline and providing FHTC at surrounding area of Alipurduar ITI College area under Birpara PWSS. Alipurduar-I Block under Alipurduar Division, PHE Dte ORD/000327/2021-2022 2200/ALD 11/01/2022 60 DAS CONSTRUCTION 42.69 30.10 98
809 Alipurduar Division Laying of UPVC/DI/MS/CI Distribution line for gap filling and FHTC Connection in ward no. 03, 04, 07, 08, 11, 15 location of augmentation of Falakata PWSS (Zone-I AND Zone-III) under Alipurduar Division, PHE Dte. ORD/000327/2022-2023 2236/ALD/ 21/11/2022 60 NARENDRA BHADANI. 33.38 33.37 0
810 Alipurduar Division Tubewell boring by ODEX-195 method of drilling including rising main connection, repair & renovation of PH, B/wall and Main building of inspection bungalow including painting works, cons of pathway, surface drain, cons of balance civil works of annex building other allied works at Jayanti Inspection bungalow under Alipurduar Divn, PHE Dte. ORD/000327/2023-2024 2424/ALD 10/11/2023 90 TAPASH KUMAR BHOWMICK 53.99 0.00 25
811 Alipurduar Division Laying of HDPE pipe line for Bijaynagar Busty Area under Radharani Water Supply Scheme, Alipurduar Division, PHE Dte. ORD/000328/2021-2022 2201/ALD 11/01/2022 60 SOUVIK ROY PALADHI 41.96 40.39 92
812 Alipurduar Division Tube well Boring by ODEX-165 method of drilling at 2nd TW Site, Construction of Pump house at 2nd site, laying of Rising Main and delivery line connection, providing FHTC and other allied works for RAYDAK Tea Garden PWSS under Alipurduar Division, PHE Dte. ORD/000328/2022-2023 2237/ALD 21/11/2022 600 DAS CONSTRUCTION 95.24 60.93 65
813 Alipurduar Division Restoration of pipe line for Turturi Khanda (Kaijali Busty Area), Culvert crossing and Laying Delivery line with DI and MS under Kaijali Busty TG WSS under Alipurduar Division, PHE Dte. ORD/000329/2021-2022 2202/ALD 11/01/2022 60 TAPASH KUMAR BHOWMICK 41.95 39.25 66
814 Alipurduar Division Tube well Boring by ODEX-165 method of drilling at 2nd TW Site, Construction of Pump house at 2nd site, laying of Rising Main and delivery line connection, providing FHTC and other allied works for Phaskhawa Tea Garden PWSS under Alipurduar Division, PHE Dte. ORD/000329/2022-2023 2238/ALD 21/11/2022 549 ASHOK SAPKOTA 22.24 20.80 100
815 Alipurduar Division Tube well Boring by ODEX-165 method at 2nd TW Site, Cons. of Pump house and boundary wall at HW site, LDS with new HDPE pipeline (Part-B) with Rising Main and delivery line connection, providing FHTC and other allied works for Kartika Tea Garden PWSS under Alipurduar Division, PHE Dte. ORD/000330/2022-2023 2239/ALD 21/11/2022 120 TAPASH DAS 79.55 66.61 84
816 Alipurduar Division Laying of 90mm & 110 mm dia UPVC pipeline for Bholardabri Water Supply Scheme uner Alipurduar Division, PHE Dte. ORD/000331/2020-2021 1467/ALD 25/01/2021 45 HARI CONSTRUCTION 5.08 10.16 0
817 Alipurduar Division Tube well Boring by ODEX-165 method of drilling at 3rd TWsite including laying Distribution system with new HDPE Pipeline (Part-A), Providing FHTC and other allied works for augmentation of KAIJALI BUSTY PWSS under Alipurduar Division, PHE Dte. ORD/000331/2022-2023 2240/ALD 21/11/2022 600 KAMALESH ROY 70.16 60.09 68
818 Alipurduar Division Construction of boundary wall at 2nd TW site at Loknathpur WSS under Alipurduar Division PHE Dte. ORD/000333/2021-2022 2109/ALD 05/01/2022 45 GOUTAM KUMAR DAS 4.67 4.70 62
819 Alipurduar Division Cons. Of pathway, surface drain and chatal, Installation of Paver block, land development along with the other allied works at Samuktala Zone-II H/W, 2nd site and 3rd Tube well Site under Alipurduar Division, PHE Dte. ORD/000333/2023-2024 2519/ALD 24/11/2023 60 CREATIVE UN EMPLOYED ENGINEERSCO OPER SOCYLIMITED 23.26 0.00 0
820 Alipurduar Division Land Development, repairing of Pump house, construction of Pathway and protection work of 3rd TW site of Narathali PWSS under Alipurduar Divn, PHE Dte. ORD/000334/2023-2024 2520/ALD 24/11/2023 60 SREE MAA CONSTRUCTION 6.99 4.93 100
821 Alipurduar Division Construction of Pump House Boundary Wall Land development & pathway TW Boring (2nd Suite of OHR-1 ODEX 165) Raising Main for Jainti TG PWSS at Kumargram under Alipurduar Division. ORD/000335/2019-2020 2020/ALD 20/03/2020 0 DAS CONSTRUCTION 17.19 29.99 0
822 Alipurduar Division SUPPLY, INSTALLATION,COMMISSIONING AND TRIAL OPERATION OF ELECTRO MECHANICAL COMPONENTS OF RIGBORE T/W(2NOS.) FOR BANDAPANI AREA ALONG WITH CONS. OF 2NOS. P/H OF SIZE 3.00M X 3.60M ORD/000335/2020-2021 1485/ALD 27/01/2021 60 DILIP MAHATO 22.00 32.74 25
823 Alipurduar Division Laying of Rising Main line with HDPE PN 10, bridge and culvert crossing, cons. Of pathway, surface drain and chatal, Installation of Paver block, land development along with the other allied works at Sankosh TG H/W Site under Alipurduar Division, PHE Dte. ORD/000335/2023-2024 390/ALD 05/02/2024 450 K S ENTERPRISE 48.17 0.00 65
824 Alipurduar Division SUPPLY, INSTALLATION, COMMISSIONING AND TRIAL OPERATION OF ELECTRO MECHANICAL COMPONENTS OF RIGBORE T/W (1 NOS) FOR GOPALPUR TG ALONG WITH CONS. OF 1 NO. P/H OF SIZE 3.00M X 3.60M ORD/000336/2020-2021 1486/ALD 27/01/2021 60 DILIP MAHATO 11.00 16.39 78
825 Alipurduar Division Laying distribution system with new DI line & Supply of necessary specials, construction of sluice valve chamber, Construction of pump house and boundary wall at HW site of Shrinathpur TG Area PWSS under Alipurduar Division, PHE Dte. ORD/000336/2022-2023 2245/ALD 21/11/2022 120 TRIBENI CONSTRUCTION 14.48 0.00 0
826 Alipurduar Division Laying of Rising Main line with HDPE PN 10, bridge and culvert crossing, cons. Of pathway, surface drain and chatal, Installation of Paver block, land development along with the other allied works at Newlands TG H/W Site under Alipurduar Division, PHE Dte. ORD/000336/2023-2024 391/ALD 05/02/2024 450 K S ENTERPRISE 48.23 0.00 65
827 Alipurduar Division Laying distribution system with new DI line and Supply of necessary specials, construction of sluice valve chamber, Construction of pump house and boundary wall at 2nd site of Shrinathpur TG Area PWSS under Alipurduar Division, PHE Dte. ORD/000337/2022-2023 2246/ALD 21/11/2022 660 PRAPTI DUTTA 11.32 11.07 100
828 Alipurduar Division Laying of new UPVC/DI pipeline for filling of Gap in the distribution system and laying of delivery line connection, land development works, construction of surface drain, pathway, supply of CIDF specials and other allied works in connection with the Paschim Chengmari PWSS under Alipurduar Division, PHE Dte. ORD/000337/2023-2024 2523/ALD 24/11/2023 270 M/S SSB CONSTRUCTION CO. 83.57 48.17 57
829 Alipurduar Division Laying distribution system with new DI line and Supply of necessary specials, construction of sluice valve chamber, Construction of pump house and boundary wall at 2nd site of Kartika TG Area PWSS under Alipurduar Division, PHE Dte. ORD/000338/2022-2023 2247/ALD 21/11/2022 120 MONORAMA ENTERPRISE 10.80 9.70 78
830 Alipurduar Division Repairing of HW site boundary wall (40M), construction of pathway, surface drain, chatal and other misc works related to Narathali PWSS under Alipurduar Division, PHE Dte. ORD/000338/2023-2024 2524/ALD 24/11/2023 60 TAPAN CHANDA 5.33 5.33 100
831 Alipurduar Division "Providing House Connection (FHTC) at Salsalabari WSS under Alipurduar Division, PHE Dte. Part-5" ORD/000339/2021-2022 2115/ALD 05/01/2022 30 MATRI ENTERPRISE 5.04 5.04 97
832 Alipurduar Division Soil investigation works for proposed overhead reservoir of KAIJALI BUSTI PWSS under Alipurduar Division, PHE Dte. ORD/000339/2022-2023 2248/ALD 21/11/2022 30 K S GROUP 0.65 0.65 11
833 Alipurduar Division Construction of balance portion of boundary wall, pathway, surface drain and chatal, land development, laying of rising main line & delivery line connection along with the other allied works at Putimari PWSS adj. To Uttar Dhalkar PWSS under Alipurduar Division, PHE Dte. ORD/000339/2023-2024 2540/ALD 28/11/2023 90 TAPASH KUMAR BHOWMICK 25.47 20.77 100
834 Alipurduar Division Providing House Connection (FHTC) at Parokata WSS under Alipurduar Division, PHE Dte. ORD/000340/2021-2022 2116/ALD 05/01/2022 30 SREE MAA CONSTRUCTION 5.02 5.02 95
835 Alipurduar Division Laying distribution system (Part-2) and providing FHTC for BANDAPANI TG AREA PWSS (ZONE-I) under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000340/2022-2023 2249/ALD 21/11/2022 130 PRAMESH LAMA 52.84 30.31 83
836 Alipurduar Division Laying of rising main and delivery line connection, construction of boundary wall at headwork site of Samuktala Zone-I PWSS under Alipurduar Division, PHE Dte. ORD/000340/2023-2024 2541/ALD 28/11/2023 360 DIPAK DAS 28.74 18.77 100
837 Alipurduar Division Providing House Connection (FHTC) at Birpara (APD) WSS under Alipurduar Division, PHE Dte.Part-6 ORD/000341/2021-2022 2117/ALD 05/01/2022 30 DAS CONSTRUCTION 5.00 5.00 96
838 Alipurduar Division Construction of 150 cum OHR as per Departmental Design and drawing, Tube well Boring by ODEX-165 method of drilling 1 nos. respectively at H/W site, Rising main and distribution line (part-1) for BANDAPANI TG AREA PWSS (ZONE-II) under Birpara Sub-Division , Alipurduar Division, PHE Dte. ORD/000341/2022-2023 2250/ALD 21/11/2022 540 SAMIRON PODDER 88.70 85.63 85
839 Alipurduar Division Rising Main, Laying of DI (K7), gap filling of HDPE pipe, construction of sluice valve chamber for washout purpose in the command area of Malsagaon PWSS under Alipurduar Division, PHE Dte. ORD/000341/2023-2024 2542/ALD 28/11/2023 90 BHAGWATI BHUJEL 76.02 76.00 100
840 Alipurduar Division Providing House Connection (FHTC) at Birpara (APD) WSS under Alipurduar Division, PHE Dte. Part-7 ORD/000342/2021-2022 2118/ALD 05/01/2022 30 DAS CONSTRUCTION 5.00 4.38 96
841 Alipurduar Division 5 nos Tube well boring by ODEX - 165 Method of drilling for the works of augmentation of SAMUKTALA PWSS under Alipurduar Division ,PHE Dte ORD/000342/2022-2023 2221/ALD 21/11/2022 30 S.G. CONSTRUCTION 32.14 25.17 50
842 Alipurduar Division Construction of Pump House, B/wall, TW boring by ODEX-165 method of drilling and rising main for Zone-I Headwork TW Site at Augmentation od Birpara PWSS under Alipurduar Division, PHE Dte. ORD/000342/2023-2024 2543/ALD 28/11/2023 600 KAMALESH ROY 44.55 5.69 50
843 Alipurduar Division Laying of DI & HDPE pipeline, construction of sluice valve chamber, trenchless pipe, laying & other works for providing FHTC at Uttar deogaon PWSS under Birpara Sub-Division, PHE Dte. ORD/000342/2024-2025 3230/ALD 10/09/2024 60 DILIP MAHATO (OPC) PRIVATE LIMITED 43.70 0.00 0
844 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna ( for public/Govt. organisations etc. ) at JDA WSS (Zone-II) under Alipurduar Division, PHE Dte. Part-2 ORD/000343/2021-2022 2136/ALD 06/01/2022 30 D. K. & SONS 5.02 5.02 67
845 Alipurduar Division Supply of fuel for Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for inspection and monitoring of Jal Jeevan Mission (JJM) works under Alipurduar Division, P.H.E. Dte.(from 08.08.2022 to 31.10.2022) ORD/000343/2022-2023 1191/ALD 05/08/2022 92 NIRANJAN KIRTANIA 0.70 0.39 100
846 Alipurduar Division Construction of Pump House, B/wall, TW boring by ODEX-165 method of drilling and rising main for Zone-III Headwork TW Site at Augmentation of Birpara PWSS under Alipurduar Division, PHE Dte. ORD/000343/2023-2024 2544/ALD 28/11/2023 850 RATAN DUTTA 46.23 6.37 5
847 Alipurduar Division Laying of DI/HDPE distribution line, land filling at HW site, trial run and allied works at Dakshin Barajhar Forest under Aipurduar Division, PHE Dte. ORD/000343/2024-2025 3231/ALD 10/09/2024 60 DILIP MAHATO (OPC) PRIVATE LIMITED 19.62 7.92 5
848 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna ( for public/Govt. organisations etc. ) at JDA WSS (Zone-II) under Alipurduar Division, PHE Dte. Part-3 ORD/000344/2021-2022 2137/ALD 06/01/2022 30 D. K. & SONS 5.02 5.02 65
849 Alipurduar Division Continuation order of Supply of fuel for Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for inspection and monitoring of Jal Jeevan Mission (JJM) works under Alipurduar Division, P.H.E. Dte.(from 01.11.2022 to 31.01.2023) ORD/000344/2022-2023 2013/ALD 28/10/2022 92 NIRANJAN KIRTANIA 0.70 0.47 100
850 Alipurduar Division Laying leftout pipeline (not including at Lop of pipeline) at kadambini TG PWSS (Zone-I & II) under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000344/2024-2025 3233/ALD 10/09/2024 120 DILIP MAHATO (OPC) PRIVATE LIMITED 25.10 6.65 80
851 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Chandirjhar WSS under Alipurduar Division, PHE Dte. Part-4 ORD/000345/2021-2022 2138/ALD 06/01/2022 30 SASANKA ROY 5.04 5.04 49
852 Alipurduar Division Continuation for the work of Hiring of Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for inspection and monitoring of Jal Jeevan Mission (JJM) works under Alipurduar Division, P.H.E. Dte.(from 01.11.2022 to 31.01.2023) ORD/000345/2022-2023 2014/ALD 28/10/2022 92 NIRANJAN KIRTANIA 0.50 0.50 100
853 Alipurduar Division Providing FHTC from existing distribution system as per specification for Augmentation of DAKSHIN SONAPUR PWSS at Uttar Sonapur and adjoining moujas under Alipurduar Division, PHE Dte. ORD/000345/2023-2024 2546/ALD 28/11/2023 90 TULIP ENGINEERS CO-OPERATIVE SOCIETY LTD. 42.34 0.00 0
854 Alipurduar Division Sinking of one no. Big dia Tube Well (250 x 200 x 150 mm dia 270mtr) by Modified DTH - ODEX method of Cha-Sundori Project (JJM- SM/10054) within Lankapara Tea Garden Area Piped Water Supply Scheme, Madarihat-Birpara block of Birpara Sub-Division under Alipurduar Division, PHE Dte. ORD/000345/2024-2025 3339/ALD 20/09/2024 105 EFFLUENT AND WATERTREATMENT ENGINEERS PVT LTD 32.35 25.90 51
855 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Chandirjhar WSS under Alipurduar Division, PHE Dte. Part-5 ORD/000346/2021-2022 2139/ALD 06/01/2022 30 SASANKA ROY 5.04 5.04 49
856 Alipurduar Division Laying of HDPE pipeline for restoration of damaged pipeline and others allied works for Jainty WSS under Alipurduar Division, PHE Dte. ORD/000346/2022-2023 2490/ALD 13/12/2022 30 TAPASH KUMAR BHOWMICK 2.14 2.14 64
857 Alipurduar Division Continuation order for the work of "Collection of house hold details at prescribed format through mobile app/Hard Copy including Geo-reference as directed by the E.I.C. and submission the same to PHE Dte. (in soft copy) Part-B" ORD/000346/2024-2025 3424/ALD 26/09/2024 181 TAPASH KUMAR BHOWMICK 4.67 1.24 100
858 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Bholardabri WSS under Alipurduar Division, PHE Dte. Part-11 ORD/000347/2021-2022 2140/ALD 06/01/2022 30 HARIDAS GHOSH 5.04 5.04 64
859 Alipurduar Division Construction of pump house, Boundary Wall, Tube well Boring (ODEX-165 method), rising main of 3rd TW site of Rahimabad WSS under Alipurduar Division, PHE Dte. ORD/000347/2022-2023 2493/ALD 13/12/2022 120 DULAL DAS 23.52 14.88 27
860 Alipurduar Division Laying of new UPVC/DI pipeline for filling of gap in the distribution system and laying of delivery line connection, providing FHTC, land development cons. Of surface drain, pathway and other allied work in connection with the Uttar Kamakhyaguri PWSS under Alipurduar Division, PHE Dte. ORD/000347/2023-2024 2564/ALD 29/11/2023 540 DEBAJYOTI SUTRADHAR 46.90 5.15 65
861 Alipurduar Division Continuation for the work of "Entry of data for house Connection (JJM) of PWSS in website under Alipurduar division, PHE Dte. " ORD/000347/2024-2025 3425/ALD 26/09/2024 181 TAPASH KUMAR BHOWMICK 4.29 0.00 100
862 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Bholardabri WSS under Alipurduar Division, PHE Dte. Part-12 ORD/000348/2021-2022 2141/ALD 06/01/2022 60 HARIDAS GHOSH 5.04 4.66 65
863 Alipurduar Division Tube well boring by ODEX-195 Method of drilling, Construction of 1no. of Pump house, boundary wall an distribution line with FHTC for Augmentation of NEPANIA PWSS under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000348/2022-2023 2489/ALD 13/12/2022 120 BHAGWATI BHUJEL 59.01 42.45 80
864 Alipurduar Division Laying of UPVC / DI pipeline for filling of Gap in the distribution system and laying of delivery line connection, Land Development works, Construction of surface drain, supply of CIDF specials and other allied works in connection with the Birpara(APD) PWSS under Alipurduar Division, PHE Dte. ORD/000348/2023-2024 2600/ALD 04/12/2023 540 DAS CONSTRUCTION 38.10 0.00 30
865 Alipurduar Division Laying of new UPVC/DI pipeline for interconnection in the distribution system, fixing of FHTC by means of PCC Concrete Block and others allied works in connection with the Purba Narathali (SM/16537) PWSS under Alipurduar Division, PHE Dte. ORD/000348/2024-2025 3418/ALD 26/09/2024 60 MADHAB SAHA 57.80 0.00 0
866 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Tapshikhata WSS under Alipurduar Division, PHE Dte. Part-5 ORD/000349/2021-2022 2142/ALD 06/01/2022 30 DEBAJYOTI SUTRADHAR 5.02 5.02 52
867 Alipurduar Division Land development, construction of pathway of HWS and 2nd site of different sluice valve chamber and concrete blocks for MS pipe Jainti TG (Nimbu Dhora) WSS under Alipurduar Division, PHE Dte. ORD/000349/2022-2023 2491/ALD 13/12/2022 60 DAS CONSTRUCTION 9.41 0.00 0
868 Alipurduar Division Laying of new UPVC / DI pipeline for filling of Gap in the distribution system and laying of delivery line connection, Land Development works, Construction of surface drain, supply of CIDF specials and other allied works in connection with the Brajerkuti PWSS under Alipurduar Division, PHE Dte. ORD/000349/2023-2024 2601/ALD 04/12/2023 404 TAPASH KUMAR BHOWMICK 77.06 52.52 25
869 Alipurduar Division CONSTRUCTION OF PUMP HOUSE and BOUNDARY WALL FOR ADDITIONAL TUBEWELL and LAYING DISTRIBUTION SYSTEM FOR PROVIDING FHTC AND LAND DEVELOPMENT AT HW SITE and 2ND SITE AT MADHYA KHAIRBARI PWSS WITHIN MADARIHAT-BIRPARA BLOCK. ORD/000349/2024-2025 3419/ALD 26/09/2024 240 MITHUN DAS 64.12 0.00 50
870 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Tapshikhata WSS under Alipurduar Division, PHE Dte. Part-6 ORD/000350/2021-2022 2143/ALD 06/01/2022 30 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 5.03 3.02 76
871 Alipurduar Division Land development, construction of pathway of HWS and culvert crossing with DI pipe under Kumargram TG WSS under Alipurduar Division, PHE Dte. ORD/000350/2022-2023 2492/ALD 13/12/2022 90 HARIDAS GHOSH 12.45 12.33 43
872 Alipurduar Division Construction of Pump House, B/wall, TW boring by ODEX-165 method of drilling and rising main for Zone-I 3rd TW Site at Augmentation of Birpara PWSS under Alipurduar Division, PHE Dte. ORD/000350/2023-2024 2602/ALD 04/12/2023 482 FAUDA SINGH CHHETRI 31.46 18.97 61
873 Alipurduar Division Laying of DI & HDPE pipeline, construction of sluice valve chamber, trenchless pipe, laying & other works for providing FHTC at Paschim deogaon PWSS under Birpara Sub-Division, PHE Dte. ORD/000350/2024-2025 3420/ALD 26/09/2024 60 SOUVIK ROY PALADHI 35.92 0.00 0
874 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Bakla WSS under Alipurduar Division, PHE Dte. Part-5 ORD/000351/2021-2022 2150/ALD 06/01/2022 30 SHIB RATAN BHOWMIK 4.99 4.99 73
875 Alipurduar Division Development of TW, Yield testing with BHT Pump and water sample collection and chemical test at different tubewell of Purba Kathal Bari PWSS at Alipurduar-I Block, Alipurduar Division PHED. ORD/000351/2022-2023 2495/ALD 13/12/2022 60 SAMIRON PODDER 5.68 0.00 0
876 Alipurduar Division Laying of new UPVC / DI pipeline for filling of Gap in the distribution system and laying of delivery line connection, Land Development works, Construction of surface drain, supply of CIDF specials and other allied works in connection with the Bakla PWSS under Alipurduar Division, PHE Dte. ORD/000351/2023-2024 2603/ALD 04/12/2023 90 SHYAMAL ROY 32.04 4.74 50
877 Alipurduar Division Laying of CIDI Pipes & UPVC pipeline and other allied works for Atiabari Tea Garden PWSS under ALipurduar Division, PHE Dte. ORD/000351/2024-2025 3421/ALD 26/09/2024 60 SOUVIK ROY PALADHI 35.90 0.00 0
878 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Bakla WSS under Alipurduar Division, PHE Dte. Part-6 ORD/000352/2021-2022 2151/ALD 06/01/2022 30 PROGRESSIVE UNEMPLOYED CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 5.00 5.00 73
879 Alipurduar Division Construction of river bank protection wall with wire create and land filling near 3 No. PHE pump house at SK Line under Lankapara GP within Madarihat-Birpara Block under Alipurduar Division, PHE Dte. ORD/000352/2022-2023 2496/ALD 13/12/2022 90 RATAN DUTTA 1.31 1.17 100
880 Alipurduar Division Construction of intake structure ground level reservoir, boundary wall, Pump House, laying of distribution network and providing FHTC under Augmentation of Totopara PWSS under Alipurduar Division, PHE Dte. ORD/000352/2023-2024 2604/ALD 04/12/2023 600 DULAL DAS 63.10 12.27 35
881 Alipurduar Division Laying of new UPVC/DI pipeline for interconnection in the distribution system and bridge/culvert crossing in connection with the FHTC, fixing of FHTC by means of PCC concrete block fixing of FHTC by mean of PCC concrete block at Samuktalata Zone-II PWSS under Alipurduar Division, PHE Dte. (SM/12561) ORD/000352/2024-2025 3422/ALD 26/09/2024 521 KAMALESH ROY 75.37 0.00 80
882 Alipurduar Division Construction of 200 cum OHR as per Departmental Design and drawing at KAIJALI BUSTY PWSS under Alipurduar Division, PHE Dte. ORD/000353/2022-2023 2497/ALD 13/12/2022 540 MAHENDRA CHHETRI 68.63 66.32 70
883 Alipurduar Division Gap filling by DI and HDPE pipeline in Jagijhora Barabak PWSS under Alipurduar Division, PHE Dte. ORD/000353/2023-2024 2605/ALD 04/12/2023 240 MONORAMA ENTERPRISE 9.99 8.79 80
884 Alipurduar Division Laying of new UPVC/DI pipeline for interconnection in the distribution system and other allied works under Bholardabri PWSS, Alipurduar Division, PHE Dte. (SM/09883) ORD/000353/2024-2025 3423/ALD 26/09/2024 180 TAPASH DAS 20.57 0.00 70
885 Alipurduar Division Laying of HDPE pipeline & other misc work related to Jayanti WSS under Alipurduar Division, PHE Dte. ORD/000354/2021-2022 2119/ALD 05/01/2022 30 TAPASH KUMAR BHOWMICK 4.28 3.87 71
886 Alipurduar Division 2 nos Tube well boring by ODEX-165 Method of drilling for the works implementation of Shrinathpur Tea Garden Area PWSS under Alipurduar Division, PHE Dte. ORD/000354/2022-2023 2499/ALD 13/12/2022 45 S.G. CONSTRUCTION 13.14 10.24 0
887 Alipurduar Division Construction of slab culvert, pathway and other allied works at 3rd TW Site, painting existing boundary wall, pump house, roof treatment, plinth protection at 2nd TW site of Chhoto Salkumar WSS adjacent to Mairadanga PWSS including gap filling in distribution line (90mm dia) under Alipurduar Division, PHE Dte. ORD/000354/2023-2024 2606/ALD 04/12/2023 692 ASSOCIATE CONSTRUCTION COMPANY 23.88 0.00 95
888 Alipurduar Division Fabrication,Erection of Signage (268 nos) of Pump house/OHR site democration with in Kumargram, Falakata,Madarihat-Birpara Block for Different PWSS of JJM Project Under Alipurduar Division P.H.E.Dte. ORD/000354/2024-2025 3520/ALD 04/10/2024 330 LIMRA SOCIAL WELFARE SOCIETY 31.26 7.09 92
889 Alipurduar Division Restoration of laying distribution system by replacing of damaged AC pipeline with UPVC pipe at Bhatibari WSS under Alipurduar Division PHE Dte. ORD/000355/2021-2022 2120/ALD 05/01/2022 30 SREE MAA CONSTRUCTION 4.95 4.66 0
890 Alipurduar Division Laying distribution system with new UPVC pipeline, providing FHTC and other allied works for Samuktala Zone-II PWSS under Alipurduar Division, PHE Dte. ORD/000355/2022-2023 2500/ALD 13/12/2022 120 TAPASH KUMAR BHOWMICK 88.46 80.56 50
891 Alipurduar Division Fabrication,Erection of Signage (135 nos) of Pump house/OHR site democration with in Alipurduar-II and Kalchini Block for Different PWSS of JJM Project Under Alipurduar Division P.H.E.Dte. ORD/000355/2024-2025 3442/ALD 27/09/2024 196 M/S SARKAR & CO 14.84 6.82 100
892 Alipurduar Division soil investigation work at 4 different places of Alipurduar District under Alipurduar Division PHE Dte. Part-1 Places : 1)Uttar Kamakhyaguri 2)Uttar Majherdabri. 3)Bholardabri. 4) Narathali. ORD/000356/2021-2022 2121/ALD 05/01/2022 30 MOYTEC 4.90 4.90 69
893 Alipurduar Division Laying distribution system with new UPVC pipeline, providing FHTC and other allied works for Samuktala Zone-III PWSS under Alipurduar Division, PHE Dte. ORD/000356/2022-2023 2501/ALD 13/12/2022 120 MADHAB SAHA 93.21 81.56 49
894 Alipurduar Division Fabrication,Erection of Signage (127 nos) of Pump house/OHR site democration with in Alipurduar-I Block for Different PWSS of JJM Project Under Alipurduar Division P.H.E.Dte. ORD/000356/2024-2025 3443/ALD 27/09/2024 15 M/S SARKAR & CO 13.95 13.73 100
895 Alipurduar Division Laying of DI/MS/HDPE Pipe line for the Dimdima Zone-II and Nangdala Extension, Dimdima WSS under Alipurduar Division, PHE Dte. ORD/000357/2020-2021 1795/ALD 22/02/2021 60 DILIP MAHATO 31.27 51.07 87
896 Alipurduar Division Laying distribution system with new UPVC pipeline, Construction of 2 Nos Pump House ,Pipe Support Structure, Land Development, Boundary Wall, Path way, Providing FHTC, and other allied works for Gram Busty Area Under 28 & 29 Mile Basty (Zone-IV) PIPED WATER SUPPLY SCHEME under Alipurduar Division, PHE Dte. ORD/000357/2023-2024 2608/ALD 04/12/2023 420 HITANGSHU CHOUDHURY 70.82 14.23 45
897 Alipurduar Division Laying of HDPE pipe line for Madarihat Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000358/2021-2022 2284/ALD 21/01/2022 60 DILIP MAHATO 37.73 35.81 97
898 Alipurduar Division Interconnection of distribution system by laying of DI pipe resting over RCC pillars/hanging support by M.S. Structural works to cross Gadhadhar River and other allied works at Bhatibari PWSS under Alipurduar Division, PHE Dte.(SM/14096) ORD/000358/2024-2025 3521/ALD 04/10/2024 90 DEBAJYOTI SUTRADHAR 5.34 1.32 100
899 Alipurduar Division Laying of HDPE pipe line for Madarihat Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000359/2021-2022 2285/ALD 21/01/2022 60 MAHENDRA CHHETRI 37.73 32.37 99
900 Alipurduar Division Laying of new UPVC / DI pipeline for filling of Gap in the distribution system and laying of delivery line connection, Land Development works, Construction of surface drain, supply of CIDF specials and other allied works in connection with the Salsalabari PWSS under Alipurduar Division, PHE Dte. ORD/000359/2023-2024 2745/ALD 14/12/2023 420 MATRI ENTERPRISE 16.16 0.00 100
901 Alipurduar Division Laying of Distribution Line (HDPE and DI) for retrofitting of FHTC for BIRPARA WSS under Alipurduar Division, PHE Dte. ORD/000360/2020-2021 1754/ALD 19/02/2021 45 BILTU DAS 47.98 41.91 61
902 Alipurduar Division soil investigation work at 4 different places of Alipurduar District under Alipurduar Division PHE Dte. Part-2 Venue: 1) Jogijhora 2)Jateswar 3)Gopalpur 4)Madhya Parokata ORD/000360/2021-2022 2122/ALD 05/01/2022 30 MOYTEC 4.90 4.90 26
903 Alipurduar Division Providing FHTC from existing distribution system as per specification for Augmentation of DAKSHIN SONAPUR PWSS at Kumarpara and adjoining moujas under Alipurduar Division, PHE Dte. ORD/000360/2023-2024 2746/ALD 14/12/2023 60 KAMALESH ROY 34.00 0.00 0
904 Alipurduar Division Soil investigation work at 4 different places of Alipurduar District under Alipurduar Division PHE Dte. Part-3 VENUE : 1)Chuniajhora TG 2) Dakshin Paitkapara 3)Jay Birpara 4) Bhutnirghat ORD/000361/2021-2022 2123/ALD 05/01/2022 30 R B TESTING 4.86 4.86 67
905 Alipurduar Division Soil investigation work at 4 different places of Alipurduar District under Alipurduar Division PHE Dte. Part-4 Venue : Putimari 2)Mechpara 3)Mathura 4)Gangutia. ORD/000362/2021-2022 2124/ALD 05/01/2022 30 MABCO CONSULTANT, 4.86 4.86 94
906 Alipurduar Division Soil investigation work at 4 different places of Alipurduar District under Alipurduar Division PHE Dte. Part-5 Venue : 1)Madarihat (1 no.) 2)Mujnai (2 nos) 3)Sidhabari (1 no.) ORD/000363/2021-2022 2125/ALD 05/01/2022 30 G. MITRA & ASSOCIATES, 4.90 4.90 50
907 Alipurduar Division Providing House connection at LANKAPARA TG (Part-A) PWSS under Alipuduar Division, P.H.E. Dte. ORD/000364/2020-2021 1807/ALD 22/02/2021 920 GHOSH & SAHA CONSTRUCTION 41.88 10.17 50
908 Alipurduar Division Extension and replacement of damaged pipeline and providing FHTC at surrounding area of Putimari PWSS, Alipurduar Block under Alipurduar Division, PHE Dte. ORD/000364/2021-2022 2291/ALD 24/01/2022 1200 HARI CONSTRUCTION 45.52 42.55 100
909 Alipurduar Division Providing House connection for MADARI ROAD/ PARANGERPAR, FALAKATA AUG. PWSS ZONE-I under Alipuduar Division, P.H.E. Dte. ORD/000365/2020-2021 1758/ALD 19/02/2021 60 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 39.97 48.77 63
910 Alipurduar Division Gap filling in main and branch road of Nabanagar area by HDPE/DI pipe as required under Pashchim Deogaon PWSS under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000365/2023-2024 81/ALD 10/01/2024 90 SOUVIK ROY PALADHI 38.20 0.00 0
911 Alipurduar Division Providing House connection for RABINDRANAGAR, FALAKATA AUG. PWSS ZONE-III under Alipuduar Division, P.H.E. Dte. ORD/000366/2020-2021 1759/ALD 19/02/2021 1320 BILTU DAS 39.46 30.30 86
912 Alipurduar Division Laying of DI & HDPE pipeline, construction of valve chamber and other works for Tulshipara TG at Lonkapara PWSS, Birpara Sub-Division, PHE Dte. ORD/000366/2023-2024 82/ALD 10/01/2024 135 SUBIR GHOSH 6.78 3.19 10
913 Alipurduar Division Providing House connection for DESHBANDHUPARA, FALAKATA AUG. PWSS ZONE-III under Alipurduar Division, P.H.E. Dte. ORD/000367/2020-2021 1760/ALD 19/02/2021 60 ASHIT KUMAR SINGHA 40.25 40.25 65
914 Alipurduar Division Extension and replacement of damaged pipeline and providing FHTC at Uttar Kashigram area under Sonapur PWSS under Alipurduar Division, Division, PHE Dte. ORD/000367/2021-2022 2295/ALD 24/01/2022 1500 NARENDRA BHADANI. 45.29 24.47 18
915 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling including Rising Main at Bhatibari Zone-II PWSS Under Alipurduar Division PHE DTE ORD/000367/2022-2023 2611/ALD/ 21/12/2022 630 RATAN DUTTA 24.73 18.96 60
916 Alipurduar Division Construction of pump house, boundary wall, TW boring (by ODEX-165 method of drilling) and Rising main for 2nd TW site at Bandapani PWSS (Zone-II) under Alipurduar Division, PHE Dte. ORD/000367/2023-2024 83/ALD 10/01/2024 240 MITHUN DAS 24.21 19.15 85
917 Alipurduar Division Providing House connection for SOUTH FALAKATA AREA, FALAKATA AUG. PWSS ZONE-III under Alipuduar Division, P.H.E. Dte. ORD/000368/2020-2021 1761/ALD 19/02/2021 60 HARIDAS GHOSH 40.13 62.80 66
918 Alipurduar Division Construction of 1no. Boundary Wall and 2nos. Tube well Boring by Reverse Rotary Method of drilling for BHATIBARI ZONE-III and ZONE-IV PWSS Under Alipurduar Division PHE DTE. ORD/000368/2022-2023 2612/ALD 21/12/2022 540 AASHIRBAD ENTERPRISE 24.63 23.93 100
919 Alipurduar Division Laying of rising main line with HDPE PN10, horizontal boring by HDD method , bridge and culvert crossing, construction of pathway, surface drain and chatal, installation of paver block, land development along with the other allied works at NURPUR HW site PWSS under Alipurduar Division, PHE Dte. ORD/000368/2023-2024 84/ALD 10/01/2024 90 BENGAL YOUTH UN EMPLOYED ENGINEERS CO OPERATIVE SOCIETY LIMITED 33.28 0.00 0
920 Alipurduar Division Extension and replacement of damaged pipeline and providing FHTC at surrounding area of North side of Pukuritola area under Tapshikatha PWSS. Alipurduar-I Block under Alipurduar Division, PHE Dte. ORD/000369/2021-2022 2292/ALD 24/01/2022 60 DEBAJYOTI SUTRADHAR 26.52 24.90 78
921 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Bhatibari PWSS under Alipurduar Division, PHE Dte. Part-6 ORD/000369/2022-2023 2613/ALD 21/12/2022 211 TAPASH KUMAR BHOWMICK 34.47 24.13 70
922 Alipurduar Division Laying of rising main line with HDPE PN10, horizontal boring by HDD method , bridge and culvert crossing, Supply of DI pipe and specials, construction of pathway, surface drain and chatal, installation of paver block, land development along with the other allied works at MARAKHATA HW site PWSS under Alipurduar Division, PHE Dte. ORD/000369/2023-2024 85/ALD 10/01/2024 360 HARIDAS GHOSH 65.13 42.19 35
923 Alipurduar Division Providing House connection for BIRPARA PWSS, MADARIHAT-BIRPARA Block under Alipuduar Division, P.H.E. Dte ORD/000370/2020-2021 1766/ALD 19/02/2021 60 BILTU DAS 39.46 33.54 83
924 Alipurduar Division Extension and replacement of damaged pipeline and providing FHTC at surrounding area of Kamakhyaguri PWSS, Kumargram Block under Alipurduar Division, PHE Dte. ORD/000370/2021-2022 2289/ALD 24/01/2022 60 GOUTAM KUMAR DAS 27.39 8.81 93
925 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Bhatibari PWSS under Alipurduar Division, PHE Dte. Part-7 ORD/000370/2022-2023 2614/ALD 21/12/2022 45 HARIDAS GHOSH 34.76 13.04 21
926 Alipurduar Division Laying of DI & HDPE pipeline, River and road crossing construction of valve chamber, community water tank and other misc. works for Lonkapara PWSS, Birpara Sub-Division, PHE Dte. ORD/000370/2023-2024 86/ALD 10/01/2024 90 SUDDHYA SING LAMA 27.70 0.00 0
927 Alipurduar Division Providing House connection for BHOLARDABRI PWSS under Alipuduar Division, P.H.E. Dte. ORD/000371/2020-2021 1767/ALD 19/02/2021 60 HARIDAS GHOSH 10.03 20.07 0
928 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Bhatibari PWSS under Alipurduar Division, PHE Dte. Part-8 ORD/000371/2022-2023 2615/ALD 21/12/2022 45 GOUTAM KUMAR DAS 34.60 0.00 0
929 Alipurduar Division Laying of rising main line with HDPE PN10, horizontal boring by HDD method , bridge and culvert crossing, construction of pathway, surface drain and chatal, installation of paver block, land development along with the other allied works at PURBA NARATHALI HW site PWSS under Alipurduar Division, PHE Dte. ORD/000371/2023-2024 87/ALD 10/01/2024 90 MADHAB SAHA 34.86 16.14 45
930 Alipurduar Division Retrofitting and Extension of pipeline for Kalchini area under DIMA PWSS at Kalchini Block under Alipurduar Division. PHE Dte. Part-A ORD/000372/2020-2021 1768/ALD 19/02/2021 60 SUNDAR SING LAMA 41.98 0.00 86
931 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna ( for AWC, school & public/Govt. organisations etc. ) at JDA WSS (Existing) under Alipurduar Division, PHE Dte. ORD/000372/2021-2022 2154/ALD 06/01/2022 30 MAHENDRA CHHETRI 5.02 5.02 62
932 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Bhatibari PWSS under Alipurduar Division, PHE Dte. Part-9 ORD/000372/2022-2023 2616/ALD 21/12/2022 45 TAPASH KUMAR BHOWMICK 34.47 0.00 0
933 Alipurduar Division Retrofitting and Extension of pipeline for Kalchini area under DIMA PWSS at Kalchini Block under Alipurduar Division. PHE Dte. Part-B ORD/000373/2020-2021 1769/ALD 19/02/2021 60 RAMESH SHARMA 49.52 12.89 93
934 Alipurduar Division Providing House Connection (FHTC) at Bhatibari WSS under Alipurduar Division, PHE Dte.Part-4 ORD/000373/2022-2023 2619/ALD 21/12/2022 30 SREE MAA CONSTRUCTION 5.02 4.88 21
935 Alipurduar Division Providing House Connection (FHTC) at Bhatibari WSS under Alipurduar Division, PHE Dte.Part-5 ORD/000374/2022-2023 2620/ALD 21/12/2022 30 DEBAJYOTI SUTRADHAR 5.02 5.02 22
936 Alipurduar Division Laying of HDPE pipeline for Malangi Tea Garden Area within Hasimara Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000375/2021-2022 2375/ALD 31/01/2022 60 MADHAB SAHA 74.82 74.67 94
937 Alipurduar Division Laying distribution pipe line by DI pipe (with pillar) along the flank of Alipurduar-Bhatibari PWD Road (From Charmile to Bhatibari) of Bhatibari WSS under Alipurduar Division, PHE Dte. ORD/000375/2022-2023 2621/ALD 21/12/2022 553 DEBAJYOTI SUTRADHAR 28.20 23.43 83
938 Alipurduar Division Laying of HDPE pipeline for New Hasimara Area within Hasimara Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000376/2021-2022 2376/ALD 31/01/2022 60 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 73.83 58.99 99
939 Alipurduar Division Soil investigation work at 4 different places of Bhatibari within Alipurduar District under Alipurduar Division PHE Dte. ORD/000376/2022-2023 2622/ALD 21/12/2022 30 R B TESTING 4.86 0.00 0
940 Alipurduar Division Extension and replacement of damaged pipeline and providing FHTC at Satkodali and surrounding area of Banchukamari PWSS. Alipurduar-I Block under Alipurduar Division, PHE Dte ORD/000377/2021-2022 2377/ALD 31/01/2022 60 MATRI ENTERPRISE 56.50 40.70 0
941 Alipurduar Division Extension and replacement of damaged pipeline and providing FHTC at surrounding area of Banchukamari PWSS. Alipurduar-I Block under Alipurduar Division, PHE Dte. ORD/000378/2021-2022 2378/ALD 31/01/2022 60 SHIBA ENTERPRISE 51.82 9.81 87
942 Alipurduar Division Providing House connection for DALSINGPARA, JAIGAON DEVLOPMENT AREA ZONE-5A under Alipurduar Division, P.H.E. Dte. ORD/000379/2020-2021 1762ALD 19/02/2021 60 AQUEDUCT PLASTICS PVT. LTD. 40.17 80.34 0
943 Alipurduar Division Construction of Pump House, Boundary Wall, laying distribution system and providing FHTC for BHUTNIRGHAT Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000379/2021-2022 2379/ALD 31/01/2022 90 DILIP MAHATO 92.34 91.26 98
944 Alipurduar Division Providing House connection for JAIGAON DEVLOPMENT AREA ZONE-5B under Alipurduar Division, P.H.E. Dte. ORD/000380/2020-2021 1763ALD 19/02/2021 60 AQUEDUCT PLASTICS PVT. LTD. 40.17 40.17 0
945 Alipurduar Division Laying of UPVC pipeline and Tube well Boring by Reverse Rotary method of drilling for BHUTNIRGHAT Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000380/2021-2022 2380/ALD 31/01/2022 60 DILIP MAHATO 95.15 94.85 97
946 Alipurduar Division Laying of new UPVC/DI pipeline for interconnection in the distribution system and bridge/culvert crossing in connection with the FHTC, fixing of FHTC by means of PCC concrete block fixing of FHTC by mean of PCC concrete block at Samuktalata Zone-III PWSS under Alipurduar Division, PHE Dte. (SM/12561) ORD/000380/2024-2025 3774/ALD 13/11/2024 90 DAS CONSTRUCTION 60.38 0.00 0
947 Alipurduar Division Providing FHTC including Rising main and laying of distribution pipeline for BHUTNIRGHAT Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000381/2021-2022 2381/ALD 31/01/2022 1300 DILIP MAHATO 89.08 64.50 94
948 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe along with FHTC Connection of BHATIBARI ZONE-I WSS under Alipurduar Division, PHE Dte. (Part-A) ORD/000381/2022-2023 2627/ALD/ 21/12/2022 60 SHIBA ENTERPRISE 100.55 73.39 72
949 Alipurduar Division Sinking of 250mm x 200 mmx 150 mtr big dia Tubewell by Reverse rotary drilling method at Purba barachauki Area for Augmentation of Bhatibari PWSS under Alipurduar Division, PHE Dte. ORD/000381/2024-2025 3775/ALD 13/11/2024 150 DAS CONSTRUCTION 11.48 0.00 100
950 Alipurduar Division Providing House connection for existing PWSS, JAIGAON DEVLOPMENT AREA ZONE- 1 and 2 under Alipurduar Division, P.H.E. Dte. ORD/000382/2020-2021 1765/ALD 19/02/2021 60 MAHENDRA CHHETRI 40.23 40.23 63
951 Alipurduar Division Construction of Pump House ,Boundary Wall and Providing FHTC including Laying of UPVC pipeline and Tube well Boring by ODEX-165 Method of drilling for Bholardabri PWSS under Alipurduar Division PHE DTE. ORD/000382/2021-2022 2382/ALD 31/01/2022 1080 HARIDAS GHOSH 82.30 46.48 80
952 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe along with FHTC Connection of BHATIBARI ZONE-II WSS under Alipurduar Division, PHE Dte. (Part-A) ORD/000382/2022-2023 2628/ALD/ 21/12/2022 148 TAPASH KUMAR BHOWMICK 100.89 76.17 50
953 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe along with FHTC Connection of BHATIBARI ZONE-I WSS under Alipurduar Division, PHE Dte. (Part-B) ORD/000383/2022-2023 2629/ALD/ 21/12/2022 60 MATRI ENTERPRISE 100.29 92.25 87
954 Alipurduar Division Laying of UPVC pipeline and Tube well Boring by ODEX-165 Method of drilling for Madhya Parokata Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000384/2021-2022 2384/ALD 31/01/2022 60 SOUVIK ROY PALADHI 96.14 101.62 95
955 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe along with FHTC Connection of BHATIBARI ZONE-II WSS under Alipurduar Division, PHE Dte. (Part-B) ORD/000384/2022-2023 2630/ALD 21/12/2022 840 HARIDAS GHOSH 98.45 80.75 18
956 Alipurduar Division Construction of boundary wall, Pump house, TW, Rising main for Gargenda PWSS under Alipurduar Division, PHE Dte. ORD/000384/2023-2024 196/ALD 16/01/2024 120 DILIP MAHATO 27.12 0.00 0
957 Alipurduar Division Providing FHTC including Rising main for Madhya Parokata Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000385/2021-2022 2385/ALD 31/01/2022 60 SOUVIK ROY PALADHI 74.19 64.79 94
958 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe along with FHTC Connection of BHATIBARI ZONE-IV WSS under Alipurduar Division, PHE Dte. (Part-A) ORD/000385/2022-2023 2631/ALD 21/12/2022 60 DEBAJYOTI SUTRADHAR 75.53 61.22 20
959 Alipurduar Division Providing House connection for MADARIHAT PWSS under Alipuduar Division, P.H.E. Dte. ORD/000386/2020-2021 1806/ALD 22/02/2021 60 DILIP MAHATO 20.13 20.13 90
960 Alipurduar Division Construction of Pump House, Boundary Wall and laying distribution system for PUTIMARI Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000386/2021-2022 2386/ALD 31/01/2022 90 TAPASH KUMAR BHOWMICK 93.77 93.18 96
961 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe along with FHTC Connection of BHATIBARI ZONE-IV WSS under Alipurduar Division, PHE Dte. (Part-B) ORD/000386/2022-2023 2632/ALD 21/12/2022 780 KAMALESH ROY 74.77 65.08 87
962 Alipurduar Division Construction of boundary wall, Pump house, TW, Rising main for Gargenda (Near Dukhiya Line) PWSS under Alipurduar Division, PHE Dte. ORD/000386/2023-2024 197/ALD 16/01/2024 600 MANI PRADHAN 27.78 0.00 70
963 Alipurduar Division CONS. OF BOUNDARY WALL (80 m), PUMPHOUSE( 1.Nos) ,TUBEWELL (2 Nos.), RISING MAIN AND DISTRIBUTION LINE FOR MUJNAI T.G (All Other Division & Line 60 unit) CHA SUNDARI WATER SUPPLY SCHEME UNDER ALIPURDUAR DIVISION PHE DTE. ORD/000387/2020-2021 1946/ALD 25/02/2021 840 GHOSH & SAHA CONSTRUCTION 36.68 29.51 100
964 Alipurduar Division Laying of UPVC pipeline and Tube well Boring by ODEX-165 Method of drilling for PUTIMARI Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000387/2021-2022 2387/ALD 31/01/2022 60 TAPASH KUMAR BHOWMICK 76.84 75.28 97
965 Alipurduar Division Laying distribution pipe with DI and UPVC pipe of Chilurghat, Bhatibari area under Bhatibari Zone-III WSS under Alipurduar Division, PHE Dte.(Part-I) ORD/000387/2022-2023 2633/ALD 21/12/2022 60 DAS CONSTRUCTION 98.50 86.88 88
966 Alipurduar Division Laying of new UPVC/DI pipeline for filling of Gap in the distribution system and laying of delivery line connection, land development works, construction of surface drain, pathway, supply of CIDF specials and other allied works in connection with the PURBA CHIKLIGURI PIPED WATER SUPPLY SCHEME under Alipurduar Division, PHE Dte. ORD/000387/2023-2024 198/ALD 16/01/2024 450 SOUVIK ROY PALADHI 60.36 43.39 5
967 Alipurduar Division CONS. OF RESERVOIR (100M3), BOUNDARY WALL (80 m), PUMPHOUSE( 1.Nos) ,TUBEWELL (2 Nos.), RISING MAIN AND DISTRIBUTION LINE FOR MUJNAI T.G (All Other Division & Line 475 unit) CHA SUNDARAI WATER SUPPLY SCHEME UNDER ALIPURDUAR DIVISION PHE DTE. ORD/000388/2020-2021 1947/ALD 25/02/2021 812 BILTU DAS 113.04 82.72 80
968 Alipurduar Division Providing FHTC including Rising main and laying distribution system for PUTIMARI Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000388/2021-2022 2388/ALD 31/01/2022 60 HARI CONSTRUCTION 71.64 68.88 94
969 Alipurduar Division Laying distribution pipe with DI and UPVC pipe of Chilurghat, Kumarijan area under Bhatibari Zone-III WSS under Alipurduar Division, PHE Dte.(Part-II) ORD/000388/2022-2023 2634/ALD 21/12/2022 60 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 83.66 62.39 19
970 Alipurduar Division Laying of rising main and delivery line connection, horizontal boring by HDD method with HDPE pipe, distribution gap filling with UPVC pipe and others allied works at Barobisha Zone-I PWSS under Alipurduar Division, PHE Dte. ORD/000388/2023-2024 199/ALD 16/01/2024 540 SREE MAA CONSTRUCTION 22.86 0.00 100
971 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna ( for AWC and school & others) at Chhoto Salkumar WSS under Alipurduar Division, PHE Dte.Part-5 ORD/000389/2021-2022 2303/ALD 25/01/2022 30 AASHIRBAD ENTERPRISE 5.03 3.99 61
972 Alipurduar Division Laying distribution pipe with DI and UPVC pipe of Chikliguri area under Bhatibari Zone-III WSS under Alipurduar Division, PHE Dte.(Part-III) ORD/000389/2022-2023 2635/ALD 21/12/2022 60 TAPASH DAS 74.46 43.73 21
973 Alipurduar Division Construction of 2nos pump house, boundary wall, TW boring by ODEX-195 method of drilling for Augmentation of Dhumchipara PWSS under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000389/2023-2024 200/ALD 16/01/2024 480 MITHUN DAS 54.27 0.00 50
974 Alipurduar Division Extension of UPVC pipeline for Putimari WSS under Dakshin Shibkata Mousa under Alipurduar Division, P.H.E. Dte. ORD/000390/2021-2022 2304/ALD 25/01/2022 30 HARI CONSTRUCTION 5.05 5.05 91
975 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by Reverse Rotary Method of drilling including Rising Main at H/W site and 2nd site along with repairing of office godown for Bhatibari Zone-I PWSS Under Alipurduar Division PHE DTE ORD/000390/2022-2023 2636/ALD 21/12/2022 180 DULAL DAS 51.35 35.53 85
976 Alipurduar Division Extension of UPVC pipeline for Putimari WSS under Dakshin Dhalkar Mousa under Alipurduar Division, P.H.E. Dte. ORD/000391/2021-2022 2305/ALD 25/01/2022 30 PRAPTI DUTTA 5.04 4.55 95
977 Alipurduar Division Construction of 1no. Boundary Wall and 2nos. Pump House for BHATIBARI ZONE-III and ZONE-IV PWSS Under Alipurduar Division PHE DTE. ORD/000391/2022-2023 2637/ALD 21/12/2022 810 CREATIVE UN EMPLOYED ENGINEERSCO OPER SOCYLIMITED 17.67 0.00 100
978 Alipurduar Division Laying of new UPVC/DI pipeline for filling of Gap in the distribution system and other allied works in connection with the complain address in the CMRO portal in the command area of Chandirjhar PWSS under Alipurduar Division, PHE Dte. ORD/000391/2023-2024 202/ALD 16/01/2024 480 KAMALESH ROY 14.05 6.87 65
979 Alipurduar Division Hiring of additional Diesel Vehicle Maxi Cab (At least 7 seater) for Assistant Engineer, Head Quarter, Alipurduar Division, P.H.E. Dte. ORD/000391/2024-2025 3883/ALD 22/11/2024 365 SOUVIK ROY PALADHI 4.80 0.00 0
980 Alipurduar Division Laying distribution system the new HDPE pipeline (Part-A) with rising and delivery line connection, providing FHTC and others allied works for Shrinathpur Tea Garden Area PWSS under Alipurduar Division, PHE Dte. ORD/000392/2022-2023 2657/ALD/ 22/12/2022 600 DEBAJYOTI SUTRADHAR 96.35 94.46 95
981 Alipurduar Division Gap filling by HDPE/DI pipe in Ethelbari TG under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000392/2023-2024 203/ALD 16/01/2024 60 BHAGWATI BHUJEL 14.02 13.28 85
982 Alipurduar Division Laying of new HDPE pipeline for interconnection in the distribution system and bridge/culvert crossing land developmentworks, construction of surface drain, pathway and other allied works in connection with the Augmentation of KAijali Basty PWSS (SM/11958) under Alipurduar Division, PHE Dte. ORD/000392/2024-2025 3958/ALD 26/11/2024 60 MAHENDRA CHHETRI 29.40 0.00 0
983 Alipurduar Division Construction of roof truss, field development and other allied works at Headwork site of Old Jaigaon WSS under Alipurduar Division, PHE Dte. ORD/000393/2021-2022 2307/ALD 25/01/2022 30 DILIP MAHATO 4.17 4.14 75
984 Alipurduar Division Laying distribution system with new UPVC/DI pipeline along with rising and delivery line connection, providing FHTC and others allied works for Samuktala Zone-II PWSS under Alipurduar Division, PHE Dte. ORD/000393/2022-2023 2658/ALD 22/12/2022 900 HARIDAS GHOSH 88.71 80.24 48
985 Alipurduar Division Laying of rising main line HDPE PN10, horizontal boring by HDD method, bridge and culvert crossing, construction of pathway, surface drain and chatal, installation of paver block along with the others allied works at Loknathpur PWSS under Alipurduar Division, PHE Dte. ORD/000393/2023-2024 204/ALD 16/01/2024 450 SOUVIK ROY PALADHI 26.65 12.58 60
986 Alipurduar Division Laying of HDPE/DI pipe line near Dangi Aashram Ground and Kohinur Gram Panchayat office area for interconnection in the distribution system and bridge /culvert crossing under KOHINUR TEA GARDEN PWSS Alipurduar Sadar Sub-Division, under Alipurduar Division PHE DTE. (SM/12113) ORD/000393/2024-2025 4179/ALD 03/12/2024 60 MAHAPRABHU ENTERPRISE 61.89 0.00 0
987 Alipurduar Division Road crossing (by NP3 Hume pipe) at Dhupguri Road under under Zone-II of augmentation of Falakata WSS and infront of bhutnirghat WSS due to widening of PWD Road under Alipurduar Division, PHE Dte. (3 nos) ORD/000394/2021-2022 2308/ALD 25/01/2022 30 ASSOCIATE CONSTRUCTION COMPANY 2.49 2.45 89
988 Alipurduar Division Laying distribution system with new UPVC/DI pipeline along with rising and delivery line connection, providing FHTC and other allied works for Samuktala Zone-III PWSS under Alipurduar Division, PHE Dte. ORD/000394/2022-2023 2659/ALD 22/12/2022 120 ESCON INDIA 90.53 50.31 50
989 Alipurduar Division Laying of rising main line HDPE PN10, horizontal boring by HDD method, bridge and culvert crossing, construction of pathway, surface drain and chatal, installation of paver block, Land development along with the others allied works at Telipara Headwork site PWSS under Alipurduar Division, PHE Dte. ORD/000394/2023-2024 205/ALD 16/01/2024 360 HARIDAS GHOSH 31.65 0.00 90
990 Alipurduar Division LAYING OF HDPE PIPELINE FOR LEFTOUT PORTION OF FHTC AT JOGIJHORA & BHUTNIRGHAT MOUZA UNDER AUGMENTATION OF JAGIJHORA BARABAK SCHEME (SM/10169) UNDER ALIPURDUAR DIVISION, PHE DTE. ORD/000394/2024-2025 4180/ALD 03/12/2024 391 NARENDRA BHADANI. 57.58 0.00 100
991 Alipurduar Division Construction of Boundary wall near head work site of Lankapara PWSS under Alipurduar Division, PHE Dte. ORD/000395/2021-2022 2309/ALD 25/01/2022 45 ASHOK SAPKOTA 4.78 3.04 98
992 Alipurduar Division Construction of Rig Bored tubewells (1 nos.) by Reverse rotary method of drilling at HW site , construction of pump house and boundary wall at H/W, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Ethelbari Tea Garden PWSS (zone-2) Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000395/2022-2023 2660/ALD 22/12/2022 600 M/S DUTTA AND CO 87.73 39.95 26
993 Alipurduar Division Laying of rising main/distribution pipeline, supply of DI pipe and specials, horizontal boring by HDD method, bridge and culvert crossing, along with the other allied works at Dakshin Majidkhana PWSS under under Alipurduar Division, PHE Dte. ORD/000395/2023-2024 206/ALD 16/01/2024 510 HARIDAS GHOSH 41.16 30.10 25
994 Alipurduar Division Laying of UPVC pipes & other allied works for Rajhabhat TG PWSS under Alipurduar Division, PHE Dte. ORD/000395/2024-2025 4234/ALD 12/12/2024 210 PRITAM DAS 19.98 0.00 100
995 Alipurduar Division Gap filling by UPVC pipe at different zone of Falakata water supply scheme under Alipurduar Division, PHE Dte. Part-4 ORD/000396/2020-2021 1582/ALD 10/02/2021 60 SWAPAN SAHA 5.01 5.06 64
996 Alipurduar Division Construction of Pump House with sanitary & plumbing arrangement near head work site of Lankapara PWSS under Alipurduar Division, PHE Dte. ORD/000396/2021-2022 2310/ALD 25/01/2022 60 ASHOK SAPKOTA 5.03 4.68 98
997 Alipurduar Division Laying of distribution pipe in Uttar Sishubari Bazar area and Madarihat Bazar Area and allied works Under Birpara Sub-division, Alipurduar Division PHE DTE. ORD/000396/2022-2023 .2663/ALD 22/12/2022 120 MITHUN DAS 25.68 25.17 100
998 Alipurduar Division Laying of CIDI pipes & HDPE (PN-10) pipeline and other allied works for Nimtijhora Tea Garden PWSS under Alipurduar Division, PHE Dte. ORD/000396/2023-2024 207/ALD 16/01/2024 450 SAMIRON PODDER 44.44 12.93 100
999 Alipurduar Division Supply of DI/DIDF Specials for Madhya Kamakhyaguri (SM/15517)WSS under Alipurduar Division, PHE Dte. ORD/000396/2024-2025 4235/ALD 12/12/2024 30 MADHAB SAHA 16.91 0.00 0
1000 Alipurduar Division Gap filling by UPVC pipe at different zone of Falakata water supply scheme under Alipurduar Division, PHE Dte. Part-5 ORD/000397/2020-2021 1583/ALD 10/02/2021 60 PROGRESSIVE UNEMPLOYED CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 5.01 5.01 67
1001 Alipurduar Division Laying distribution line of UPVC and providing FHTC connection for Chhoto Salkumar Water Supply Scheme Area under Alipurduar Division, P.H.E. Dte. ORD/000397/2021-2022 2311/ALD 25/01/2022 45 AASHIRBAD ENTERPRISE 5.01 3.88 62
1002 Alipurduar Division Road crossing and laying of different dia pipeline for Dakshin Sonapur WSS under Alipurduar-I Block under Alipurduar Division, P.H.E. Dte. ORD/000397/2022-2023 2664/ALD/ 22/12/2022 610 M/S AMIT KUMAR GUPTA 31.75 28.10 88
1003 Alipurduar Division Supply and installation of sign board for different Cha Sundori projects under Madarihat -Birpara Block under Alipurduar Division, PHE Dte. ORD/000397/2023-2024 208/ALD 16/01/2024 30 KOUSHIK BHOWMICK 1.09 1.09 100
1004 Alipurduar Division Laying of new UPVC/DI pipeline for interconnection in the distribution system and bridge/culvert crossing, Land development works, construction of surface drain, pathway, trial run and others allied works in connection with the Purba Khailshmari PWSS under Alipurduar Division, PHE Dte. ORD/000397/2024-2025 4236/ALD 12/12/2024 60 HARI CONSTRUCTION 75.41 0.00 0
1005 Alipurduar Division Construction of Pump House, Boundary Wall, and Tube well Boring by ODEX-195 method of drilling including Rising main for MAKRAPARA Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000398/2021-2022 2389/ALD 31/01/2022 90 INDRAYOODH BHOWAL 27.18 23.11 0
1006 Alipurduar Division Soil investigation work for proposed overhead reservoir , Constructions of 150 Cum OHR at HW site and providing FHTC as per Departmental Design & drawing for Ramjhora PWSS Under Birpara Sub-division, Alipurduar Division PHE DTE. ORD/000398/2022-2023 2661/ALD 22/12/2022 600 SUDDHYA SING LAMA 91.76 89.94 90
1007 Alipurduar Division Laying of HDPE/DI Pipeline for filling up the gap & bridge / culvert crossing, specials repair with trial run of pipeline and allied works at Sankosh TG PWSS under Alipurduar Division, PHE Dte. ORD/000398/2023-2024 209/ALD 16/01/2024 450 SOUVIK ROY PALADHI 19.84 3.66 80
1008 Alipurduar Division Supply of CIDF Specials and Jeffy Coupling for Dakshin Majidkhana (SM/13305) WSS under Alipurduar Division, PHE Dte. ORD/000398/2024-2025 4264/ALD 13/12/2024 60 GUHA ENTERPRISE 19.58 4.23 50
1009 Alipurduar Division Providing House connection for BHOLARDABRI WSS at Alipurduar-II Block under Alipurduar Division, PHE Dte. (Part-4) ORD/000399/2020-2021 1585/ALD 10/02/2021 60 HARIDAS GHOSH 4.98 9.96 0
1010 Alipurduar Division Construction of Pump House, Boundary Wall, and Tube well Boring by ODEX-195 method of drilling including Rising main for DHUMCHIPARA Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000399/2021-2022 2390/ALD 31/01/2022 90 DILIP MAHATO 27.18 26.69 18
1011 Alipurduar Division Laying of HDPE/DI Pipeline for filling up the gap and bridge / culvert crossing, specials repair with trial run of pipeline and allied works at Shrinnathpur TG PWSS under Alipurduar Division, PHE Dte. ORD/000399/2023-2024 210/ALD 16/01/2024 540 DEBAJYOTI SUTRADHAR 29.55 15.15 10
1012 Alipurduar Division Supply of CIDF Specials & Jeffy Coupling for Pakriguri (SM/14223) under Alipurduar Division, PHE Dte. ORD/000399/2024-2025 4265/ALD 13/12/2024 60 BARMAN ENTERPRISE 19.64 3.38 51
1013 Alipurduar Division Providing House connection for BHOLARDABRI WSS at Alipurduar-II Block under Alipurduar Division, PHE Dte. (Part-5) ORD/000400/2020-2021 1586/ALD 10/02/2021 60 HARIDAS GHOSH 4.98 9.97 0
1014 Alipurduar Division Construction of Pump House, Boundary Wall, and Tube well Boring by ODEX-195 method of drilling including Rising main for GARGENDA Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000400/2021-2022 2391/ALD 31/01/2022 90 MITHUN DAS 27.16 25.52 100
1015 Alipurduar Division Supply of CIDF Specials and Jeffy Coupling for Purba Narathali (SM/16537) WSS under Alipurduar Division, PHE Dte. ORD/000400/2024-2025 4266/ALD 13/12/2024 30 HITANGSHU CHOUDHURY 19.67 0.00 0
1016 Alipurduar Division Tube well Boring by ODEX-195 method of drilling including Rising main for JAYANTI Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000401/2021-2022 2392/ALD 31/01/2022 90 TAPASH KUMAR BHOWMICK 12.78 11.81 44
1017 Alipurduar Division LAYING OF DISTRIBUTION PIPELINE AT DALIMPUR (ZONE-II, PART-A) PWSS UNDER ALIPURDUAR DIVISION, PHE DTE. ORD/000401/2024-2025 4537/ALD 26/12/2024 120 HITANGSHU CHOUDHURY 55.82 0.00 80
1018 Alipurduar Division Supply of CIDF Specials & Jeffy Coupling for Augmentation of Chandirjhar (SM/10677) under Alipurduar Division, PHE Dte. ORD/000402/2024-2025 4538/ALD 26/12/2024 30 MAHENDRA CHHETRI 19.05 0.00 0
1019 Alipurduar Division Construction of Pump House ,Boundary Wall, and Tube well Boring by Reverse Rotary method of drilling including Rising main for JASHODANGA Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000403/2021-2022 2394/ALD 31/01/2022 90 MATRI ENTERPRISE 24.02 17.80 44
1020 Alipurduar Division Supply of CIDF Specials & Jeffy Coupling for Turturi (SM/14219) WSS under Alipurduar Division, PHE Dte. ORD/000403/2024-2025 4539/ALD 26/12/2024 30 SOUVIK ROY PALADHI 19.99 0.00 0
1021 Alipurduar Division Laying of DI pipe line for discharge of washed out water from Tube well No. 1 within Falakata PWSS(Existing) under Alipurduar Division PHED. ORD/000404/2021-2022 57/PHE-Brp 03/02/2022 30 KANKAN SARKAR 0.22 0.22 67
1022 Alipurduar Division Supply of CIDF Specials & Jeffy Coupling for Chalnipak (SM/15534) WSS under Alipurduar Division, PHE Dte. ORD/000404/2024-2025 4540/ALD 26/12/2024 30 SOUVIK ROY PALADHI 19.94 0.00 0
1023 Alipurduar Division Extension of UPVC pipeline for Putimari WSS under Putimari Mousa under Alipurduar Division, P.H.E. Dte. ORD/000405/2021-2022 2312/ALD 25/01/2022 30 HIMALAYAN CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 5.04 5.04 94
1024 Alipurduar Division Soil investigation work at proposed OHR construction site of Hasimara PWSS under Alipurduar Division PHE Dte. ORD/000405/2022-2023 2790/ALD 10/01/2023 30 MOYTEC 0.95 0.95 100
1025 Alipurduar Division Installation of 125mm X 80mm X 90 mtr. Deep Tube Well (Mark-II TW) for fresh drinking water sources(with provision of lowering of sub-merssible pump) by ODEX-115 method of Drilling Near House of Lt. Jhagru Rai, East Hirdaypur of Angrabhasa GP-I under Nagrakata Block under Jalpaiguri District. ORD/000406/2020-2021 1827/ALD 23/02/2021 15 RAMESH SHARMA 4.08 0.00 40
1026 Alipurduar Division Extension of UPVC pipeline for Putimari WSS under Putimari Mousa under Alipurduar Division, P.H.E. Dte. ORD/000406/2021-2022 2313/ALD 25/01/2022 30 AASHIRBAD ENTERPRISE 5.04 5.04 93
1027 Alipurduar Division Soil investigation work for Augmentaion of Dakshin Sonapur PWSS under Alipurduar Division PHE Dte. ORD/000406/2022-2023 2791/ALD 10/01/2023 30 MOYTEC 0.95 0.95 0
1028 Alipurduar Division Extension of UPVC pipeline for Putimari WSS under Uttar Dhalkar Mousa under Alipurduar Division, P.H.E. Dte. ORD/000407/2021-2022 2314/ALD 25/01/2022 30 PRAPTI DUTTA 5.04 5.04 92
1029 Alipurduar Division Construction of Rig Machine Approach Road of Bholardabri 3rd TW Site under Alipurduar Division, PHE Dte. ORD/000407/2022-2023 2792/ALD 10/01/2023 30 HIMALAYAN CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 0.33 0.32 64
1030 Alipurduar Division Road Restoration at kalchini Old Scheme area within Kalchini block under Alipurduar Division, PHE Dte. ORD/000407/2024-2025 4536/ALD 26/12/2024 60 RK DISTRIBUTORS 2.08 2.08 100
1031 Alipurduar Division Construction of 550cum OHR for Augmentation of Narathali Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000408/2021-2022 2524/ALD 11/02/2022 180 TAPAN CHANDA 98.12 89.52 72
1032 Alipurduar Division Laying of new UPVC/DI pipeline for interconnection in the distribution system and bridge/culvert crossing, construction of RCC pillars for supporting DI Pipe, surface drain and others allied works in connection with the Augmentation of Loknathpur PWSS under Alipurduar Division, PHE Dte. ORD/000408/2024-2025 4535/ALD 26/12/2024 60 SOUVIK ROY PALADHI 80.87 0.00 0
1033 Alipurduar Division Construction of 500cum OHR for Augmentation of Jateswar Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000409/2021-2022 2525/ALD 11/02/2022 180 ASHIT KUMAR SINGHA 91.76 82.23 80
1034 Alipurduar Division Construction of Pump House ,Boundary Wall and Tube well Boring by ODEX-165 Method of drilling including Rising Main for NARATHALI PWSS under Alipurduar Division PHE DTE. ORD/000410/2021-2022 2526/ALD 11/02/2022 990 TAPAN CHANDA 41.03 27.14 100
1035 Alipurduar Division Supply of DI/DIDF Specials for Dalgaon TG (SM/16823)WSS under Alipurduar Division, PHE Dte. ORD/000410/2024-2025 4582/ALD 02/01/2025 30 TAPASH KUMAR BHOWMICK 16.98 0.00 0
1036 Alipurduar Division Construction of Pump House ,Boundary Wall, and Tube well Boring by Reverse Rotary method of drilling including Rising main for JATESWAR Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000411/2021-2022 2527/ALD 11/02/2022 990 ASHIT KUMAR SINGHA 44.59 18.47 63
1037 Alipurduar Division Construction of 400cum OHR for Augmentation of Uttar Kamakhyaguri Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000412/2021-2022 2580/ALD 17/02/2022 180 DILIP MAHATO 77.31 76.92 74
1038 Alipurduar Division Construction of 300 cum OHR as per departmental design and drawing, soil investigation work, laying of DI/CI pipeline, supplying of CI Specials and other allied works at headwork site of Shrinathpur Tea Garden Area PWSS under Alipurduar Division, PHE Dte. ORD/000412/2022-2023 2690/ALD 23/12/2022 180 KAMALESH ROY 93.98 90.03 100
1039 Alipurduar Division Laying of DI & HDPE Pipe line, Construction of sluice valve chamber, trenchless pipe laying & other works for providing FHTC at Birpara Zone-I Area under Birpara PWSS under Alipurduar Division, PHE DTE. ORD/000412/2024-2025 4595/ALD 03/01/2025 225 KAMALESH ROY 149.76 0.00 1
1040 Alipurduar Division Construction of 450cum OHR for Augmentation of Uttar Majher Dabri Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000413/2021-2022 2581/ALD 17/02/2022 720 M/S DUTTA AND CO 87.59 87.15 99
1041 Alipurduar Division Supply of CIDF Specials and Jeffy Coupling for Umacharanpur (SM/16114) WSS under Alipurduar Division, PHE Dte. ORD/000413/2024-2025 4591/ALD 03/01/2025 30 TAPASH KUMAR BHOWMICK 19.81 0.00 0
1042 Alipurduar Division Construction of 300cum OHR for Augmentation of Jagijhora Barabak Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000414/2021-2022 2582/ALD 17/02/2022 180 ASHIM KUMAR GHOSH 63.76 66.54 43
1043 Alipurduar Division Hiring of Diesel Vehicle Maxi Cab(At least 7 seater ) for Assistant Engineer, Head Quarter, Alipurduar Division, P.H.E. Dte.(from 01.01.2023 to 31.12.2023) ORD/000414/2022-2023 2729/ALD 30/12/2022 365 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 4.80 4.48 100
1044 Alipurduar Division Sinking of 1nos Big dia Tubewell (250 x 200 x 150 mm dia) by modified DTH-ODEX of drilling for Rangamati Zone-II PWSS site within Kalchini Block under Alipurduar Division, PHE Dte. ORD/000414/2024-2025 4592/ALD 03/01/2025 88 EFFLUENT AND WATERTREATMENT ENGINEERS PVT LTD 24.05 0.00 100
1045 Alipurduar Division Construction of 400cum OHR for Mathura Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000415/2021-2022 2583/ALD 17/02/2022 180 M/S SURAJIT DEY & CO 77.51 58.47 63
1046 Alipurduar Division Hiring of Diesel Vehicle Maxi Cab(At least 7 seater ) for Assistant Engineer, Alipurduar Sadar Sub-Division, P.H.E. Dte.(from 01.01.2023 to 31.12.2023) ORD/000415/2022-2023 2730/ALD 30/12/2022 365 MATRI ENTERPRISE 4.80 4.76 10
1047 Alipurduar Division Sinking of 1nos Big dia Tubewell (250 x 200 x 150 mm dia) by modified DTH-ODEX of drilling for Augmentation of new Hasimara PWSS site within Kalchini Block under Alipurduar Division, PHE Dte. ORD/000415/2024-2025 4593/ALD 03/01/2025 60 EFFLUENT AND WATERTREATMENT ENGINEERS PVT LTD 15.95 9.92 100
1048 Alipurduar Division Construction of 300cum OHR for Dakshin Paitkapara Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000416/2021-2022 2584/ALD 17/02/2022 180 Z STAR COMMOTRADE PVT LTD. 63.78 41.17 83
1049 Alipurduar Division Hiring of Diesel Vehicle Maxi Cab(At least 7 seater ) for Assistant Engineer, Alipurduar RWS Sub-Division, P.H.E. Dte.(from 01.01.2023 to 31.12.2023) ORD/000416/2022-2023 2731/ALD 30/12/2022 365 KAMALESH ROY 4.80 4.58 100
1050 Alipurduar Division Construction of 350cum OHR for Madarihat TG Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000417/2021-2022 2586/ALD 17/02/2022 180 DILIP MAHATO 71.40 71.38 90
1051 Alipurduar Division Hiring of Diesel Vehicle Maxi Cab(At least 7 seater ) for Assistant Engineer, Birpara Sub-Division, P.H.E. Dte.(from 01.01.2023 to 31.12.2023) ORD/000417/2022-2023 2732/ALD 30/12/2022 365 PARITOSH SUTRADHAR 4.80 4.58 90
1052 Alipurduar Division Construction of 250cum OHR for Sidhabari Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000418/2021-2022 2585/ALD 17/02/2022 180 MS CTR CONSTRUCTION 57.53 35.97 55
1053 Alipurduar Division Preparation of detailed D.P.R. booklets in connection to Sidhabari PWSS under Alipurduar-I Block under Alipurduar Division P.H.E Dte. ORD/000418/2022-2023 2821/ALD 11/01/2023 30 ANIK BHATTACHARJEE 0.97 0.97 56
1054 Alipurduar Division Construction of OHR 200cum for Chuniajhora TG Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000419/2021-2022 2598/ALD 17/02/2022 180 AKANSHA COMMERCIAL PRIVATE LTD. 55.36 47.96 65
1055 Alipurduar Division Construction of OHR 200cum for Gangutia Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000420/2021-2022 2599/ALD 17/02/2022 180 ANUGRAH CONSTRUCTION PRIVATE LIMITED 55.36 24.23 68
1056 Alipurduar Division Construction of OHR 200cum for Mechpara Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000421/2021-2022 2600/ALD 17/02/2022 180 M/S KAMAK ENGINEERS AND CO 55.33 21.10 80
1057 Alipurduar Division Laying of new additional pipeline opposite flanks of the higher dia UPVC pipeline and to connect the scattered house with the distribution system in view of providing FHTC, Construction of RCC pillars for supporting DI Pipe, trial run and others allied works in connection with the Telipara PWSS under Alipurduar Division, PHE Dte. ORD/000421/2024-2025 4907/ALD 31/01/2025 45 MATRI ENTERPRISE 39.90 0.00 0
1058 Alipurduar Division Construction of OHR 200cum for Jay Birpara TG Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000422/2021-2022 2601/ALD 17/02/2022 180 SUBHAS CHANDRA ROY 55.36 46.90 80
1059 Alipurduar Division Construction of pumphouse & boundary wall for 3rd site, laying of distribution system with UPVC and DI pipeline, providing FHTC, Rising main and other allied works for Pakriguri PWSS under Alipurduar Division, PHE Dte. ORD/000422/2024-2025 4906/ALD 31/01/2025 90 DEBAJYOTI SUTRADHAR 23.90 0.00 0
1060 Alipurduar Division Construction of 250cum OHR for Gopalpur Tea Garden Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000423/2021-2022 2602/ALD 17/02/2022 180 SASANKA ROY 57.59 57.96 72
1061 Alipurduar Division Construction of 150 cum OHR as per Departmental Design & drawing, laying of rising main & delivery connection . Supply of CIDF Specials and others allied works for Bhatibari Z-II PWSS Under Alipurduar Division PHE Dte. ORD/000423/2024-2025 4898/ALD 30/01/2025 180 MATRI ENTERPRISE 95.67 0.00 0
1062 Alipurduar Division Construction of Pump House ,Boundary Wall and laying distribution system for Uttar Kamkhyaguri Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000424/2021-2022 2608/ALD 17/02/2022 90 GOUTAM KUMAR DAS 90.80 77.36 74
1063 Alipurduar Division Laying of different dia. HDPE Pipe line and other allied works in connection with Jal Jeevan Mission for Bengkandi PWSS under Alipurduar Division, PHE DTE. ORD/000424/2024-2025 4948/ALD 06/02/2025 90 M/S ELITE CONSTRUCTION 106.35 0.00 0
1064 Alipurduar Division Construction of Pump House ,Boundary Wall and Tube well Boring by ODEX-165 Method of drilling including Rising Main for JAGIJHORA BARABAK PWSS under Alipurduar Division PHE DTE ORD/000425/2021-2022 2609/ALD 17/02/2022 90 SUBHAS CHANDRA ROY 21.13 13.24 100
1065 Alipurduar Division Construction of Pump House ,Boundary Wall, and Tube well Boring by Reverse Rotary method of drilling including Rising main for UTTAR KAMAKHYAGURI Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000426/2021-2022 2610/ALD 17/02/2022 90 ANUP GUPTA 23.99 0.00 0
1066 Alipurduar Division Construction of Pump House ,Boundary Wall, and Tube well Boring by Reverse Rotary method of drilling including Rising main for UTTAR MAJHERDABRI Piped Water Supply Scheme Under Alipurduar Division PHE DTE ORD/000427/2021-2022 2611/ALD 17/02/2022 90 HIGHLIFE INTERNATIONAL 44.39 43.93 100
1067 Alipurduar Division Cons. of pump house and Sinking of 250 mm x 200 mm X 150 mtr. Big dia. TW at HW and 2nd site, LDS with UPVC pipeline, Cons. of 200 cum OHR as per Departmental Design and drawing inclu. Soil testing, providing FHTC and others allied works for Dakshin Majidkhana PWSS Under Alipurduar Division PHE DTE. ORD/000427/2022-2023 2854/ALD 17/01/2023 1020 HARIDAS GHOSH 390.45 339.65 75
1068 Alipurduar Division Cons. of pump house and Sinking of 250 mm x 200 mm X 150 mtr. Big dia. TW at HW site and 2nd site, LDS with UPVC pipeline, Cons. of 200 Cum OHR as per Departmental Design and drawing inclu. Soil testing, providing FHTC and others allied works for Brajerkuthi PWSS Under Alipurduar Division PHE DTE. ORD/000428/2022-2023 2855/ALD 17/01/2023 804 TAPASH KUMAR BHOWMICK 460.44 415.10 95
1069 Alipurduar Division Laying of HDPE pipeline for Hantapara Topline under Hatapara WSS within Alipurduar Division, PHE Dte. ORD/000429/2021-2022 2627/ALD 18/02/2022 60 DILIP MAHATO 16.19 11.95 69
1070 Alipurduar Division Cons. of pump house and Sinking of 250 mm x 200 mm X 150 mtr Big dia TW at HW site and 2nd site, LDS with UPVC pipeline, Cons. of 200 Cum OHR as per Departmental Design and drawing inclu. Soil testing, providing FHTC and others allied works for BARUIPARA PWSS under Alipurduar Division PHE DTE. ORD/000429/2022-2023 2856/ALD 17/01/2023 985 TAPAN CHANDA 403.77 186.44 80
1071 Alipurduar Division Sinking of Rig bore T/W (4nos.) by Reverse Rotary method of drilling, cons. of 100 cum. OHR (2nos), cons. of P/H and B/W, Rising main, distribution line and providing FHTC at H/W and 2nd site inclu. Soil testing for KADAMBINI TG PWSS (ZONE-I and ZONE-II) under Birpara Sub-Division, Alipurduar Division, PHE Dte ORD/000430/2022-2023 2857/ALD 17/01/2023 874 DILIP MAHATO 498.42 452.83 95
1072 Alipurduar Division Balance work of Jainty Rest Shed along with laying of delivery line from CWR of Jainti WSS under Alipurduar Division, PHE Dte. ORD/000431/2021-2022 2629/ALD 18/02/2022 60 GHOSH & SAHA CONSTRUCTION 13.40 13.22 64
1073 Alipurduar Division Constructions of pump house & Sinking of 250 mm x 200 mm X 150 mtr Big dia Tubewel at HW site & 2nd site , laying of distribution system with UPVC pipeline , Constructions of 200 Cum OHR as per Departmental Design & drawing including soil test, providing FHTC and others allied works for Purba Chikliguri PWSS Under Alipurduar Division PHE DTE. ORD/000431/2022-2023 2858/ALD 17/01/2023 815 SOUVIK ROY PALADHI 481.73 324.69 65
1074 Alipurduar Division Supply of various materials at Alipurduar Divisional Stack Yard under Alipurduar Division, PHE Dte. ORD/000432/2021-2022 846/ALD 26/08/2021 30 EXECUTIVE ENGINEER, RESOURCE DIVISION 502.58 502.58 100
1075 Alipurduar Division Tube well Boring by ODEX-165 Method of drilling at HW, FIRST TUBE WELL AND SECOND TUBE WELL site including laying distribution system with new HDPE pipeline (Part-B) CONSTRUCTION OF THREE (3) NOS PUMP HOUSES ,providing FHTC and others allied works for PASCHIM SATALI PWSS Under Alipurduar Division PHE DTE. ORD/000432/2022-2023 2859/ALD 17/01/2023 1110 MAHENDRA CHHETRI 267.57 227.68 65
1076 Alipurduar Division Construction of Pump House, Boundary Wall, and Tube well Boring by ODEX-195 method of drilling including Rising main for HANTUPARA Piped Water Supply Scheme Under Alipurduar Division PHE DTE. ORD/000433/2021-2022 2713/ALD 23/02/2022 90 SUBIR GHOSH 25.31 19.71 41
1077 Alipurduar Division Constructions of 300 Cum OHR as per Departmental Design & drawing including laying distribution system with new HDPE pipeline (Part-A), RISING MAIN, CONSTRUCTION OF THREE(3) NOS OF BOUNDARY WALL, PATHWAY including soil test, providing FHTC and others allied works for PASCHIM SATALI PWSS Under Alipurduar Division PHE DTE ORD/000433/2022-2023 2860/ALD 17/01/2023 1082 DILIP MAHATO 497.97 365.27 74
1078 Alipurduar Division SOIL INVESTIGATION AT OHR AND CONS. OF 450 CUM OHR AT ZONE-3 FOR AUGMENTATIN OF BIRPARA PWSS UNDER ALIPURDUAR DIVISION OF NORTH BENGAL CIRCLE-I, PHE DTE. ORD/000433/2023-2024 234/ALD 17/01/2024 381 AMBITIOUS ENTERPRISE 239.31 25.15 55
1079 Alipurduar Division Providing FHTC at Northern side of Hasimara Piped Water Supply Scheme Under Alipurduar Division, PHE DTE. ORD/000434/2021-2022 2714/ALD 23/02/2022 60 ASHIM KUMAR GHOSH 34.64 34.64 49
1080 Alipurduar Division Cons. of Rig bored TW(2nos) by Reverse Rotary method of drilling at HW and 2nd site, cons of 200 cum OHR at HW including soil testing, cons. of P/H and B/W at HW,2nd site, Laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for ETHELBARI TG PWSS (ZONE-I)under Birpara Sub-Division, Alipurduar Division, PHE DTE. ORD/000434/2022-2023 2861/ALD 17/01/2023 180 DILIP MAHATO 385.44 323.42 90
1081 Alipurduar Division Laying of UPVC/DI/MS/CI Distribution pipe line for Gap filling of Chapaguri area at Uttar Sishubari PWSS under Alipurduar Division PHE Dte. ORD/000435/2021-2022 2652/ALD 21/02/2022 45 KAMALESH ROY 4.94 4.68 55
1082 Alipurduar Division Cons. of P/H and T/W Boring by ODEX-165 Method of drilling at HW and 2nd site , LDS with UPVC P/L including rising main and delivery connection, Cons. of 200 Cum OHR as per Departmental Design & drawing , providing FHTC and others allied works for PASCHIM CHENGMARI PWSS Under Alipurduar Division PHE DTE. ORD/000435/2022-2023 2862/ALD 17/01/2023 806 M/S SSB CONSTRUCTION CO. 312.15 201.82 65
1083 Alipurduar Division Laying of distribution of UPVC pipeline including FHTC for PASCHI NARATHALI MOUZA under NARATHALI PWSS under Alipurduar Division, PHE DTE. ORD/000436/2021-2022 2742/ALD 24/02/2022 60 MADHAB SAHA 87.55 78.76 71
1084 Alipurduar Division Constructions of P/H and T/W Boring by ODEX-165 Method of drilling at HW and 2nd site , LDS with UPVC P/L inclu. rising main and delivery connection, Cons. of 200 Cum OHR as per Departmental Design & drawing alongwith soil investigation, providing FHTC and others allied works for MARAKHATA PWSS Under Alipurduar Division PHE DTE. ORD/000436/2022-2023 2863/ALD 17/01/2023 900 HARIDAS GHOSH 355.80 264.97 27
1085 Alipurduar Division Laying of distribution of UPVC pipeline including FHTC for KHOARDANGA AREA under NARATHALI PWSS under Alipurduar Division, PHE DTE. ORD/000437/2021-2022 2743/ALD 24/02/2022 60 HARIDAS GHOSH 87.82 87.69 99
1086 Alipurduar Division Shifting and Laying distribution of P/line due to Widening of Falkata to Dhupguri rd. & other allied works to Bhutnirghat PWSS under Alipurduar Division PHED. part (II). ORD/000438/2020-2021 08/ALD 02/04/2020 1826 SHIB RATAN BHOWMIK 17.51 17.34 0
1087 Alipurduar Division Laying of distribution of UPVC pipeline including FHTC for MADHYA NARATHALI AREA under NARATHALI PWSS under Alipurduar Division, PHE DTE. ORD/000438/2021-2022 2744/ALD 24/02/2022 60 DAS CONSTRUCTION 87.58 66.41 68
1088 Alipurduar Division Construction of 550cum. OHR for Birpara TG (Middle) Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000438/2022-2023 2867/ALD 17/01/2023 180 DILIP MAHATO 98.12 86.15 85
1089 Alipurduar Division Laying of distribution of UPVC pipeline including FHTC for NARATHALI MOUZA under NARATHALI PWSS under Alipurduar Division, PHE DTE. ORD/000439/2021-2022 2745/ALD 24/02/2022 60 SASANKA ROY 87.59 78.42 70
1090 Alipurduar Division LAYING OF 25 MM DIA PP-R PIPES FROM TASHIGAON RIVER TO LEPCHAKHA AND LEPCHAKHA TO DUMBA AND OTHER ALLIED WORKS UNDER JJM PROGRAMME UNDER ALIPURDUAR DIVISION, PHE DTE. ORD/000439/2024-2025 5042/ALD 17/02/2025 120 S.D. PROJECT 8.33 0.00 100
1091 Alipurduar Division Laying of pipeline at PASCHIM NARATHALI by extension of pipeline from Uttar Kamakhyaguri PWSS under Alipurduar Division, PHE DTE. ORD/000440/2021-2022 2746/ALD 24/02/2022 1020 AKANSHA COMMERCIAL PRIVATE LTD. 93.92 81.73 100
1092 Alipurduar Division Laying of CI/DI/MS/HDPE pipe and providing FHTC for BIRPARA TEA GARDEN (ZONE-2) AREA PWSS Under Alipurduar Division PHE DTE. PART-A ORD/000440/2022-2023 2869/ALD 17/01/2023 60 AMBITIOUS ENTERPRISE 97.44 41.77 7
1093 Alipurduar Division Painting of Old OHR at Jogendrapur PWSS (400cum) under Alipurduar Division, PHE Dte. ORD/000440/2024-2025 5044/ALD 17/02/2025 45 DILIP MAHATO (OPC) PRIVATE LIMITED 3.14 0.00 0
1094 Alipurduar Division Construction of 250cum OHR for TATPARA Piped Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000441/2021-2022 2749/ALD 24/02/2022 180 M/S DUTTA AND CO 57.62 42.05 99
1095 Alipurduar Division Laying of CI/DI/MS/HDPE pipe and providing FHTC for BIRPARA TEA GARDEN (ZONE-3) AREA PWSS Under Alipurduar Division PHE DTE. PART-A ORD/000441/2022-2023 2870/ALD 17/01/2023 60 ANUP KUNDU CONSTRUCTION CO. 95.98 81.06 7
1096 Alipurduar Division Repairing of pump house at headwork site of Purba Chepani PWSS under Alipurduar Division, PHE Dte. ORD/000441/2024-2025 5045/ALD 17/02/2025 180 KOUSHIK BHOWMICK 1.01 0.00 100
1097 Alipurduar Division Extension of pipeline (UPVC) and providing FHTC at surrounding area of Tapshikhata PWSS Under Alipurduar Division, PHE DTE. ORD/000442/2021-2022 2750/ALD 24/02/2022 60 AMBITIOUS ENTERPRISE 36.94 21.18 68
1098 Alipurduar Division Extension of pipeline (UPVC) and providing FHTC at surrounding area of Birpara PWSS (APD) Under Alipurduar Division, PHE DTE. ORD/000443/2021-2022 2751/ALD 24/02/2022 60 R.K.CONSTRUCTION 31.74 31.75 60
1099 Alipurduar Division Laying of CI/DI/MS/HDPE pipe and providing FHTC for BIRPARA TEA GARDEN (ZONE-3) AREA PWSS Under Alipurduar Division PHE DTE. PART-C ORD/000443/2022-2023 2872/ALD 17/01/2023 60 DILIP MAHATO 96.76 74.45 65
1100 Alipurduar Division Painting of Old OHR at Dakshin Sonapur PWSS under Alipurduar Division, PHE Dte. ORD/000443/2024-2025 5046/ALD 17/02/2025 60 SANKAR ROY 3.78 0.00 100
1101 Alipurduar Division Extension of pipeline (UPVC) and providing FHTC at surrounding area of Bakla PWSS Under Alipurduar Division, PHE DTE. ORD/000444/2021-2022 2753/ALD 24/02/2022 1200 BENGAL YOUTH UN EMPLOYED ENGINEERS CO OPERATIVE SOCIETY LIMITED 43.78 34.75 43
1102 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for BirparaZone-I (North) PWSS under Alipurduar Division, PHE Dte. Part-1 ORD/000444/2022-2023 2873/ALD 17/01/2023 888 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 24.27 2.95 58
1103 Alipurduar Division Painting of Old OHR at Birpara(APD) PWSS under Alipurduar Division, PHE Dte. ORD/000444/2024-2025 5047/ALD 17/02/2025 60 SANKAR ROY 3.28 0.00 100
1104 Alipurduar Division Providing FHTC at surrounding area of Chhoto Salkumar Under Alipurduar Division, PHE DTE. ORD/000445/2021-2022 2754/ALD 24/02/2022 60 KAJAL KUMAR DE 34.67 22.61 45
1105 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Birpara Zone-I (North) PWSS under Alipurduar Division, PHE Dte. Part-2 ORD/000445/2022-2023 2874/ALD 17/01/2023 45 BILTU DAS 24.22 0.00 0
1106 Alipurduar Division Repairing of pump house at 4th site of Bhatibari PWSS under Alipurduar Division, PHE Dte. ORD/000445/2024-2025 5043/ALD 17/02/2025 120 AN CONSTRUCTION 1.01 0.00 100
1107 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Birpara Zone-II (Middle) PWSS under Alipurduar Division, PHE Dte. ORD/000446/2022-2023 2875/ALD 17/01/2023 45 NARENDRA BHADANI. 24.11 0.00 0
1108 Alipurduar Division Shifting of pipeline along the road of Birpara-Makrapara Gomtu Road under Alipurduar Division, PHE Dte. ORD/000447/2021-2022 2654/ALD 21/02/2022 30 DILIP MAHATO 3.62 3.11 0
1109 Alipurduar Division Providing Functional Tap Connection (FHTC) in connection with Jaldhara/JalSwapna (Schools, AWC and others) for Birpara (South) PWSS under Alipurduar Division, PHE Dte. ORD/000447/2022-2023 2876/ALD 17/01/2023 45 DILIP MAHATO 34.60 0.00 0
1110 Alipurduar Division Soil investigation work for Cha Sundori Project at 4 different places of Torsha TG & Dekhlapara TG within Alipurduar District under Alipurduar Division PHE Dte. ORD/000448/2021-2022 2655/ALD 21/02/2022 30 M/S HAZRA CONSTRUCTION 4.90 4.90 87
1111 Alipurduar Division Boring of Tubewell, Construction of pump house, boundary wall, Laying of Rising main, distribution system and providing FHTC for Torsha Forest PWSS under Alipurduar Division PHE Dte. ORD/000448/2022-2023 2919/ALD 19/01/2023 600 KAMALESH ROY 79.66 71.83 94
1112 Alipurduar Division Repairing of pump house at headwork site (existing) of Kumargram PWSS under Alipurduar Division, PHE Dte. ORD/000448/2024-2025 5061/ALD 18/02/2025 60 DULAL DAS 1.35 0.00 100
1113 Alipurduar Division Tube well Boring by ODEX-195 Method of drilling of Constructions of 1no. pump house, boundary wall, distribution line with FHTC for Lankapara 20no. Line for Augmentation of Lankapara TG for Lonkapara Hat Area PWSS Under Birpara Sub-Division, Alipurduar Division PHE DTE. ORD/000449/2022-2023 2920/ALD 19/01/2023 240 SUDDHYA SING LAMA 40.15 32.23 51
1114 Alipurduar Division Repairing of pump house at 3rd site (existing) of Kumargram PWSS under Alipurduar Division, PHE Dte. ORD/000449/2024-2025 5063/ALD 18/02/2025 60 DULAL DAS 1.05 0.00 100
1115 Alipurduar Division Laying of distribution of UPVC/DI/GI pipeline including FHTC for JATESWAR PWSS under Alipurduar Division, PHE DTE. PART-II ORD/000450/2021-2022 2747/ALD 24/02/2022 60 TAPASH DAS 49.62 47.46 59
1116 Alipurduar Division Boring of Tube Well, Construction of Pump House, Boundary Wall, Laying Of Rising Main, Distribution System and providing FHTC for Dakshin Barajhar Forest PWSS Under Alipurduar Division, PHE Dte. ORD/000450/2022-2023 2921/ALD 19/01/2023 120 BHAGWATI BHUJEL 85.20 74.21 33
1117 Alipurduar Division Repairing of Kumargram Rest Shed and other works at Kumargram PWSS, Alipurduar Sadar Sub-Division, under Alipurduar Division PHE DTE. (SM/11985) ORD/000450/2024-2025 5062/ALD 18/02/2025 45 DULAL DAS 3.09 0.00 100
1118 Alipurduar Division Laying of distribution of UPVC/DI/GI pipeline including FHTC for JATESWAR PWSS under Alipurduar Division, PHE DTE. PART-II ORD/000451/2021-2022 2748/ALD 24/02/2022 60 KAMALESH ROY 49.62 47.81 63
1119 Alipurduar Division Construction of Tubewell by ODEX-165 method of drilling at HW site, construction of pump house and boundary wall at H/W site, laying of distribution line and providing FHTC as per Departmental Design & drawing for Garochera Bandapani PWSS Under Birpara Sub-division, Alipurduar Division PHE DTE. ORD/000451/2022-2023 2922/ALD 19/01/2023 120 RATAN DUTTA 73.26 49.44 62
1120 Alipurduar Division Balance work of the boundary wall and laying of delivery line connection, land development works, surface drain & pathway at 5th site at Samuktala Zone-II in connection with Samuktala PWSS under Alipurduar Division, PHE Dte. ORD/000451/2024-2025 5064/ALD 18/02/2025 160 DULAL DAS 9.08 0.00 100
1121 Alipurduar Division T/W Boring by ODEX-165 Method of drilling at HW FIRST TW site including LDS with new HDPE P/L, Cons. of 250 Cum OHR as per Departmental Design and drawing including soil investigation works, 2nos. pumphouse and boundary wall, providing FHTC and others allied works for BHATPARA TG PWSS under Alipurduar Division PHE DTE ORD/000452/2022-2023 2969/ALD 31/01/2023 1260 MAHENDRA CHHETRI 362.78 251.60 90
1122 Alipurduar Division LAYING OF DISTRIBUTION PIPELINE AT DALIMPUR (ZONE-II, PART-B) PWSS UNDER ALIPURDUAR DIVISION, PHE DTE. ORD/000452/2024-2025 5169/ALD 25/02/2025 240 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 55.35 0.00 10
1123 Alipurduar Division Laying of HDPE and distribution pipes in different suitable locations of Sidhabari PWSS under Alipurduar Division, PHE Dte. ORD/000453/2022-2023 2970/ALD 31/01/2023 90 BILTU DAS 165.16 120.20 61
1124 Alipurduar Division Providing FHTC from existing distribution system as per specification for JATESWAR PWSS under Alipurduar Division, PHE Dte. ORD/000453/2023-2024 235/ALD 17/01/2024 90 BILTU DAS 63.54 0.00 0
1125 Alipurduar Division Restoration of pipeline for Gap filling and other allied works under Hasimara PWSS under Alipurduar Division, PHE Dte. ORD/000453/2024-2025 5170/ALD 25/02/2025 60 BRAJA GOPAL SAHA 4.47 0.00 0
1126 Alipurduar Division Laying of UPVC/DI pipe line at flank of Asian Highway Road at Jateswar to towards Kazali Bazar under Jateswar PWSS under Alipurduar Division, PHE Dte. ORD/000454/2022-2023 2944/ALD 20/01/2023 60 TAPASH DAS 16.10 16.03 95
1127 Alipurduar Division Construction of tubewells (2 nos.) by Reverse rotary method of drilling, constructions of 150 Cum OHR at HW, Cons. of pump house and Boundary wall at HW site and 2nd site, Laying of rising main, part of distribution line and providing FHTC for Dalimpur zone-II under Birpara Sub-division, Alipurduar Division of North Bengal Circle-I, PHE DTE. ORD/000454/2023-2024 366/ALD 31/01/2024 791 HARIDAS GHOSH 199.70 117.92 90
1128 Alipurduar Division Construction of 1no. Pump House boundary wall, at new Hasimara PWSS Area under Alipurduar Division, PHE Dte. ORD/000454/2024-2025 5171/ALD 25/02/2025 120 BRAJA GOPAL SAHA 17.18 0.00 0
1129 Alipurduar Division Tube well boring by ODEX-165 Method of drilling at HW site including distribution system with new HDPE pipeline, Construction of 200 cum OHR as per Departmental Design & drawing, Providing FHTC and other allied works for KARTIKA TEA GARDEN PWSS under Alipurduar Division, PHE Dte. ORD/000455/2022-2023 2976/ALD 02/02/2023 180 MAHENDRA CHHETRI 238.07 191.37 90
1130 Alipurduar Division Cons. of 100 cum OHR,BOUNDARY WALL, PUMP HOUSE, TUBE, RISING MAIN FOR Mouza-MUJNAI TEA GARDEN(JL NO.39,RL Plot No.121,129 &155) 410 unit CHA SUNDARI WATER SUPPLY SCHEME UNDER ALIPURDUAR DIVISION, PHE DTE. of North Bengal Circle-I, PHE Dte. ORD/000455/2023-2024 436/ALD 07/02/2024 660 MITHUN DAS 108.05 113.06 80
1131 Alipurduar Division HDPE pipeline for leftout household connection and gap joint works under Uttar Latabari PWSS under Alipurduar Division, PHE Dte. ORD/000455/2024-2025 5172/ALD 25/02/2025 156 PRAPTI DUTTA 9.61 0.00 100
1132 Alipurduar Division Tube well boring by ODEX-165 Method of drilling at HW site including distribution system with new HDPE pipeline, Construction of 200 cum OHR as per Departmental Design & drawing, Providing FHTC and other allied works for PHASKHAWA TEA GARDEN PWSS under Alipurduar Division, PHE Dte ORD/000456/2022-2023 2977/ALD 02/02/2023 180 DILIP MAHATO 133.11 96.44 61
1133 Alipurduar Division Continuation for the work of Hiring of Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for inspection and monitoring of Jal Jeevan Mission (JJM) works under Alipurduar Division, P.H.E. Dte.(from 01.11.2023 to 31.01.2024) ORD/000456/2023-2024 2340/ALD 30/10/2023 92 NIRANJAN KIRTANIA 0.50 0.50 0
1134 Alipurduar Division Tube well boring by ODEX-165 Method of drilling at HW site including distribution system with new HDPE pipeline, Construction of 300 cum OHR as per Departmental Design & drawing, Providing FHTC and other allied works for RAYDAK TEA GARDEN PWSS under Alipurduar Division, PHE Dte. ORD/000457/2022-2023 2978/ALD 02/02/2023 180 CHINMOY BHATTACHARJEE 233.78 161.96 54
1135 Alipurduar Division Continuation for the work of Supply of fuel for Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for inspection and monitoring of Jal Jeevan Mission (JJM) works under Alipurduar Division, P.H.E. Dte.(from 01.11.2023 to 31.01.2024) ORD/000457/2023-2024 2341/ALD 30/10/2023 92 NIRANJAN KIRTANIA 0.70 0.50 0
1136 Alipurduar Division Continuation of work of Hiring of Diesel Vehicle Maxi Cab (At least 7 seater ) for Executive Engineer, Alipurduar Division, P.H.E. Dte.(from 01.01.2025 to 31.03.2025) ORD/000457/2024-2025 4552/ALD 30/12/2024 90 APSARI BHOWMICK 1.20 0.00 0
1137 Alipurduar Division Tube well boring by ODEX-165 Method of drilling at HW site including distribution system with new HDPE pipeline, Construction of 400 cum OHR as per Departmental Design & drawing, Providing FHTC and other allied works for KOHINUR TEA GARDEN PWSS under Alipurduar Division, PHE Dte. ORD/000458/2022-2023 2979/ALD 02/02/2023 360 DILIP MAHATO 237.14 203.99 86
1138 Alipurduar Division Arrangement for online application in Paribesh Portal for getting Forest permission at 7nos BOPs under Alipurduar Division P.H.E Dte. ORD/000458/2023-2024 496/ALD 16/02/2024 30 HILL GROUND CONSULTANCY 1.83 0.00 100
1139 Alipurduar Division Continuation of work of Hiring of Diesel Vehicle Maxi Cab(At least 7 seater ) for Assistant Engineer, Head Quarter, Alipurduar Division, P.H.E. Dte.(from 01.01.2025 to 31.03.2025) ORD/000458/2024-2025 4553/ALD 30/12/2024 90 DIPAK DAS 1.20 1.07 0
1140 Alipurduar Division Boring of Tube Well, Construction of Pump House, Boundary Wall, OHR (100cum) including soil testing, Laying Of Rising Main, Distribution System and providing FHTC for Ballalguri PWSS Under Alipurduar Division, PHE Dte. ORD/000459/2022-2023 2980/ALD 02/02/2023 847 DILIP MAHATO 255.82 177.55 70
1141 Alipurduar Division Soil investigation at OHR site and construction of 450cum OHR at Zone-1 for Augmentation of Birpara PWSS under Alipurduar Divisionof North Bengal Circle-I, PHE Dte. ORD/000459/2023-2024 495/ALD 16/02/2024 585 KAMALESH ROY 120.29 58.79 10
1142 Alipurduar Division Tube well Boring by ODEX-165 Method of drilling at HW, FIRST TUBE WELL site including laying distribution system with new UPVC pipeline , Constructions of 250 Cum OHR as per Departmental Design & drawing including soil investigation works , 2nos pump house & boundary wall, providing FHTC and others allied works for ATIABARI TEA GARDEN PWSS Under Alipurduar Division PHE DTE. ORD/000460/2022-2023 2981/ALD 02/02/2023 540 SOUVIK ROY PALADHI 438.53 371.60 75
1143 Alipurduar Division Laying of HDPE/DI Pipeline, horizontal boring by HDD method, bridge and culvert crossing, providing FHTC, specials repair with trial run of pipeline and allied works at Chuniajhora PWSS under Alipurduar Division, PHE Dte.(SM/14219 & SM/10179) ORD/000460/2023-2024 672/ALD 06/03/2024 240 ASHOK SAPKOTA 19.39 0.00 100
1144 Alipurduar Division Continuation of work of Hiring of Diesel Vehicle Maxi Cab(At least 7 seater ) for Assistant Engineer, Alipurduar RWS Sub-Division, P.H.E. Dte.(from 01.01.2025 to 31.03.2025) ORD/000460/2024-2025 4555/ALD 30/12/2024 90 SASANKA ROY 1.20 1.19 0
1145 Alipurduar Division Hiring of Diesel Vehicle Maxi Cab(At least 7 seater ) for Assistant Engineer, Head Quarter, Alipurduar Division, P.H.E. Dte.(from 01.01.2024 to 31.12.2024) ORD/000462/2023-2024 161/ALD 11/01/2024 366 DIPAK DAS 4.80 4.42 0
1146 Alipurduar Division Interconnection of distribution system by laying of DI and HDPE pipes along with bridge/culvert crossing and other allied works at Shrinathpur TG Adjacent to Samuktala PWSS (Zone-I) under Alipurduar Division, PHE Dte. ORD/000462/2024-2025 5288/ALD 07/03/2025 60 DEBAJYOTI SUTRADHAR 18.28 0.00 0
1147 Alipurduar Division Construction of 1 no. pump house, boundary wall, 1 no. T/W boring by ODEX- 165 method of drilling at Uttar Mendabari pwss area under Alipurduar Division, PHE Dte. ORD/000463/2024-2025 5297/ALD 07/03/2025 120 D.K & SONS 20.47 0.00 0
1148 Alipurduar Division Tube well boring by ODEX-165, Construction of pump house and boundary wall including laying distribution system with new UPVC pipeline with rising and delivery line connection, Providing FHTC and other allied works for KUMARGRAM PWSS under Alipurduar Division, PHE Dte. ORD/000464/2022-2023 3000/ALD 06/02/2023 180 ANUGRAH CONSTRUCTION PRIVATE LIMITED 1,152.29 660.00 50
1149 Alipurduar Division Supply of CIDF/CIPE pipes and specials for Jayanti TG-II Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000464/2023-2024 607/ALD 29/02/2024 30 BARMAN ENTERPRISE 8.60 1.42 61
1150 Alipurduar Division Supplying and Laying of Water supply line (using HDD/micro tunneling machine) for supply of drinking water in different areas of Alipurduar district under Alipurduar Division PHE Dte. ORD/000464/2024-2025 5287/ALD 07/03/2025 240 APEX ENGINEERING 74.36 0.00 65
1151 Alipurduar Division Supply of CI Sluice Valve and Special & CI Jeffy Coupling for Umachndrapur Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000465/2023-2024 608/ALD 29/02/2024 30 MANSAROVAR CASTING 11.95 11.95 85
1152 Alipurduar Division Providing FHTC at Southern side of Hasimara Piped Water Supply Scheme Under Alipurduar Division, PHE DTE. ORD/000466/2021-2022 2811/ALD 28/02/2022 60 MAHENDRA CHHETRI 34.74 31.27 91
1153 Alipurduar Division Cons. of pump house and Sinking of 250 mm x 200 mm X 150 mtr. big dia. TW at HW site and 2nd site, LDS with UPVC pipeline, Cons. of 350 cum OHR as per Departmental Design & drawing , providing FHTC and others allied works for MADHYA KAMAKHYAGURI PWSS Under Alipurduar Division PHE DTE. ORD/000466/2022-2023 3155/ALD 22/02/2023 180 GHOSH & SAHA CONSTRUCTION 478.58 453.17 85
1154 Alipurduar Division Laying of rising Main,Road and Calvert crossing and Balance distribution pipeline in Dalimpur(Zone-I) under Alipurduar Division,PHE Dte of North Bengal Circle-I, PHE Dte. under JJM Programme. ORD/000466/2023-2024 670/ALD 06/03/2024 300 UJJWAL ROY 132.10 121.02 80
1155 Alipurduar Division Laying of distribution of UPVC/DI/GI pipeline including FHTC for JATESWAR PWSS under Alipurduar Division, PHE DTE. PART-I ORD/000467/2021-2022 2812/ALD 28/02/2022 60 SOUVIK ROY PALADHI 98.49 96.33 63
1156 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Augmentation of Samuktala Water Supply Scheme under Alipurduar Division P.H.E. Dte. (SM/12561) ORD/000467/2023-2024 673/ALD 06/03/2024 30 BHAGWATI BHUJEL 11.36 11.34 15
1157 Alipurduar Division Extension and replacement of damaged pipeline and providing FHTC at surrounding area of Silbarihat under Patlakhawa PWSS. ORD/000468/2021-2022 2766/ALD 25/02/2022 60 TAPASH KUMAR BHOWMICK 42.34 30.19 75
1158 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Augmentation of Kohinur TG Water Supply Scheme under Alipurduar Division P.H.E. Dte.(SM/12113) ORD/000468/2023-2024 674/ALD 06/03/2024 150 BHAGWATI BHUJEL 11.36 11.33 80
1159 Alipurduar Division Extension of pipeline (UPVC) and providing FHTC at surrounding area of Salsalabari Under Alipurduar Division, PHE DTE. ORD/000469/2021-2022 2765/ALD 25/02/2022 1140 NARENDRA BHADANI. 47.70 29.58 97
1160 Alipurduar Division Laying of distribution line with HDPE,UPVC and CI/DI pipes, laying of paver block at pump house no-1 and 2 and providing FHTC for Aug. Of Tapshikhata PWSS under Alipurduar Division. ORD/000469/2023-2024 675/ALD 06/03/2024 720 TAPASH DAS 43.25 26.98 10
1161 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe along with FHTC Connection of Uttar Majherdabri WSS under Alipurduar Division, PHE Dte. (Part-A) ORD/000470/2021-2022 2870/ALD 07/03/2022 1080 DILIP MAHATO 101.03 96.04 80
1162 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe along with FHTC Connection of Uttar Majherdabri WSS under Alipurduar Division, PHE Dte. (Part-B) ORD/000471/2021-2022 2871/ALD 07/03/2022 1200 TAPAN CHANDA 100.90 74.42 100
1163 Alipurduar Division Laying of rising main line /distribution pipeline, supply of DI pipe and specials, horizontal boring by HDD method, bridge and culvert crossing, specials repair with trial run of pipeline and allied works at Aug. of Kumargram WSS under Alipurduar Division, PHE Dte. ORD/000471/2023-2024 689/ALD 07/03/2024 270 HARI CONSTRUCTION 40.90 0.00 0
1164 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe along with FHTC Connection of Uttar Majherdabri WSS under Alipurduar Division, PHE Dte. (Part-C) ORD/000472/2021-2022 2872/ALD 07/03/2022 60 MAHENDRA CHHETRI 94.52 77.53 73
1165 Alipurduar Division Constructions of pump house and Sinking of 250 mm x 200 mm X 150 mtr Big dia Tubewel at HW site , 2nd site and 3 rd Site Laying of distribution system with UPVC pipeline , Constructions of 200 Cum OHR as per Departmental Design and drawing , including the Soil investigation works providing FHTC and others allied works for Chalnipak PWSS Under Alipurduar Division PHE DTE. ORD/000472/2022-2023 3156/ALD 22/02/2023 720 SOUVIK ROY PALADHI 481.77 424.68 50
1166 Alipurduar Division Laying of DI and HDPE pipeline, trenchless pipe laying by HDD process, providing FHTC and others for Hossainabad PWSS under Alipurduar Division, PHE Dte. ORD/000472/2023-2024 690/ALD 07/03/2024 270 SASANKA ROY 62.82 34.23 80
1167 Alipurduar Division Extension of pipeline (UPVC) and providing FHTC at surrounding area of Barobisha PWSS (Part-I) Under Alipurduar Division, PHE DTE. ORD/000473/2021-2022 2763/ALD 25/02/2022 60 TAPAN CHANDA 50.32 49.23 69
1168 Alipurduar Division Hiring of Diesel Vehicle Maxi Cab (At least 7 seater ) for Deputy Superintending Engineer, North Bengal Circle-I , P.H.E. Dte.(from 01.03.2023 to 29.02.2024) ORD/000473/2022-2023 3232/ALD 27/02/2023 365 MAHENDRA CHHETRI 4.80 0.00 0
1169 Alipurduar Division Construction of Tubewell by ODEX-165 method of drilling at HWS, construction of pump house and boundary wall at HWS, laying of rising main for Aug. Of Uttar Sishubari PWSS under Alipurduar Division, PHE Dte. ORD/000473/2023-2024 691/ALD 07/03/2024 45 MITHUN DAS 31.88 0.00 0
1170 Alipurduar Division Extension of pipeline (UPVC) and providing FHTC at surrounding area of Barobisha PWSS (Part-II) Under Alipurduar Division, PHE DTE. ORD/000474/2021-2022 2764/ALD 25/02/2022 60 TAPAN CHANDA 50.32 48.74 60
1171 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling at H/W site & 2nd site including laying distribution system and providing FHTC for KALCHINI TG ZONE-II PWSS Under Alipurduar Division PHE DTE ORD/000474/2022-2023 3228/ALD 27/02/2023 120 SHREE RANISATI ENTERPRISE 179.69 0.00 0
1172 Alipurduar Division Balance portion of boundary wall and Gap joint of new HDPE/DI pipeline, and land development of HW Site,1st and 2nd site of Paschim Satali PWSS (Part) Kalchini Block Alipurduar Division, PHE Dte. ORD/000474/2023-2024 692/ALD 07/03/2024 509 DILIP MAHATO 61.82 0.00 45
1173 Alipurduar Division Extension of pipeline (UPVC) and providing FHTC at surrounding area of Chandirjhar PWSS under Alipurduar Division, PHE DTE. ORD/000475/2021-2022 2761/ALD 25/02/2022 60 MATRI ENTERPRISE 58.00 45.22 49
1174 Alipurduar Division Tube well Boring by ODEX-165 Method of drilling at HW, FIRST TUBE WELL site including laying distribution system with new HDPE pipeline , Constructions of 150 Cum OHR as per Departmental Design & drawing , TWO nos pump house & boundary wall, providing FHTC, Soil Investigation work and other allied works for BHATKHAWA TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE. ORD/000475/2022-2023 3193/ALD 27/02/2023 673 S.G. CONSTRUCTION 325.36 147.41 60
1175 Alipurduar Division Balance portion of 110 mm HDPE/DI pipe laying, boundary wall, pump house, land development for HWS and 1st site and platform for FHTC for Nimti Domohoni PWSS Alipurduar Division, PHE Dte. ORD/000475/2023-2024 693/ALD 07/03/2024 449 PINTU SAHA 79.36 5.12 30
1176 Alipurduar Division Providing FHTC at surrounding area of Radharani Piped Water Supply Scheme Under Alipurduar Division, PHE DTE. ORD/000476/2021-2022 2762/ALD 25/02/2022 60 SOUVIK ROY PALADHI 34.95 24.47 92
1177 Alipurduar Division Construction of a pump house at Old Hasimara HW Site PWSS under Alipurduar Division, PHE Dte. ORD/000476/2023-2024 694/ALD 07/03/2024 380 AMIT BARDHAN 7.20 6.41 100
1178 Alipurduar Division Laying of distribution of HDPE/DI pipeline for Jogijhora Barabak PWSS under Alipurduar Division, PHE DTE. ORD/000477/2021-2022 2896/ALD 08/03/2022 960 MS DEYS CONSTRUCTION 56.01 53.21 100
1179 Alipurduar Division Tube well Boring by ODEX-165 Method drilling at HW, First TW Site including laying distribution system with new UPVC PIPELINE, Cons. of 150cum OHR as per departmental Design & drawing , 2nos Pump House & boundary wall, providing FHTC, soil investigation works and others allied works for Rajabhat Tea Garden PWSS Under Alipurduar Division PHE DTE. (2nd call) ORD/000477/2022-2023 3194/ALD 27/02/2023 720 ASHIM KUMAR GHOSH 219.89 192.74 77
1180 Alipurduar Division Laying of UPVC and DI distribution line, repairing and renovation of 2nos pump house for Aug. Of Banchukamari PWSS Alipurduar Division, PHE Dte. ORD/000477/2023-2024 695/ALD 07/03/2024 180 DAS CONSTRUCTION 50.59 35.81 2
1181 Alipurduar Division Laying of distribution of HDPE pipeline and providing FHTC for Garochira area, Makrapara PWSS under Alipurduar Division, PHE DTE. ORD/000478/2021-2022 2897/ALD 08/03/2022 60 DILIP MAHATO 33.90 19.97 45
1182 Alipurduar Division Cons. Of pump house & TW boring by ODEX-165 method of drilling at HW & 2nd site, LDS with UPVC pipeline including rising main & delivery connection, cons. Of 100cum OHR as per departmental design & drawing along with soil investigation works, providing FHTC including platform and others allied works for NURPUR PWSS Under Alipurduar Division PHE DTE. (2nd call) ORD/000478/2022-2023 3195/ALD 27/02/2023 721 BENGAL YOUTH UN EMPLOYED ENGINEERS CO OPERATIVE SOCIETY LIMITED 182.40 141.29 95
1183 Alipurduar Division Supply of CIDF/CIPE pipes and specials & CI Jeffy Coupling for Lachman Dabri Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000478/2023-2024 696/ALD 07/03/2024 300 HARIDAS GHOSH 18.07 18.07 65
1184 Alipurduar Division Extension and replacement of damaged pipeline and providing FHTC at surrounding area of Salkumarhat PWSS, Alipurduar-I Block under Alipurduar Division, PHE Dte. ORD/000479/2021-2022 2898/ALD 08/03/2022 1381 DILIP MAHATO 48.52 6.40 65
1185 Alipurduar Division Construction of 700cum OHR for Augmentation of HASIMARA Water Supply Scheme under Alipurduar Division, PHE Dte.(3rd call) ORD/000479/2022-2023 3196/ALD 27/02/2023 180 BRAJA GOPAL SAHA 121.92 85.66 90
1186 Alipurduar Division Supply of CIDF/CIPE pipes and specials & Sluice Valve for Paschim Satali Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000479/2023-2024 697/ALD 07/03/2024 90 SSPR VALVE MANUFACTURING PVT LTD 18.08 18.08 80
1187 Alipurduar Division Laying of distribution of HDPE/DI pipeline for TURTURI TG area, Kaijali Busty PWSS under Alipurduar Division, PHE DTE. ORD/000480/2021-2022 2899/ALD 08/03/2022 60 ASHOK SAPKOTA 34.24 32.92 68
1188 Alipurduar Division Boring of Tube Well, Construction of Pump House, Boundary Wall, Laying Of Rising Main, Distribution System for Augmentation of Dakshin Sonapur PWSS under Alipurduar Division, PHE Dte. (2nd call) ORD/000480/2022-2023 3197/ALD 27/02/2023 900 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 171.88 83.31 35
1189 Alipurduar Division Supply of CIPE Special & CI Jeffy Coupling for Kayakhata Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000480/2023-2024 698/ALD 07/03/2024 30 HARI CONSTRUCTION 15.33 15.33 85
1190 Alipurduar Division Withdrawing and relaying and laying of UPVC/DI/MS/CI distribution pipeline and other misc. works for Dhumchipara PWSS under Alipurduar Division, PHE Dte. ORD/000481/2021-2022 2900/ALD 08/03/2022 60 MITHUN DAS 25.93 25.83 100
1191 Alipurduar Division Laying distribution line, providing road and culvert crossing, and providing FHTC for Jogendrapur and Satpukuria Mouzas and adjacent areas, Cons. of Tubewell by ODEX-165 method of drilling, cons. of pump house and boundary wall for augmentation of JOGENDRAPUR PWSS. (2nd call) ORD/000481/2022-2023 3198/ALD 27/02/2023 180 BIJOY ROY 159.61 67.65 25
1192 Alipurduar Division Supply of CIDF/CIPE Pipes and Special & CI Jeffy Coupling for Purba Khalishamari Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000481/2023-2024 699/ALD 07/03/2024 30 HARI CONSTRUCTION 15.31 15.31 70
1193 Alipurduar Division Laying of additional dedicated HDPE pipeline near PH No-1 village for the Hantapara WSS under Alipurduar Division, PHE Dte. ORD/000482/2021-2022 2904/ALD 08/03/2022 60 SUBIR GHOSH 11.78 8.03 39
1194 Alipurduar Division Balance work of construction of boundary wall & repairing of pump house at 2nd Tubewell site of Uttar Majherdabri WSS under Alipurduar Division, PHE Dte. ORD/000483/2021-2022 2659/ALD 21/02/2022 45 TAPASH KUMAR BHOWMICK 4.49 3.62 73
1195 Alipurduar Division Distribution line for Lankapara Sukundi line and adjoining areas for Augmentation of Lankapara TG for Lonkapara Hat PWSS under Birpara Sub-Division, Alipurduar Division, PHE Dte. ORD/000483/2022-2023 3318/ALD 13/03/2023 714 SHYAMAL ROY 18.77 12.60 87
1196 Alipurduar Division Supply of CIDF/CIPE pipes and specials & CI Jeffy Coupling for Kalchini TG Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000483/2023-2024 739/ALD 12/03/2024 30 MADHAB SAHA 13.81 0.00 0
1197 Alipurduar Division Balance work of construction of boundary wall (2nd site) at Loknathpur WSS under Alipurduar Division PHE Dte. ORD/000484/2021-2022 .2657/ALD 21/02/2022 45 GOUTAM KUMAR DAS 4.47 0.00 0
1198 Alipurduar Division Supply of CIDF/CIPE Pipes and Special & CI Jeffy Coupling for Brajerkuthi Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000484/2023-2024 740/ALD 12/03/2024 30 TAPASH KUMAR BHOWMICK 17.30 8.49 51
1199 Alipurduar Division Supply of CIDF/CIPE Pipes and Special & CI Jeffy Coupling for Tasati TG Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000485/2023-2024 741/ALD 12/03/2024 30 MADHAB SAHA 12.19 0.00 0
1200 Alipurduar Division Laying of rising main line with HDPE PN10, horizontal boring by HDD method, bridge and culvert crossing, construction of pathway, surface drain and chatal, installation of paver block along with the others allied works at Madhya Parokata head works site PWSS adjacent to adjacent to Purba Chikliguri WSS under Alipurduar Division, PHE Dte. ORD/000486/2023-2024 742/ALD 12/03/2024 450 SOUVIK ROY PALADHI 57.31 0.00 30
1201 Alipurduar Division Construction of Pump House, Boundary Wall, Tube well Boring by ODEX-165 Method of drilling including providing FHTC and Rising main for JAY BIRPARA TG AREA PWSS under Alipurduar Division PHE DTE. ORD/000487/2021-2022 2911/ALD 08/03/2022 120 ALOK ENTERPRISE 156.25 64.37 50
1202 Alipurduar Division Land Development, Paver Block installation and Laying and distribution of UPVC pipeline at 2nd Pumphouse site and Adjacent Area of Bakla PWSS under Alipurduar Division, PHE Dte. ORD/000487/2022-2023 3319/ALD 13/03/2023 90 SHYAMAL ROY 11.10 10.92 100
1203 Alipurduar Division Construction of boulder apron for Dimdima PWSS in sishujhumra mouza for protection of existing HW site under Alipurduar Division. ORD/000487/2023-2024 743/ALD 12/03/2024 135 SUBIR GHOSH 4.03 1.08 10
1204 Alipurduar Division Land development works at headwork site and laying of new UPVC/DI pipeline for filling gap in distribution system Samuktala Zone-III PWSS under Alipurduar Division, PHE Dte. ORD/000488/2022-2023 3320/ALD 13/03/2023 60 BHAGWATI BHUJEL 9.19 9.15 100
1205 Alipurduar Division Construction of boulder apron for Dhumchipara PWSS for protection of existing Pump house under Alipurduar Division. ORD/000488/2023-2024 744/ALD 12/03/2024 45 MANI PRADHAN 3.59 3.58 50
1206 Alipurduar Division Soil investigation work for Cha Sundori Project at 4 different places of Lankapara TG (3 nos GLR & 1 No OHR) within Alipurduar District under Alipurduar Division PHE Dte. ORD/000489/2021-2022 .2660/ALD 21/02/2022 30 GLORY ENGINEERS SYNDICATE 4.89 4.89 80
1207 Alipurduar Division Laying of UPVC pipeline for filling of Gap in distribution system Samuktala Zone-I PWSS under Alipurduar Division, PHE Dte. ORD/000489/2022-2023 3321/ALD 13/03/2023 60 CHANDAN KIRTONIA 5.37 5.37 0
1208 Alipurduar Division Balance portion of boundary wall and pump house and land development of HW site, 1st site and construction of culvert and platform for BEECH TG PWSS under Kalchini Block, Alipurduar Division, PHE Dte. ORD/000491/2023-2024 747/ALD 12/03/2024 710 MAHENDRA CHHETRI 29.65 28.95 100
1209 Alipurduar Division Providing FHTC in school in Paitkapara PWSS under Alipurduar Division P.H.E Dte. ORD/000492/2022-2023 3356/ALD 14/03/2023 30 HARIDAS GHOSH 0.07 0.00 100
1210 Alipurduar Division Laying of Rising main, delivery main, bypass arrangement, laying of HDPE pipeline for left out household connecting to Narasingpur PWSS (both H/W and 2nd site) (SM/15758) of Birpara Sub-Division under Alipurduar Division, PHE Dte. ORD/000492/2023-2024 748/ALD 12/03/2024 120 DILIP MAHATO 91.41 79.14 85
1211 Alipurduar Division Providing FHTC in school in Banchukamari PWSS under Alipurduar Division P.H.E Dte. ORD/000493/2022-2023 3357/ALD 14/03/2023 30 HARI CONSTRUCTION 0.87 0.00 100
1212 Alipurduar Division Sinking of Big dia. Tubewell (200 x 150 mm dia.)by modified DTH -ODEX method of drilling at Paschim Khairbari PWSS(SM/10672) and Birpara PWSS Zone-II, 4th TW site(SM/14233)of Birpara Sub-Division under Alipurduar Division, PHE Dte. ORD/000493/2023-2024 749/ALD 12/03/2024 135 EFFLUENT AND WATERTREATMENT ENGINEERS PVT LTD 33.26 25.29 50
1213 Alipurduar Division Providing FHTC in school in Loknathpur PWSS under Alipurduar Division P.H.E Dte. ORD/000494/2022-2023 3358/ALD 14/03/2023 30 HARIDAS GHOSH 0.22 0.00 100
1214 Alipurduar Division Sinking big dia. Tube well of 250mm X 200mm dia. Using MS slotted strainer at required depth by Reverse Rotary Method of drilling at 2nd site for Aug. of Jateswar PWSS (SM/10156) of Birpara Sub-Division under Alipurduar Division, PHE Dte. ORD/000494/2023-2024 750/ALD 12/03/2024 90 EFFLUENT AND WATERTREATMENT ENGINEERS PVT LTD 20.48 19.91 100
1215 Alipurduar Division Supply of different materials for Alipurduar Divisional Stack Yard under Alipurduar Division, PHE Dte. ORD/000495/2021-2022 939/ALD 08/09/2021 30 EXECUTIVE ENGINEER, RESOURCE DIVISION 1,200.00 1,200.00 0
1216 Alipurduar Division Providing FHTC in school in Bholardabri PWSS under Alipurduar Division P.H.E Dte. ORD/000495/2022-2023 3359/ALD 14/03/2023 30 HARIDAS GHOSH 0.25 0.25 100
1217 Alipurduar Division Conceptualization, design and implementing mass awareness generation through Wall writing at 113 nos. villages (Block - Falakata, Kalchini, Madarihat) by dissemination of awareness generation IEC messages FHTC, Provision on legal provision damage or illegal connection of PWSS; safe handling & storage of safe water Quality issues, water conservation and WASH related issues as per guideline of JJM at Alipurduar district under Alipurduar Division, PHE Dte, Govt. of West Bengal.(SM/16506) ORD/000495/2023-2024 751/ALD 12/03/2024 130 LIMRA SOCIAL WELFARE SOCIETY 27.08 26.66 100
1218 Alipurduar Division Providing FHTC in school in Uttar Majherdabri PWSS under Alipurduar Division P.H.E Dte. ORD/000496/2022-2023 3360/ALD 14/03/2023 30 HARIDAS GHOSH 0.22 0.22 100
1219 Alipurduar Division Conceptualization, design and implementing mass awareness generation through Wall writing at 20 nos. villages (Block - Kalchini) by dissemination of awareness generation IEC messages FHTC, Provision on legal provision damage or illegal connection of PWSS; safe handling & storage of safe water Quality issues, water conservation and WASH related issues as per guideline of JJM at Alipurduar district under Alipurduar Division, PHE Dte, Govt. of West Bengal. (SM/13248) ORD/000496/2023-2024 752/ALD 12/03/2024 60 M/S SARKAR & CO 4.76 4.68 100
1220 Alipurduar Division Laying Distribution pipe with DI and UPVC pipe along with FHTC Connection of Uttar Majherdabri WSS under Alipurduar Division, PHE Dte. (Part-D) ORD/000497/2021-2022 3002/ALD 15/03/2022 60 M/S DUTTA AND CO 95.57 74.72 71
1221 Alipurduar Division Providing FHTC in school in Salsalabari PWSS under Alipurduar Division P.H.E Dte. ORD/000497/2022-2023 3361/ALD 14/03/2023 30 HARIDAS GHOSH 0.29 0.29 100
1222 Alipurduar Division Conceptualization, design and implementing mass awareness generation through Wall writing at 22 nos. villages (Block - Madarihat) by dissemination of awareness generation IEC messages FHTC, Provision on legal provision damage or illegal connection of PWSS; safe handling & storage of safe water Quality issues, water conservation and WASH related issues as per guideline of JJM at Alipurduar district under Alipurduar Division, PHE Dte, Govt. of West Bengal.( SM/15482) ORD/000497/2023-2024 753/ALD 12/03/2024 30 BARMAN ENTERPRISE 5.27 5.27 100
1223 Alipurduar Division Restoration of Laying Distribution system by replacing damaged AC pipeline with DI and UPVC pipe for TATPARA WSS under Alipurduar Division, PHE Dte. (Part-B) ORD/000498/2021-2022 3003/ALD 15/03/2022 60 PROGRESSIVE UNEMPLOYED CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 39.20 37.80 98
1224 Alipurduar Division Providing FHTC in school in Josodanga PWSS under Alipurduar Division P.H.E Dte. ORD/000498/2022-2023 3362/ALD 14/03/2023 30 HARI CONSTRUCTION 0.36 0.36 100
1225 Alipurduar Division Hiring of Diesel Vehicle Maxi Cab(At least 7 seater ) for Assistant Engineer, Alipurduar Sadar Sub-Division, P.H.E. Dte. (from 01.01.2024 to 31.12.2024) ORD/000498/2023-2024 487/ALD 15/02/2024 366 MATRI ENTERPRISE 4.80 0.00 0
1226 Alipurduar Division Retrofitting of pipeline with DI/UPVC pipeline for JAL SWAPNO programme (FHTC for every household) for LOKNATHPUR WSS under Alipurduar Division, PHE Dte. ORD/000499/2021-2022 3004/ALD 15/03/2022 60 HIMALAYAN CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 20.09 16.34 0
1227 Alipurduar Division Supply ,delivery and installation of split type air condition for the Chamber of Division Account Office under Alipurduar Division , P.H.E Dte. ORD/000499/2022-2023 3363/ALD 14/03/2023 30 HARI CONSTRUCTION 0.64 0.00 0
1228 Alipurduar Division Hiring of Diesel Vehicle Maxi Cab(At least 7 seater ) for Assistant Engineer, Alipurduar RWS Sub-Division, P.H.E. Dte.(from 01.01.2024 to 31.12.2024) ORD/000499/2023-2024 488/ALD 15/02/2024 366 SASANKA ROY 4.80 3.54 0
1229 Alipurduar Division Supply ,delivery and installation of split type air condition for the Accounts section under Alipurduar Division , P.H.E Dte. ORD/000500/2022-2023 3364/ALD 14/03/2023 30 HARI CONSTRUCTION 0.64 0.00 0
1230 Alipurduar Division Hiring of Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for inspection and monitoring of Jal Jeevan Mission (JJM) works under Alipurduar Division, P.H.E. Dte..(from 01.02.2024 to 31.01.2025) ORD/000500/2023-2024 372/ALD 31/01/2024 366 CHANDAN KIRTONIA 4.80 4.25 0
1231 Alipurduar Division Construction of pump house, boundary wall and Rising main for 4th Tube well site at Paschim Khairbari PWSS of Birpara Sub-Division under Alipurduar Division, PHE Dte. (SM/10672) ORD/000501/2023-2024 819/ALD 14/03/2024 807 TAPASH KUMAR BHOWMICK 16.68 0.00 70
1232 Alipurduar Division Boring of TW, Construction of Pumphouse, Boundary wall, Laying of Distribution system for Augmentation of Dhumchipara PWSS under Alipurduar Division, PHE Dte. ORD/000502/2022-2023 3324/ALD 13/03/2023 840 GIRIRAJ ENTERPRISE 22.78 18.97 70
1233 Alipurduar Division Balance work of rising main, delivery main, bypass arrangement, land development, pipeline for left out household connection and other allied works at Augmentation of Dalimpur(Zone-3)(H/W site) of Birpara Sub-Division under Alipurduar Division, PHE Dte. (SM/18254) ORD/000502/2023-2024 820/ALD 14/03/2024 480 UJJWAL ROY 41.61 0.00 40
1234 Alipurduar Division Laying of DI and HDPE pipeline, Trenchless Pipe laying by HDD Process & other works for PURBA KATHALBARI ZONE-I 3rd pump house area for Purba Kathalbari PWSS of Alipurduar RWS Sub-Division under Alipurduar Division, PHE Dte. (SM/11459) ORD/000503/2023-2024 821/ALD 14/03/2024 480 KAJAL KUMAR DE 39.26 0.00 70
1235 Alipurduar Division Cons. of pump house at 2nd site, laying of UPVC pipeline for left out household connection and rising main with CIDF pipe and specials and other allied works for Augmentation of Jateswar PWSS of Birpara Sub-Division under Alipurduar Division, PHE Dte.(SM/10156) ORD/000504/2023-2024 822/ALD 14/03/2024 480 TAPASH DAS 50.51 13.50 75
1236 Alipurduar Division Providing FHTC in school in Loknathpur PWSS under Alipurduar Division P.H.E Dte. ORD/000505/2022-2023 .3358/ALD 14/03/2023 30 HARIDAS GHOSH 0.22 0.00 100
1237 Alipurduar Division Replacement of damaged pipeline with HDPE and DI pipes for Dhumchipara PWSS of Alipurduar RWS Sub-Division under Alipurduar Division, PHE Dte. (SM/09896) ORD/000505/2023-2024 823/ALD 14/03/2024 60 MONORAMA ENTERPRISE 5.73 0.00 5
1238 Alipurduar Division Protective and Decorative Acrylic exterior paint on existing 350 cum OHR at Birpara of Birpara Sub-Division under Alipurduar Division, P.H.E.Dte. (SM/14233) ORD/000506/2023-2024 824/ALD 14/03/2024 60 BHAGWATI BHUJEL 1.96 1.95 10
1239 Alipurduar Division Protective and Decorative Acrylic exterior paint on existing 350 cum OHR at Dimdima of Birpara Sub-Division under Alipurduar Division, P.H.E.Dte. (SM/07068) ORD/000507/2023-2024 825/ALD 14/03/2024 60 BHAGWATI BHUJEL 1.96 1.94 10
1240 Alipurduar Division Constructions of pump house & Tube well Boring by ODEX-165 Method of drilling at HW site & 2nd site , laying of distribution system with UPVC pipeline , Constructions of 200 Cum OHR as per Departmental Design & drawing , providing FHTC and others allied works for Chuota Daldali PWSS Under Alipurduar Division PHE DTE. ORD/000508/2022-2023 3393/ALD 16/03/2023 777 DAS CONSTRUCTION 278.20 126.18 65
1241 Alipurduar Division Repairing bottom dome, conical, shell wall etc. of existing Dalmore 350 cum OHR including protective and Decorative Acrylic exterior paint of Birpara Sub-Division under Alipurduar Division, P.H.E.Dte. (SM/07132) ORD/000508/2023-2024 826/ALD 14/03/2024 90 BHAGWATI BHUJEL 4.79 4.79 100
1242 Alipurduar Division Cons. of Rig bored TW(2nos) by ODEX-165 method of drilling at HW and 2nd site, cons of 100 cum OHR at HW including soil testing, cons. of P/H and B/W at HW,2nd site, Laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Dakshin Rangalibazna PWSS under Birpara Sub-Division, Alipurduar Division, PHE DTE. ORD/000509/2022-2023 3396/ALD 16/03/2023 180 S.G. CONSTRUCTION 247.26 77.23 32
1243 Alipurduar Division Construction of boundary wall for Jogijhora Barabak PWSS of Birpara Sub-Division under Alipurduar Division, P.H.E. Dte. (SM/10169) ORD/000509/2023-2024 827/ALD 14/03/2024 60 MANI PRADHAN 2.50 0.00 95
1244 Alipurduar Division Boring of Tube Well, Construction of Pump House, Boundary Wall, OHR (150 cum) including soil testing, Laying Of Rising Main, Distribution System and providing FHTC for Pararpar PWSS Under Alipurduar Division, PHE Dte. (2nd call) ORD/000510/2022-2023 3397/ALD 16/03/2023 900 SASANKA ROY 324.42 219.59 3
1245 Alipurduar Division Laying of HDPE Pipeline for left out household connection, boundary wall, pump house, OHR, Land Development, Pathway Platform for FHTC and allied works at Bhatpara PWSS under Alipurduar Division, P.H.E. Dte. (SM/14212) ORD/000510/2023-2024 828/ALD 14/03/2024 700 MAHENDRA CHHETRI 47.40 42.11 100
1246 Alipurduar Division Tube well Boring by ODEX-165 Method of drilling at HW, FIRST TUBE WELL site including laying distribution system with new HDPE pipeline , Constructions of 150 Cum OHR as per Departmental Design & drawing , TWO nos. pump house & boundary wall, providing FHTC, Soil Investigation work and others allied works for BEECH TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE. (2nd call) ORD/000511/2022-2023 3398/ALD 16/03/2023 540 MAHENDRA CHHETRI 309.23 304.60 91
1247 Alipurduar Division Laying of rising main, delivery main, bypass arrangement, Laying of HDPE Pipeline for left out household connection and other allied works at Dhanirampur PWSS (both H/W and 2nd site) of Birpara Sub-Division under Alipurduar Division, P.H.E. Dte. (SM/15208) ORD/000511/2023-2024 829/ALD 14/03/2024 45 DILIP MAHATO 58.70 47.31 70
1248 Alipurduar Division Boring of Tube Well, Construction of Pump House, Boundary Wall, OHR, Laying Of Rising Main, Distribution System including soil test and providing FHTC for Prodhanpara PWSS Under Alipurduar Division, PHE Dte. (2nd call) ORD/000512/2022-2023 3394/ALD 16/03/2023 838 MESSRS A.B.G CONSTRUCTION 425.86 169.60 20
1249 Alipurduar Division Road crossing, hume pipe culvert crossing, and bridge crossing by G.I. pipe at Dalimpur Zone-III PWSS including Laying of UPVC Pipeline for left out household connection of Birpara Sub-Division under Alipurduar Division, P.H.E. Dte. (SM/18254) ORD/000512/2023-2024 830/ALD 14/03/2024 60 MITHUN DAS 9.04 8.79 10
1250 Alipurduar Division Supply of DI Special and CI Jeffy Coupling for Mathura TG Water Supply Scheme (SM/10172) of Alipurduar-I Block under Alipurduar Division P.H.E. Dte. ORD/000513/2023-2024 831/ALD 14/03/2024 60 TAPASH KUMAR BHOWMICK 11.60 10.93 50
1251 Alipurduar Division Cons. of pump house and Sinking of 250 mm x 200 mm X 150 mtr. big dia. TW at HW site and 2nd site, LDS with UPVC pipeline, Cons. of 200 cum OHR as per Departmental Design & drawing including soil investigation works, providing FHTC and others allied works for KAYAKHATA PWSS Under Alipurduar Division PHE DTE. (2nd call) ORD/000514/2022-2023 3395/ALD 16/03/2023 1022 GOUTAM KUMAR DAS 316.20 243.76 43
1252 Alipurduar Division Supply of DI specials and CI Jeffy coupling for Purba Narathali Water Supply Scheme(SM/16537) of Kumargram Block under Alipurduar Division P.H.E. Dte. ORD/000514/2023-2024 833/ALD 14/03/2024 30 DILIP MAHATO 13.51 0.00 0
1253 Alipurduar Division Collectio of house hold details at prescribrd format through mobile app/Hard Copy including Geo-reference as directed by the E.I.C. and submission the same to PHE Dte. in soft copy.(Part-B) ORD/000515/2020-2021 844/ALD 13/10/2020 60 TAPASH KUMAR BHOWMICK 0.98 1.96 0
1254 Alipurduar Division Construction of pumphouse, boundary wall,laying of UPVC pipeline & rising main connection for Salsalabari PWSS proposed 4th TW site PWSS under Alipurduar Division, PHE Dte. ORD/000515/2022-2023 3400/ALD 16/03/2023 90 BRAJA GOPAL SAHA 39.58 0.00 0
1255 Alipurduar Division Supply of DI specials and CI Jeffy coupling for Telipara Water Supply Scheme (SM/13303) of Kumargram Block under Alipurduar Division P.H.E. Dte. ORD/000515/2023-2024 834/ALD 14/03/2024 360 HARI CONSTRUCTION 13.58 11.52 80
1256 Alipurduar Division Entry of data for house Connection (JJM) of PWSS in website under Alipurduar division, PHE Dte. (Part-B) ORD/000516/2020-2021 845/ALD 13/10/2020 60 TAPASH KUMAR BHOWMICK 0.96 1.92 0
1257 Alipurduar Division Laying of new UPVC/DI pipeline for replacement of 75mm dia UPVC pipe with 90mm dia pipeline, gap filling and re distribution of branch line in the distribution system along with the others allied works under Munshipara PWSS under Alipurduar Division, PHE Dte. ORD/000516/2022-2023 3401/ALD 16/03/2023 955 NARENDRA BHADANI. 90.61 51.29 85
1258 Alipurduar Division Supply of DI specials and CI Jeffy coupling for Raydak TG Water Supply Scheme(SM/12114) of Kumargram Block under Alipurduar Division P.H.E. Dte. ORD/000516/2023-2024 835/ALD 14/03/2024 360 HARI CONSTRUCTION 15.18 8.28 80
1259 Alipurduar Division Collectio of house hold details at prescribrd format through mobile app/Hard Copy including Geo-reference as directed by the E.I.C. and submission the same to PHE Dte. in soft copy.(Part-C) ORD/000517/2020-2021 1091/ALD 02/12/2020 60 HARIDAS GHOSH 0.98 1.96 0
1260 Alipurduar Division Boring of TW, Construction of Pumphouse, Boundary wall, Laying of Distribution system for Augmentation of Hantupara PWSS under Alipurduar Division, PHE Dte. ORD/000517/2022-2023 3317/ALD 13/03/2023 585 DULAL DAS 23.80 20.28 98
1261 Alipurduar Division Entry of data for house Connection (JJM) of PWSS in website under Alipurduar division, PHE Dte. (Part-C) ORD/000518/2020-2021 1092/ALD 02/12/2020 60 HARIDAS GHOSH 0.96 1.92 0
1262 Alipurduar Division CONS of PH and Sinking of 250 mm x 200 mm X 150 mtr Big dia TW at HW site and 2nd site , LDS with UPVC P/LINE , CONS of 200 Cum OHR , incl the Soil investigation works, providing FHTC and others allied works for Uttar Majidkhana PWSS Under Alipurduar Division PHE DTE. ORD/000518/2022-2023 3416/ALD 17/03/2023 925 TAPASH KUMAR BHOWMICK 490.21 376.32 95
1263 Alipurduar Division Construction of pump House, boundary wall, laying of UPVC pipe linr & Rising main connection for Purba Chepani PWSS proposed 4th TW SITE under Alipurduar Division, PHE Dte. ORD/000519/2022-2023 3494/ALD 23/03/2023 90 PROGRESSIVE UNEMPLOYED CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 41.66 20.16 48
1264 Alipurduar Division Supply of DIDF pipes and DI specials and CI Jeffy Coupling for Dhanirampur Water Supply Scheme (SM/15208) of Falakata Block under Alipurduar Division P.H.E. Dte. ORD/000519/2023-2024 838/ALD 14/03/2024 30 BARMAN ENTERPRISE 9.78 9.78 90
1265 Alipurduar Division Boring of TW, Construction of PH, B/Wall and LDS for Augmentation of Gargenda PWSS under Alipurduar Division, PHE Dte. ORD/000520/2022-2023 3473/ALD 22/03/2023 480 SHYAMAL ROY 36.57 18.74 60
1266 Alipurduar Division Supply of DIDF pipes and specials and Sluice Valve for Rangamati TG Water Supply Scheme (SM/14213) of Kalchini Block under Alipurduar Division P.H.E. Dte. ORD/000520/2023-2024 839/ALD 14/03/2024 360 SSPR VALVE MANUFACTURING PVT LTD 16.24 7.38 15
1267 Alipurduar Division Supply of CIDF/CIPE pipes and specials and Sluice Valve for Atiabari TG Water Supply Scheme(SM/14092) of Kalchini Block under Alipurduar Division P.H.E. Dte. ORD/000521/2023-2024 840/ALD 14/03/2024 459 MADHAB SAHA 16.01 0.00 15
1268 Alipurduar Division Supply of DI specials and CI Jeffy coupling for Kartika TG Water Supply Scheme (SM/11991) of Kumargram Block under Alipurduar Division P.H.E. Dte. ORD/000522/2023-2024 841/ALD 14/03/2024 30 MANSAROVAR CASTING 13.34 13.34 92
1269 Alipurduar Division Extension of pipeline for implementation of FHTC at Bandapani TG Area attached with Nangdala TG (for Dimdima PWSS Zone-II) under Alipurduar Division, PHE Dte. ORD/000523/2021-2022 2997/ALD 15/03/2022 60 DILIP MAHATO 15.04 15.04 87
1270 Alipurduar Division Supply of DI specials and CI Jeffy coupling for Baruipara Water Supply Scheme (SM/13241) of Kumargram Block under Alipurduar Division P.H.E. Dte. ORD/000523/2023-2024 842/ALD 14/03/2024 187 MAKALI ENGINEERING CORPORATION 15.15 15.15 55
1271 Alipurduar Division Laying of HDPE pipe line for Dalmore Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000524/2021-2022 2996/ALD 15/03/2022 60 MS DEYS CONSTRUCTION 8.33 7.04 58
1272 Alipurduar Division "Supply of DIDF Pipes and DI Special and CI Jeffy Coupling for Augmentation of Nathoatari Water Supply Scheme (SM/12754) of Alipurduar-I Block under Alipurduar Division P.H.E. Dte. " ORD/000524/2023-2024 843/ALD 14/03/2024 183 MAKALI ENGINEERING CORPORATION 14.43 14.43 25
1273 Alipurduar Division "Supply of DIDF Pipes and DI Special and CI Jeffy Coupling for Purba Chikliguri Water Supply Scheme(SM/13301) of Alipurduar-II Block under Alipurduar Division P.H.E. Dte. " ORD/000525/2023-2024 844/ALD 14/03/2024 186 MAKALI ENGINEERING CORPORATION 15.23 15.23 25
1274 Alipurduar Division "Supply of DIDF Pipes and DI Special and CI Jeffy Coupling for Kadambini TG Water Supply Scheme (SM/13239) of Falakata Block under Alipurduar Division P.H.E. Dte. " ORD/000526/2023-2024 845/ALD 14/03/2024 30 MANSAROVAR CASTING 13.20 0.00 0
1275 Alipurduar Division "Supply of DIDF Special and CI Jeffy Coupling for Dalgaon TG Water Supply Scheme(SM/16823) of Falakata Block under Alipurduar Division P.H.E. Dte. " ORD/000527/2023-2024 846/ALD 14/03/2024 90 MADHAB SAHA 16.41 16.41 62
1276 Alipurduar Division "Supply of DIDF Special and CI Jeffy Coupling for Uttar Deogaon TG Water Supply Scheme(SM/16817) of Falakata Block under Alipurduar Division P.H.E. Dte. " ORD/000528/2023-2024 847/ALD 14/03/2024 90 SOUVIK ROY PALADHI 16.48 16.48 59
1277 Alipurduar Division Supply of CI Sluice Valve and Special and CI Jeffy Coupling for Paschim Deogaon Water Supply Scheme(SM/15207) of Falakata Block under Alipurduar Division P.H.E. Dte. ORD/000529/2023-2024 848/ALD 14/03/2024 90 SOUVIK ROY PALADHI 18.86 18.86 90
1278 Alipurduar Division Laying of different dia., CIDF, DI, UPVC, HDPE Pipeline, Trenchless Pipe laying by HDD Process, HDPE pipe line for left out household connection, Trial and run the entire PURBA KATHALBARI ZONE-4 PWSS Scheme with maintaining for 3 months after successfully running water, cons. of surface drain, pathway at H/W site and other works for Purba Kathalbari PWSS of Alipurduar RWS Sub-Division under Alipurduar Division, PHE Dte. (SM/11459) ORD/000530/2023-2024 849/ALD 14/03/2024 360 NARENDRA BHADANI. 57.56 24.23 100
1279 Alipurduar Division Cons. of pump house, boundary wall and Rising Main for Zone-II 4thTube well site at Aug. of Birpara PWSS of Birpara Sub-Division under Alipurduar Division, PHE Dte. (SM/14233) ORD/000531/2023-2024 850/ALD 14/03/2024 360 RATAN DUTTA 18.26 3.06 65
1280 Alipurduar Division Laying Distribution pipe with DI pipe with pillar of TATPARA WSS under Alipurduar Division, PHE Dte. ORD/000532/2021-2022 3106/ALD 24/03/2022 60 HARI CONSTRUCTION 7.06 6.94 98
1281 Alipurduar Division Sinking of Big dia. Tubewell (200 x 150 mm dia.)by modified DTH -ODEX method of drilling at Gargenda-1 no site (SM/16824) of Birpara Sub-Division under Alipurduar Division, PHE Dte. ORD/000532/2023-2024 890/ALD 15/03/2024 180 EFFLUENT AND WATERTREATMENT ENGINEERS PVT LTD 17.23 15.62 5
1282 Alipurduar Division Restoration of laying distribution system by replacing of damaged AC Pipeline with UPVC pipeline of Bholardabri Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000533/2021-2022 3107/ALD 24/03/2022 60 HARI CONSTRUCTION 56.51 51.82 100
1283 Alipurduar Division Sinking of Big dia. Tubewell (200 x 150 mm dia.)By modified DTH -ODEX method of drilling at Dhumchipara-2nos. site (SM/09896 & SM/16824) of Birpara Sub-Division under Alipurduar Division, PHE Dte. ORD/000533/2023-2024 891/ALD 15/03/2024 180 EFFLUENT AND WATERTREATMENT ENGINEERS PVT LTD 34.47 28.84 10
1284 Alipurduar Division Laying of different dia., CIDF, DI, UPVC, HDPE Pipeline, Trenchless Pipe laying by HDD Process, HDPE pipe line for left out household connection,Trial and run the entire PURBA KATHALBARI ZONE-3 PWSS Scheme with maintaining for 3 months after successfully running water, cons. of surface drain, pathway at H/W site and other works works for Purba Kathalbari PWSS of Alipurduar RWS Sub-Division under Alipurduar Division, PHE Dte. (SM/11459) ORD/000534/2023-2024 892/ALD 15/03/2024 355 MADHAB SAHA 49.29 4.78 60
1285 Alipurduar Division Supply of DI specials and CI Jeffy coupling for Nimjhora TG Water Supply Scheme(SM/14215) of Kalchini Block under Alipurduar Division P.H.E. Dte. ORD/000535/2023-2024 851/ALD 14/03/2024 30 MANSAROVAR CASTING 13.34 13.34 50
1286 Alipurduar Division Supply of DIDF Pipes and DI Special and CI Jeffy Coupling for Mathura Tea Garden Area Piped Water Supply Scheme (SM-10172) of Alipurduar - I Block under Alipurduar Division PHE Dte. ORD/000536/2023-2024 852/ALD 14/03/2024 30 GUHA ENTERPRISE 11.62 11.62 75
1287 Alipurduar Division Construction of 150cum OHR as per Departmental Design & drawing, laying of rising main & delivery connection, Supply of CIDF specials and others allied works for Bhatibari Zone -IV PWSS Under Alipurduar Division PHE Dte. ORD/000537/2023-2024 895/ALD 15/03/2024 690 KAMALESH ROY 98.47 50.36 50
1288 Alipurduar Division Hiring of Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for Assistant Engineer ,Birpara Sub- Division ,P.H.E. Dte..(from 01.04.2024 to 01.03.2025) ORD/000538/2023-2024 893/ALD 15/03/2024 365 PARITOSH SUTRADHAR 4.80 4.78 0
1289 Alipurduar Division Laying of UPVC/DI/MS/CI distribution pipe line for gap filling and FHTC connection for Sahapara and adjoining area of Jateswar PWSS under Alipurduar Division, PHE Dte. ORD/000539/2021-2022 3191/ALD 28/03/2022 60 AASHIRBAD ENTERPRISE 12.35 10.78 78
1290 Alipurduar Division Laying of distribution pipeline with DI and UPVC pipes for interconnection of Dhaolajhora PWSS with Loknathpur PWSS under Alipurduar Division, PHE Dte. ORD/000540/2021-2022 3192/ALD 28/03/2022 60 GOUTAM KUMAR DAS 49.89 31.80 81
1291 Alipurduar Division Laying of HDPE pipe line for left out house hold connection at Ethelbari TG PWSS(SM/13449) of Birpara Sub-Division under Alipurduar Division, PHE Dte. ORD/000540/2023-2024 894/ALD 15/03/2024 360 DILIP MAHATO 18.65 0.00 100
1292 Alipurduar Division Supply of CI Sluice Valve and Special & CI Jeffy Coupling for Benkandi Water Supply Scheme under Alipurduar Division P.H.E. Dte. ORD/000541/2023-2024 754/ALD 12/03/2024 90 SSPR VALVE MANUFACTURING PVT LTD 12.88 12.88 15
1293 Alipurduar Division Continuation of Hiring of Diesel Vehicle Maxi Cab(At least 7 seater ) for Assistant Engineer, Alipurduar Sadar Sub-Division, P.H.E. Dte.(from 01.01.2024 to 29.02.2024) ORD/000544/2023-2024 2905/ALD 29/12/2023 62 MATRI ENTERPRISE 0.80 0.00 0
1294 Alipurduar Division Cons. of Rig bored TW(2nos) by ODEX-165 method of drilling at HW and 2nd site, cons of 100 cum OHR at HW including soil testing, cons. of P/H and B/W at HW,2nd site, Laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing , providing FHTC and others allied works for Uttar Rangalibazna PWSS under Birpara Sub-Division, Alipurduar Division, PHE DTE. ORD/000546/2022-2023 3570/ALD 27/03/2023 1102 SAMIRON PODDER 271.90 112.72 75
1295 Alipurduar Division Continuation of Hiring of Diesel Vehicle Maxi Cab(At least 7 seater ) for Assistant Engineer, Birpara Sub-Division, P.H.E. Dte.(from 01.01.2024 to 29.02.2024) ORD/000546/2023-2024 2907/ALD 29/12/2023 62 PARITOSH SUTRADHAR 0.80 0.77 0
1296 Alipurduar Division Continuation order of "Collection of house hold details at prescribed format through mobile app/Hard Copy including Geo-reference as directed by the E.I.C. and submission the same (in soft copy) to PHE Dte. PART-B" ORD/000547/2023-2024 313/ALD 25/01/2024 180 TAPASH KUMAR BHOWMICK 4.67 4.67 100
1297 Alipurduar Division Construction of 2 nos. Tube well boring by ODEX-165 Method of drilling at HW site including distribution system with new HDPE pipeline, Construction of 200 cum OHR as per Departmental Design & drawing, Pump House , Boundary Wall, Path way including soil test, Providing FHTC and other allied works for NIMTI DOMOHANI PIPED WATER SUPPLY SCHEME under Alipurduar Division, PHE Dte. ORD/000548/2022-2023 3571/ALD 27/03/2023 480 DOOARS CONSTRUCTION COMPANY 446.14 376.24 90
1298 Alipurduar Division Continuation order of "Entry of data for house Connection (JJM) of PWSS in website under Alipurduar division, PHE Dte." ORD/000548/2023-2024 314/ALD 25/01/2024 180 TAPASH KUMAR BHOWMICK 4.29 4.29 100
1299 Alipurduar Division Boring of Tube Well, Construction of Pump House, Boundary Wall, OHR (100cum) including soil testing, Laying Of Rising Main, Distribution System and providing FHTC for Foskadanga PWSS Under Alipurduar Division, PHE Dte. ORD/000549/2022-2023 3572/ALD 27/03/2023 737 MADHAB SAHA 321.67 219.01 10
1300 Alipurduar Division Continuation of work of "Hiring of Diesel Vehicle Maxi Cab (At least 7 seater ) for Deputy Superintending Engineer, North Bengal Circle-I , P.H.E. Dte.(from 01.03.2024 to 31.07.2024)" ORD/000549/2023-2024 602/ALD 27/02/2024 151 MAHENDRA CHHETRI 2.00 0.00 0
1301 Alipurduar Division Constructions of pump house & Tube well Boring by ODEX-165 Method of drilling at HW site & 2nd site , laying of distribution system with UPVC pipeline including rising main & delivery connection, Constructions of 250 Cum OHR as per Departmental Design & drawing along with the Soil investigation works , providing FHTC and others allied works for Purba Narathali PWSS Under Alipurduar Division PHE DTE. ORD/000550/2022-2023 3573ALD 27/03/2023 1011 MADHAB SAHA 373.15 311.75 5
1302 Alipurduar Division Cons. of Pump House & Tube well Boring by ODEX-165 Method drilling at HW Site & 2nd Site, laying distribution system with UPVC pipeline including rising main & delivery connection, Cons. of 150cum OHR as per departmental Design & drawing along with soil investigation works, providing FHTC including cons. of platform and others allied works for TURTURI PWSS Under Alipurduar Division, PHE DTE ORD/000551/2022-2023 3574/ALD 27/03/2023 720 TAPASH KUMAR BHOWMICK 399.05 350.21 90
1303 Alipurduar Division Boring of TW, Cons. Of Pump House, boundary wall, OHR (300 cum) inclu. Soil investigation works, Laying of rising main, distribution system and providing FHTC for MADHYA KHAIRBARI PWSS under Alipurduar Division PHE DTE. ORD/000553/2022-2023 3575/ALD 27/03/2023 900 DILIP MAHATO 553.32 428.63 85
1304 Alipurduar Division Laying of HDPE pipeline near existing PH No-01 village for the Makrapara PWSS under Alipurduar Division, PHE Dte. ORD/000554/2021-2022 3046/ALD 21/03/2022 30 DILIP MAHATO 4.95 2.22 42
1305 Alipurduar Division Extension of Distribution pipe line (Barman Para and Beltala) with UPVC Connection of BAROBISA PWSS under Alipurduar Division, PHE Dte. ORD/000555/2021-2022 3082/ALD 22/03/2022 60 AASHIRBAD ENTERPRISE 13.46 9.39 70
1306 Alipurduar Division 3 nos. of Tube well Boring by ODEX-165 Method of drilling at HW site, 2nd TW and 3rd site site and Constructions of 350 Cum OHR at HW site inclu. soil testing , construction of pump house and boundary wall at H/W, 2nd site and 3rd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for SISHA JUMRHA PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000555/2022-2023 3576/ALD 27/03/2023 902 DILIP MAHATO 539.73 365.61 23
1307 Alipurduar Division Repairing of HW Site Boundary Wall (15M) Samuktala WSS under Alipurduar Division, PHE Dte. ORD/000556/2022-2023 3501/ALD 23/03/2023 120 PROGRESSIVE UNEMPLOYED CO-OPERATIVE LABOUR CONTRACT & CONSTRUCTION SOCIETY LTD. 2.14 1.80 100
1308 Alipurduar Division Constructions of pump house & Sinking of 250 mm x 200 mm X 150 mtr. Big dia. Tube well at HW site & 2nd site , laying of distribution system with UPVC pipeline , Constructions of 250 Cum OHR as per Departmental Design & drawing including soil test, providing FHTC and others allied works for Purba Khalisamari PWSS Under Alipurduar Division PHE DTE. ORD/000557/2022-2023 3577/ALD 27/03/2023 840 HARIDAS GHOSH 438.25 358.40 72
1309 Alipurduar Division Water supply for Makrapara Kali Mandir at Makarapara within Birpara Sub-Division under Alipurduar Division, PHE Dte. ORD/000558/2021-2022 3216/ALD 30/03/2022 45 RATAN DUTTA 4.40 0.00 0
1310 Alipurduar Division Construction of 2nos Tw boring by ODEX-165 method of drilling including distribution system with new UPVC pipeline, 2 nos Pump house, Boundary wall, pathway, providing FHTC and other allied works for 28 and 29 mile busty PWSS under Alipurduar Division, PHE Dte. ORD/000558/2022-2023 3502/ALD 23/03/2023 600 HITANGSHU CHOUDHURY 76.18 29.23 80
1311 Alipurduar Division Land development, construction of new pathway, surface drain (2nd site near Tea Factory) and other misc. works related to Jayanti TG PWSS under Alipurduar Division, PHE Dte. ORD/000559/2022-2023 3503/ALD 23/03/2023 60 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 4.39 0.00 0
1312 Alipurduar Division Boring of Tube Well, Construction of Pump House, Boundary Wall, OHR, Laying Of Rising Main, Distribution System including soil test and providing FHTC for Kolaberia PWSS Under Alipurduar Division, PHE Dte ORD/000560/2022-2023 3578/ALD 27/03/2023 900 SASANKA ROY 283.27 190.14 12
1313 Alipurduar Division Gap filling and replacing lower dia pipe and FHTC connection at Pararpar PWSS under Alipurduar Division, PHE Dte. ORD/000562/2022-2023 3505/ALD 23/03/2023 180 TAPASH DAS 6.38 6.35 98
1314 Alipurduar Division Construction of RCC clear water Reservoir (CWR) of capacity 100 cum, laying distribution system and providing FHTC at Buxa PWSS under Alipurduar Division, PHE Dte. ORD/000563/2022-2023 3506/ALD 23/03/2023 180 ASHOK SAPKOTA 30.80 0.00 100
1315 Alipurduar Division Construction of 350cum OHR for Kalchini TG Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000564/2022-2023 3233/ALD 27/02/2023 180 Z STAR COMMOTRADE PVT LTD. 71.41 0.00 0
1316 Alipurduar Division Laying of different dia., CIDF, DI Pipeline, UPVC pipe line for left out household connection and other works at PURBA KATHALBARI ZONE-I area of Purba Kathalbari PWSS of Alipurduar RWS Sub-Division under Alipurduar Division, PHE Dte. ORD/000564/2024-2025 5360/ALD 12/03/2025 60 ANIRBAN DEY SARKAR CONSTRUCTION 3.00 0.00 70
1317 Alipurduar Division Installation of 125mm X 80mm X 90 mtr. Deep Tube Well (Mark-II TW) for fresh drinking water sources(with provision of lowering of sub-merssible pump) by ODEX-115 method of Drilling at Truck Stand of Jaigaon PS (East side) within Alipurduar District under Alipurduar Division, PHE Dte. ORD/000565/2021-2022 3139/ALD 25/03/2022 20 MAHENDRA CHHETRI 3.32 3.30 67
1318 Alipurduar Division Construction of 500cum OHR for Kalchini TG Water Supply Scheme under Alipurduar Division, PHE Dte. ORD/000565/2022-2023 3234ALD 27/02/2023 360 SHREE RANISATI ENTERPRISE 91.81 41.04 40
1319 Alipurduar Division Reparing of Pump House at Headwork site of Kaijali Basty PWSS Under Alipurduar Division PHE DTE. ORD/000565/2024-2025 5381/ALD 17/03/2025 60 TAPASH KUMAR BHOWMICK 0.94 0.00 0
1320 Alipurduar Division Installation of 125mm X 80mm X 90 mtr. Deep Tube Well (Mark-II TW) for fresh drinking water sources(with provision of lowering of sub-merssible pump) by ODEX-115 method of Drilling at Truck Stand of Jaigaon PS (West side) within Alipurduar District under Alipurduar Division, PHE Dte. ORD/000566/2021-2022 3140/ALD 25/03/2022 20 D. K. & SONS 3.32 3.30 61
1321 Alipurduar Division Continuation order of Supply of fuel for Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for inspection and monitoring of Jal Jeevan Mission (JJM) works under Alipurduar Division, P.H.E. Dte.(from 01.02.2023 to 30.04.2023) ORD/000566/2022-2023 2952/ALD 24/01/2023 90 NIRANJAN KIRTANIA 0.70 0.51 0
1322 Alipurduar Division Reparing of Pump House at 2nd TW site of Kaijali Basty PWSS Under Alipurduar Division PHE DTE. ORD/000566/2024-2025 5382/ALD 17/03/2025 60 TAPASH KUMAR BHOWMICK 0.92 0.00 0
1323 Alipurduar Division Continuation for the work of Hiring of Additional Diesel Vehicle Maxi Cab(At least 7 seater ) for inspection and monitoring of Jal Jeevan Mission (JJM) works under Alipurduar Division, P.H.E. Dte.(from 01/02/2023 to 30/04/2023) ORD/000567/2022-2023 2953/ALD 24/01/2023 90 NIRANJAN KIRTANIA 0.50 0.50 0
1324 Alipurduar Division Reparing of Pump House at HW and 2nd TW site of SALSALABARI PWSS Under Alipurduar Division PHE DTE. ORD/000567/2024-2025 5383/ALD 17/03/2025 60 HARI CONSTRUCTION 0.96 0.00 0
1325 Alipurduar Division Reparing of Pump House at HW site and 2nd TW site of Jashodanga PWSS Under Alipurduar Division PHE DTE. ORD/000568/2024-2025 5384/ALD 17/03/2025 60 TAPASH KUMAR BHOWMICK 0.96 0.00 0
1326 Alipurduar Division Construction of pathway with paver block and repairing of old H/W site's Guest House of Jaigaon WSS under Alipurduar Division, PHE Dte. ORD/000570/2021-2022 3143/ALD 25/03/2022 30 D. K. & SONS 4.86 4.85 67
1327 Alipurduar Division Remaining portion of pipeline of JDA Zone-I & Zone-II and special Road repairing of Zone-I and II and Zone-4B, providing pipeline and FHTC of Ramgaon. ORD/000570/2022-2023 3623/ALD 30/03/2023 810 D. K. & SONS 54.46 11.23 96
1328 Alipurduar Division Reparing of Pump House at 2nd site of SALKUMARHAT PWSS Under Alipurduar Division PHE DTE. ORD/000570/2024-2025 5385/ALD 17/03/2025 60 TAPASH DAS 0.79 0.00 0
1329 Alipurduar Division Construction of Boundary wall 2nd TW site of Jaigaon PWSS (near Hanuman Mandir) under Alipurduar Division, PHE Dte. ORD/000571/2021-2022 3144/ALD 25/03/2022 45 D. K. & SONS 4.75 4.64 62
1330 Alipurduar Division Providing Functional Household Tap Connection (FHTC) in connection with Jaldhara Jal Swapna at Jogijhora WSS under Alipurduar Division, PHE Dte. Part-3 (2 nd call) ORD/000572/2021-2022 3145/ALD 25/03/2022 30 M/S SURAJIT DEY & CO 5.02 0.00 0
1331 Alipurduar Division Construction of tube wells (2 nos.) by Reverse rotary method of drilling at HW site and 2nd TW site , constructions of 200 Cum OHR at HW including soil investigation , construction of pump house and boundary wall at H/W and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Dalgaon Tea Garden PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000573/2022-2023 3634/ALD 31/03/2023 1271 M/S MRITYUNJAY PAUL AND SONS 390.34 197.43 51
1332 Alipurduar Division Reparing of Pump House at 2nd TW site of PAITKAPARA PWSS Under Alipurduar Division PHE DTE. ORD/000573/2024-2025 5387/ALD 17/03/2025 60 DAS CONSTRUCTION 0.79 0.00 0
1333 Alipurduar Division Construction of tube wells (3 nos.) by Reverse rotary method of drilling Method of drilling at HW site, 2nd TW site and 3rd site, soil investigation at HW site, constructions of 100 Cum OHR at HW, construction of pump house and boundary wall at H/W, 2nd site and 3rd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for Dalmoney Tea Garden PWSS (Zone-I & Zone-II) Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000574/2022-2023 3635/ALD 31/03/2023 180 M/S HARI BHUSHAN GHOSH AND CO. 202.87 0.00 10
1334 Alipurduar Division Construction of tubewells (2 nos.) by Reverse rotary method of drilling at HW site and 2nd TW site , Soil investigation at OHR site, constructions of 250 Cum OHR at HW , construction of pump house and boundary wall at H/W and 2nd site, laying of rising main, distribution line and providing FHTC as per Departmental Design & drawing for DHANIRAMPUR PWSS Under Birpara Subdivision, Alipurduar Division PHE DTE. ORD/000575/2022-2023 3636/ALD 31/03/2023 900 DILIP MAHATO 457.51 430.34 95
1335 Alipurduar Division Reparing of Pump House at HEADWORK site of PAITKAPARA PWSS Under Alipurduar Division PHE DTE. ORD/000575/2024-2025 5389/ALD 17/03/2025 60 DAS CONSTRUCTION 0.95 0.00 0
1336 Alipurduar Division Cons of PH and Sinking of 250 mm x 200 mm X 150 mtr Big dia TW at HW site , 2nd site and 3rd TW site LDS with UPVC p/line , cons of 100 Cum OHR incl the Soil investigation works providing FHTC and others allied works for Pakriguri PWSS Under Alipurduar Division PHE DTE. ORD/000576/2022-2023 3637/ALD 31/03/2023 1080 DEBAJYOTI SUTRADHAR 183.60 136.16 65
1337 Alipurduar Division Reparing of Pump House at HEADWORK site of SALKUMARHAT PWSS Under Alipurduar Division PHE DTE. ORD/000576/2024-2025 5390/ALD 17/03/2025 60 TAPASH DAS 0.94 0.00 0
1338 Alipurduar Division Laying of UPVC/DI/MS/CI distribution pipeline for Gap filling of Chhoto Salkumar PWSS under Alipurduar Division, PHE Dte. ORD/000577/2021-2022 3132/ALD 25/03/2022 30 PRITAM DAS 5.04 5.01 71
1339 Alipurduar Division Construction of Tube Well, Pump House, Boundary Wall, OHR, Laying Of Rising Main, Distribution System including soil test and providing FHTC for Naothoartari PWSS Under Alipurduar Division, PHE Dte. ORD/000577/2022-2023 3638/ALD 31/03/2023 1260 CHINMOY BHATTACHARJEE 267.68 164.49 40
1340 Alipurduar Division "Collectio of house hold details at prescribrd format through mobile app/Hard Copy including Geo-reference as directed by the E.I.C. and submission the same (soft copy) to P.H.E. Dte. (for the financial year 2022-2023 from 01/04/2022 onwards)" ORD/000578/2021-2022 3223/ALD 31/03/2022 365 DILIP MAHATO 4.96 4.96 54
1341 Alipurduar Division Tube well Boring by ODEX-165 Method of drilling at HW, FIRST TUBE WELL site including laying distribution system with new HDPE pipeline , Constructions of 100 Cum OHR as per Departmental Design & drawing , TWO nos. pump house & boundary wall, providing FHTC, Soil Investigation work and others allied works for NIMTIJHORA TEA GARDEN AREA PWSS Under Alipurduar Division PHE DTE ORD/000578/2022-2023 3639/ALD 31/03/2023 720 SAMIRON PODDER 207.36 166.43 95
1342 Alipurduar Division Reparing of Pump House at HEADWORK site of BIRPARA (APD) PWSS Under Alipurduar Division PHE DTE. ORD/000578/2024-2025 5392/ALD 17/03/2025 60 DAS CONSTRUCTION 0.94 0.00 0
1343 Alipurduar Division Constructions of P/H and T/W Boring by ODEX-165 Method of drilling at HW and 2nd site , LDS with UPVC P/L including rising main and delivery connection, Cons. of 200 Cum OHR as per Departmental Design & drawing along with soil investigation works, providing FHTC and others allied works for TELIPARA PWSS Under Alipurduar Division PHE DTE. ORD/000579/2022-2023 3640/ALD 31/03/2023 180 MATRI ENTERPRISE 225.29 167.75 85
1344 Alipurduar Division Reparing of Pump House at HEADWORK site of MUNSHIPARA PWSS Under Alipurduar Division PHE DTE. ORD/000579/2024-2025 5393/ALD 17/03/2025 60 TAPASH DAS 0.94 0.00 0
1345 Alipurduar Division Reparing of Pump House at 2nd site of BIRPARA (APD) PWSS Under Alipurduar Division PHE DTE. ORD/000580/2024-2025 5394/ALD 17/03/2025 60 DAS CONSTRUCTION 0.79 0.00 0
1346 Alipurduar Division Reparing of Pump House at 2nd TW site of MUNSHIPARA PWSS Under Alipurduar Division PHE DTE. ORD/000581/2024-2025 5395/ALD 17/03/2025 60 TAPASH DAS 0.79 0.00 0
1347 Alipurduar Division Entry of data of Functional Household Tape Connection (FHTC under JJM) of PWSS in website under Alipurduar Division, PHE Dte. (Part-A) ORD/000583/2021-2022 1967/ALD 24/12/2021 90 HARIDAS GHOSH 0.96 0.96 39
1348 Alipurduar Division Entry of data of Functional Household Tape Connection (FHTC under JJM) of PWSS in website under Alipurduar Division, PHE Dte. (Part-B) ORD/000584/2021-2022 1968/ALD 24/12/2021 90 TAPASH DAS 0.96 0.96 78
1349 Alipurduar Division Entry of data of Functional Household Tape Connection (FHTC under JJM) of PWSS in website under Alipurduar Division, PHE Dte. (Part-C) ORD/000585/2021-2022 1969/ALD 24/12/2021 90 TAPASH KUMAR BHOWMICK 0.96 0.96 64
1350 Alipurduar Division Entry of data of Functional Household Tap Connection (FHTC under JJM) of PWSS in Website under Alipurduar Division, PHE Dte. (Part-A) ORD/000586/2021-2022 743/ALD 11/08/2021 90 TAPASH KUMAR BHOWMICK 0.96 0.96 65
1351 Alipurduar Division Entry of data of Functional Household Tape Connection (FHTC under JJM) of PWSS in website under Alipurduar Division, PHE Dte. (Part-C) ORD/000588/2021-2022 745/ALD 11/08/2021 90 HARIDAS GHOSH 0.96 0.96 74
1352 Alipurduar Division Entry of data of Functional Household Tape Connection (FHTC under JJM) of PWSS in website under Alipurduar Division, PHE Dte. (Part-A) ORD/000589/2021-2022 359/ALD 08/06/2021 90 HARIDAS GHOSH 0.96 0.96 40
1353 Alipurduar Division Entry of data of Functional Household Tape Connection (FHTC under JJM) of PWSS in website under Alipurduar Division, PHE Dte. (Part-C) ORD/000591/2021-2022 361/ALD 08/06/2021 90 TAPASH DAS 0.96 0.96 77
1354 Alipurduar Division Laying of new HDPE/DI pipeline and replacement of Old distribution line and repairing of FHTC for Augmentation of paschim Khairbari PWSS under Alipurduar Division, PHE Dte. ORD/000591/2024-2025 5504/ALD 21/03/2025 60 MONORAMA ENTERPRISE 13.99 0.00 0
1355 Alipurduar Division Reparing of Pump House at Headwork site of Kalchini PWSS Under Alipurduar Division PHE DTE. ORD/000592/2024-2025 5421/ALD 19/03/2025 60 DOOARS SOCIAL WELFARE ORGANISATION 0.98 0.00 0
1356 Alipurduar Division Reparing of Pump House at 3nd site of Kalchini PWSS Under Alipurduar Division PHE DTE. ORD/000594/2024-2025 5423/ALD 19/03/2025 60 DOOARS SOCIAL WELFARE ORGANISATION 0.98 0.00 0
1357 Alipurduar Division Reparing of Pump House at Headwork site of Uttar Latabari PWSS Under Alipurduar Division PHE DTE. ORD/000595/2024-2025 5424/ALD 19/03/2025 60 DOOARS SOCIAL WELFARE ORGANISATION 0.93 0.00 0
1358 Alipurduar Division Reparing of Pump House at 4th site of Uttar Latabari PWSS Under Alipurduar Division PHE DTE ORD/000596/2024-2025 5425/ALD 19/03/2025 60 DOOARS SOCIAL WELFARE ORGANISATION 0.93 0.00 0
1359 Alipurduar Division Reparing of Pump House at 2nd site of Uttar Latabari PWSS Under Alipurduar Division PHE DTE. ORD/000597/2024-2025 5426/ALD 19/03/2025 60 DOOARS SOCIAL WELFARE ORGANISATION 0.93 0.00 0
1360 Alipurduar Division Reparing of Pump House at Headwork site of HASIMARA PWSS Under Alipurduar Division PHE DTE. ORD/000598/2024-2025 5427/ALD 19/03/2025 60 DOOARS SOCIAL WELFARE ORGANISATION 0.78 0.00 0
1361 Alipurduar Division Reparing of Pump House at 2nd site of Kalchini PWSS Under Alipurduar Division PHE DTE. ORD/000601/2024-2025 5422/ALD 19/03/2025 60 DOOARS SOCIAL WELFARE ORGANISATION 0.93 0.00 0
1362 Alipurduar Division Extension work order for Hiring of Diesel vehicle Maxi Cab(At least 7 seater) for Executive Engineer, Alipurduar Division under Alipurduar Division, PHE Dte.( 01.04.2021 to 30.06.2021) ORD/000609/2020-2021 3051/ALD 31/03/2021 91 APSARI BHOWMICK 0.54 0.00 100
1363 Alipurduar Division Reparing of Pump House at 1st site of Jogijhora Barabak PWSS Under Alipurduar Division PHE DTE. ORD/000609/2024-2025 5599/ALD 27/03/2025 60 NARENDRA BHADANI. 0.78 0.00 0
1364 Alipurduar Division Reparing of Pump House at 2nd site of Jogijhora Barabak PWSS Under Alipurduar Division PHE DTE. ORD/000610/2024-2025 5600/ALD 27/03/2025 60 NARENDRA BHADANI. 0.79 0.00 0
1365 Alipurduar Division Reparing of Pump House no 2 at HW site of SAMUKTALA PWSS Under Alipurduar Division PHE DTE.(2nd call) ORD/000611/2024-2025 5601/ALD 27/03/2025 60 ALIPURDUAR CO-OPERATIVE LABOUR CONTRUCT & CONSTRUCTION SOCIETY LTD. 0.96 0.00 0
1366 Alipurduar Division Reparing of Pump House at 2nd TW site of PURBA CHEPANI PWSS Under Alipurduar Division PHE DTE.(2nd call) ORD/000612/2024-2025 5602/ALD 27/03/2025 120 KOUSHIK BHOWMICK 0.85 0.00 100
1367 Alipurduar Division Reparing of Pump House at 3nd site of BHATIBARI PWSS Under Alipurduar Division PHE DTE.(2nd call) ORD/000613/2024-2025 5603/ALD 27/03/2025 60 SREE MAA CONSTRUCTION 0.97 0.00 0
1368 Alipurduar Division Reparing of Pump House at 3nd site of Jogijhora Barabak PWSS Under Alipurduar Division PHE DTE. ORD/000614/2024-2025 5604/ALD 27/03/2025 60 NARENDRA BHADANI. 0.95 0.00 0
1369 Alipurduar Division Reparing of Pump House at HEADWORK site of BHOLARDABRI PWSS Under Alipurduar Division PHE DTE. ORD/000615/2024-2025 5605/ALD 27/03/2025 120 CHANDAN DAS 0.88 0.00 100
1370 Alipurduar Division Providing House connection for TORSA TG AREA, JAIGAON DEVLOPMENT AREA ZONE-3B under Alipuduar Division, P.H.E. Dte. ORD/000726/2020-2021 1764/ALD 19/02/2021 60 AQUEDUCT PLASTICS PVT. LTD. 40.17 38.44 67
1371 Alipurduar Division Continuation of work of Hiring of Diesel Vehicle Maxi Cab (At least 7 seater ) for Executive Engineer, Alipurduar Division, P.H.E. Dte. (from 01.04.2025 to 30.04.2025) ORD/000745/2024-2025 5591/ALD 26/03/2025 31 APSARI BHOWMICK 0.40 0.00 0
1372 Alipurduar Division Material Requisition To Resource Division RTOR000001/2024-2025 3606/ALD 24/10/2024 0 Resource Division 9.11 0.00 0
1373 Alipurduar Division Material Requisition To Resource Division RTOR000001/2025-2026 1560/ALD 31/07/2025 0 Resource Division 5.52 0.00 0
1374 Alipurduar Division Material Requisition To Resource Division RTOR000002/2022-2023 394/ALD 11/05/2022 0 Resource Division 11.54 0.00 0
1375 Alipurduar Division Material Requisition To Resource Division RTOR000002/2024-2025 3607/ALD 24/10/2024 0 Resource Division 5.11 0.00 0
1376 Alipurduar Division Material Requisition To Resource Division RTOR000002/2025-2026 1561/ald 31/07/2025 0 Resource Division 5.02 0.00 0
1377 Alipurduar Division Material Requisition To Resource Division RTOR000003/2022-2023 395/ALD 11/05/2022 0 Resource Division 3.16 0.00 0
1378 Alipurduar Division Material Requisition To Resource Division RTOR000003/2024-2025 3608/ALD 24/10/2024 0 Resource Division 4.11 0.00 0
1379 Alipurduar Division Material Requisition To Resource Division RTOR000003/2025-2026 1562/ald 31/07/2025 0 Resource Division 8.04 0.00 0
1380 Alipurduar Division Material Requisition To Resource Division RTOR000004/2022-2023 396/ALD 11/05/2022 0 Resource Division 9.83 0.00 0
1381 Alipurduar Division Material Requisition To Resource Division RTOR000004/2023-2024 185/ALD 28/04/2023 0 Resource Division 33.51 0.00 0
1382 Alipurduar Division Material Requisition To Resource Division RTOR000004/2024-2025 3609/ALD 24/10/2024 0 Resource Division 11.11 0.00 0
1383 Alipurduar Division Material Requisition To Resource Division RTOR000004/2025-2026 1563/ALD 31/07/2025 0 Resource Division 6.91 0.00 0
1384 Alipurduar Division Material Requisition To Resource Division RTOR000005/2022-2023 397/ALD 11/05/2022 0 Resource Division 3.59 0.00 0
1385 Alipurduar Division Material Requisition To Resource Division RTOR000005/2023-2024 186/ALD 28/04/2023 0 Resource Division 246.11 0.00 0
1386 Alipurduar Division Material Requisition To Resource Division RTOR000005/2024-2025 3610/ALD 24/10/2024 0 Resource Division 11.11 0.00 0
1387 Alipurduar Division Material Requisition To Resource Division RTOR000005/2025-2026 1564/ALD 31/07/2025 0 Resource Division 5.02 0.00 0
1388 Alipurduar Division Material Requisition To Resource Division RTOR000006/2023-2024 187/ALD 28/04/2023 0 Resource Division 24.01 0.00 0
1389 Alipurduar Division Material Requisition To Resource Division RTOR000006/2024-2025 3611/ALD 24/10/2024 0 Resource Division 9.89 0.00 0
1390 Alipurduar Division Material Requisition To Resource Division RTOR000006/2025-2026 1564/ALD 31/07/2025 0 Resource Division 6.91 0.00 0
1391 Alipurduar Division Material Requisition To Resource Division RTOR000007/2021-2022 2928/ALD 10/03/2022 0 Resource Division 17.75 0.00 0
1392 Alipurduar Division Material Requisition To Resource Division RTOR000007/2023-2024 188/ALD 28/04/2023 0 Resource Division 18.72 0.00 0
1393 Alipurduar Division Material Requisition To Resource Division RTOR000007/2024-2025 3612/ALD 24/10/2024 0 Resource Division 7.78 0.00 0
1394 Alipurduar Division Material Requisition To Resource Division RTOR000007/2025-2026 1565/ALD 31/07/2025 0 Resource Division 3.52 0.00 0
1395 Alipurduar Division Material Requisition To Resource Division RTOR000008/2023-2024 189/ALD 28/04/2023 0 Resource Division 15.48 0.00 0
1396 Alipurduar Division Material Requisition To Resource Division RTOR000008/2024-2025 3613/ALD 24/10/2024 0 Resource Division 7.78 0.00 0
1397 Alipurduar Division Material Requisition To Resource Division RTOR000008/2025-2026 1566/ALD 31/07/2025 0 Resource Division 5.78 0.00 0
1398 Alipurduar Division Material Requisition To Resource Division RTOR000009/2022-2023 491/ALD 18/05/2022 0 Resource Division 149.46 0.00 0
1399 Alipurduar Division Material Requisition To Resource Division RTOR000009/2023-2024 206/ALD/2023-2024 02/05/2023 0 Resource Division 5.44 0.00 0
1400 Alipurduar Division Material Requisition To Resource Division RTOR000009/2024-2025 3614/ALD 24/10/2024 0 Resource Division 8.11 0.00 0
1401 Alipurduar Division Material Requisition To Resource Division RTOR000009/2025-2026 1567/ALD 31/07/2025 0 Resource Division 6.91 0.00 0
1402 Alipurduar Division Material Requisition To Resource Division RTOR000010/2022-2023 715/ALD 13/06/2022 0 Resource Division 71.41 0.00 0
1403 Alipurduar Division Material Requisition To Resource Division RTOR000010/2023-2024 207/ALD/2023-2024 02/05/2023 0 Resource Division 44.73 0.00 0
1404 Alipurduar Division Material Requisition To Resource Division RTOR000010/2024-2025 3615/ALD 24/10/2024 0 Resource Division 8.11 0.00 0
1405 Alipurduar Division Material Requisition To Resource Division RTOR000010/2025-2026 2034/ALD 15/09/2025 0 Resource Division 3.40 0.00 0
1406 Alipurduar Division Material Requisition To Resource Division RTOR000011/2022-2023 716/ALD 13/06/2022 0 Resource Division 51.21 0.00 0
1407 Alipurduar Division Material Requisition To Resource Division RTOR000011/2023-2024 217/ALD 03/05/2023 0 Resource Division 18.80 0.00 0
1408 Alipurduar Division Material Requisition To Resource Division RTOR000011/2024-2025 3946/ALD 26/11/2024 0 Resource Division 14.35 0.00 0
1409 Alipurduar Division Material Requisition To Resource Division RTOR000011/2025-2026 2035/ALD 15/09/2025 0 Resource Division 3.40 0.00 0
1410 Alipurduar Division Material Requisition To Resource Division RTOR000012/2022-2023 717/ALD 13/06/2022 0 Resource Division 49.83 0.00 0
1411 Alipurduar Division Material Requisition To Resource Division RTOR000012/2023-2024 218/ALD 03/05/2023 0 Resource Division 35.18 0.00 0
1412 Alipurduar Division Material Requisition To Resource Division RTOR000012/2024-2025 3947/ALD 26/11/2024 0 Resource Division 25.05 0.00 0
1413 Alipurduar Division Material Requisition To Resource Division RTOR000012/2025-2026 2036/ALD 15/09/2025 0 Resource Division 4.07 0.00 0
1414 Alipurduar Division Material Requisition To Resource Division RTOR000013/2022-2023 718/ALD 13/06/2022 0 Resource Division 87.66 0.00 0
1415 Alipurduar Division Material Requisition To Resource Division RTOR000013/2023-2024 219/ALD 03/05/2023 0 Resource Division 13.81 0.00 0
1416 Alipurduar Division Material Requisition To Resource Division RTOR000013/2025-2026 2037/ALD 15/09/2025 0 Resource Division 6.28 0.00 0
1417 Alipurduar Division Material Requisition To Resource Division RTOR000014/2022-2023 825/ALD 28/06/2022 0 Resource Division 26.08 0.00 0
1418 Alipurduar Division Material Requisition To Resource Division RTOR000014/2023-2024 220/ALD 03/05/2023 0 Resource Division 36.92 0.00 0
1419 Alipurduar Division Material Requisition To Resource Division RTOR000014/2024-2025 3948/ALD 26/11/2024 0 Resource Division 10.47 0.00 0
1420 Alipurduar Division Material Requisition To Resource Division RTOR000015/2022-2023 826/ALD 28/06/2022 0 Resource Division 30.31 0.00 0
1421 Alipurduar Division Material Requisition To Resource Division RTOR000015/2023-2024 221/ALD 03/05/2023 0 Resource Division 9.77 0.00 0
1422 Alipurduar Division Material Requisition To Resource Division RTOR000015/2024-2025 3949/ALD 26/11/2024 0 Resource Division 6.18 0.00 0
1423 Alipurduar Division Material Requisition To Resource Division RTOR000016/2022-2023 827/ALD 28/06/2022 0 Resource Division 25.20 0.00 0
1424 Alipurduar Division Material Requisition To Resource Division RTOR000016/2023-2024 222/ALD 03/05/2023 0 Resource Division 12.68 0.00 0
1425 Alipurduar Division Material Requisition To Resource Division RTOR000016/2024-2025 3950/ALD 26/11/2024 0 Resource Division 12.32 0.00 0
1426 Alipurduar Division Material Requisition To Resource Division RTOR000017/2022-2023 828/ALD 28/06/2022 0 Resource Division 34.42 0.00 0
1427 Alipurduar Division Material Requisition To Resource Division RTOR000017/2023-2024 223/ALD 03/05/2023 0 Resource Division 16.73 0.00 0
1428 Alipurduar Division Material Requisition To Resource Division RTOR000017/2024-2025 3951/ALD 26/11/2024 0 Resource Division 6.17 0.00 0
1429 Alipurduar Division Material Requisition To Resource Division RTOR000018/2022-2023 917/ALD 07/07/2022 0 Resource Division 61.60 0.00 0
1430 Alipurduar Division Material Requisition To Resource Division RTOR000018/2023-2024 224/ALD 03/05/2023 0 Resource Division 13.14 0.00 0
1431 Alipurduar Division Material Requisition To Resource Division RTOR000018/2024-2025 3952/ALD 26/11/2024 0 Resource Division 7.84 0.00 0
1432 Alipurduar Division Material Requisition To Resource Division RTOR000019/2022-2023 967/ALD 15/07/2022 0 Resource Division 1.43 0.00 0
1433 Alipurduar Division Material Requisition To Resource Division RTOR000019/2023-2024 1257/ALD 10/08/2023 0 Resource Division 35.74 0.00 0
1434 Alipurduar Division Material Requisition To Resource Division RTOR000019/2024-2025 3953/ALD 26/11/2024 0 Resource Division 13.97 0.00 0
1435 Alipurduar Division Material Requisition To Resource Division RTOR000020/2023-2024 1258/ALD 10/08/2023 0 Resource Division 13.15 0.00 0
1436 Alipurduar Division Material Requisition To Resource Division RTOR000020/2024-2025 3954/ALD 26/11/2024 0 Resource Division 7.29 0.00 0
1437 Alipurduar Division Material Requisition To Resource Division RTOR000021/2023-2024 1259/ALD 10/08/2023 0 Resource Division 61.75 0.00 0
1438 Alipurduar Division Material Requisition To Resource Division RTOR000021/2024-2025 3955/ALD 26/11/2024 0 Resource Division 9.86 0.00 0
1439 Alipurduar Division Material Requisition To Resource Division RTOR000022/2023-2024 1260/ALD 10/08/2023 0 Resource Division 2.17 0.00 0
1440 Alipurduar Division Material Requisition To Resource Division RTOR000022/2024-2025 3980/ALD 27/11/2024 0 Resource Division 30.80 0.00 0
1441 Alipurduar Division Material Requisition To Resource Division RTOR000023/2022-2023 1588/ALD 14/09/2022 0 Resource Division 30.75 0.00 0
1442 Alipurduar Division Material Requisition To Resource Division RTOR000023/2023-2024 1261/ALD 10/08/2023 0 Resource Division 7.92 0.00 0
1443 Alipurduar Division Material Requisition To Resource Division RTOR000023/2024-2025 39818/ALD 27/11/2024 0 Resource Division 9.47 0.00 0
1444 Alipurduar Division Material Requisition To Resource Division RTOR000024/2022-2023 1589/ALD 14/09/2022 0 Resource Division 12.30 0.00 0
1445 Alipurduar Division Material Requisition To Resource Division RTOR000024/2023-2024 1269/ALD 11/08/2023 0 Resource Division 21.78 0.00 0
1446 Alipurduar Division Material Requisition To Resource Division RTOR000024/2024-2025 3982/ALD 27/11/2024 0 Resource Division 13.03 0.00 0
1447 Alipurduar Division Material Requisition To Resource Division RTOR000025/2022-2023 1590/ALD 14/09/2022 0 Resource Division 130.15 0.00 0
1448 Alipurduar Division Material Requisition To Resource Division RTOR000025/2023-2024 1270/ALD 11/08/2023 0 Resource Division 17.99 0.00 0
1449 Alipurduar Division Material Requisition To Resource Division RTOR000025/2024-2025 3983/ALD 27/11/2024 0 Resource Division 3.49 0.00 0
1450 Alipurduar Division Material Requisition To Resource Division RTOR000026/2022-2023 1591/ALD 14/09/2022 0 Resource Division 6.68 0.00 0
1451 Alipurduar Division Material Requisition To Resource Division RTOR000026/2023-2024 1271/ALD 11/08/2023 0 Resource Division 35.15 0.00 0
1452 Alipurduar Division Material Requisition To Resource Division RTOR000026/2024-2025 3984/ALD 27/11/2024 0 Resource Division 3.66 0.00 0
1453 Alipurduar Division Material Requisition To Resource Division RTOR000027/2023-2024 1272/ALD 11/08/2023 0 Resource Division 77.78 0.00 0
1454 Alipurduar Division Material Requisition To Resource Division RTOR000027/2024-2025 3985/ALD 27/11/2024 0 Resource Division 12.92 0.00 0
1455 Alipurduar Division Material Requisition To Resource Division RTOR000028/2022-2023 1702/ALD 21/09/2022 0 Resource Division 61.60 0.00 0
1456 Alipurduar Division Material Requisition To Resource Division RTOR000028/2023-2024 1273/ALD 11/08/2023 0 Resource Division 20.82 0.00 0
1457 Alipurduar Division Material Requisition To Resource Division RTOR000028/2024-2025 3986/ALD 27/11/2024 0 Resource Division 4.21 0.00 0
1458 Alipurduar Division Material Requisition To Resource Division RTOR000029/2023-2024 1274/ALD 11/08/2023 0 Resource Division 34.39 0.00 0
1459 Alipurduar Division Material Requisition To Resource Division RTOR000029/2024-2025 3987/ALD 27/11/2024 0 Resource Division 3.71 0.00 0
1460 Alipurduar Division Material Requisition To Resource Division RTOR000030/2022-2023 1704/ALD 21/09/2022 0 Resource Division 61.51 0.00 0
1461 Alipurduar Division Material Requisition To Resource Division RTOR000030/2023-2024 1275/ALD 11/08/2023 0 Resource Division 54.68 0.00 0
1462 Alipurduar Division Material Requisition To Resource Division RTOR000030/2024-2025 3988/ALD 27/11/2024 0 Resource Division 4.89 0.00 0
1463 Alipurduar Division Material Requisition To Resource Division RTOR000031/2023-2024 1276/ALD 11/08/2023 0 Resource Division 11.58 0.00 0
1464 Alipurduar Division Material Requisition To Resource Division RTOR000032/2022-2023 1705/ALD 21/09/2022 0 Resource Division 61.60 0.00 0
1465 Alipurduar Division Material Requisition To Resource Division RTOR000032/2023-2024 1277/ALD 11/08/2023 0 Resource Division 49.36 0.00 0
1466 Alipurduar Division Material Requisition To Resource Division RTOR000032/2024-2025 4248/ALD 13/12/2024 0 Resource Division 3.63 0.00 0
1467 Alipurduar Division Material Requisition To Resource Division RTOR000033/2022-2023 2107/ALD 09/11/2022 0 Resource Division 10.92 0.00 0
1468 Alipurduar Division Material Requisition To Resource Division RTOR000033/2023-2024 1278/ALD 11/08/2023 0 Resource Division 12.57 0.00 0
1469 Alipurduar Division Material Requisition To Resource Division RTOR000033/2024-2025 4249/ALD 13/12/2024 0 Resource Division 29.54 0.00 0
1470 Alipurduar Division Material Requisition To Resource Division RTOR000034/2022-2023 3014/ALD, 07/02/2023 0 Resource Division 10.87 0.00 0
1471 Alipurduar Division Material Requisition To Resource Division RTOR000034/2023-2024 1472/ALD 16/08/2023 0 Resource Division 24.30 0.00 0
1472 Alipurduar Division Material Requisition To Resource Division RTOR000034/2024-2025 4250/ALD 13/12/2024 0 Resource Division 31.17 0.00 0
1473 Alipurduar Division Material Requisition To Resource Division RTOR000035/2022-2023 3015/ALD/2022-23 07/02/2023 0 Resource Division 13.69 0.00 0
1474 Alipurduar Division Material Requisition To Resource Division RTOR000035/2023-2024 1473/ALD 16/08/2023 0 Resource Division 35.41 0.00 0
1475 Alipurduar Division Material Requisition To Resource Division RTOR000035/2024-2025 4251/ALD 13/12/2024 0 Resource Division 31.69 0.00 0
1476 Alipurduar Division Material Requisition To Resource Division RTOR000036/2022-2023 3044/ALD 08/02/2023 0 Resource Division 21.01 0.00 0
1477 Alipurduar Division Material Requisition To Resource Division RTOR000036/2023-2024 1474/ALD 16/08/2023 0 Resource Division 38.52 0.00 0
1478 Alipurduar Division Material Requisition To Resource Division RTOR000036/2024-2025 4252/ALD 13/12/2024 0 Resource Division 1.61 0.00 0
1479 Alipurduar Division Material Requisition To Resource Division RTOR000037/2022-2023 3045/ALD 08/02/2023 0 Resource Division 7.53 0.00 0
1480 Alipurduar Division Material Requisition To Resource Division RTOR000037/2023-2024 1475/ALD 16/08/2023 0 Resource Division 29.72 0.00 0
1481 Alipurduar Division Material Requisition To Resource Division RTOR000037/2024-2025 4253/ALD 13/12/2024 0 Resource Division 43.88 0.00 0
1482 Alipurduar Division Material Requisition To Resource Division RTOR000038/2022-2023 3046/ALD 08/02/2023 0 Resource Division 25.40 0.00 0
1483 Alipurduar Division Material Requisition To Resource Division RTOR000038/2023-2024 1476/ALD 16/08/2023 0 Resource Division 21.37 0.00 0
1484 Alipurduar Division Material Requisition To Resource Division RTOR000038/2024-2025 4257/ALD 13/12/2024 0 Resource Division 36.71 0.00 0
1485 Alipurduar Division Material Requisition To Resource Division RTOR000039/2022-2023 3047/ALD 08/02/2023 0 Resource Division 61.86 0.00 0
1486 Alipurduar Division Material Requisition To Resource Division RTOR000039/2023-2024 1478/ALD 16/08/2023 0 Resource Division 40.60 0.00 0
1487 Alipurduar Division Material Requisition To Resource Division RTOR000039/2024-2025 4254/ALD 13/12/2024 0 Resource Division 38.94 0.00 0
1488 Alipurduar Division Material Requisition To Resource Division RTOR000040/2022-2023 3048/ALD 08/02/2023 0 Resource Division 29.21 0.00 0
1489 Alipurduar Division Material Requisition To Resource Division RTOR000040/2023-2024 1479/ALD 16/08/2023 0 Resource Division 21.37 0.00 0
1490 Alipurduar Division Material Requisition To Resource Division RTOR000040/2024-2025 4255/ALD 13/12/2024 0 Resource Division 20.10 0.00 0
1491 Alipurduar Division Material Requisition To Resource Division RTOR000041/2022-2023 3483/ALD 23/03/2023 0 Resource Division 61.60 0.00 0
1492 Alipurduar Division Material Requisition To Resource Division RTOR000041/2023-2024 1480/ALD 16/08/2023 0 Resource Division 21.43 0.00 0
1493 Alipurduar Division Material Requisition To Resource Division RTOR000041/2024-2025 4256/ALD 13/12/2024 0 Resource Division 9.16 0.00 0
1494 Alipurduar Division Material Requisition To Resource Division RTOR000042/2022-2023 3484/ALD 23/03/2023 0 Resource Division 36.96 0.00 0
1495 Alipurduar Division Material Requisition To Resource Division RTOR000042/2023-2024 1481/ALD 16/08/2023 0 Resource Division 16.32 0.00 0
1496 Alipurduar Division Material Requisition To Resource Division RTOR000042/2024-2025 4258/ALD 13/12/2024 0 Resource Division 1.53 0.00 0
1497 Alipurduar Division Material Requisition To Resource Division RTOR000043/2022-2023 3485/ALD 23/03/2023 0 Resource Division 11.64 0.00 0
1498 Alipurduar Division Material Requisition To Resource Division RTOR000043/2023-2024 1482/ALD 16/08/2023 0 Resource Division 21.99 0.00 0
1499 Alipurduar Division Material Requisition To Resource Division RTOR000043/2024-2025 4259/ALD 13/12/2024 0 Resource Division 11.34 0.00 0
1500 Alipurduar Division Material Requisition To Resource Division RTOR000044/2022-2023 3486/ALD 23/03/2023 0 Resource Division 11.43 0.00 0
1501 Alipurduar Division Material Requisition To Resource Division RTOR000044/2023-2024 1952/ALD 12/09/2023 0 Resource Division 129.38 0.00 0
1502 Alipurduar Division Material Requisition To Resource Division RTOR000044/2024-2025 4260/ALD 13/12/2024 0 Resource Division 13.75 0.00 0
1503 Alipurduar Division Material Requisition To Resource Division RTOR000045/2022-2023 3487ALD 23/03/2023 0 Resource Division 4.89 0.00 0
1504 Alipurduar Division Material Requisition To Resource Division RTOR000045/2023-2024 1953/ALD 12/09/2023 0 Resource Division 33.29 0.00 0
1505 Alipurduar Division Material Requisition To Resource Division RTOR000045/2024-2025 4261/ALD 13/12/2024 0 Resource Division 13.19 0.00 0
1506 Alipurduar Division Material Requisition To Resource Division RTOR000046/2023-2024 1954/ALD 12/09/2023 0 Resource Division 40.05 0.00 0
1507 Alipurduar Division Material Requisition To Resource Division RTOR000046/2024-2025 4262/ALD 13/12/2024 0 Resource Division 22.34 0.00 0
1508 Alipurduar Division Material Requisition To Resource Division RTOR000047/2023-2024 2395/ALD 08/11/2023 0 Resource Division 8.64 0.00 0
1509 Alipurduar Division Material Requisition To Resource Division RTOR000047/2024-2025 4267/ALD 13/12/2024 0 Resource Division 13.19 0.00 0
1510 Alipurduar Division Material Requisition To Resource Division RTOR000048/2023-2024 2396/ALD 08/11/2023 0 Resource Division 11.63 0.00 0
1511 Alipurduar Division Material Requisition To Resource Division RTOR000048/2024-2025 4268/ALD 13/12/2024 0 Resource Division 13.19 0.00 0
1512 Alipurduar Division Material Requisition To Resource Division RTOR000049/2023-2024 2397/ALD 08/11/2023 0 Resource Division 6.18 0.00 0
1513 Alipurduar Division Material Requisition To Resource Division RTOR000049/2024-2025 4269/ALD 13/12/2024 0 Resource Division 25.24 0.00 0
1514 Alipurduar Division Material Requisition To Resource Division RTOR000050/2023-2024 2398/ALD 08/11/2023 0 Resource Division 6.34 0.00 0
1515 Alipurduar Division Material Requisition To Resource Division RTOR000050/2024-2025 4270/ALD 13/12/2024 0 Resource Division 22.34 0.00 0
1516 Alipurduar Division Material Requisition To Resource Division RTOR000051/2023-2024 2399/ALD 08/11/2023 0 Resource Division 10.15 0.00 0
1517 Alipurduar Division Material Requisition To Resource Division RTOR000051/2024-2025 4271/ALD 13/12/2024 0 Resource Division 19.92 0.00 0
1518 Alipurduar Division Material Requisition To Resource Division RTOR000052/2023-2024 2698/ALD 12/12/2023 0 Resource Division 21.43 0.00 0
1519 Alipurduar Division Material Requisition To Resource Division RTOR000052/2024-2025 4272/ALD 13/12/2024 0 Resource Division 12.78 0.00 0
1520 Alipurduar Division Material Requisition To Resource Division RTOR000053/2023-2024 2699/ALD 12/12/2023 0 Resource Division 68.94 0.00 0
1521 Alipurduar Division Material Requisition To Resource Division RTOR000053/2024-2025 4273/ALD 13/12/2024 0 Resource Division 11.33 0.00 0
1522 Alipurduar Division Material Requisition To Resource Division RTOR000054/2023-2024 2700/ALD 12/12/2023 0 Resource Division 84.45 0.00 0
1523 Alipurduar Division Material Requisition To Resource Division RTOR000054/2024-2025 4274/ALD 13/12/2024 0 Resource Division 11.82 0.00 0
1524 Alipurduar Division Material Requisition To Resource Division RTOR000055/2023-2024 2701/ALD 12/12/2023 0 Resource Division 84.45 0.00 0
1525 Alipurduar Division Material Requisition To Resource Division RTOR000055/2024-2025 4275/ALD 13/12/2024 0 Resource Division 26.21 0.00 0
1526 Alipurduar Division Material Requisition To Resource Division RTOR000056/2023-2024 2702 12/12/2023 0 Resource Division 68.94 0.00 0
1527 Alipurduar Division Material Requisition To Resource Division RTOR000056/2024-2025 4276/ALD 13/12/2024 0 Resource Division 7.63 0.00 0
1528 Alipurduar Division Material Requisition To Resource Division RTOR000057/2023-2024 2719/ALD 13/12/2023 0 Resource Division 60.01 0.00 0
1529 Alipurduar Division Material Requisition To Resource Division RTOR000058/2023-2024 2720/ALD 13/12/2023 0 Resource Division 68.94 0.00 0
1530 Alipurduar Division Material Requisition To Resource Division RTOR000059/2023-2024 2721/ALD 13/12/2023 0 Resource Division 97.75 0.00 0
1531 Alipurduar Division Material Requisition To Resource Division RTOR000060/2023-2024 2722/ALD 13/12/2023 0 Resource Division 137.01 0.00 0
1532 Alipurduar Division Material Requisition To Resource Division RTOR000061/2023-2024 2723/ALD 13/12/2023 0 Resource Division 84.45 0.00 0
1533 Alipurduar Division Material Requisition To Resource Division RTOR000062/2023-2024 2772/ALD 18/12/2023 0 Resource Division 7.29 0.00 0
1534 Alipurduar Division Material Requisition To Resource Division RTOR000063/2023-2024 2773/ALD 18/12/2023 0 Resource Division 7.84 0.00 0
1535 Alipurduar Division Material Requisition To Resource Division RTOR000064/2023-2024 2774 18/12/2023 0 Resource Division 15.16 0.00 0
1536 Alipurduar Division Material Requisition To Resource Division RTOR000065/2023-2024 2775/ALD 18/12/2023 0 Resource Division 18.81 0.00 0
1537 Alipurduar Division Material Requisition To Resource Division RTOR000066/2023-2024 2776/ALD 18/12/2023 0 Resource Division 9.12 0.00 0
1538 Alipurduar Division Material Requisition To Resource Division RTOR000067/2023-2024 2774/ALD 18/12/2023 0 Resource Division 15.16 0.00 0
1539 Alipurduar Division Material Requisition To Resource Division RTOR000068/2023-2024 2781/ALD 18/12/2023 0 Resource Division 11.43 0.00 0
1540 Alipurduar Division Material Requisition To Resource Division RTOR000069/2023-2024 2782/ALD 18/12/2023 0 Resource Division 12.78 0.00 0
1541 Alipurduar Division Material Requisition To Resource Division RTOR000070/2023-2024 2783/ALD 18/12/2023 0 Resource Division 9.88 0.00 0
1542 Alipurduar Division Material Requisition To Resource Division RTOR000071/2023-2024 2784/ALD 18/12/2023 0 Resource Division 6.17 0.00 0
1543 Alipurduar Division Material Requisition To Resource Division RTOR000072/2023-2024 2785/ALD 18/12/2023 0 Resource Division 11.61 0.00 0
1544 Alipurduar Division Material Requisition To Resource Division RTOR000073/2023-2024 98/ALD 10/01/2024 0 Resource Division 10.79 0.00 0
1545 Alipurduar Division Material Requisition To Resource Division RTOR000074/2023-2024 99/ALD 10/01/2024 0 Resource Division 13.03 0.00 0
1546 Alipurduar Division Material Requisition To Resource Division RTOR000075/2023-2024 99/ALD 10/01/2024 0 Resource Division 14.30 0.00 0
1547 Alipurduar Division Material Requisition To Resource Division RTOR000076/2023-2024 100/ALD 10/01/2024 0 Resource Division 9.73 0.00 0
1548 Alipurduar Division Material Requisition To Resource Division RTOR000077/2023-2024 101/ALD 10/01/2024 0 Resource Division 12.67 0.00 0
1549 Alipurduar Division Material Requisition To Resource Division RTOR000078/2023-2024 102/ALD 10/01/2024 0 Resource Division 16.34 0.00 0
1550 Alipurduar Division Material Requisition To Resource Division RTOR000079/2023-2024 103/ALD 10/01/2024 0 Resource Division 3.49 0.00 0
1551 Alipurduar Division Material Requisition To Resource Division RTOR000080/2023-2024 104/ALD 10/01/2024 0 Resource Division 9.73 0.00 0
1552 Alipurduar Division Material Requisition To Resource Division RTOR000081/2023-2024 105/ALD 10/01/2024 0 Resource Division 9.02 0.00 0
1553 Alipurduar Division Material Requisition To Resource Division RTOR000082/2023-2024 106/ALD 10/01/2024 0 Resource Division 11.82 0.00 0
1554 Alipurduar Division Material Requisition To Resource Division RTOR000083/2023-2024 107/ALD 10/01/2024 0 Resource Division 12.32 0.00 0
1555 Alipurduar Division Material Requisition To Resource Division RTOR000084/2023-2024 108/ALD 10/01/2024 0 Resource Division 4.47 0.00 0
1556 Alipurduar Division Material Requisition To Resource Division RTOR000085/2023-2024 109/ALD 10/01/2024 0 Resource Division 11.51 0.00 0
1557 Alipurduar Division Material Requisition To Resource Division RTOR000086/2023-2024 110/ALD 10/01/2024 0 Resource Division 14.30 0.00 0
1558 Alipurduar Division Material Requisition To Resource Division RTOR000087/2023-2024 111/ALD 10/01/2024 0 Resource Division 14.35 0.00 0
1559 Alipurduar Division Material Requisition To Resource Division RTOR000088/2023-2024 112/ALD 10/01/2024 0 Resource Division 4.89 0.00 0
1560 Alipurduar Division Material Requisition To Resource Division RTOR000089/2023-2024 113/ALD 10/01/2024 0 Resource Division 16.53 0.00 0
1561 Alipurduar Division Material Requisition To Resource Division RTOR000090/2023-2024 114/ALD 10/01/2024 0 Resource Division 4.49 0.00 0
1562 Alipurduar Division Material Requisition To Resource Division RTOR000091/2023-2024 115/ALD 10/01/2024 0 Resource Division 15.17 0.00 0
1563 Alipurduar Division Material Requisition To Resource Division RTOR000092/2023-2024 116/ALD 10/01/2024 0 Resource Division 4.21 0.00 0
1564 Alipurduar Division Material Requisition To Resource Division RTOR000093/2023-2024 117/ALD 10/01/2024 0 Resource Division 8.33 0.00 0
1565 Alipurduar Division Material Requisition To Resource Division RTOR000094/2023-2024 118/ALD 10/01/2024 0 Resource Division 6.56 0.00 0
1566 Alipurduar Division Material Requisition To Resource Division RTOR000095/2023-2024 119/ALD 10/01/2024 0 Resource Division 9.56 0.00 0
1567 Alipurduar Division Material Requisition To Resource Division RTOR000096/2023-2024 120/ALD 10/01/2024 0 Resource Division 15.91 0.00 0
1568 Alipurduar Division Material Requisition To Resource Division RTOR000097/2023-2024 121/ALD 10/01/2024 0 Resource Division 12.92 0.00 0
1569 Alipurduar Division Material Requisition To Resource Division RTOR000098/2023-2024 122/ALD 10/01/2024 0 Resource Division 3.71 0.00 0
1570 Alipurduar Division Material Requisition To Resource Division RTOR000099/2023-2024 123/ALD 10/01/2024 0 Resource Division 1.27 0.00 0
1571 Alipurduar Division Material Requisition To Resource Division RTOR000100/2023-2024 214/ALD 10/01/2024 0 Resource Division 10.47 0.00 0
1572 Alipurduar Division Material Requisition To Resource Division RTOR000101/2023-2024 125/ALD 10/01/2024 0 Resource Division 6.17 0.00 0
1573 Alipurduar Division Material Requisition To Resource Division RTOR000102/2023-2024 26/ALD 10/01/2024 0 Resource Division 10.95 0.00 0
1574 Alipurduar Division Material Requisition To Resource Division RTOR000103/2023-2024 127/ALD 10/01/2024 0 Resource Division 8.85 0.00 0
1575 Alipurduar Division Material Requisition To Resource Division RTOR000104/2023-2024 128/ALD 10/01/2024 0 Resource Division 10.13 0.00 0
1576 Alipurduar Division Material Requisition To Resource Division RTOR000105/2023-2024 129/ALD 10/01/2024 0 Resource Division 12.31 0.00 0
1577 Alipurduar Division Material Requisition To Resource Division RTOR000106/2023-2024 130/ALD 10/01/2024 0 Resource Division 9.20 0.00 0
1578 Alipurduar Division Material Requisition To Resource Division RTOR000107/2023-2024 131/ALD 10/01/2024 0 Resource Division 8.44 0.00 0
1579 Alipurduar Division Material Requisition To Resource Division RTOR000108/2023-2024 132/ALD 10/01/2024 0 Resource Division 3.47 0.00 0
1580 Alipurduar Division Material Requisition To Resource Division RTOR000109/2023-2024 133/ALD 10/01/2024 0 Resource Division 5.72 0.00 0
1581 Alipurduar Division Material Requisition To Resource Division RTOR000110/2023-2024 134/ALD 10/01/2024 0 Resource Division 6.95 0.00 0
1582 Alipurduar Division Material Requisition To Resource Division RTOR000111/2023-2024 135/ALD 10/01/2024 0 Resource Division 2.16 0.00 0
1583 Alipurduar Division Material Requisition To Resource Division RTOR000112/2023-2024 136/ALD 10/01/2024 0 Resource Division 3.50 0.00 0
1584 Alipurduar Division Material Requisition To Resource Division RTOR000113/2023-2024 137/ALD 10/01/2024 0 Resource Division 14.03 0.00 0
1585 Alipurduar Division Material Requisition To Resource Division RTOR000114/2023-2024 138/ALD 10/01/2024 0 Resource Division 61.13 0.00 0
1586 Alipurduar Division Material Requisition To Resource Division RTOR000115/2023-2024 139/ALD 10/01/2024 0 Resource Division 9.16 0.00 0
1587 Alipurduar Division Material Requisition To Resource Division RTOR000116/2023-2024 140/ALD 10/01/2024 0 Resource Division 9.76 0.00 0
1588 Alipurduar Division Material Requisition To Resource Division RTOR000117/2023-2024 141/ALD 10/01/2024 0 Resource Division 11.38 0.00 0
1589 Alipurduar Division Material Requisition To Resource Division RTOR000118/2023-2024 142/ALD 10/01/2024 0 Resource Division 10.48 0.00 0
1590 Alipurduar Division Fuel bill for the month of August 2021 VCH/000567/2021-2022 117/21-22/PFMS 08/09/2021 0 SHIVAM SERVICE STATION 0.11 0.00 0
1591 Alipurduar Division Fuel bill for the month of August 2021 VCH/000568/2021-2022 118/21-22/PFMS 08/09/2021 0 SHIVAM SERVICE STATION 0.21 0.00 0
1592 Alipurduar Division Fuel bill for the month of August 2021 VCH/000569/2021-2022 120/21-22/PFMS 08/09/2021 0 SHIVAM SERVICE STATION 0.18 0.00 0
1593 Alipurduar Division Fuel bill for the month of August 2021 VCH/000570/2021-2022 121/21-22/PFMS 08/09/2021 0 SHIVAM SERVICE STATION 0.22 0.00 0
1594 Alipurduar Division Fuel bill for the month of August 2021 VCH/000571/2021-2022 122/21-22/PFMS 08/09/2021 0 SHIVAM SERVICE STATION 0.22 0.00 0
1595 Alipurduar Division Laying of DI/MS/HDPE pipe line from Nepali School (H.S.) towards Birpara Boro Houda WSS providing Functional Household Tap connection (FHTC) in connection with Jaldhara/Jal Sapna for the Birpara Boro Houda WSS under Alipurduar Division, PHE Dte.(Phase-I) VCH/000942/2020-2021 570/20-21 26/03/2021 0 GOUTAM KUMAR DAS 15.00 0.00 0
1596 Alipurduar Division Providing House connection for SALSALABARI water supply scheme at Alipurduar -II Block underAlipuduar Division, P.H.E. Dte. Part-II VCH/000945/2020-2021 572/20-21 26/03/2021 0 TAPASH KUMAR BHOWMICK 14.00 0.00 0
1597 Northern Mechanical Division II Quotation for new service connection at Salkumarhat TW No-III, Application No- 4002994687 BILL/00001/2022-2023 21/11/2022 0 WBSEDCL 1.42 0.00 0
1598 Northern Mechanical Division II Quotation for new service connection at Patlakhawa P/H No- III, Application NO- 4003028004 BILL/00007/2022-2023 BP-97/22-23 02/12/2022 0 WBSEDCL 1.34 0.00 0
1599 Northern Mechanical Division II Quotation for new service connection at Bakla P/H No- III, Application NO- 4003022080 BILL/00008/2022-2023 28/11/2022 0 WBSEDCL 1.37 0.00 0
1600 Northern Mechanical Division II Quotation for new service connection at Mathura TG P/H No-I. Application No- 4003027935 BILL/00016/2022-2023 BP-109/22-23 19/12/2022 0 WBSEDCL 1.34 0.00 0
1601 Northern Mechanical Division II Quotation for new service connection at Birpara (apd) TG P/H No-III. Application No- 4003027982 BILL/00017/2022-2023 BP-110/22-23 19/12/2022 0 WBSEDCL 1.34 0.00 0
1602 Northern Mechanical Division II Quotation for new service connection at kumargram TG P/H No-I. Application No- 4003039105 BILL/00018/2022-2023 BP-108/22-23 19/12/2022 0 WBSEDCL 1.58 0.00 0
1603 Northern Mechanical Division II Quotation for new service connection at kumargram TG P/H No-II. Application No- 4003039118 BILL/00019/2022-2023 BP-107/22-23 19/12/2022 0 WBSEDCL 1.58 0.00 0
1604 Northern Mechanical Division II Quotation for new service connection at Newland TG P/H No-I. Application No- 4003039040 BILL/00020/2022-2023 BP-103/22-23 19/12/2022 0 WBSEDCL 1.58 0.00 0
1605 Northern Mechanical Division II Quotation for new service connection at Newland TG P/H No-II. Application No- 4003039064 BILL/00021/2022-2023 BP-104/22-23 19/12/2022 0 WBSEDCL 1.58 0.00 0
1606 Northern Mechanical Division II Quotation for new service connection at Sankosh TG P/H No-I. Application No- 4003039354 BILL/00022/2022-2023 BP-105/22-23 19/12/2022 0 WBSEDCL 1.58 0.00 0
1607 Northern Mechanical Division II Quotation for new service connection at Sankosh TG P/H No-II. Application No- 4003039376 BILL/00023/2022-2023 BP-106/22-23 19/12/2022 0 WBSEDCL 1.58 0.00 0
1608 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT JATESWAR PWSS PH NO-IV BILL/00031/2023-2024 BP-2023-24-21 27/04/2023 0 WBSEDCL 1.34 0.00 0
1609 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT TELIPARA PWSS PH NO-II BILL/00032/2023-2024 BP-2023-24-50 12/05/2023 0 WBSEDCL 1.21 0.00 0
1610 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT PASCHIM CHENGMARI PWSS PH NO-I BILL/00033/2023-2024 BP-2023-24-14 27/04/2023 0 WBSEDCL 1.21 0.00 0
1611 Northern Mechanical Division II Quotation for new service connection at Dima TG TW No III BILL/00034/2022-2023 BP-120/22-23 09/01/2023 0 WBSEDCL 1.34 0.00 0
1612 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT PASCHIM CHENGMARI PWSS PH NO-II BILL/00034/2023-2024 BP-2023-24-27 27/04/2023 0 WBSEDCL 1.21 0.00 0
1613 Northern Mechanical Division II Quotation for new service connection at Gangutia TG TW No I BILL/00035/2022-2023 BP-121/22-23 09/01/2023 0 WBSEDCL 1.34 0.00 0
1614 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT PURBA NARTHALI PWSS PH NO-I BILL/00035/2023-2024 BP-2023-24-49 12/05/2023 0 WBSEDCL 1.21 0.00 0
1615 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT PURBA NARTHALI PWSS PH NO-II BILL/00036/2023-2024 BP-2023-24-48 12/05/2023 0 WBSEDCL 1.21 0.00 0
1616 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT MARAKHATA PWSS PH NO-I BILL/00037/2023-2024 BP-2023-24-15 27/04/2023 0 WBSEDCL 1.21 0.00 0
1617 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT MARAKHATA PWSS PH NO-II BILL/00038/2023-2024 BP-2023-24-26 27/04/2023 0 WBSEDCL 1.21 0.00 0
1618 Northern Mechanical Division II Quotation for new service connection at Dhumchipara TW No- IV BILL/00039/2022-2023 BP-140/22-23 23/02/2023 0 WBSEDCL 1.99 0.00 0
1619 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT PAKRIGURI PWSS PH NO-I BILL/00039/2023-2024 BP-2023-24-47 12/05/2023 0 WBSEDCL 1.21 0.00 0
1620 Northern Mechanical Division II Quotation for new service connection at Hantapara TW No- III BILL/00040/2022-2023 BP-129/22-23 13/01/2023 0 WBSEDCL 1.81 0.00 0
1621 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT PAKRIGURI PWSS PH NO-II BILL/00040/2023-2024 BP-2023-24-46 12/05/2023 0 WBSEDCL 1.21 0.00 0
1622 Northern Mechanical Division II Quotation for new service connection at Makrapara TW No- IV BILL/00041/2022-2023 BP-130/22-23 13/01/2023 0 WBSEDCL 1.49 0.00 0
1623 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT PAKRIGURI PWSS PH NO-III BILL/00041/2023-2024 BP-2023-24-45 12/05/2023 0 WBSEDCL 1.21 0.00 0
1624 Northern Mechanical Division II Quotation for new service connection at Gargenda TG TW No- IV BILL/00042/2022-2023 BP-139/22-23 23/02/2023 0 WBSEDCL 1.49 0.00 0
1625 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT TELIPARA PWSS PH NO-I BILL/00042/2023-2024 BP-2023-24-51 12/05/2023 0 WBSEDCL 1.21 0.00 0
1626 Northern Mechanical Division II Quotation for new service connection at gopalpur tg TW No- I BILL/00043/2022-2023 BP-128/22-23 13/01/2023 0 WBSEDCL 1.23 0.00 0
1627 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT CHOTO DALDALI PWSS PH NO-II BILL/00043/2023-2024 BP-2023-24-44 12/05/2023 0 WBSEDCL 1.21 0.00 0
1628 Northern Mechanical Division II ADDITIONAL QUOTATION FOR PURBA NARARTHALI PH NO-I BILL/00043/2024-2025 BP-04/24-25 08/04/2024 0 WBSEDCL 2.27 0.00 0
1629 Northern Mechanical Division II Quotation for new service connection at Gopalpur TG TW No- II BILL/00044/2022-2023 BP-131/22-23 13/01/2023 0 WBSEDCL 1.23 0.00 0
1630 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT CHOTO DALDALI PWSS PH NO-I BILL/00044/2023-2024 BP-2023-24-43 12/05/2023 0 WBSEDCL 1.21 0.00 0
1631 Northern Mechanical Division II ADDITIONAL QUOTATION FOR MARAKHATA PWSS PH NO-2 BILL/00044/2024-2025 BP-01/24-25 08/04/2024 0 WBSEDCL 4.30 0.00 0
1632 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT MADHYA KAMAKHYAGURI PWSS PH NO-II BILL/00045/2023-2024 BP-2023-24-42 12/05/2023 0 WBSEDCL 1.21 0.00 0
1633 Northern Mechanical Division II ADDITIONAL QUOTATION FOR PURBA NARARTHALI PH NO-2 BILL/00045/2024-2025 BP-05/24-25 08/04/2024 0 WBSEDCL 12.74 0.00 0
1634 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT MADHYA KAMAKHYAGURI PWSS PH NO-I BILL/00046/2023-2024 BP-2023-24-41 12/05/2023 0 WBSEDCL 1.21 0.00 0
1635 Northern Mechanical Division II New Service connection charges for UTTAR DEOGAON PWSS TW No-I under Alipurduar District BILL/00046/2024-2025 BP-09/24-25 08/04/2024 0 WBSEDCL 5.67 0.00 0
1636 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT MATHURA TG PWSS PH NO-II BILL/00047/2023-2024 BP-2023-24-9 20/04/2023 0 WBSEDCL 1.41 0.00 0
1637 Northern Mechanical Division II ADDITIONAL QUOTATION FOR INFRASTRUCTURE DEVELOPMENT FOR TURTURI P/H NO-I BILL/00047/2024-2025 BP-03/24-25 08/04/2024 0 WBSEDCL 4.54 0.00 0
1638 Northern Mechanical Division II New Service Connection Charges for UMACHARANPUR PWSS P/H NO-I,10 mile BILL/00050/2024-2025 BP-10/24-25 08/04/2024 0 WBSEDCL 12.04 0.00 0
1639 Northern Mechanical Division II New Service Connection Cgarges for UTTAR DEOGAON PWSS P/H NO-II BILL/00051/2024-2025 BP-11/24-25 08/04/2024 0 WBSEDCL 8.77 0.00 0
1640 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR KAYAKHATA PWSS PH NO -I BILL/00053/2024-2025 BP-13/24-25 08/04/2024 0 WBSEDCL 3.20 0.00 0
1641 Northern Mechanical Division II New Service Connection Charges For Kumargram Z-1 P/H NO-2 in the dist. of Alipurduar under NMD-II BILL/00054/2025-2026 04/04/2025 0 WBSEDCL 9.91 0.00 0
1642 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT BHUTNIRGHAT TW NO-III BILL/00057/2023-2024 BP-2023-24-69 13/05/2023 0 WBSEDCL 1.43 0.00 0
1643 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT KADAMBINI TG TW NO-II,Z-II BILL/00058/2023-2024 BP-2023-24-52 15/05/2023 0 WBSEDCL 1.37 0.00 0
1644 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT KADAMBINI TG TW NO-I,Z-II BILL/00059/2023-2024 BP-2023-24-54 15/05/2023 0 WBSEDCL 1.37 0.00 0
1645 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT KADAMBINI TG TW NO-I,Z-I BILL/00060/2023-2024 BP-2023-24-53 15/05/2023 0 WBSEDCL 1.37 0.00 0
1646 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT KADAMBINI TG TW NO-II,Z-I BILL/00061/2023-2024 BP-2023-24-55 15/05/2023 0 WBSEDCL 1.37 0.00 0
1647 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT HOASINABAD TG TW NO-II BILL/00062/2023-2024 BP-2023-24-57 13/05/2023 0 WBSEDCL 1.60 0.00 0
1648 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT HOASINABAD TG TW NO-I BILL/00063/2023-2024 BP-2023-24-56 13/05/2023 0 WBSEDCL 1.60 0.00 0
1649 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT GAROCHIRA BANDAPANI TW NO-I BILL/00064/2023-2024 BP-2023-24-58 13/05/2023 0 WBSEDCL 1.46 0.00 0
1650 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT BANDAPANI TG TW NO-II BILL/00065/2023-2024 BP-2023-24-60 13/05/2023 0 WBSEDCL 1.60 0.00 0
1651 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT BANDAPANI TG TW NO-I BILL/00066/2023-2024 BP-2023-24-59 13/05/2023 0 WBSEDCL 1.60 0.00 0
1652 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT ETHELBARI TG TW NO-I,Z-II BILL/00067/2023-2024 BP-2023-24-62 13/05/2023 0 WBSEDCL 1.60 0.00 0
1653 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT ETHELBARI TG TW NO-II,Z-I BILL/00068/2023-2024 BP-2023-24-63 13/05/2023 0 WBSEDCL 1.60 0.00 0
1654 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT ETHELBARI TG TW NO-I,Z-I BILL/00069/2023-2024 BP-2023-24-61 13/05/2023 0 WBSEDCL 1.60 0.00 0
1655 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT JAYBIRPARA TG TW NO-II BILL/00070/2023-2024 BP-2023-24-65 13/05/2023 0 WBSEDCL 1.46 0.00 0
1656 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT JAYBIRPARA TG TW NO-I BILL/00071/2023-2024 BP-2023-24-64 13/05/2023 0 WBSEDCL 1.46 0.00 0
1657 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT JOGOJHORA BARABAK TW NO-III BILL/00072/2023-2024 BP-2023-24-66 13/05/2023 0 WBSEDCL 1.46 0.00 0
1658 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT BALLALGURI TW NO-I BILL/00073/2023-2024 BP-2023-24-68 13/05/2023 0 WBSEDCL 1.60 0.00 0
1659 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT BALLALGURI TW NO-II BILL/00074/2023-2024 BP-2023-24-67 13/05/2023 0 WBSEDCL 1.60 0.00 0
1660 Northern Mechanical Division II Quotation for Meter Burn at DUMCHIPARA TG PH NO-2 BILL/00173/2024-2025 23/04/2024 0 WBSEDCL 0.10 0.00 0
1661 Northern Mechanical Division II ADDITIONAL QUOTATION FOR AUGUMANTION OF MADHARIHAT BILL/00174/2024-2025 BP-41/24-25 26/04/2024 0 WBSEDCL 0.58 0.00 0
1662 Northern Mechanical Division II QUOTATION CHARGES FOR METER BURN AT DHUMCHIPARA TG PH NO-I BILL/00175/2024-2025 23/04/2024 0 WBSEDCL 0.10 0.00 0
1663 Northern Mechanical Division II ADDITIONAL QUOTATION CHARGES FOR MUNSHIPARA PWSS . BILL/00209/2024-2025 BP-42/24-25 29/04/2024 0 WBSEDCL 0.36 0.00 0
1664 Northern Mechanical Division II SHIFTING OF LTOH LINE AT BHANUNAGAR UNDER BIRPARA CCC BILL/00234/2023-2024 BP-2023-24-130 23/05/2023 0 WBSEDCL 0.47 0.00 0
1665 Northern Mechanical Division II QUOTATION CHARGES FOR MALANGI TG PWSS BILL/00273/2024-2025 BP-66/24-25 09/05/2024 0 WBSEDCL 1.36 0.00 0
1666 Northern Mechanical Division II QUOTATION CHARGES FOR PURBAKATHALBARI PWSS, ZONE-II PH NO-II BILL/00276/2024-2025 BP-80/24-25 16/05/2024 0 WBSEDCL 11.03 0.00 0
1667 Northern Mechanical Division II Additional Quotation for Uttar Rangalibazna PH NO-2 Against Previous Application ID-4003065175 in the dist. of Alipurduar under NMD-II BILL/00277/2025-2026 05/05/2025 0 WBSEDCL 2.83 0.00 0
1668 Northern Mechanical Division II Additional Charges for NIMTI DOMOHANI PWSS PH NO-II in the dist. of Alipurduar Under NMD-II BILL/00278/2025-2026 05/05/2025 0 WBSEDCL 1.67 0.00 0
1669 Northern Mechanical Division II Additional Quotation for JAYBIRPARA PH NO-2 against previous Application ID-4003127162 in the dist. of Alipurduar under NMD-II BILL/00279/2025-2026 05/05/2025 0 WBSEDCL 4.04 0.00 0
1670 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR 15 NO LINE GARGENDA TG PWSS ZONE-I, TW NO-I BILL/00298/2024-2025 BP-82/24-25 16/05/2024 0 WBSEDCL 3.74 0.00 0
1671 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR GARGENDA TG JR. SCHOOL PWSS ZONE-I, TW NO-II BILL/00299/2024-2025 BP-81/24-25 16/05/2024 0 WBSEDCL 4.54 0.00 0
1672 Northern Mechanical Division II Additional Quotation for PARPATLAKHAWA PWSS PH NO-I Against Ref ID-4003317590 in the dist. of Alipurduar Under NMD-II BILL/00354/2025-2026 07/05/2025 0 WBSEDCL 0.36 0.00 0
1673 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT TAPSHIKHATA PH NO III BILL/00379/2023-2024 BP-2023-24-137 24/05/2023 0 WBSEDCL 1.34 0.00 0
1674 Northern Mechanical Division II QUOTATION FOR NSC AT PHASKHAWA PH NO-I BILL/00422/2023-2024 BP-2023-24-153 01/06/2023 0 WBSEDCL 1.31 0.00 0
1675 Northern Mechanical Division II QUOTATION FOR NSC AT PHASKHAWA TG PH NO-II BILL/00423/2023-2024 BP-2023-24-152 01/06/2023 0 WBSEDCL 1.31 0.00 0
1676 Northern Mechanical Division II Additional Quotation charges for Uttar Kamakhyaguri PH NO-V PWSS against Ref. Id-4002930579 in the dist. of Alipurduar Under NMD-II BILL/00433/2025-2026 20/05/2025 0 WBSEDCL 3.50 0.00 0
1677 Northern Mechanical Division II New Service Connection Charges for REJUVINATION OF 28 & 29 Mile Basti PH NO-2 BILL/00523/2024-2025 BP-120/24-25 24/05/2024 0 WBSEDCL 8.22 0.00 0
1678 Northern Mechanical Division II New Service Connection Charges For Rejuvination of 28 & 29 Mile Basti PWSS PH NO-1 BILL/00524/2024-2025 BP-119/24-25 24/05/2024 0 WBSEDCL 3.90 0.00 0
1679 Northern Mechanical Division II New Service connection charge for Paschim Satali PWSS P/H No-I. BILL/00558/2023-2024 BP-2023-24-188 22/06/2023 0 WBSEDCL 1.36 0.00 0
1680 Northern Mechanical Division II New Service connection charge for Paschim Satali PWSS P/H No-II BILL/00559/2023-2024 BP-2023-24-187 22/06/2023 0 WBSEDCL 1.36 0.00 0
1681 Northern Mechanical Division II New Service connection charge for Paschim Satali PWSS P/H No-III BILL/00560/2023-2024 BP-2023-24-186 22/06/2023 0 WBSEDCL 1.36 0.00 0
1682 Northern Mechanical Division II New Service connection charge for Nimti Jhora tea garden PWSS P/H No-I. BILL/00561/2023-2024 BP-2023-24-190 22/06/2023 0 WBSEDCL 1.36 0.00 0
1683 Northern Mechanical Division II New Service connection charge for Nimti Jhora tea garden PWSS P/H No-II BILL/00562/2023-2024 BP-2023-24-189 22/06/2023 0 WBSEDCL 1.36 0.00 0
1684 Northern Mechanical Division II NEW SERVICE CONNECTIO CHARGE FOR DAKSHIN MAJIDKHANA W/S/S P/H NO.1 BILL/00591/2023-2024 BP-2023-24-178 15/06/2023 0 WBSEDCL 1.41 0.00 0
1685 Northern Mechanical Division II NEW SERVICE CONNECTIO CHARGE FOR PURBA KHALISHAMARI W/S/S P/H NO.1 BILL/00592/2023-2024 BP-2023-24-181 15/06/2023 0 WBSEDCL 1.41 0.00 0
1686 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR PURBA KHALISHAMARI W/S/S P/H NO.2 BILL/00593/2023-2024 BP-2023-24-182 15/06/2023 0 WBSEDCL 1.41 0.00 0
1687 Northern Mechanical Division II NEW SERVICE CONNECTIO CHARGE FOR PURBA CHIKLIGURI W/S/S P/H NO.1 BILL/00594/2023-2024 BP-2023-24-179 15/06/2023 0 WBSEDCL 1.41 0.00 0
1688 Northern Mechanical Division II NEW SERVICE CONNECTIO CHARGE FOR PURBA CHIKLIGURI W/S/S P/H NO.2 BILL/00595/2023-2024 BP-2023-24-180 15/06/2023 0 WBSEDCL 1.41 0.00 0
1689 Northern Mechanical Division II NEW SERVICE CONNECTIO CHARGE FOR CHALNIPAK W/S/S P/H NO.2 BILL/00596/2023-2024 BP-2023-24-177 15/06/2023 0 WBSEDCL 1.41 0.00 0
1690 Northern Mechanical Division II Quotation for NSC at P/H No.I under Nurpur W/S/S BILL/00597/2023-2024 BP-2023-24-175 15/06/2023 0 WBSEDCL 1.31 0.00 0
1691 Northern Mechanical Division II Quotation for NSC at P/H No.II under Nurpur W/S/S BILL/00598/2023-2024 BP-2023-24-176 15/06/2023 0 WBSEDCL 1.31 0.00 0
1692 Northern Mechanical Division II Quotation for NSC at P/H No.I under Kohinoor TG W/S/S BILL/00599/2023-2024 BP-2023-24-172 15/06/2023 0 WBSEDCL 1.31 0.00 0
1693 Northern Mechanical Division II Quotation for NSC at P/H No.II under Kohinoor TG W/S/S BILL/00600/2023-2024 BP-2023-24-173 15/06/2023 0 WBSEDCL 1.31 0.00 0
1694 Northern Mechanical Division II Quotation for NSC at P/H No.III under Kohinoor TG W/S/S BILL/00601/2023-2024 BP-2023-24-174 15/06/2023 0 WBSEDCL 1.31 0.00 0
1695 Northern Mechanical Division II Quotation for NSC at P/H No.I under Kartika TG Area W/S/S BILL/00602/2023-2024 BP-2023-24-170 15/06/2023 0 WBSEDCL 1.31 0.00 0
1696 Northern Mechanical Division II Quotation for NSC at P/H No.II under Kartika TG Area W/S/S BILL/00603/2023-2024 BP-2023-24-171 15/06/2023 0 WBSEDCL 1.31 0.00 0
1697 Northern Mechanical Division II Quotation for NSC at P/H No.III under Dhaoljhora TG W/S/S BILL/00604/2023-2024 BP-2023-24-169 15/06/2023 0 WBSEDCL 1.31 0.00 0
1698 Northern Mechanical Division II New Service Connection charges for Dalimpur Zone-II PH NO-II,JATESWAR BILL/00617/2024-2025 BP-140/24-25 11/06/2024 0 WBSEDCL 4.35 0.00 0
1699 Northern Mechanical Division II New Service Connection Charges for Dalimpur Zone-II, PH NO-I Jateswar BILL/00618/2024-2025 BP-141/24-25 11/06/2024 0 WBSEDCL 3.72 0.00 0
1700 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR TASTI TG ( NEAR- FOOTBALL MATH) PWSS PH NO-II BILL/00619/2024-2025 BP-142/24-25 11/06/2024 0 WBSEDCL 5.12 0.00 0
1701 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR TASTI TG (NEAR-RATION SHOP) PWSS PH NO-I. BILL/00620/2024-2025 BP-143/24-25 11/06/2024 0 WBSEDCL 4.53 0.00 0
1702 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR UTTAR SISHUBARI MADARIHAT GOPAL BAGAN PWSS BILL/00630/2024-2025 BP-170/24-25 03/07/2024 0 WBSEDCL 5.41 0.00 0
1703 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES AT PASCHIM DEOGAON PWSS TW NO- I IN THE DIST OF ALIPURDUAR. BILL/00631/2024-2025 BP-171/24-25 03/07/2024 0 WBSEDCL 6.77 0.00 0
1704 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR MALSAGAON PWSS TW NO-II IN THE DIST OF ALIPURDUAR. BILL/00632/2024-2025 BP-174/24-25 03/07/2024 0 WBSEDCL 0.50 0.00 0
1705 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR BUXA FOREST ZONE-2 PH NO-2 BILL/00633/2024-2025 BP-172/24-25 03/07/2024 0 WBSEDCL 4.94 0.00 0
1706 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR BUXA FOREST PWSS ZONE-3 TW NO-1 BILL/00634/2024-2025 BP-173/24-25 03/07/2024 0 WBSEDCL 5.98 0.00 0
1707 Northern Mechanical Division II New Service connection charges under Malsagaon pwss TW no-I in the dist of Alipurduar. BILL/00662/2024-2025 BP-175/24-25 03/07/2024 0 WBSEDCL 9.94 0.00 0
1708 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR PURBA KATHALBARI zONE-IV P/H NO.I BILL/00676/2023-2024 BP-2023-24-198 22/06/2023 0 WBSEDCL 1.71 0.00 0
1709 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR PURBA KATHALBARI zONE-III P/H NO.I BILL/00677/2023-2024 BP-2023-24-197 22/06/2023 0 WBSEDCL 1.71 0.00 0
1710 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR PURBA KATHALBARI zONE-III P/H NO.II BILL/00678/2023-2024 BP-2023-24-196 22/06/2023 0 WBSEDCL 1.71 0.00 0
1711 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR PURBA KATHALBARI zONE-I P/H NO.II BILL/00679/2023-2024 BP-2023-24-195 22/06/2023 0 WBSEDCL 1.71 0.00 0
1712 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR SALKUMARHAT P/H NO.IV BILL/00680/2023-2024 BP-2023-24-194 22/06/2023 0 WBSEDCL 1.48 0.00 0
1713 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR MUNSHIPARA P/H NO.III BILL/00681/2023-2024 06/06/2023 0 WBSEDCL 1.00 0.00 0
1714 Northern Mechanical Division II New Service Connection Charges for Malongi TG PWSS PH NO-02 BILL/00733/2024-2025 BP-196/24-25 09/07/2024 0 WBSEDCL 9.66 0.00 0
1715 Northern Mechanical Division II New Service connection charges for Malongi TG PWSS PH NO-01, HASHIMARA BILL/00734/2024-2025 BP-195/24-25 09/07/2024 0 WBSEDCL 5.06 0.00 0
1716 Northern Mechanical Division II New Service Connection Charges for Chegmari PWSS PH NO-1 BILL/00735/2024-2025 BP-193/24-25 09/07/2024 0 WBSEDCL 3.31 0.00 0
1717 Northern Mechanical Division II New service connection charges for LANKAPARA HAT 20 NO LINE PWSS PH NO-1 BILL/00736/2024-2025 BP-194/24-25 09/07/2024 0 WBSEDCL 5.07 0.00 0
1718 Northern Mechanical Division II NEW SEVICE CONNECTION CHARGES FOR TURTURI PWSS P/H NO.I BILL/00739/2023-2024 BP-2023-24-282 18/08/2023 0 WBSEDCL 1.48 0.00 0
1719 Northern Mechanical Division II NEW SEVICE CONNECTION CHARGES FOR TURTURI PWSS P/H NO.II BILL/00740/2023-2024 BP-2023-24-273 18/08/2023 0 WBSEDCL 1.48 0.00 0
1720 Northern Mechanical Division II NEW SEVICE CONNECTION CHARGES FOR SAMUKTALA PWSS ZONE-IIP/H NO.I BILL/00741/2023-2024 BP-2023-24-218 13/07/2023 0 WBSEDCL 1.54 0.00 0
1721 Northern Mechanical Division II New Service Connection at Raydak TG p/h-I BILL/00747/2023-2024 BP-2023-24-193 22/06/2023 0 WBSEDCL 1.31 0.00 0
1722 Northern Mechanical Division II New Service Connection at Raydak TG p/h-II BILL/00748/2023-2024 BP-2023-24-192 22/06/2023 0 WBSEDCL 1.31 0.00 0
1723 Northern Mechanical Division II New Service Connection at Raydak TG p/h-III BILL/00749/2023-2024 BP-2023-24-191 22/06/2023 0 WBSEDCL 1.31 0.00 0
1724 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR SAMUKTALA ZONE -III P/H NO.I BILL/00785/2023-2024 BP-2023-24-219 13/07/2023 0 WBSEDCL 1.54 0.00 0
1725 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR SAMUKTALA ZONE -III P/H NO.II BILL/00786/2023-2024 BP-2023-24-220 13/07/2023 0 WBSEDCL 1.54 0.00 0
1726 Northern Mechanical Division II New Service Connection Charges for Nurpur, Uttar Rampur, PWSS PH NO-3 BILL/00824/2024-2025 BP-292/24-25 20/08/2024 0 WBSEDCL 13.73 0.00 0
1727 Northern Mechanical Division II New Service Connection for Chengmari PWSS P/H NO-2 BILL/00825/2024-2025 BP-272/24-25 12/08/2024 0 WBSEDCL 0.76 0.00 0
1728 Northern Mechanical Division II Additional Quotation Charges for Ethelbari Zone-II,PH NO-I PWSS BILL/00826/2024-2025 BP-271/24-25 12/08/2024 0 WBSEDCL 6.53 0.00 0
1729 Northern Mechanical Division II New Service Connection Charges for Baruipara pwss PH NO-II BILL/00860/2024-2025 BP-261/24-25 09/08/2024 0 WBSEDCL 5.87 0.00 0
1730 Northern Mechanical Division II Additional quotation for PAKRIGURI PH NO-3 BILL/00862/2024-2025 BP-264/24-25 09/08/2024 0 WBSEDCL 5.46 0.00 0
1731 Northern Mechanical Division II Additional quotation for PAKRIGURI PH NO-2 BILL/00863/2024-2025 BP-262/24-25 09/08/2024 0 WBSEDCL 5.41 0.00 0
1732 Northern Mechanical Division II Additional quotation for Pakriguri PH NO-1 BILL/00864/2024-2025 BP-263/24-25 09/08/2024 0 WBSEDCL 3.01 0.00 0
1733 Northern Mechanical Division II Additional Quotation for CHOTO DALDALI PH NO-2 BILL/00865/2024-2025 BP-266/24-25 09/08/2024 0 WBSEDCL 5.79 0.00 0
1734 Northern Mechanical Division II Additional Quotation for CHOTO DALDALI PH NO-1 BILL/00866/2024-2025 BP-265/24-25 09/08/2024 0 WBSEDCL 3.48 0.00 0
1735 Northern Mechanical Division II New Service Connection Charges for AUGMENTATION OF KUMARGRAM (Uttar Haldibari) pwss PH NO-II Zone-III BILL/00890/2024-2025 BP-288/24-25 22/08/2024 0 WBSEDCL 4.46 0.00 0
1736 Northern Mechanical Division II New Service Connection Charges for AUGMENTATION OF KUMARGRAM (Uttar Haldibari) pwss ph NO-I Zone-III BILL/00891/2024-2025 BP-289/24-25 22/08/2024 0 WBSEDCL 3.22 0.00 0
1737 Northern Mechanical Division II New Service Connection Charges for AUGMENTATION OF KUMARGRAM (AMARPUR) pwss PH NO-I Zone-IV BILL/00892/2024-2025 BP-290/24-25 22/08/2024 0 WBSEDCL 5.75 0.00 0
1738 Northern Mechanical Division II New Service Connection Charge For Shrinathpur TG BILL/00899/2023-2024 BP-2023-24-224 13/07/2023 0 WBSEDCL 0.81 0.00 0
1739 Northern Mechanical Division II New Service Connection Charges For BANDAPANI TG Zone-II PH NO-II Near RETI PWSS Under NMD-II in the dist. of ALIPURDUAR BILL/00899/2025-2026 13/06/2025 0 WBSEDCL 6.09 0.00 0
1740 Northern Mechanical Division II New Service Connection Charge For Shrinathpur TG T/W NO.I BILL/00900/2023-2024 BP-2023-24-223 13/07/2023 0 WBSEDCL 0.81 0.00 0
1741 Northern Mechanical Division II New Service Connection Charge For Samuktala Z-I P/H NO-II BILL/00901/2023-2024 BP-2023-24-221 13/07/2023 0 WBSEDCL 1.54 0.00 0
1742 Northern Mechanical Division II New Service Connection Charge For Samuktala Z-I P/H No.I BILL/00902/2023-2024 BP-2023-24-222 13/07/2023 0 WBSEDCL 1.54 0.00 0
1743 Northern Mechanical Division II New Service Connection for Mairadanga PH NO-II PWSS BILL/00984/2024-2025 BP-278/24-25 22/08/2024 0 WBSEDCL 5.22 0.00 0
1744 Northern Mechanical Division II New Servivce Connection for Marindanga PH NO-I PWSS BILL/00985/2024-2025 BP-279/24-25 22/08/2024 0 WBSEDCL 7.07 0.00 0
1745 Northern Mechanical Division II New Service Connection Charges for Kayakhata PWSS PH NO-II BILL/00986/2024-2025 BP-282/24-25 20/08/2024 0 WBSEDCL 9.90 0.00 0
1746 Northern Mechanical Division II New Service Connection for Umacharanpur PH NO-II PWSS BILL/00987/2024-2025 BP-276/24-25 22/08/2024 0 WBSEDCL 10.48 0.00 0
1747 Northern Mechanical Division II New service connection charges for Khagenhat PWSS PH NO-2 BILL/01179/2024-2025 BP-330/24-25 03/10/2024 0 WBSEDCL 1.07 0.00 0
1748 Northern Mechanical Division II New Service Connection charges for Khagenhat PWSS PH NO-1 under NMD-II BILL/01180/2024-2025 BP-327/24-25 03/10/2024 0 WBSEDCL 7.59 0.00 0
1749 Northern Mechanical Division II New Service Connection Charges for Baruipara pwss PH NO-I under NMD-II BILL/01181/2024-2025 BP-326/24-25 04/10/2024 0 WBSEDCL 5.85 0.00 0
1750 Northern Mechanical Division II New Service Connection for Uttar Dhalkar PWSS PH NO-I in the dist of Alipurduar BILL/01182/2024-2025 BP-328/24-25 03/10/2024 0 WBSEDCL 4.90 0.00 0
1751 Northern Mechanical Division II New Service Connection Charges for Samuktala Zone-II PH NO-II BILL/01265/2024-2025 BP-386/24-25 05/10/2024 0 WBSEDCL 11.40 0.00 0
1752 Northern Mechanical Division II New Service Connection Charges for Dhantali PH NO-2 BILL/01409/2024-2025 BP-406/24-25 30/10/2024 0 WBSEDCL 5.21 0.00 0
1753 Northern Mechanical Division II New Service Connection Charges for Dhantali PWSS PH NO-1 BILL/01411/2024-2025 BP-404/24-25 30/10/2024 0 WBSEDCL 9.12 0.00 0
1754 Northern Mechanical Division II New Service Connection Charges for Gopalpur TG BILL/01412/2024-2025 BP-405/24-25 30/10/2024 0 WBSEDCL 5.59 0.00 0
1755 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT CHALNIPAK PWSS P/H NO-III BILL/01446/2023-2024 BP-2023-24-286 21/08/2023 0 WBSEDCL 5.44 0.00 0
1756 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT CHALNIPAK PWSS P/H NO. I BILL/01447/2023-2024 BP-2023-24-291 21/08/2023 0 WBSEDCL 8.12 0.00 0
1757 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT PURBA KATHALBARI PWSS PALASHBARI, FLOOD SHELTER, ZONE-I,P/H NO-I BILL/01448/2023-2024 BP-2023-24-293 21/08/2023 0 WBSEDCL 6.38 0.00 0
1758 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT NATHUATARI PWSS P/H NO.I BILL/01449/2023-2024 BP-2023-24-294 21/08/2023 0 WBSEDCL 5.92 0.00 0
1759 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT NATHUATARI PWSS P/H NO. II BILL/01450/2023-2024 BP-2023-24-285 21/08/2023 0 WBSEDCL 5.45 0.00 0
1760 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT DAKSHIN BARAJHAR FOREST PWSS P/H NO. I BILL/01451/2023-2024 BP-2023-24-284 21/08/2023 0 WBSEDCL 5.32 0.00 0
1761 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT DAKSHIN MAJIDKHANA PWSS P/H NO. II BILL/01452/2023-2024 BP-2023-24-292 21/08/2023 0 WBSEDCL 5.99 0.00 0
1762 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT PARARPAR PWSS P/H NO-I BILL/01453/2023-2024 BP-2023-24-287 21/08/2023 0 WBSEDCL 5.89 0.00 0
1763 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT PARARPAR PWSS P/H-II BILL/01454/2023-2024 BP-2023-24-288 21/08/2023 0 WBSEDCL 5.63 0.00 0
1764 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT DAKSHIN SONAPUR W/S SCHEME P/H NO.-V BILL/01455/2023-2024 BP-2023-24-289 21/08/2023 0 WBSEDCL 4.20 0.00 0
1765 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT DAKSHIN SONAPUR WS SCHEME P/H NO.-VI BILL/01456/2023-2024 BP-2023-24-290 21/08/2023 0 WBSEDCL 4.20 0.00 0
1766 Northern Mechanical Division II New Service Connection Charges for Dalmore & Ramjhora TG PH NO-IV BILL/01584/2024-2025 BP-412/24-25 20/11/2024 0 WBSEDCL 6.75 0.00 0
1767 Northern Mechanical Division II New Service Connection at Bairaguri P/H No.I BILL/01685/2023-2024 BP-2023-24-347 27/09/2023 0 WBSEDCL 7.58 0.00 0
1768 Northern Mechanical Division II New Service Connection at Bairaguri P/H No.II BILL/01686/2023-2024 BP-2023-24-348 27/09/2023 0 WBSEDCL 3.88 0.00 0
1769 Northern Mechanical Division II New Service Connection at Bairaguri P/H No.III BILL/01687/2023-2024 BP-2023-24-349 27/09/2023 0 WBSEDCL 6.08 0.00 0
1770 Northern Mechanical Division II New Service Connection at Uttar Masjidkhana P/H No.I BILL/01688/2023-2024 BP-2023-24-337 27/09/2023 0 WBSEDCL 6.58 0.00 0
1771 Northern Mechanical Division II QUOTATION FOR NSC AT MUNSHIPARA PH NO-III BILL/01750/2023-2024 BP-2023-24-359 27/09/2023 0 WBSEDCL 1.00 0.00 0
1772 Northern Mechanical Division II QUOTATION FOR NSC AT FOSKADANGA PH NO-I BILL/01782/2023-2024 BP-2023-24-371 27/09/2023 0 WBSEDCL 14.07 0.00 0
1773 Northern Mechanical Division II NEW SERVICE CONNECTION FOR SISHUJHUMRA PWSS P/H NO-I,BIRPARA,ALIPURDUAR, APPLICATION NO 4003068997 BILL/01783/2023-2024 BP-2023-24-366 27/09/2023 0 WBSEDCL 6.89 0.00 0
1774 Northern Mechanical Division II NEW SERVICE CONNECTION FOR SISHUJHUMRA PWSS,P/H NO II,BIRPARA,ALIPURDUAR, APPLICATION NO 4003068181 BILL/01784/2023-2024 BP-2023-24-365 27/09/2023 0 WBSEDCL 9.33 0.00 0
1775 Northern Mechanical Division II NEW SERVICE CONNECTION FOR SISHUJHUMRA PWSS,P/H NO- III,BIRPARA, ALIPURDUAR, APPLICATION NO 4003068999 BILL/01785/2023-2024 BP-2023-24-364 27/09/2023 0 WBSEDCL 6.65 0.00 0
1776 Northern Mechanical Division II NEW SERVICE CONNECTION FOR MADHYA KHAIRBARI PWSS P/H NO I APPLICATION NO 4003065159 BILL/01788/2023-2024 BP-2023-24-367 27/09/2023 0 WBSEDCL 15.45 0.00 0
1777 Northern Mechanical Division II NEW CONNECTION SETRVICE FOR MADHYA KHAIRBARI PWSS P/H NO II APPLICATION NO 4003065166 BILL/01789/2023-2024 BP-2023-24-368 27/09/2023 0 WBSEDCL 8.34 0.00 0
1778 Northern Mechanical Division II NEW CONNECTION SETRVICE FOR MADHYA KHAIRBARI PWSS P/H NO III APPLICATION NO 4003065168 BILL/01790/2023-2024 BP-2023-24-369 27/09/2023 0 WBSEDCL 5.82 0.00 0
1779 Northern Mechanical Division II NEW CONNECTION SETRVICE FOR UTTAR RANGALIBAZNA PWSS P/H NO I APPLICATION NO 4003065172 BILL/01793/2023-2024 BP-2023-24-362 27/09/2023 0 WBSEDCL 7.70 0.00 0
1780 Northern Mechanical Division II NEW CONNECTION SERVICE FOR UTTAR RANGALIBAZNA PWSS P/H NO II BILL/01796/2023-2024 BP-2023-24-363 27/09/2023 0 WBSEDCL 5.74 0.00 0
1781 Northern Mechanical Division II NEW CONNECTION SERVICE FOR DAKSHIN RANGALIBAZNA PWSS P/H NO I APPLICATION NO 4003065178 BILL/01798/2023-2024 BP-2023-24-382 27/09/2023 0 WBSEDCL 11.71 0.00 0
1782 Northern Mechanical Division II NEW CONNECTION SERVICE FOR DAKSHIN RANGALIBAZNA PWSS P/H NO II APPLICATION NO 4003065179 BILL/01802/2023-2024 BP-2023-24-381 27/09/2023 0 WBSEDCL 11.63 0.00 0
1783 Northern Mechanical Division II NEW CONNECTION SETRVICE FOR KALCHINI T.G.,PWSS P/H NO I,ZONE II, KALCHINI APPLICATION NO 4003208203 BILL/01806/2023-2024 BP-2023-24-380 27/09/2023 0 WBSEDCL 5.60 0.00 0
1784 Northern Mechanical Division II NEW CONNECTION SETRVICE FOR RAJABHAT T.G. PWSS P/H I,KALCHINI APPLICATION NO 4003210055 BILL/01807/2023-2024 BP-2023-24-379 27/09/2023 0 WBSEDCL 4.08 0.00 0
1785 Northern Mechanical Division II QUOTATION FOR NSC AT FOSKARDANGA TW NO-II BILL/01808/2023-2024 BP-2023-24-370 27/09/2023 0 WBSEDCL 13.41 0.00 0
1786 Northern Mechanical Division II QUOTATION FOR NSC AT PRADHAN PARA PH NO-I BILL/01809/2023-2024 BP-2023-24-374 27/09/2023 0 WBSEDCL 3.96 0.00 0
1787 Northern Mechanical Division II QUOTATION FOR NSC AT KALABARIA PH NO-I BILL/01810/2023-2024 BP-2023-24-373 27/09/2023 0 WBSEDCL 4.76 0.00 0
1788 Northern Mechanical Division II QUOTATION FOR NSC AT KALABARIA PH NO-II BILL/01811/2023-2024 BP-2023-24-372 27/09/2023 0 WBSEDCL 3.72 0.00 0
1789 Northern Mechanical Division II QUOTATION FOR NSC AT TORSHA FOREST PH NO-I BILL/01812/2023-2024 BP-2023-24-375 27/09/2023 0 WBSEDCL 4.07 0.00 0
1790 Northern Mechanical Division II NEW SERVICE CONNECTION FOR BEECH TG PWSS P/H NO I,HASIMARA APPLICATION NO 4003208190 BILL/01814/2023-2024 BP-2023-24-323 27/09/2023 0 WBSEDCL 5.40 0.00 0
1791 Northern Mechanical Division II NEW SERVIVCE CONNECTION FOR KALCHINI TG PWSS P/H NO II,ZONE-I,KALCHINI APPLICATION NO 4003208205 BILL/01817/2023-2024 BP-2023-24-321 27/09/2023 0 WBSEDCL 5.56 0.00 0
1792 Northern Mechanical Division II NEW SERVICE CONNECTION FOR KALCHINI TG PWSS P/H NO II,ZONE-II,KALCHINI APPLICATION NO 4003208210 BILL/01821/2023-2024 BP-2023-24-322 27/09/2023 0 WBSEDCL 9.42 0.00 0
1793 Northern Mechanical Division II NEW SERVICE CONNECTION FOR BEECH TG PWSS P/H NO II,HASIMARA APPLICATION NO 4003208193 BILL/01823/2023-2024 BP-2023-24-324 27/09/2023 0 WBSEDCL 5.67 0.00 0
1794 Northern Mechanical Division II QUOTATION FOR BURNT METER AT BIRPARA BILL/01825/2023-2024 BP-2023-24-329 27/09/2023 0 WBSEDCL 0.09 0.00 0
1795 Northern Mechanical Division II ADDITIONAL QUOTATION FOR APPLICATION NO 4003209532 SITE PARARPAR PWSS ALIPURDUAR. BILL/01826/2023-2024 BP-2023-24-331 27/09/2023 0 WBSEDCL 2.44 0.00 0
1796 Northern Mechanical Division II NEW SERVICE CONNECTION FOR BHUTRI FOREST PWSS P/H NO I,KALCHINI APPLICATION NO 4003208197 BILL/01827/2023-2024 BP-2023-24-320 27/09/2023 0 WBSEDCL 4.10 0.00 0
1797 Northern Mechanical Division II QUOTATION FOR NSC AT ATIABARI PH NO-II BILL/01828/2023-2024 BP-2023-24-326 27/09/2023 0 WBSEDCL 4.70 0.00 0
1798 Northern Mechanical Division II QUOTATION FOR NSC AT BHATKHAWA TG PH NO-I BILL/01829/2023-2024 BP-2023-24-325 27/09/2023 0 WBSEDCL 12.30 0.00 0
1799 Northern Mechanical Division II QUOTATION FOR NSC AT ATIABARI PH NO-II BILL/01830/2023-2024 25/09/2023 0 WBSEDCL 7.97 0.00 0
1800 Northern Mechanical Division II QUOTATION FOR 3 PHASE UNIT METER ID -402728652 BILL/01831/2023-2024 BP-2023-24-330 27/09/2023 0 WBSEDCL 0.10 0.00 0
1801 Northern Mechanical Division II QUOTATION FOR NSC AT BHATKHAWA TG TW NO-II BILL/01848/2023-2024 BP-2023-24-391 06/10/2023 0 WBSEDCL 7.97 0.00 0
1802 Northern Mechanical Division II New service connection Charges for Dalimpur PWSS Zone-I PH NO-I under NMD-II BILL/01887/2024-2025 BP-426/24-25 16/12/2024 0 WBSEDCL 5.05 0.00 0
1803 Northern Mechanical Division II New Service Connection charges for Purba Kathalbari Zone-IV PH NO-II under NMD-II BILL/01888/2024-2025 BP-444/24-25 16/12/2024 0 WBSEDCL 6.36 0.00 0
1804 Northern Mechanical Division II New Service Connection charges for Aug of Dalimpur Zone-III PH NO-II under NMD-II BILL/01889/2024-2025 BP-423/24-25 16/12/2024 0 WBSEDCL 14.15 0.00 0
1805 Northern Mechanical Division II New Service Connection Charges for Aug of Dalimpur Zone-I PH NO-II under NMD-II BILL/01890/2024-2025 BP-424/24-25 16/12/2024 0 WBSEDCL 5.85 0.00 0
1806 Northern Mechanical Division II New Service connection charges for DALMUNI Zone-I PHNO-II under NMD-II BILL/01891/2024-2025 BP-430/24-25 16/12/2024 0 WBSEDCL 5.16 0.00 0
1807 Northern Mechanical Division II New Service Connection Charges For Aug of Dalimpur Zone-III PH NO-I under NMD-II BILL/01892/2024-2025 BP-425/24-25 16/12/2024 0 WBSEDCL 16.01 0.00 0
1808 Northern Mechanical Division II New Service Connection Charges for Parpatlakhowa PWSS PH NO-II under NMD-II BILL/01893/2024-2025 BP-427/24-25 16/12/2024 0 WBSEDCL 13.63 0.00 0
1809 Northern Mechanical Division II New Service Connection Charges for Uttar Dhalkar PWSS PH NO-2 under NMD-II BILL/01894/2024-2025 BP-428/24-25 16/12/2024 0 WBSEDCL 5.25 0.00 0
1810 Northern Mechanical Division II New service connection charges for AUG of Kumargram Zone-IV, P/H-II(Amarpur) under NMD-II BILL/01895/2024-2025 BP-443/24-25 16/12/2024 0 WBSEDCL 7.59 0.00 0
1811 Northern Mechanical Division II New Service Connection Charges for Lacchi Mendabari, Lacchi Mendabari PWSS, TW No-I Under NMD-II BILL/01896/2024-2025 BP-431/24-25 16/12/2024 0 WBSEDCL 3.47 0.00 0
1812 Northern Mechanical Division II New Service Connection Charges for Paschim Deogaon PWSS, P/H-II under NMD-II BILL/01897/2024-2025 BP-436/24-25 16/12/2024 0 WBSEDCL 2.53 0.00 0
1813 Northern Mechanical Division II New service connection charges for Aug of Kumargram Z-I, P/H-I under NMD-II BILL/01899/2024-2025 BP-443/24-25 16/12/2024 0 WBSEDCL 6.26 0.00 0
1814 Northern Mechanical Division II NEW SERVICE CONNECTION AT JOGENDRAPUR TW III BILL/01972/2023-2024 BP-2023-24-462 07/12/2023 0 WBSEDCL 5.36 0.00 0
1815 Northern Mechanical Division II NEW CONNECTION FOR BIRPARA(AUG) ZONE- IPHNO-II BILL/02001/2023-2024 BP-2023-24-460 07/12/2023 0 WBSEDCL 4.26 0.00 0
1816 Northern Mechanical Division II NEW CONNECTION FOR BIRPARA (AUG) ZONE-I PHNO-III BILL/02002/2023-2024 BP-2023-24-461 07/12/2023 0 WBSEDCL 5.50 0.00 0
1817 Northern Mechanical Division II New Service Connection Charges for Uttar Medabari PWSS PH NO-I Zone-II Under NMD-II BILL/02021/2024-2025 BP-432/24-25 16/12/2024 0 WBSEDCL 8.13 0.00 0
1818 Northern Mechanical Division II New Service Connection Charges for New Line Saradapally H.W.C Z-II P/H NO-III Birpara under NMD-II in the dist. of Alipurduar BILL/02032/2024-2025 BP-458/24-25 09/01/2025 0 WBSEDCL 15.17 0.00 0
1819 Northern Mechanical Division II New Service Connection Charges for Lachmandabri PWSS under NMD-II in the dist of Alipurduar BILL/02037/2024-2025 BP-453/24-25 09/01/2025 0 WBSEDCL 11.80 0.00 0
1820 Northern Mechanical Division II Additional Quotation for chengmari PH NO-2 under NMD-II BILL/02038/2024-2025 BP-452/24-25 09/01/2025 0 WBSEDCL 3.32 0.00 0
1821 Northern Mechanical Division II Additional QUOTATION for Madhya Kamakhyaguri P/H NO-II under NMD-II BILL/02039/2024-2025 BP-454/24-25 09/01/2025 0 WBSEDCL 3.03 0.00 0
1822 Northern Mechanical Division II Additional quotation for Munshipara p/h-III BILL/02150/2023-2024 BP-2023-24-479 12/12/2023 0 WBSEDCL 3.86 0.00 0
1823 Northern Mechanical Division II New service connection charge for Uttar majidkhana p/h-II BILL/02151/2023-2024 BP-2023-24-472 12/12/2023 0 WBSEDCL 6.20 0.00 0
1824 Northern Mechanical Division II Additional Quotation for BANDAPANI TG P/HNO-II(Application No-4003127203) BILL/02163/2023-2024 BP-2023-24-471 12/12/2023 0 WBSEDCL 25.52 0.00 0
1825 Northern Mechanical Division II Quotation for Nepania P/H NO-I BILL/02164/2023-2024 01/12/2023 0 WBSEDCL 28.07 0.00 0
1826 Northern Mechanical Division II Qutation for Jayani TG-2 P/HNO-I BILL/02165/2023-2024 BP-2023-24-470 12/12/2023 0 WBSEDCL 16.18 0.00 0
1827 Northern Mechanical Division II Additional Quotation for Nurpur P/H No.III BILL/02165/2024-2025 BP-468/24-25 21/01/2025 0 WBSEDCL 2.10 0.00 0
1828 Northern Mechanical Division II New service connection for Bhatibari PWSS ZONE-III P/HNO-2 BILL/02196/2023-2024 BP-2023-24-473 12/12/2023 0 WBSEDCL 5.17 0.00 0
1829 Northern Mechanical Division II New service connection for Bhatibari zone-II, P/HNO-I BILL/02197/2023-2024 BP-2023-24-474 12/12/2023 0 WBSEDCL 3.91 0.00 0
1830 Northern Mechanical Division II QUOTATION BILL/02198/2023-2024 BP-2023-24-475 12/12/2023 0 WBSEDCL 4.13 0.00 0
1831 Northern Mechanical Division II QUOTATION BILL/02199/2023-2024 BP-2023-24-476 12/12/2023 0 WBSEDCL 5.51 0.00 0
1832 Northern Mechanical Division II QUOTATION BILL/02200/2023-2024 BP-2023-24-477 12/12/2023 0 WBSEDCL 8.14 0.00 0
1833 Northern Mechanical Division II QUOTATION BILL/02201/2023-2024 BP-2023-24-478 12/12/2023 0 WBSEDCL 5.17 0.00 0
1834 Northern Mechanical Division II QUATATION BILL/02208/2023-2024 BP-2023-24-484 12/12/2023 0 WBSEDCL 5.11 0.00 0
1835 Northern Mechanical Division II QUOTATION BILL/02209/2023-2024 BP-2023-24-485 12/12/2023 0 WBSEDCL 11.22 0.00 0
1836 Northern Mechanical Division II QUOTATION BILL/02210/2023-2024 BP-2023-24-483 12/12/2023 0 WBSEDCL 3.05 0.00 0
1837 Northern Mechanical Division II New Service Connection for Birpara Thana PWSS, Zone-II, P/H No-II BILL/02301/2023-2024 BP-2023-24-618 16/02/2024 0 WBSEDCL 3.74 0.00 0
1838 Northern Mechanical Division II Nee Service Connection for Dhumchipara T.G PWSS BILL/02302/2023-2024 BP-2023-24-503 05/01/2024 0 WBSEDCL 6.73 0.00 0
1839 Northern Mechanical Division II New Service Connection for Rajabhat T.G PWSS P/H NO-II,Kalchini BILL/02303/2023-2024 BP-2023-24-504 05/01/2024 0 WBSEDCL 3.76 0.00 0
1840 Northern Mechanical Division II New Service Connection for Atiabari T.G PWSS P/H No-I, Kalchini BILL/02304/2023-2024 BP-2023-24-509 05/01/2024 0 WBSEDCL 5.81 0.00 0
1841 Northern Mechanical Division II New Service Connection for Mechpara T.G Area P/HNo-II, Kalchini. BILL/02305/2023-2024 BP-2023-24-508 05/01/2024 0 WBSEDCL 6.53 0.00 0
1842 Northern Mechanical Division II New Service Connection for Mechpara TG Area PWSS P/H No-I,Kalchini BILL/02306/2023-2024 BP-2023-24-510 05/01/2024 0 WBSEDCL 5.93 0.00 0
1843 Northern Mechanical Division II New Service Connection for Nimti Jhora Domohani PWSS P/H NO-I BILL/02307/2023-2024 BP-2023-24-505 05/01/2024 0 WBSEDCL 5.68 0.00 0
1844 Northern Mechanical Division II New Service Connection for Brajerkuti PWSS P/HNo-I BILL/02311/2023-2024 BP-2023-24-493 21/12/2023 0 WBSEDCL 0.71 0.00 0
1845 Northern Mechanical Division II New Service Connection For Brajerkuthi PWSS P/H No-II BILL/02312/2023-2024 BP-2023-24-492 21/12/2023 0 WBSEDCL 0.71 0.00 0
1846 Northern Mechanical Division II New Service Connection charges for BHATIBARI Z-II PH NO-III under NMD-II in the District of ALIPURDUAR. BILL/02399/2025-2026 30/10/2025 0 WBSEDCL 7.54 0.00 0
1847 Northern Mechanical Division II New Service Connection for Kalchini TG PWSS, Zone-II, P/H-II BILL/02402/2023-2024 BP-2023-24-530 11/01/2024 0 WBSEDCL 7.15 0.00 0
1848 Northern Mechanical Division II New Service connection for Kalchini TG PWSS, Zone-II, P/H-IV BILL/02403/2023-2024 BP-2023-24-529 11/01/2024 0 WBSEDCL 5.43 0.00 0
1849 Northern Mechanical Division II New Service connection for Rangamati TG PWSS, Zone-I, P/H-I BILL/02404/2023-2024 BP-2023-24-526 11/01/2024 0 WBSEDCL 6.39 0.00 0
1850 Northern Mechanical Division II New Service Connection for Rangamati TG PWSS, Zone-I, P/H-II BILL/02405/2023-2024 BP-2023-24-525 11/01/2024 0 WBSEDCL 5.22 0.00 0
1851 Northern Mechanical Division II New Service Connection for Rangamati PWSS, Zone-II, P/H no.-I BILL/02406/2023-2024 BP-2023-24-524 11/01/2024 0 WBSEDCL 5.58 0.00 0
1852 Northern Mechanical Division II New Service Connection for Rangamati TG PWSS, Zone-II, P/H no.-II BILL/02407/2023-2024 BP-2023-24-527 11/01/2024 0 WBSEDCL 6.97 0.00 0
1853 Northern Mechanical Division II New Service connection for Uttar Mendabari PWSS, Zone-I, P/H no.-I BILL/02408/2023-2024 BP-2023-24-528 11/01/2024 0 WBSEDCL 6.69 0.00 0
1854 Northern Mechanical Division II New Service connection for Bhatpara TG PWSS, P/H-II BILL/02409/2023-2024 BP-2023-24-532 11/01/2024 0 WBSEDCL 5.26 0.00 0
1855 Northern Mechanical Division II New Service connection for Nimti Jhora Domohani PWSS, P/H no.-II BILL/02410/2023-2024 BP-2023-24-531 11/01/2024 0 WBSEDCL 6.47 0.00 0
1856 Northern Mechanical Division II Additional quotation For Brajerkuthi P/H No.I BILL/02444/2023-2024 BP-2023-24-560 19/01/2024 0 WBSEDCL 4.21 0.00 0
1857 Northern Mechanical Division II Additional service Connection Charge for Brajerkuthi Ph No.II BILL/02445/2023-2024 BP-2023-24-559 19/01/2024 0 WBSEDCL 6.00 0.00 0
1858 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR HANTUPARA P/H NO-IV PWSS BILL/02451/2023-2024 BP-2023-24-551 18/01/2024 0 WBSEDCL 5.27 0.00 0
1859 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR DALMORE& RAMJHORA T.G P/H NO-V PWSS BILL/02452/2023-2024 BP-2023-24-550 18/01/2024 0 WBSEDCL 5.99 0.00 0
1860 Northern Mechanical Division II NEW SERVICE CONNECTION FOR UTTAR MENDABARI PWSS ZONE-I P/H NO-I BILL/02470/2023-2024 BP-2023-24-549 18/01/2024 0 WBSEDCL 10.65 0.00 0
1861 Northern Mechanical Division II NEW SERVICE CONNECTION FOR Augumentation of Birpara PWSS ZONE-IIII P/H NO-III BILL/02471/2023-2024 BP-2023-24-572 01/02/2024 0 WBSEDCL 12.06 0.00 0
1862 Northern Mechanical Division II Additional Quotation for New Service connection charges for Kadambini T.G PWSS, Zone-I,P/H No-I BILL/02622/2023-2024 BP-2023-24-588 02/02/2024 0 WBSEDCL 11.92 0.00 0
1863 Northern Mechanical Division II New Service Connection Charge for Bhatpara TG PWSS P/HNO-I BILL/02636/2023-2024 BP-2023-24-601 15/02/2024 0 WBSEDCL 21.27 0.00 0
1864 Northern Mechanical Division II New Service Connection Charges for Gangutia TG PWSS P/HNO-II BILL/02637/2023-2024 BP-2023-24-600 15/02/2024 0 WBSEDCL 6.02 0.00 0
1865 Northern Mechanical Division II New service connection charges for UTTAR MADARIHAT PWSS PH NO-III BILL/02732/2023-2024 BP-2023-24-623 20/02/2024 0 WBSEDCL 7.47 0.00 0
1866 Northern Mechanical Division II ADDITIONAL QUOTATION FOR NEW SERVICE CONNECTION CHARGES FOR KADAMBINI T.G PWSS, ZONE-I,P/HNO-II BILL/02750/2023-2024 BP-2023-24-621 20/02/2024 0 WBSEDCL 5.15 0.00 0
1867 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR PRADHAN PARA PWSS P/H NO-II BILL/02752/2023-2024 BP-2023-24-622 20/02/2024 0 WBSEDCL 7.75 0.00 0
1868 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR PURBA MAJHERDABRI W/S/SCHEME PH NO.I BILL/02800/2023-2024 BP-2023-24-640 29/02/2024 0 WBSEDCL 3.89 0.00 0
1869 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE AT PURBA MAJHERDABRI W/S/SCHEME PH NO.II BILL/02801/2023-2024 BP-2023-24-641 29/02/2024 0 WBSEDCL 6.04 0.00 0
1870 Northern Mechanical Division II NEW SERVICE CONNECTION FOR MADHYA HALDIBARI PWSS ZONE-II P/H NO-I BILL/02802/2023-2024 BP-2023-24-643 29/02/2024 0 WBSEDCL 6.22 0.00 0
1871 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR MADHYA HALDIBARI PWSS ZONE-II P/H NO-II BILL/02803/2023-2024 BP-2023-24-642 29/02/2024 0 WBSEDCL 12.17 0.00 0
1872 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR KFC GROUND AUGUMENTATION OF BIRPARA PWSS ZONE-III P/H NO-II BILL/02804/2023-2024 BP-2023-24-644 29/02/2024 0 WBSEDCL 7.01 0.00 0
1873 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR PURBA KATHALBARI PWSS ZONE-II P/H NO-II BILL/02806/2023-2024 BP-2023-24-646 29/02/2024 0 WBSEDCL 9.80 0.00 0
1874 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES AT BENGKANDI PWSS P/H NO-I DIST- ALIPURDUAR. BILL/02828/2023-2024 BP-2023-24-660 04/03/2024 0 WBSEDCL 5.92 0.00 0
1875 Northern Mechanical Division II New service Connection Charges at Bengkandi PWSS P/H No- II in the Dist of Alipurduar. BILL/02829/2023-2024 BP-2023-24-659 04/03/2024 0 WBSEDCL 4.74 0.00 0
1876 Northern Mechanical Division II ADDITIONAL QUOTATION FOR RAYDAK T.G P/H NO-II BILL/02956/2023-2024 BP-2023-24-682 12/03/2024 0 WBSEDCL 4.70 0.00 0
1877 Northern Mechanical Division II ADDITIONAL QUOTATION FOR RAYDAK P/H NO-III BILL/02957/2023-2024 BP-162/24-25 21/06/2024 0 WBSEDCL 5.90 0.00 0
1878 Northern Mechanical Division II ADDITIONAL QUOTATION FOR TURTURI PH NO-II BILL/02959/2023-2024 BP-02/24-25 08/04/2024 0 WBSEDCL 7.36 0.00 0
1879 Northern Mechanical Division II ADDITIONAL QUOTATION FOR CHALNIRPAK PH NO-III BILL/02960/2023-2024 BP-06/24-25 08/04/2024 0 WBSEDCL 0.38 0.00 0
1880 Northern Mechanical Division II New Service Connection Charge For Gangutia T.G PWSS P/H NO-II BILL/02977/2025-2026 13/01/2026 0 WBSEDCL 6.02 0.00 0
1881 Northern Mechanical Division II NEW SERIVICE CONNECTION CHARGES FOR DALGAON TG PWSS TW NO-I BILL/03010/2023-2024 BP-2023-24-687 14/03/2024 0 WBSEDCL 21.42 0.00 0
1882 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR AUGUMENTATION OF BIRPARA Z-II P/HNO-IV BILL/03011/2023-2024 BP-2023-24-688 14/03/2024 0 WBSEDCL 6.55 0.00 0
1883 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR NARASINGPUR PWSS TW NO-II BILL/03012/2023-2024 BP-2023-24-689 14/03/2024 0 WBSEDCL 7.52 0.00 0
1884 Northern Mechanical Division II NEW SERVICE CONNECTION FOR DALMONI TG PWSS TW NO-I BILL/03013/2023-2024 BP-2023-24-690 14/03/2024 0 WBSEDCL 6.67 0.00 0
1885 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR DHANIRAMPURPH NO-I BILL/03014/2023-2024 BP-2023-24-691 14/03/2024 0 WBSEDCL 4.08 0.00 0
1886 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR DALGAON TG P/H NO-II BILL/03015/2023-2024 BP-2023-24-692 14/03/2024 0 WBSEDCL 4.69 0.00 0
1887 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE DHANIRAMPUR PH NO-II BILL/03016/2023-2024 BP-2023-24-693 14/03/2024 0 WBSEDCL 5.85 0.00 0
1888 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR NARSINGHPUR PH NO-I BILL/03017/2023-2024 BP-2023-24-694 14/03/2024 0 WBSEDCL 7.52 0.00 0
1889 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR BIRPARA CIRCUS GROUND ZONE-III, P/H NO-I BILL/03018/2023-2024 BP-2023-24-695 14/03/2024 0 WBSEDCL 9.12 0.00 0
1890 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGE FOR AUGUMENTATION OF BIRPARA ZONE-I P/HNO-I BILL/03019/2023-2024 BP-2023-24-696 14/03/2024 0 WBSEDCL 7.90 0.00 0
1891 Northern Mechanical Division II New Service Connection Charges for Gargenda TG PH-I Zone-II under NMD-II in the dist. of Alipurduar. BILL/03114/2024-2025 19/03/2025 0 WBSEDCL 16.58 0.00 0
1892 Northern Mechanical Division II New service connection charges for Kalchini TG zone-I,PH- IV under NMD-II BILL/03116/2024-2025 19/03/2025 0 WBSEDCL 16.70 0.00 0
1893 Northern Mechanical Division II New service connection charges for Aug Kalchini TG zone-I ,PH-III under NMD-II BILL/03117/2024-2025 19/03/2025 0 WBSEDCL 11.75 0.00 0
1894 Northern Mechanical Division II New Service Connection Charges for JATESWAR P/H NO-V in the dist. of APD under NMD-II BILL/03118/2024-2025 19/03/2025 0 WBSEDCL 7.21 0.00 0
1895 Northern Mechanical Division II NEW SERVICE CONNECTION CHARGES FOR PAR PATLAKHAWA PWSS P/H NO-I BILL/03128/2023-2024 BP-235/24-25 29/07/2024 0 WBSEDCL 6.17 0.00 0
1896 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Narthali Water Supply Scheme TW No. - V under NMD-II, PHE Dte., Alipurduar. ORD/000001/2022-2023 473/NMD-II 07/04/2022 30 M/S PARITOSH BHOWMICK & CO. 7.85 7.85 100
1897 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Banchukamari Water Supply Scheme TW No.-III under NMD-II,PHE.Dte Alipurduar. ORD/000002/2022-2023 527/NMD-II 19/04/2022 30 B.B CONCERNED 7.75 7.62 100
1898 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Augmentation of SAMUKTALA water supply scheme, TW no I AND II OF ZONE-I , TW no I AND II OF ZONE-II , TW no I AND II OF ZONE-III under Jal Jeevan Mission under NMD-II, PHE Dte.APD. ORD/000002/2023-2024 759/NMD-II 04/04/2023 30 AHALYA ENGINEERING WORKS 63.40 57.95 40
1899 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Uttar Majherdabri Water Supply Scheme TW No.- IV under NMD-II PHE Dte Alipurduar. ORD/000003/2022-2023 475/NMD-II 07/04/2022 817 DEB CONSTRUCTION 7.85 5.80 100
1900 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Kumargram TG water supply scheme, TW no II under Northern Mechanical Division-II, PHE Dte.Alipurduar ORD/000003/2023-2024 770/NMD-II 06/04/2023 30 BEE GEE CONSTRUCTION 10.74 10.62 90
1901 Northern Mechanical Division II Supply & delivery of Stand by pumping machinery for Choto Salkumar water supply scheme, P/H No. II under JJM project in the dist. of Alipurduar under NMD-II, PHE Dte. ORD/000003/2024-2025 179/AMSD 02/04/2024 15 M/S RATAN KUMAR DASGUPTA & CO. 0.77 0.00 100
1902 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Uttar Majherdabri Water Supply Scheme TW No.-III under NMD-II,PHE. Dte Alipurduar. ORD/000004/2022-2023 532/NMD-II 20/04/2022 30 M/S P.P ELECTRICALS 7.82 5.85 69
1903 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Putimari Water Supply Scheme TW No.-III under NMD-II,PHE Dte Alipurduar. ORD/000005/2022-2023 533/NMD-II 20/04/2022 30 TAPAN BISWAS 7.83 7.72 100
1904 Northern Mechanical Division II Hiring of Motor Cab (Non-air conditioned) for site visit of JJM Works under the Office of the EE/NMD-II, PHE Dte. ORD/000005/2024-2025 220/AMSD 26/04/2024 61 MUSTAFI CONCERN 0.75 0.00 0
1905 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Hasimara Water Supply Scheme TW No.-III under NMD-II,PHE Dte Alipurduar. ORD/000006/2022-2023 534/NMD-II 20/04/2022 30 M/S RATAN KUMAR DASGUPTA & CO. 8.46 7.95 100
1906 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Madhya Parokata water supply scheme TW No. III under NMD-II, PHE Dte. Alipurduar. ORD/000007/2022-2023 555/NMD-II 26/04/2022 30 M/S UTPAL CHAKRABORTY & CO. 7.85 7.73 100
1907 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Loknathpur water supply scheme TW No. V under NMD-II, PHE Dte. Alipurduar. ORD/000008/2022-2023 556/NMD-II 26/04/2022 30 S.S ENTERPRISES 7.85 7.75 100
1908 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Uttar Kamakhyaguri water supply scheme TW No. V under NMD-II, PHE Dte. Alipurduar. ORD/000009/2022-2023 557/NMD-II 26/04/2022 30 BLUE PINE 7.85 0.00 0
1909 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Sankosh water supply scheme, TW no I(H/W Site) under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/000010/2023-2024 860/NMD-II 26/04/2023 30 SAIKAT SINHA 10.76 10.66 100
1910 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Sankosh water supply scheme, TW no II under Northern Mechanical Division-II, PHEDte.Alipurduar. ORD/000011/2023-2024 864/NMD-II 26/04/2023 30 KARMAKAR CONSTRUCTION 10.74 10.62 90
1911 Northern Mechanical Division II Supply, installation, commissioning and Trial operation of Electro Mechanical components of LOKNATHPUR Water Supply Scheme TW No.-IV (NEAR DANGI AREA)under NMD-II,PHE.Dte,Alipurduar. ORD/000012/2020-2021 1034/NMD-II 03/09/2020 90 SUBODH KUMAR BANIK 6.41 0.00 0
1912 Northern Mechanical Division II Supply,deliver and installation of open well pumping machineries and allied works at CWR of Lankapara W/S SCHEME under NMD-II, in the dist. of Alipurduar ORD/000012/2023-2024 30/AMSD 28/04/2023 20 SARKAR ELECTRIC 6.60 6.60 0
1913 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Hasimara Water Supply Scheme TW No.-IV under NMD-II PHE Dte Alipurduar. ORD/000013/2022-2023 595/NMD-II 05/05/2022 30 M/S B ENTERPRISE 8.49 8.49 100
1914 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Hantapara T.G water supply scheme TW No. III under NMD-II, PHE Dte. Alipurduar. ORD/000014/2022-2023 598/NMD-II 05/05/2022 30 MIHIR SARKAR 10.66 10.66 100
1915 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Augumentation of Jateswar water supply scheme, TW no. IV and V under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/000014/2023-2024 889/NMD-II 02/05/2023 30 HARA PROSAD DAS 21.70 19.38 60
1916 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Kumargram TG water supply scheme, TW no I(H/W Site) under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/000017/2023-2024 902/NMD-II 04/05/2023 30 MAA ENTERPRISES 10.74 0.00 0
1917 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Augumentation of Jogijhora Barabak water supply scheme, TW no. III under Northern Mechanical Division-II,PHE Dte. ORD/000018/2023-2024 907/NMD-II 04/05/2023 30 A.K SIKDAR 10.36 10.24 100
1918 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Bandapani TG water supply scheme, TW no I and II of Zone-I and TW no I and II of Zone-II under NMD-II, PHE Dte.APD ORD/000020/2023-2024 936/NMD-II 10/05/2023 30 ALPHA ENTERPRISE 37.32 9.52 35
1919 Northern Mechanical Division II Supplying and delivery and fitting fixing of different outdoor decorative lighting fixture infront of new building at Jayanti bungalow in the district of Alipurduar under NMD-II, PHE Dte. ORD/000023/2022-2023 622/NMD-II 13/05/2022 30 MUSTAFI CONCERN 3.74 3.74 54
1920 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Paschim Satali water supply scheme, TW no I, II and III under Jal Jeevan Mission under NMD-II, PHE Dte.APD ORD/000026/2023-2024 944/NMD-II 11/05/2023 722 M/S BHOWMIK & CO. 27.59 22.13 55
1921 Northern Mechanical Division II Complete elctrification of renovated existing Building Cum Rest Shed AT Jayanti W/S Scheme ,in the dist. Alipurduar. Under NMD-II, P.H E Dte. ORD/000029/2022-2023 627/NMD-II 13/05/2022 30 ALPHA ENTERPRISE 3.52 3.39 64
1922 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with cu wound line voltage corrector for Augmentation of PATLAKHAWA Water Supply Scheme,TW no .I under NMD-II, PHE Dte. Apd. ORD/000034/2023-2024 968/NMD-II 13/05/2023 30 SUMON ELECTRICAL 11.02 10.89 100
1923 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Nurpur Water Supply Scheme TW No.- I ,II and III under NMD-II,PHE.Dte,APD. ORD/000035/2023-2024 983/NMD-II 15/05/2023 30 RMD TRADING 28.75 21.63 100
1924 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Rejuvination of Dhaolajhora TG Water Supply Scheme TW No.-I under NMD-II,PHE.Dte,Apd. ORD/000036/2023-2024 986/NMD-II 15/05/2023 30 MASSK ENGINEERING WORKS 10.82 10.73 100
1925 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for Rejuvenation of Birpara (APD) water supply scheme, TW no III under JJM under NMD-II, PHE Dte. APD ORD/000038/2023-2024 991/NMD-II 15/05/2023 30 P K ENGINEERING 10.95 10.30 80
1926 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Raydak TG water supply scheme, TW no I,II and III of under Northern Mechanical Division-II, PHE Dte.APD ORD/000039/2023-2024 998/NMD-II 16/05/2023 30 DEY ENTERPRISE (BALLY) 28.63 26.19 95
1927 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Torsha Forest Water Supply Scheme TW No.-I under NMD-II,PHE.Dte,Apd. ORD/000045/2023-2024 1060/NMD-II 26/05/2023 30 DIPA CHHETRI 9.38 9.25 100
1928 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Purba Kanthalbari water supply scheme, TW no I and II of Zone-III under Northern Mechanical Division-II, PHE Dte,Apd. ORD/000048/2023-2024 1085/NMD-II 01/06/2023 30 M/S P.P ELECTRICALS 22.85 22.54 100
1929 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Purba Kanthalbari water supply scheme, TW no I and II of Zone-IV under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/000050/2023-2024 1107/NMD-II 05/06/2023 30 SUMON ELECTRICAL 22.86 20.21 70
1930 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for DAKSHIN MAJIDKHANA water supply scheme, TW no I & II under Northern Mechanical Division-II, PHE Dte. Alipurduar ORD/000055/2023-2024 1165/NMD-II 15/06/2023 30 SUBODH KUMAR BANIK 21.66 20.60 100
1931 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector forGround Water Based Piped Water Supply Scheme AUGMENTATION OF BHATIBARI PIPED WATER SUPPLY SCHEME,Zone-II,P/H No-III and IV under Jal Jeevan Mission NMD-II,PHE.Dte,Alipurduar. ORD/000058/2025-2026 1150/NMD-II 16/05/2025 30 M/S SAJAHAN CHOWDHURY 22.58 0.00 0
1932 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector forGround Water Based Piped Water Supply Scheme AUGMENTATION OF SALSALABARI WATER SUPPLY SCHEME.,P/H-I (Aug) under Jal Jeevan Mission NMD-II,PHE.Dte,Alipurduar. ORD/000059/2025-2026 1149/NMD-II 16/05/2025 30 SUBODH KUMAR BANIK 11.29 0.00 0
1933 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Augumentation of Bhutnirghat water supply scheme, TW no. III under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/000060/2023-2024 1194/NMD-II 23/06/2023 30 ANUP BASU 10.59 10.48 100
1934 Northern Mechanical Division II Implementation of Affordable IoT-Enabled Water Service Delivery Measurement and Monitoring Sensing System for Rural Deployment in the Proposed Villages Under Different Water Supply Schemes at Diferrent Block of Alipurduar District in West Bengal ORD/000062/2025-2026 1155/NMD-II 19/05/2025 180 WEBEL TECHNOLOGY LIMITED 726.15 0.00 0
1935 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Shrinathpur TG water supply scheme, TW no I and II of under NMD-II, PHE Dte.APD ORD/000070/2023-2024 1217/NMD-II 27/06/2023 30 JAL PRAVAHIKA PVT. LTD. 21.60 21.33 100
1936 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for New Land TG water supply scheme, TW no I in the district of Alipurduar under Northern Mechanical Division-II, PHE Dte. ORD/000072/2023-2024 1254/NMD-II 04/07/2023 30 MALAY KUMAR SAHA 10.44 10.32 90
1937 Northern Mechanical Division II Additional works in connection with yard lighting arrangement at Dalmore water supply scheme (Aug), P/H No. III under Northern Mechanical Division II, PHE Dte. ORD/000080/2023-2024 147/AMSD 06/07/2023 20 M/S P.P ELECTRICALS 1.93 0.00 100
1938 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for BALLALGURI water supply scheme, TW no I and II under Jal Jeevan Mission under NMD-II, PHE Dte. Alipurduar. ORD/000081/2023-2024 1266/NMD-II 05/07/2023 609 MADHAB SAHA 18.40 15.44 50
1939 Northern Mechanical Division II Solarization of grid connected pumping installation at Different PWSS at Alipurduar -I & II Block in the dist.of Alipurduar under JJM programme under Northern Mechanical Division-II, PHE Dte ORD/000117/2025-2026 1293/NMD-II 12/06/2025 90 M/S SAJAHAN CHOWDHURY 26.61 0.00 0
1940 Northern Mechanical Division II Solarization of grid connected pumping installation at Different PWSS at Kalchini Block in the dist.of Alipurduar under JJM programme under Northern Mechanical Division-II, PHE Dte. ORD/000130/2025-2026 1331/NMD-II 18/06/2025 90 M R S ELECTRICAL 27.30 0.00 0
1941 Northern Mechanical Division II Solarization of grid connected pumping installation at Different PWSS at Kalchini, Madarihat -Birpara ,kumargram Block in the dist.of Alipurduar under JJM programme under Northern Mechanical Division-II, PHE Dte. ORD/000131/2025-2026 1332/NMD-II 18/06/2025 90 M R S ELECTRICAL 27.30 0.00 0
1942 Northern Mechanical Division II Solarization of grid connected pumping installation at Different PWSS at APD-I ,APD-II , Falakata Block in the dist.of Alipurduar under JJM programme under Northern Mechanical Division-II, PHE Dte. ORD/000132/2025-2026 1333/NMD-II 18/06/2025 90 M R S ELECTRICAL 27.30 0.00 0
1943 Northern Mechanical Division II Solarization of grid connected pumping installation at Different PWSS at Kalchini Block in the dist.of Alipurduar under JJM programme under Northern Mechanical Division-II, PHE Dte. ORD/000133/2025-2026 1334/NMD-II 18/06/2025 90 M. M. ENTERPRISE 16.38 0.00 0
1944 Northern Mechanical Division II Solarization of grid connected pumping installation at Different PWSS at Falakata Block in the dist.of Alipurduar under JJM programme under Northern Mechanical Division-II, PHE Dte ORD/000134/2025-2026 1344/NMD-II 19/06/2025 90 M/S SAJAHAN CHOWDHURY 42.58 0.00 0
1945 Northern Mechanical Division II Yard lighting arrangement at Head Work Site for Different PWSS (KADAMBINI TG and Others) under JJM in the BLOCK: Falakata, DISTRICT: ALIPURDUAR under NMD-II,PHE Dte. ORD/000137/2025-2026 1346/NMD-II 19/06/2025 30 M/S SAJAHAN CHOWDHURY 23.98 0.00 0
1946 Northern Mechanical Division II Yard lighting arrangement at Head Work Site for Different PWSS (PASCHIM CHENGMARI and others) under JJM in the BLOCK: Kumargram, DISTRICT: ALIPURDUAR under NMD-II,PHE Dte. ORD/000138/2025-2026 1347/NMD-II 19/06/2025 30 S.K ENTERPRISE 26.74 0.00 0
1947 Northern Mechanical Division II Yard lighting arrangement at Head Work Site for Different PWSS (PASCHIM DEOGAON and others) under JJM in the BLOCK: Falakata, DISTRICT: ALIPURDUAR under NMD-II,PHE Dte. ORD/000169/2025-2026 1385/NMD-II 26/06/2025 30 M/S SAJAHAN CHOWDHURY 20.56 0.00 0
1948 Northern Mechanical Division II Yard lighting arrangement at Head Work Site for Different PWSS (NIMTI DOMOHANI and Others) under JJM in the BLOCK: Kalchini, DISTRICT: ALIPURDUAR under NMD-II,PHE Dte. ORD/000170/2025-2026 1386/NMD-II 26/06/2025 30 AMUSAR IMPEX PVT LTD 22.95 0.00 0
1949 Northern Mechanical Division II Supply, delivery & installation of Electro Mechanical Compopnents at PASCHIM KHAIRBARI W/S Scheme, T.W No. I (Replacement), under NMD-II, PHE, Dte. in the dist of Alipurduar. ORD/000311/2022-2023 638/NMD-II 20/05/2022 30 ALPHA ENTERPRISE 2.87 2.87 0
1950 Northern Mechanical Division II Supply and Delivery of Al. armoured cable for Breakdown purpose at REJUVENATION OF MADHU TG WATER SUPPLY SCHEME in the dist. Alipurduar under,AMSD,PHE Dte. ORD/000337/2022-2023 226/AMSD 21/07/2022 15 MUSTAFI CONCERN 2.39 2.39 52
1951 Northern Mechanical Division II Supply, delivery & installation of Electro Mechanical Compopnents at HASIMARA W/S Scheme, P/H No. I(Handedover), under NMD-II, PHE, Dte. in the dist of Alipurduar. ORD/000360/2022-2023 243/AMSD 29/07/2022 15 S.K ELECTRICALS 1.06 0.00 0
1952 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Garochira Bandapani Water Supply Scheme TW No.-I under NMD-II,PHE.Dte,Apd. ORD/000400/2023-2024 1674/NMD-II 17/07/2023 30 PRAGATI CONSTRUCTION COMPANY 9.38 9.26 100
1953 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Mujnai Water Supply Scheme (Chha Sundari) TW No.-VI under NMD-II,PHE.Dte,Alipurduar. ORD/000504/2024-2025 2634/NMD-II 05/12/2024 211 MITRA ENTERPRISE 10.74 0.00 100
1954 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for GOPALPUR TG Water Supply Scheme TW No.-III under NMD-II,PHE.Dte, Alipurduar. ORD/000505/2024-2025 2638/NMD-II 06/12/2024 178 M/S P.P ELECTRICALS 10.74 0.00 100
1955 Northern Mechanical Division II Continuation order for Hiring of Motor Cab (Non-air conditioned) for site visit of JJM Works under the Office of the EE/NMD-II, PHE Dte. ORD/000518/2024-2025 340/AMSD 27/06/2024 61 MUSTAFI CONCERN 0.75 0.00 0
1956 Northern Mechanical Division II Continuation order for Hiring of Motor Cab (Non-air conditioned) for site visit of JJM Works under the Office of the EE/NMD-II, PHE Dte. ORD/000539/2024-2025 476/AMSD 29/08/2024 61 MUSTAFI CONCERN 0.75 0.00 0
1957 Northern Mechanical Division II Continuation order for Hiring of Motor Cab (Non-air conditioned) for site visit of JJM Works under the Office of the EE/NMD-II, PHE Dte. ORD/000565/2024-2025 578/AMSD 25/10/2024 61 MUSTAFI CONCERN 0.75 0.00 0
1958 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Dheklapara TG Water Supply Scheme TW No.-I (Chha sundari) under Jal Jeevan Mission NMD-II,PHE.Dte, Alipurduar. ORD/000589/2024-2025 59/NMD-II 07/01/2025 212 M/S CHANDRANATH MUKHERJEE 14.22 0.00 100
1959 Northern Mechanical Division II Yard lighting arrangement at Lankapara Water supply scheme ( Head Work site ) Under Northern Mechanical Division-II P.H.E Dte. ORD/000644/2021-2022 1103/NMD-II 20/09/2021 30 SAIKAT SINHA 3.16 3.16 12
1960 Northern Mechanical Division II Schedule for: Supply, delivery and installation of 30 KVA servo motor operated Copper wound line voltage corrector at Purba Kathalbari Water Supply Scheme TW No.-II under NMD-II,PHE.Dte,Alipurduar. ORD/000651/2021-2022 1097/NMD-II 20/09/2021 30 NIRMAN 3.94 3.94 0
1961 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Kartika TG water supply scheme, TW no I and II of under Northern Mechanical Division-II, PHE Dte.APD ORD/000676/2023-2024 2085/NMD-II 26/07/2023 30 DIAMOND ELECTRICAL WORKS 18.63 17.89 90
1962 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Ethelbari water supply scheme, TW no I and II of Zone-I under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/000677/2023-2024 2082/NMD-II 26/07/2023 30 DIAMOND ELECTRICAL WORKS 20.86 19.67 100
1963 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Phaskhawa TG water supply scheme, TW no I and II under Northern Mechanical Division-II, PHE Dte.APD ORD/000678/2023-2024 2076/NMD-II 26/07/2023 657 M/S PARITOSH BHOWMICK & CO. 18.54 8.45 100
1964 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for PARARPAR water supply scheme, TW no I and II under Jal Jeevan Mission under NMD-II, PHE Dte. Alipurduar. ORD/000682/2023-2024 2121/NMD-II 27/07/2023 30 WILFUL UNEMPLOYED ENGINEERS CO OPERATIVE SOCIETY LIMITED 18.45 17.64 75
1965 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Rejuvenation of Tapsikhata water supply scheme, TW no III under Northern Mechanical Division-II, PHE Dte.Alipurduar ORD/000683/2023-2024 2036/NMD-II 26/07/2023 30 RUBY ENTERPRISE 10.88 10.74 100
1966 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for UTTAR RANGALIBAZNA water supply scheme, TW no I and II under Jal Jeevan Mission under NMD-II, PHE Dte. Alipurduar. ORD/000685/2023-2024 2139/NMD-II 27/07/2023 615 DILIP MAHATO 18.33 4.47 100
1967 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Rejuvenation of Munshipara water supply scheme, TW no III under Northern Mechanical Division-II, PHE Dte.Alipurduar ORD/000687/2023-2024 2173/NMD-II 27/07/2023 403 M/S KUNDU CONSTRUCTION 10.81 8.19 100
1968 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Kalaberia water supply scheme, TW no I and II of under Northern Mechanical Division-II, PHE Dte.APD ORD/000689/2023-2024 2163/NMD-II 27/07/2023 463 M/S PARITOSH BHOWMICK & CO. 18.12 16.70 100
1969 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for UTTAR MAJIDKHANA water supply scheme, TW no I and II under Jal Jeevan Mission under NMD-II, PHE Dte.APD ORD/000690/2023-2024 2167/NMD-II 27/07/2023 615 MALAY KUMAR SAHA 21.13 14.79 90
1970 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Pradhan Para water supply scheme, TW no I and II of under Northern Mechanical Division-II, PHE Dte.APD ORD/000691/2023-2024 2170/NMD-II 27/07/2023 494 SAIKAT SINHA 18.20 17.36 100
1971 Northern Mechanical Division II Hiring of Motor cab for site of the Executive Engineer, Northern Mechanical Division-II, PHE Dte. ORD/000693/2023-2024 201/AMSD 28/07/2023 366 DILIP MAHATO 4.16 0.00 0
1972 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Dakhshin Barajhar Forest Water Supply Scheme TW No.-I under NMD-II,PHE.Dte,Apd. ORD/000694/2023-2024 2193/NMD-II 28/07/2023 30 MAA TARA ENTERPRISE 9.85 9.71 100
1973 Northern Mechanical Division II "Hiring of Motor Cab for site visit of the Assistant Engineer , Alipurduar Mechanical Sub- Division, P.H.E. Dte. under Northern Mechanical Division -II, P.H.E. Dte." ORD/000695/2023-2024 202/AMSD 28/07/2023 366 DILIP MAHATO 4.16 0.00 0
1974 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for MARAKHATA water supply scheme, TW no I and II under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/000696/2023-2024 2160/NMD-II 27/07/2023 30 S.S ENTERPRISES 19.12 18.84 100
1975 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Augmentation of JOGENDRAPUR water supply scheme, TW no III under Jal Jeevan Mission under NMD-II, PHE Dte.APD ORD/000703/2023-2024 2144/NMD-II 27/07/2023 702 BEE GEE CONSTRUCTION 10.57 0.00 100
1976 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Bhatkhawa TG water supply scheme, TW no I and II under Jal Jeevan Mission under NMD-II, PHE Dte.APD ORD/000704/2023-2024 2147/NMD-II 27/07/2023 30 MUSTAFI CONCERN 18.76 0.00 45
1977 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Bholardabri Water Supply Scheme TW No.- III (Aug) under NMD-II,PHE. Dte Alipurduar. ORD/000709/2022-2023 2061/NMD-II 20/12/2022 30 SUMON ELECTRICAL 10.50 10.38 100
1978 Northern Mechanical Division II supply, delivery,of standby Automatically controlled diaphragm type chlorinator for accurate dosing of chlorine solution at Chandijhar Water Supply Scheme ,in the dist. of Alipurduar under NMD-II ,PHE Dte. Alipurduar. ORD/000714/2022-2023 2100/NMD-II 29/12/2022 15 M/S ANJALI ENTERPRISE 1.80 1.80 0
1979 Northern Mechanical Division II Supply, Delivery and laying of Al. Ar cable for yard Lighting arrangement at jayanti Bungalow in the dist. Of Alipurduar under NMD-II ,P.H.E Dte. ORD/000716/2021-2022 1385/NMD-II 22/12/2021 30 MUSTAFI CONCERN 4.70 4.16 0
1980 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for MUJNAI TG Under CHAA SUNDARI water supply scheme, TW no V under Jal Jeevan Mission under NMD-II, PHE Dte. APD ORD/000717/2022-2023 2106/NMD-II 29/12/2022 30 MUSTAFI CONCERN 9.39 9.39 28
1981 Northern Mechanical Division II Upgradation of Internal illumination system and allied works at Newly Constructed Rest Shed in Jayanti under Jayanti W/S Scheme under Northern Mechanical Division-II, PHE Dte. ORD/000720/2022-2023 45/NMD-II 04/01/2023 30 ALPHA ENTERPRISE 4.03 2.72 100
1982 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Rejuvenation of Jashodanga Water Supply Scheme TW No.- IV under NMD-II,PHE.Dte,Alipurduar. ORD/000721/2022-2023 46/NMD-II 04/01/2023 30 M/S KUNDU CONSTRUCTION 4.31 4.22 100
1983 Northern Mechanical Division II Supply, delivery & installation of 20 KVA, Servo Motor operated Copper wound line voltage stabilizer of Salsalabari Water Supply Scheme TW No.-III under NMD-II,PHE. Dte, Alipurduar. ORD/000724/2021-2022 1377/NMD-II 22/12/2021 30 PRAGATI CONSTRUCTION COMPANY 2.39 2.39 0
1984 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Augmentation of Salkumarhat Water Supply Scheme TW No.-I and II under NMD-II,PHE.Dte,Apd. ORD/000728/2023-2024 2299/NMD-II 31/07/2023 30 MADHAB SAHA 20.89 19.51 100
1985 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component for Torsa TG Sawa Line, Chhetri Line, Gopa Line, Jiten Line 220 unit cha Sundari Water Supply Scheme , Zone-II ,P.H No.- I and II under NMD-II ,PHE.Dte,Alipurduar. ORD/000732/2022-2023 70/NMD-II 09/01/2023 30 SARKAR ELECTRIC 26.05 26.05 100
1986 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component for Torsa TG [Hatkhola Line,Naya Line, 3 no. Line (A) Khoyar Line ] 256 unit cha Sundari Water Supply Scheme , Zone-I ,P.H No.-IandIIunder NMD-II ,PHE.Dte,Alipurduar. ORD/000733/2022-2023 71/NMD-II 09/01/2023 30 B.B CONCERNED 26.05 26.05 87
1987 Northern Mechanical Division II Supply, delivery of Standby PDB Cum MCC Panel and Submersible pumping machinery under Rejuvination of Tapshikhata water supply scheme under NMD-II,PHE Dte. ORD/000735/2022-2023 93/NMD-II 10/01/2023 15 ALPHA ENTERPRISE 4.86 4.70 55
1988 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for CHUNIAJHORA TG AREA PWSS, TW no II in the district of ALIPURDUAR under Northern Mechanical Division-II, PHE Dte ORD/000736/2022-2023 94/NMD-II 10/01/2023 30 BONANZA ENTERPRISE 9.84 9.78 65
1989 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for CHUNIAJHORA TG AREA PWSS, TW no I (H/W Site)in the district of ALIPURDUAR under Northern Mechanical Division-II, PHE Dte. ORD/000737/2022-2023 95/NMD-II 10/01/2023 30 DIAMOND ELECTRICAL WORKS 9.83 9.79 65
1990 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Chalnipak water supply scheme, TW no I,II and III under Jal Jeevan Mission under NMD-II, PHE Dte.APD ORD/000741/2023-2024 2287/NMD-II 31/07/2023 30 QUAZI NOZRUL ISLAM 27.85 6.83 100
1991 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Purba Chenpani Water Supply Scheme TW No.-III under NMD-II,PHE Dte Alipurduar. ORD/000753/2021-2022 63/NMD-II 21/01/2022 30 M/S KUNDU CONSTRUCTION 7.75 7.73 0
1992 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Beech TG water supply scheme, TW no I and II under Jal Jeevan Mission under NMD-II, PHE Dte.APD ORD/000754/2023-2024 2336/NMD-II 01/08/2023 394 KARMAKAR CONSTRUCTION 21.39 20.10 100
1993 Northern Mechanical Division II Supply, installation, commissioning and Trial operation of Electro Mechanical components of TOTOPARA Water Supply Scheme TW No.-IV under NMD-II,PHE Dte Alipurduar. ORD/000756/2021-2022 69/NMD-II 24/01/2022 30 SUNLIT 7.57 7.57 0
1994 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Kohinur TG water supply scheme, TW no I,II and III of under Northern Mechanical Division-II, PHE Dte.APD ORD/000757/2023-2024 2340/NMD-II 01/08/2023 30 ALPHA ENTERPRISE 32.93 32.57 70
1995 Northern Mechanical Division II Supply ,delivery and Installation of pumping machinery of at newly constructed tubewell at Jayanti ,in the dist. Alipurduar , AMSD ,PHE Dte. ORD/000758/2021-2022 259/AMSD 23/07/2021 15 MUSTAFI CONCERN 0.96 0.96 0
1996 Northern Mechanical Division II Supplying and delivery and fitting fixing of different outdoor decorative lighting fixture in front of new building at Jayanti bunglow in the dist. Of Alipurduar under NMD-II ,P.H.E Dte ORD/000761/2021-2022 1376/NMD-II 22/12/2021 30 MUSTAFI CONCERN 4.38 4.38 0
1997 Northern Mechanical Division II Supply, delivery and installation of 15 KVA servo motor operated Copper wound line voltage corrector at TOTOPARA Water Supply Scheme TW No.-III under NMD-II, PHE.Dte, Alipurduar. ORD/000762/2021-2022 1096/NMD-II 20/09/2021 30 SUNLIT 2.38 2.38 0
1998 Northern Mechanical Division II Supply, delivery & installation of 20 KVA, Servo Motor operated Copper wound line voltage stabilizer of Purba Chenpani Water Supply Scheme TW No.-III under NMD-II PHE Dte Alipurduar. ORD/000769/2021-2022 1379/NMD-II 22/12/2021 30 TAPAN BISWAS 2.39 2.37 0
1999 Northern Mechanical Division II Supply, delivery & installation of 30 KVA, Servo Motor operated Copper wound line voltage stabilizer of Lankapara Water Supply scheme T/W No.VI NMD-II,PHE.Dte,Alipurduar. ORD/000777/2021-2022 166/NMD-II 22/02/2022 30 M/S A.D ENTERPRISE 3.17 2.42 11
2000 Northern Mechanical Division II Supply, delivery & installation of 20 KVA, Servo Motor operated Copper wound line voltage stabilizer of Jashodanga Water Supply Scheme TW No.-III (Near Jashodanga Rural Hospital Premises) under NMD-II,PHE.Dte,Alipurduar. ORD/000778/2021-2022 167/NMD-II 22/02/2022 30 BEE GEE CONSTRUCTION 2.39 2.39 43
2001 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for DHUMCHIPARA TG Water Supply Scheme TW No.-IV under NMD-II,PHE Dte. Alipurduar. ORD/000783/2022-2023 247/NMD-II 13/02/2023 30 ALPHA ENTERPRISE 13.78 13.78 100
2002 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Turturi water supply scheme, TW no I and II under Jal Jeevan Mission under NMD-II, PHE Dte.APD ORD/000785/2023-2024 2339/NMD-II 01/08/2023 489 M/S J.K ENGINEERING CO. 18.77 17.46 80
2003 Northern Mechanical Division II Supply, delivery & installation of 10 KVA, Servo Motor operated Copper wound line voltage stabilizer of Mujnai T.G Water Supply Scheme TW No.-IV under NMD-II,PHE.Dte,Alipurduar. ORD/000786/2021-2022 169/NMD-II 22/02/2022 30 WILFUL UNEMPLOYED ENGINEERS CO OPERATIVE SOCIETY LIMITED 1.81 1.81 28
2004 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for SISHU JUMRHA water supply scheme, TW no I , II and III under Jal Jeevan Mission under NMD-II, PHE Dte.APD ORD/000787/2023-2024 2357/NMD-II 07/08/2023 30 GEETA CONSTRUCTION 27.96 26.38 100
2005 Northern Mechanical Division II Supply, delivery of standby Automatically controlled diaphragm type chlorinator for accurate dosing of chlorine solution at Putimari Water Supply Scheme ,in the dist. of COOCHBEHAR under NMD-II, PHE. Dte. Alipurduar. ORD/000792/2022-2023 270/NMD-II 16/02/2023 15 DILIP MAHATO 1.80 0.00 100
2006 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for PURBA KHALISHAMARI water supply scheme, TW no I and II under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/000793/2023-2024 2365/NMD-II 08/08/2023 30 MENAKA ENTERPRISE 21.73 21.50 100
2007 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector of Madarihat TG PWSS, TW no .I in the district of Alipurduar under Northern Mechanical Division-II, PHE Dte ORD/000794/2022-2023 291/NMD-II 17/02/2023 30 SUNLIT 10.73 10.73 80
2008 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Purba Kanthalbari water supply scheme, TW no I and II of Zone-II under Northern Mechanical Division-II, PHE Dte.Alipurduar ORD/000794/2023-2024 2366/NMD-II 08/08/2023 604 SUMON ELECTRICAL 22.50 0.00 80
2009 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector of Madarihat TG PWSS, TW no .III in the district of Alipurduar under Northern Mechanical Division-II, PHE Dte ORD/000795/2022-2023 299/NMD-II 18/02/2023 30 MUSTAFI CONCERN 10.72 10.72 90
2010 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Purba Kanthalbari water supply scheme, TW no I and II of Zone-I under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/000801/2022-2023 368/NMD-II 22/02/2023 649 ALPHA ENTERPRISE 22.84 19.58 100
2011 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Brajerkuthi water supply scheme, TW no I and II of under Northern Mechanical Division-II, PHE Dte.APD ORD/000801/2023-2024 2377/NMD-II 09/08/2023 30 SARKAR ELECTRIC 18.59 18.37 100
2012 Northern Mechanical Division II upply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for REJUVENATION of MADHU TG PWSS, TW no .III in the district of ALIPURDUAR under Northern Mechanical Division-II, PHE Dte. ORD/000804/2022-2023 388/NMD-II 23/02/2023 30 HARAGOURI ENTERPRISE 11.59 11.46 100
2013 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for MATHURA TG water supply scheme, TW no I and II under Northern Mechanical Division-II, PHE Dte. Alipurduar. ORD/000805/2022-2023 393/NMD-II 23/02/2023 30 B.B CONCERNED 22.77 22.69 100
2014 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Mujnai T.G Water Supply scheme T/W No.IV under NMD-II,PHE Dte Alipurduar. ORD/000808/2021-2022 191/NMD-II 24/02/2022 30 SUMON ELECTRICAL 6.86 6.86 28
2015 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Rejuvenation of Makrapara TG Water Supply Scheme TW No.-I under NMD-II,PHE.Dte,Apd. ORD/000808/2022-2023 415/NMD-II 24/02/2023 30 BONANZA ENTERPRISE 15.21 15.10 100
2016 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Mechpara TG water supply scheme, TW no I and II of under NMD-II, PHE Dte.APD ORD/000808/2023-2024 2385/NMD-II 09/08/2023 632 B.B CONCERNED 21.97 18.44 50
2017 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Mujnai T.G Water Supply scheme T/W No. III under NMD-II,PHE Dte Alipurduar. ORD/000810/2021-2022 193/NMD-II 24/02/2022 30 RIPON DAS 6.83 6.83 100
2018 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Jashodanga Water Supply Scheme TW No.-III (Near Jashodanga Rural Hospital Premises) under NMD-II,PHE Dte Alipurduar. ORD/000813/2021-2022 197/NMD-II 24/02/2022 30 NABAUDYAG ELECTRICAL ENGINEERING CO- OPERATIVE SOCIETY LTD. 7.74 7.71 44
2019 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Naothoatari water supply scheme, TW no I and II of under Northern Mechanical Division-II, PHE Dte.APD ORD/000815/2023-2024 2389/NMD-II 09/08/2023 601 MUSTAFI CONCERN 18.11 0.00 90
2020 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Jayanti Area TG II water supply scheme, TW no I and II of under Northern Mechanical Division-II, PHE Dte.APD ORD/000818/2023-2024 2390/NMD-II 09/08/2023 762 SUNLIT 18.09 0.00 80
2021 Northern Mechanical Division II Supply, delivery & installation of 10 KVA, Servo Motor operated Copper wound line voltage stabilizer of Mujnai T.G Water Supply Scheme TW No.-III under NMD-II,PHE.Dte,Alipurduar. ORD/000822/2021-2022 186/NMD-II 23/02/2022 30 ASHWIRBAD WOOD CRAFT 1.82 1.33 27
2022 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for REJUVINATION OF BAKLA water supply scheme, TW no III under Jal Jeevan Mission under NMD-II, PHE Dte.APD ORD/000822/2022-2023 478/NMD-II 02/03/2023 30 M/S A.D. ENTERPRISE 10.86 10.73 80
2023 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Lankapara Water Supply Scheme TW No.-V under NMD-II,PHE Dte Alipurduar. ORD/000823/2021-2022 202/NMD-II 24/02/2022 30 M/S RATAN KUMAR DASGUPTA & CO. 10.44 10.44 100
2024 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Lankapara Water Supply Scheme TW No.-VI under NMD-II,PHE Dte Alipurduar. ORD/000824/2021-2022 204/NMD-II 24/02/2022 30 SARKAR ELECTRIC 10.46 10.46 10
2025 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for JAY BIRPARA TG water supply scheme, TW no I and II under Northern Mechanical Division-II, PHE Dte.Alipurduar ORD/000825/2023-2024 2398/NMD-II 09/08/2023 601 GEETA CONSTRUCTION 21.71 0.00 65
2026 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Hosainbad TG water supply scheme, TW no. I and II under Northern Mechanical Division-II, PHE Dte.APD ORD/000826/2022-2023 485/NMD-II 02/03/2023 30 MITRA ENTERPRISE 27.77 27.60 99
2027 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for SIDHABARI water supply scheme, TW no II in the district of Alipurduar under Northern Mechanical Division-II, ORD/000827/2022-2023 489/NMD-II 02/03/2023 30 MITRA ENTERPRISE 9.85 9.70 85
2028 Northern Mechanical Division II Renovation of the electrical installation of NARARTHALI W/S scheme P/H No. I under NMD-II , PHE, Dte. Alipurduar . ORD/000830/2022-2023 494/NMD-II 02/03/2023 15 SARKAR ELECTRIC 1.09 0.00 0
2029 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for BARUIPARA TG water supply scheme, TW no I and II under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/000831/2023-2024 2412/NMD-II 10/08/2023 30 A.S. ENTERPRISE 18.42 0.00 0
2030 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Gargenda TG water supply scheme, TW no IV in the district of Alipurduar under Northern Mechanical Division-II, PHE Dte. ORD/000833/2022-2023 519/NMD-II 14/03/2023 30 DEY ENTERPRISE (BALLY) 13.60 13.46 90
2031 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Bhatpara TG water supply scheme, TW no I and II under Jal Jeevan Mission under NMD-II, PHE Dte. APD ORD/000833/2023-2024 2414/NMD-II 10/08/2023 570 SARKAR ELECTRIC 21.92 20.59 90
2032 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Pakriguri water supply scheme, TW no I,II and III under Jal Jeevan Mission under NMD-II, PHE Dte.APD ORD/000835/2023-2024 2415/NMD-II 10/08/2023 631 ALPHA ENTERPRISE 27.58 0.00 100
2033 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for TELIPARA water supply scheme, TW no I & II under Northern Mechanical Division-II, PHE Dte.Alipurduar ORD/000837/2023-2024 2421/NMD-II 10/08/2023 572 QUAZI NOZRUL ISLAM 21.70 0.00 100
2034 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Nimtijhora TG water supply scheme, TW no I and II under Jal Jeevan Mission under NMD-II, PHE Dte.APD ORD/000838/2023-2024 2413/NMD-II 10/08/2023 358 SUNLIT 18.75 17.28 100
2035 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for DAKSHIN PATKAPARA AREA PWSS, TW no I (H/W SITE) in the district of ALIPURDUAR under Northern Mechanical Division-II, PHE Dte. ORD/000840/2022-2023 0568/NMD-II 17/03/2023 625 TALUKDAR ENTERPRISE 9.88 9.20 100
2036 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Buxa Forest (Raja bhatKhawa) water supply scheme, TW no I of Zone-I and TW-I and II of Zone-II and TW No-I of Zone-III of under NMD-II, PHE Dte.APD ORD/000840/2023-2024 2418/NMD-II 10/08/2023 30 M/S P.P ELECTRICALS 38.78 0.00 0
2037 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for GANGUTIA TG water supply scheme, TW no I and II under Northern Mechanical Division-II, PHE Dte.Alipurduar ORD/000841/2022-2023 571/NMD-II 17/03/2023 30 SUMON ELECTRICAL 21.73 17.90 100
2038 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector of Madarihat TG PWSS, TW no .II in the district of Alipurduar under Northern Mechanical Division-II, PHE Dte ORD/000843/2022-2023 585/NMD-II 18/03/2023 30 M/S MATRI CONSTRUCTION 10.82 10.17 100
2039 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for CHOTO DALDALI water supply scheme, TW no I and II under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/000843/2023-2024 2424/NMD-II 10/08/2023 637 M/S SAJAHAN CHOWDHURY 21.72 0.00 100
2040 Northern Mechanical Division II Supply, delivery and installation of 25 KVA servo motor operated Copper wound line voltage corrector at Hantapara T.G Water Supply Scheme TW No.-I under NMD-II,PHE.Dte,Alipurduar. ORD/000847/2022-2023 610/NMD-II 20/03/2023 20 S.K ENTERPRISE 3.30 3.30 100
2041 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector of Dakshin Paitkapara PWSS, TW no .II in the district of Alipurduar under Northern Mechanical Division-II, PHE Dte ORD/000850/2022-2023 625/NMD-II 21/03/2023 30 SARKAR ELECTRIC 9.93 9.93 100
2042 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for REJUVINATION OF CHOTO SALKUMAR water supply scheme, TW no III under Jal Jeevan Mission under NMD-II, PHE Dte. APD. ORD/000852/2022-2023 635/NMD-II 22/03/2023 30 PRAGATI CONSTRUCTION COMPANY 10.86 10.60 100
2043 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Kadambini water supply scheme, TW no I and II of Zone-II under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/000854/2023-2024 2437/NMD-II 11/08/2023 30 A.G ENTERPRISE 18.46 17.16 90
2044 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Rejuvenation of Paschim Khairbari water supply scheme, TW no IV under Northern Mechanical Division-II, PHE Dte.Alipurduar ORD/000855/2023-2024 2438/NMD-II 11/08/2023 30 M/S MATRI CONSTRUCTION 10.95 0.00 0
2045 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Gopalpur TG water supply scheme, TW no I in the district of Alipurduar under Northern Mechanical Division-II, PHE Dte. ORD/000857/2022-2023 651/NMD-II 24/03/2023 30 RMD TRADING 9.91 9.77 100
2046 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Rejuvenation of Uttar Madarihat water supply scheme, TW no III under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/000857/2023-2024 2435/NMD-II 11/08/2023 30 TALUKDAR ENTERPRISE 12.13 9.63 100
2047 Northern Mechanical Division II Supply, delivery & installation of 30 KVA, Servo Motor operated Copper wound line voltage stabilizer Lankapara Water Supply Scheme TW No.-V under NMD-II,PHE.Dte,Coochbehar. ORD/000859/2021-2022 185/ NMD-II 23/02/2022 30 M/S PALI DEB ENGINEERING 3.16 3.16 12
2048 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Gopalpur TG water supply scheme, TW no II in the district of Alipurduar under Northern Mechanical Division-II PHE Dte APD ORD/000862/2022-2023 659/NMD-II 24/03/2023 30 M/S ABHISEK ENGINEERING CONCERN 9.91 9.91 90
2049 Northern Mechanical Division II Supply, delivery of Electro mechanical components at Dima T.G Water Supply Scheme, in the dist. of ALIPURDUAR under NMD-II, PHE. Dte, Alipurduar. ORD/000865/2021-2022 307/NMD-II 10/03/2022 30 DIAMOND ELECTRICAL WORKS 8.32 8.32 30
2050 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for New Land TG water supply scheme, TW no II in the district of Alipurduar under Northern Mechanical Division-II PHE Dte. APD. ORD/000865/2022-2023 664/NMD-II 24/03/2023 30 SARKAR ELECTRIC 10.46 10.39 90
2051 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Sidhabari water supply scheme, TW no I in the district of Alipurduar under Northern Mechanical Division-II, PHE Dte. APD. ORD/000867/2022-2023 674/NMD-II 27/03/2023 767 SOUMEN ELECTRIC 9.87 7.36 100
2052 Northern Mechanical Division II Supply & delivery,of Electro mechanical components at Patlakhawa Water Supply Scheme,TW-I in the dist of ALIPURDUAR under NMD-II,PHE.Dte,Alipurduar. ORD/000868/2021-2022 632/AMSD 03/03/2022 15 MADHAB SAHA 2.35 2.35 68
2053 Northern Mechanical Division II Supply, delivery of Electro mechanical components at Mujnai T.G Water Supply Scheme in the dist of ALIPURDUAR under NMD-II PHE Dte Alipurduar. ORD/000871/2021-2022 332/NMD-II 14/03/2022 30 SARKAR ELECTRIC 11.50 11.50 27
2054 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for AUGUMENTATION OF DALIMPUR water supply scheme, TW no I and II of Zone - I and TW no I and II of Zone - II and TW no I and II of Zone - III under Jal Jeevan Mission under NMD-II, PHE Dte. Alipurduar. ORD/000875/2023-2024 2453/NMD-II 11/08/2023 540 ALPHA ENTERPRISE 65.55 7.99 35
2055 Northern Mechanical Division II Supply, delivery & installation of 15 KVA, Servo Motor operated Copper wound line voltage stabilizer of Totopara Water Supply Scheme TW No.-IV under NMD-II, PHE. Dte, Alipurduar. ORD/000881/2021-2022 1374/NMD-II 22/12/2021 30 SANJIB SAHA 2.15 2.15 0
2056 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for FOKSHADANGA water supply scheme, TW no I and II under Jal Jeevan Mission under NMD-II, PHE Dte. Alipurduar. ORD/000881/2023-2024 2457/NMD-II 11/08/2023 584 SAIKAT SINHA 18.31 12.92 100
2057 Northern Mechanical Division II Supply, delivery & installation of 30 KVA, Servo Motor operated Copper wound line voltage stabilizer of HASIMARA Water Supply Scheme TW No.- IV under NMD-II, PHE. Dte. ORD/000882/2021-2022 400/NMD-II 22/03/2022 30 M/S A.D. ENTERPRISE 3.17 3.17 0
2058 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Dakhshin Rangalibazna Water Supply Scheme TW No.-I and II under NMD-II,PHE.Dte,Apd. ORD/000886/2023-2024 2464/NMD-II 11/08/2023 605 S.D CONCERN WORKSHOP 20.48 0.00 49
2059 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Madhya Kamakhyaguri Water Supply Scheme TW No.-I and II under NMD-II,PHE.Dte,Apd. ORD/000888/2023-2024 2466/NMD-II 11/08/2023 30 M/S PARITOSH BHOWMICK & CO. 21.92 10.30 100
2060 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Paschim Deogaon Water Supply Scheme TW No.-I and II under NMD-II,PHE.Dte,Apd. ORD/000892/2023-2024 2477/NMD-II 11/08/2023 30 SUNLIT 21.78 0.00 50
2061 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Augmentation of Kaijali Basty Water Supply Scheme TW No.- I and II under NMD-II,PHE.Dte,Apd. ORD/000893/2023-2024 2480/NMD-II 11/08/2023 30 DIAMOND ELECTRICAL WORKS 25.08 11.74 90
2062 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Uttar Mandabari Water Supply Scheme TW No.- I and II of Zone-I and TW No- I of Zone-II under NMD-II,PHE.Dte,APD. ORD/000894/2023-2024 2481/NMD-II 11/08/2023 30 DEY ENTERPRISE (MALDA) 32.91 25.72 60
2063 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Umacharanpur Water Supply Scheme TW No.-I and II under NMD-II,PHE.Dte,Apd. ORD/000895/2023-2024 2476/NMD-II 11/08/2023 30 CINZANO 21.90 0.00 0
2064 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Mairadanga Water Supply Scheme TW No.-I and II under NMD-II,PHE.Dte,Apd. ORD/000896/2023-2024 2475/NMD-II 11/08/2023 753 SUBODH KUMAR BANIK 21.06 0.00 80
2065 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Narsingpur Water Supply Scheme TW No.-I and II under NMD-II,PHE.Dte,Apd. ORD/000898/2023-2024 2474/NMD-II 11/08/2023 541 SUMON ELECTRICAL 21.78 9.02 90
2066 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Dhanirampur Water Supply Scheme TW No.-I and II under NMD-II,PHE.Dte,Apd. ORD/000899/2023-2024 2473/NMD-II 11/08/2023 508 SARKAR ELECTRIC 21.08 2.74 60
2067 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Chandijhar Water Supply Scheme TW No.-III under NMD-II,PHE.Dte,Alipurduar. ORD/000900/2021-2022 427/NMD-II 25/03/2022 30 KASHI NATH DEY 7.85 7.76 100
2068 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Paschim Chengmari Water Supply Scheme TW No.-I and II under NMD-II,PHE.Dte,Apd ORD/000900/2023-2024 2484/NMD-II 11/08/2023 541 DILIP MAHATO 20.14 18.51 100
2069 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for KALCHINI TG AREA Water Supply Scheme TW No.-I,II,III of Zone-I and TW No.-I,II,III,IV of Zone-II under NMD-II,Apd ORD/000906/2023-2024 2490/NMD-II 14/08/2023 30 M/S P.P ELECTRICALS 81.19 56.97 40
2070 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of submersible pumping machinery including auto cum manual control panel and other related accessories of Narthali Water Supply Scheme TW No.- IV under NMD-II,PHE.Dte,Alipurduar. ORD/000907/2021-2022 437/ NMD-II 29/03/2022 579 ASHOKE ADHIKARY 7.85 7.33 100
2071 Northern Mechanical Division II Supply, delivery & installation of 20 KVA, Servo Motor operated Copper wound line voltage stabilizer of Uttar Majherdabri Water Supply Scheme TW No.-IV under NMD-II, PHE. Dte, Alipurduar. ORD/000910/2021-2022 0401/NMD-II 22/03/2022 30 S P ENTERPRISE (KOLKATA) 2.39 2.38 100
2072 Northern Mechanical Division II Supply, delivery & installation of 20 KVA, Servo Motor operated Copper wound line voltage stabilizer of Madhya Parokata Water Supply Scheme TW No.-III under NMD-II,PHE.Dte, Alipurduar. ORD/000911/2021-2022 402/NMD-II 22/03/2022 30 TALUKDAR ENTERPRISE 2.38 2.36 0
2073 Northern Mechanical Division II Supply, delivery & installation of 20 KVA, Servo Motor operated Copper wound line voltage stabilizer of Narthali Water Supply Scheme TW No.-IV under NMD-II,PHE.Dte, Alipurduar. ORD/000912/2021-2022 403/NMD-II 22/03/2022 30 RMD TRADING 2.39 2.39 100
2074 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Augmentation of Dhumchipara TG Water Supply Scheme TW No.- I under NMD-II,PHE.Dte,Apd. ORD/000912/2023-2024 2468/NMD-II 11/08/2023 479 M/S ANJALI ENTERPRISE 14.86 10.83 100
2075 Northern Mechanical Division II Supply, delivery & installation of 20 KVA, Servo Motor operated Copper wound line voltage stabilizer of Paitkapara Tea Garden Water Supply Scheme TW No.-III under NMD-II,PHE.Dte, Alipurduar. ORD/000913/2021-2022 404/NMD-II 22/03/2022 30 SAIKAT SINHA 2.39 2.39 0
2076 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Augmentation of Nepania Water Supply Scheme TW No.-I under NMD-II,PHE.Dte,,Apd ORD/000913/2023-2024 2491/NMD-II 14/08/2023 30 M/S DE ENGINEERING CONCERN 12.95 0.00 0
2077 Northern Mechanical Division II Supply, delivery & installation of 20 KVA, Servo Motor operated Copper wound line voltage stabilizer of Narthali Water Supply Scheme TW No.-V under NMD-II, PHE. Dte, Alipurduar. ORD/000914/2021-2022 405/NMD-II 22/03/2022 30 HARAGOURI ENTERPRISE 2.38 2.38 0
2078 Northern Mechanical Division II Hiring of Motor Cab (Non-air conditioned) for site visit of the Assistant Engineer , Alipurduar Mechanical Sub- Division, P.H.E. Dte. for Inspection of different PWSS under JJM like Newland TG , Kumargram TG & Sankosh TG under Northern Mechanical Division -II, P.H.E. Dte. ORD/000914/2023-2024 139/AMSD 30/06/2023 62 MUSTAFI CONCERN 0.69 0.50 100
2079 Northern Mechanical Division II Supply, delivery & installation of 20 KVA, Servo Motor operated Copper wound line voltage stabilizer of Uttar Kamakhyaguri Water Supply Scheme TW No.- V under NMD-II, PHE. Dte, Alipurduar. ORD/000915/2021-2022 0406/NMD-II 22/03/2022 30 GURUKRIPA ENTERPRISE 2.37 0.00 0
2080 Northern Mechanical Division II Supply, delivery & installation of 20 KVA, Servo Motor operated Copper wound line voltage stabilizer of Putimari Water Supply Scheme TW No.-III under NMD-II,PHE.Dte, Alipurduar. ORD/000916/2021-2022 407/NMD-II 22/03/2022 30 MALAY KUMAR SAHA 2.39 2.36 100
2081 Northern Mechanical Division II Supply, delivery & installation of 30 KVA, Servo Motor operated Copper wound line voltage stabilizer of Hasimara Water Supply scheme T/W No.III NMD-II, PHE. Dte, Alipurduar. ORD/000917/2021-2022 408/NMD-II 22/03/2022 30 MAA TARA ENTERPRISE 3.16 3.16 0
2082 Northern Mechanical Division II Supply, delivery & installation of 20 KVA, Servo Motor operated Copper wound line voltage stabilizer of Chandijhar Water Supply Scheme TW No.- III under NMD-II, PHE. Dte, Alipurduar. ORD/000926/2021-2022 409/NMD-II 22/03/2022 30 M/S J.K ENGINEERING CO. 2.39 2.38 0
2083 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Augmentation of KUMARGRAM Water Supply Scheme TW No.-I,II,III,IV,V,VI,VII and VIII under NMD-II,PHE.Dte,APD ORD/000926/2023-2024 2512/NMD-II 14/08/2023 829 ALPHA ENTERPRISE 93.39 0.00 70
2084 Northern Mechanical Division II Supply, delivery & installation of 20 KVA, Servo Motor operated Copper wound line voltage stabilizer of Loknathpur Water Supply Scheme TW No.- V under NMD-II, PHE. Dte, Alipurduar. ORD/000927/2021-2022 410/NMD-II 22/03/2022 30 MITRA ENTERPRISE 2.39 2.38 0
2085 Northern Mechanical Division II Supply, delivery & installation of 20 KVA, Servo Motor operated Copper wound line voltage stabilizer of Uttar Majherdabri Water Supply Scheme TW No.-III under NMD-II,PHE.Dte,Alipurduar. ORD/000928/2021-2022 411/NMD-II 22/03/2022 30 QUAZI NOZRUL ISLAM 2.39 2.37 0
2086 Northern Mechanical Division II Electrification and Earthing of the Newly Renovated pump house No. I and same other allied work ar Bhatibari water supply scheme under JJM. in the Dist. of Alipurduar. ORD/000930/2022-2023 652/AMSD 02/03/2023 15 TALUKDAR ENTERPRISE 0.93 0.00 100
2087 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for Rejuvenation of BENGKANDI water supply scheme, TW no I AND II under JJM under NMD-II,PHE Dte. APD ORD/000930/2023-2024 2541/NMD-II 16/08/2023 1342 A.S. ENTERPRISE 22.88 0.00 90
2088 Northern Mechanical Division II Supply, delivery, installation, commissioning andtrial run of electro-mechanical components alongwith Cu wound line voltage corrector forRejuvenation of DALGAON T.G water supplyscheme, TW no I AND II underJJM under NMD II,PHE Dte. APD. ORD/000935/2023-2024 2544/NMD-II 16/08/2023 762 M/S MATRI CONSTRUCTION 21.85 0.00 80
2089 Northern Mechanical Division II Supply, delivery, installation, commissioning andtrial run of electro-mechanical components alongwith Cu wound line voltage corrector forRejuvenation of TASTI T.G water supply scheme,TW no I AND II under JJM under NMD-II,PHE Dte.APD. ORD/000938/2023-2024 2542/NMD-II 16/08/2023 30 MADHAB SAHA 21.86 4.37 50
2090 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Rejuvention of 28 AND 29 MILE BASTI Water Supply Scheme TW No.- I and II under NMD-II,PHE.Dte,Apd. ORD/000939/2023-2024 2543/NMD-II 16/08/2023 30 DILIP MAHATO 22.96 0.00 0
2091 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for BUXA PWSS,TW No.-I and II under NMDII, PHE.Dte,Alipurduar. ORD/000947/2023-2024 2532/NMD-II 16/08/2023 30 MUSTAFI CONCERN 25.54 0.00 0
2092 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for Rejuvenation of UTTAR DEOGAON water supply scheme, TW no I AND II under JJM under NMD-II, PHE Dte. APD. ORD/000952/2023-2024 2558/NMD-II 18/08/2023 30 SUNLIT 22.20 0.00 50
2093 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for DALMONI T.G water supply scheme, TW no I and II of ZONE-I AND TW NO.I OF ZONE-II under JJM under NMD-II, PHE Dte. APD. ORD/000953/2023-2024 2559/NMD-II 18/08/2023 30 B.B CONCERNED 31.29 20.91 45
2094 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Augmentation of GARGENDA TG Water Supply Scheme TW No.-I,II ,III and IV of Zone-I under NMD-II,PHE.Dte,Alipurduar. ORD/000957/2023-2024 2561/NMD-II 18/08/2023 30 SARKAR ELECTRIC 54.50 43.19 5
2095 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for Rejuvenation of MALSAGAON water supply scheme, TW no I AND II under JJM under NMD-II, PHE Dte. APD. ORD/000963/2023-2024 2572/NMD-II 22/08/2023 680 M/S ANJALI ENTERPRISE 22.82 0.00 100
2096 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for Rejuvenation of LACHHIAMANDABRI water supply scheme, TW no I AND II under JJM under NMD-II, PHE Dte. APD. ORD/000964/2023-2024 2571/NMD-II 22/08/2023 30 DEY ENTERPRISE (MALDA) 22.20 17.77 100
2097 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for MALANGI T.G water supply scheme, TW no I and II under JJM under NMD-II, PHE Dte. APD. ORD/000990/2023-2024 2620/NMD-II 25/08/2023 578 B.B CONCERNED 21.90 0.00 40
2098 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for KHAGENHAT water supply scheme, TW no I AND II under JJM under NMD-II, PHE Dte. APD. ORD/000991/2023-2024 2621/NMD-II 25/08/2023 30 ASHOKE ADHIKARY 21.88 14.35 40
2099 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for CHENGMARI water supply scheme, TW no I AND II under JJM under NMD-II, PHE Dte. APD. ORD/000992/2023-2024 2622/NMD-II 25/08/2023 588 P K ENGINEERING 22.00 20.58 100
2100 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for PARPATLA KHAWA water supply scheme, TW no I and II of under JJM under NMD-II, PHE Dte. APD. ORD/000993/2023-2024 2625/NMD-II 25/08/2023 30 HARA PROSAD DAS 21.25 0.00 40
2101 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for DHANTALI water supply scheme, TW no I AND II under JJM under NMD-II, PHE Dte. APD. ORD/000994/2023-2024 2623/NMD-II 25/08/2023 677 RUBY ENTERPRISE 22.00 0.00 80
2102 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for PURBBA MAJHERDABRI T.G. AREA water supply scheme, TW no I AND II under JJM under NMD-II, PHE Dte. APD. ORD/000995/2023-2024 2624/NMD-II 25/08/2023 610 BONANZA ENTERPRISE 21.27 5.17 100
2103 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Bariguri water supply scheme, TW no I,II and III of under Northern Mechanical Division-II, PHE Dte.APD ORD/001034/2023-2024 2664/NMD-II 04/09/2023 475 A.S. ENTERPRISE 27.56 21.58 100
2104 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Raja Bhat TG Water Supply Scheme TWNo-I and II under NMD-II,PHE.Dte,APD. ORD/001038/2023-2024 2679/NMD-II 11/09/2023 577 RMD TRADING 21.66 5.83 80
2105 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Purba Narthali Water Supply Scheme TW No.- I and,II under NMD-II,PHE.Dte,APD. ORD/001046/2023-2024 2693/NMD-II 14/09/2023 849 P K ENGINEERING 21.75 8.20 100
2106 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for UTTAR DHALKAR Water Supply Scheme TW No.- I AND II under NMD-II,PHE.Dte,APD. ORD/001067/2023-2024 2578/NMD-II 22/08/2023 818 M/S B ENTERPRISE 21.17 0.00 75
2107 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro-mechanical components along with Cu wound line voltage corrector for Rejuvenation of DIMA T.G water supply scheme, TW no III under NMD-II, PHE Dte 106. APD. ORD/001076/2023-2024 2766/NMD-II 04/10/2023 668 ASHWIRBAD WOOD CRAFT 10.68 0.00 90
2108 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Kadambini water supply scheme, TW no I and II of Zone-I under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/001090/2023-2024 2792/NMD-II 06/10/2023 485 ASHUTOSH DAS & CO. 18.45 0.00 100
2109 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Uttar Barajhar FOREST Water Supply Scheme TW No.- I AND II under NMD-II,PHE.Dte,APD. ORD/001095/2023-2024 2809/NMD-II 09/10/2023 30 SUBODH KUMAR BANIK 19.86 0.00 0
2110 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for BHATIBARI Water Supply Scheme TWNo- I,II,of Zone-I TWNo- I,II,of Zone-II TWNo- I,II,of Zone-III under NMD-II,PHE.Dte,APD.. ORD/001098/2023-2024 2826/NMD-II 11/10/2023 508 DEY ENTERPRISE (BALLY) 65.07 50.79 100
2111 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Augmentation of Dakshin Sonapur Water Supply Scheme TW No.-I and II under NMD-II,PHE.Dte,Apd. ORD/001099/2023-2024 2827/NMD-II 11/10/2023 30 WILFUL UNEMPLOYED ENGINEERS CO OPERATIVE SOCIETY LIMITED 21.93 14.28 50
2112 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Ethelbari water supply scheme, TW no I of Zone-II under Northern Mechanical Division-II, PHE Dte.Alipurduar. ORD/001101/2023-2024 2834/NMD-II 12/10/2023 30 MITRA ENTERPRISE 9.72 6.43 100
2113 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for BHUTRI FOREST Water Supply Scheme TW No- I under NMDII, PHE.Dte,APD. ORD/001102/2023-2024 2836/NMD-II 12/10/2023 30 PRAGATI CONSTRUCTION COMPANY 10.18 10.07 100
2114 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Atiabari TG water supply scheme, TW no I and II under Jal Jeevan Mission under NMD-II, PHE Dte.APD ORD/001127/2023-2024 2942/NMD-II 09/11/2023 30 M/S ABHISEK ENGINEERING CONCERN 21.50 21.20 100
2115 Northern Mechanical Division II Supply, delivery, installation, commissioning and trial run of electro mechanical component along with Cu. wound line voltage corrector for Augmentation of Birpara water supply scheme TW No.- I,II and III of Zone-I and TW No.- I,II,III and IV of Zone-II and TW No.- I,II and III of Zone-III under Northern Mechanical Division-II, PHE Dte, Alipurduar. ORD/001136/2023-2024 2873/NMD-II 17/10/2023 808 EASTERN INDIA SALES & SERVICE 176.42 118.20 80
2116 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Rangamati TG water supply scheme, TW no I and II of Zone-I and TW no I and II of Zone-II under Jal Jeevan Mission under NMD-II, PHE Dte.APD ORD/001137/2023-2024 2933/NMD-II 07/11/2023 30 S.P ENTERPRISE (SLG) 44.02 30.63 60
2117 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Madhya Khairbari Water Supply Scheme TW No.- I,II AND III under NMDII, PHE.Dte,APD. ORD/001141/2023-2024 2886/NMD-II 17/10/2023 473 M/S BHOWMIK & CO. 29.84 24.35 100
2118 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Augmentation of UTTAR SISHUBARI Water Supply Scheme TWNo- I AND II under NMDII,PHE.Dte,APD. ORD/001143/2023-2024 2887/NMD-II 17/10/2023 762 S.D CONCERN WORKSHOP 22.02 0.00 45
2119 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Nimti Domohini Water Supply Scheme TWNo-I and II under NMD-II,PHE.Dte,APD. ORD/001178/2023-2024 2909/NMD-II 31/10/2023 562 GURUKRIPA ENTERPRISE 21.48 0.00 50
2120 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Purba Chikliguri Water Supply Scheme TW No.- I AND II under NMD-II,PHE.Dte,APD ORD/001180/2023-2024 2911/NMD-II 31/10/2023 459 M/S CHANDRANATH MUKHERJEE 18.82 12.02 90
2121 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Augmentation of Jayanti Water Supply Scheme TW No.-I under NMD-II,PHE.Dte,,Apd. ORD/001181/2023-2024 2913/NMD-II 31/10/2023 30 MUSTAFI CONCERN 12.17 0.00 0
2122 Northern Mechanical Division II Solarization of grid connected pumping installation at different PWSS at Alipurduar -II block in the dist.of Alipurduar under JJM programme under Northern Mechanical Division-II, PHE Dte. ORD/001205/2024-2025 819/NMD-II 06/03/2025 30 THE BUSINESS ENGINEERS INDIA 28.94 0.00 0
2123 Northern Mechanical Division II Solarization of grid connected pumping installation at Different PWSS at Kumargram Block in the dist.of Alipurduar under JJM programme under Northern Mechanical Division-II, PHE Dte. ORD/001206/2024-2025 820/NMD-II 06/03/2025 30 WATER TECH 29.68 0.00 0
2124 Northern Mechanical Division II Solarization of grid connected pumping installation at Different PWSS at Falakata Block in the dist.of Alipurduar under JJM programme under Northern Mechanical Division-II, PHE Dte. ORD/001207/2024-2025 821/NMD-II 06/03/2025 30 THE BUSINESS ENGINEERS INDIA 28.94 0.00 0
2125 Northern Mechanical Division II Solarization of grid connected pumping installation at Different PWSS at Alipurduar-I Block in the dist.of Alipurduar under JJM programme under Northern Mechanical Division-II, PHE Dte. ORD/001208/2024-2025 822/NMD-II 06/03/2025 30 THE BUSINESS ENGINEERS INDIA 28.94 0.00 0
2126 Northern Mechanical Division II Solarization of grid connected pumping installation at Different PWSS at Kalchini Block in the dist.of Alipurduar under JJM programme under Northern Mechanical Division-II, PHE Dte. ORD/001209/2024-2025 823/NMD-II 06/03/2025 30 THE BUSINESS ENGINEERS INDIA 28.94 0.00 0
2127 Northern Mechanical Division II "Hiring of Motor Cab (Non-air conditioned) for site visit of JJM Works under the Office of the EE/NMD-II P.H.E. Dte." ORD/001226/2024-2025 716/AMSD 30/12/2024 60 D.K AND SONS 0.75 0.00 0
2128 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for AUGMENTATION OF DALMORE & RAMJHORA TEA GARDEN PIPED WATER SUPPLY SCHEME,TW No.- I of Zone-I AND II under NMD-II,PHE.Dte,Alipurduar. ORD/001234/2023-2024 2968/NMD-II 21/11/2023 469 B.B CONCERNED 28.76 19.86 90
2129 Northern Mechanical Division II "Hiring of Motor Cab (Non-air conditioned) for site visit of JJM Works under the Office of the EE/NMD-II P.H.E. Dte." ORD/001249/2023-2024 419/AMSD 16/10/2023 61 MUSTAFI CONCERN 0.69 0.00 100
2130 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Lankapara in Relation With Chaa Sundori Water Supply Scheme TWNo- I,II,III,IV under NMD-II,PHE.Dte,APD. ORD/001261/2023-2024 2988/NMD-II 28/11/2023 30 SARKAR ELECTRIC 59.29 46.95 58
2131 Northern Mechanical Division II Supply and Delivery at site of Calcium granules Hypochlorite Birpara, Dakshin Borojhar Forest & Torsha Forest pwss in the dist. of Alipurduar under NMD-II PHE Dte. ORD/001606/2025-2026 128/AMSD 13/03/2026 15 PRAGATI CONSTRUCTION COMPANY 0.76 0.00 0
2132 Northern Mechanical Division II "Hiring of Motor Cab (Non-air conditioned) for site visit of JJM Works under the Office of the EE/NMD-II P.H.E. Dte." ORD/001615/2023-2024 588/AMSD 29/12/2023 62 MUSTAFI CONCERN 0.75 0.00 0
2133 Northern Mechanical Division II Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for Augmentation of HANTUPARA water supply scheme, TW no- I Under JJM under Northern Mechanical Division-II, PHE Dte. ORD/002039/2023-2024 1187/NMD-II 11/03/2024 266 DEY ENTERPRISE (MALDA) 11.26 11.21 100
2134 Northern Mechanical Division II Supply, installation, commissioning of 15KVA copper wound line voltage corrector for BANCHUKAMARI water supply scheme TW no- III under JJM under Northern Mechanical Division-II, PHE Dte. ORD/002081/2023-2024 1207/NMD-II 13/03/2024 30 D.K AND SONS 2.39 2.38 100
2135 Northern Mechanical Division II Continuation order for "Hiring of Motor Cab (Non-air conditioned) for site visit of JJM Works under the Office of the EE/NMD-II P.H.E. Dte." ORD/002126/2023-2024 102/AMSD 21/02/2024 60 MUSTAFI CONCERN 0.75 0.00 0
2136 Northern Mechanical Division II Supply & delivery of Stand by pumping machinery for Choto Salkumar and adjucent mouza water supply scheme, under JJM project in the dist. of Alipurduar under NMD-II, PHE Dte. ORD/002273/2023-2024 116./AMSD 29/02/2024 15 TAPAN BISWAS 0.77 0.77 100
2137 Northern Mechanical Division II Supply & delivery of Stand by pumping machinery for Choto Salkumar water supply scheme, P/H No. I under JJM project in the dist. of Alipurduar under NMD-II, PHE Dte. ORD/002320/2023-2024 127/AMSD 05/03/2024 15 CHOWDHURY AND BASU ENTERPRISE 0.77 0.00 100
2138 Northern Mechanical Division II Supply, delivery, installation, commissioning and Trial run of electro mechanical component along with Cu wound line voltage corrector for Kayakhata Water Supply Scheme TW No.-I and II under NMD-II,PHE.Dte,Apd. ORD/002506/2023-2024 2465/NMD-II 11/08/2023 569 KAMAKHYA ENTERPRISE 20.14 12.86 100
2139 Northern Mechanical Division II Quotation for new service connection at Loknathpur W/SS TW No-V Application No-4002937212 VCH/000641/2022-2023 14/07/2022 0 WBSEDCL 0.87 0.00 0
2140 Northern Mechanical Division II QUOTATION FOR NEW SERVICE CONNECTION AT CHANDIJHAR W/SS TW NO-III VCH/000642/2022-2023 14/07/2022 0 WBSEDCL 0.95 0.00 0
2141 Northern Mechanical Division II Quotation for new service connection at Loknathpur W/SS Application No-4002937212 VCH/000643/2022-2023 14/07/2022 0 WBSEDCL 0.87 0.00 0
2142 Northern Mechanical Division II Quotation for new service connection at Loknathpur W/SS Application No-4002943882 VCH/000644/2022-2023 14/07/2022 0 WBSEDCL 0.95 0.00 0
2143 Northern Mechanical Division II Quotation for new service connection at Hasimara W/SS Tw No-IV Application No- 4002954692 VCH/000685/2022-2023 02/08/2022 0 WBSEDCL 1.63 0.00 0
2144 Northern Mechanical Division II Quotation for new service connection at Hasimara W/SS Tw No-III Application No- 4002954503 VCH/000686/2022-2023 02/08/2022 0 WBSEDCL 1.63 0.00 0
2145 Northern Mechanical Division II Quotation for new service connection at banchukamari W/SS TW No-III, Application No-4002956342 VCH/000689/2022-2023 04/08/2022 0 WBSEDCL 0.87 0.00 0
2146 Northern Mechanical Division II Quotation for new service connection at putimari W/SS TW No III Application No-4002956347 VCH/000690/2022-2023 04/08/2022 0 WBSEDCL 0.87 0.00 0
2147 Northern Mechanical Division II Quotation for new service connection at uttar majherdabri W/SS TW No III Application No-4002956327 VCH/000691/2022-2023 04/08/2022 0 WBSEDCL 0.87 0.00 0
2148 Northern Mechanical Division II Quotation for new service connection at Uttar majherdabri W/SS TW No IV Application No-4002956335 VCH/000692/2022-2023 04/08/2022 0 WBSEDCL 0.87 0.00 0
2149 Northern Mechanical Division II NARATHALI T/W no.V, Alipurduar II, Application no. 4002930550, Ref no. 402824235, SM/10154/159 VCH/000696/2022-2023 BP-24/22-23 15/07/2022 0 WBSEDCL 0.87 0.00 0
2150 Northern Mechanical Division II NARATHALI T/W no.IV, Alipurduar II, Application no. 4002930565, Ref no. 402824639, SM10154/159 VCH/000697/2022-2023 BP-25/22-23 15/07/2022 0 WBSEDCL 0.87 0.00 0
2151 Northern Mechanical Division II MADHYA PAROKATA T/W no. III, Application no. 4002930511, Ref no. 402824640, SM/09886/160 VCH/000698/2022-2023 BP-26/22-23 15/07/2022 0 WBSEDCL 0.87 0.00 0
2152 Northern Mechanical Division II Uttar Kamakhya guri, T/W no. V, Application no. 4002930579, Ref no. 402824641, VCH/000699/2022-2023 BP-27/22-23 15/07/2022 0 WBSEDCL 0.87 0.00 0
2153 Northern Mechanical Division II Quotation for Loknath pur w/s scheme T/W no. Y, under NMD-II PHE Dte. application no. 4002937212( New Connection) Ref no. 402828607 VCH/001057/2022-2023 BP-37/22-23 08/08/2022 0 WBSEDCL 0.87 0.00 0
2154 Northern Mechanical Division II New Connection Chandirjhar P/H no. III, Appplication no. 402943882,Ref no. 402837622 (SM/09892) VCH/001067/2022-2023 BP-38/22-23 08/08/2022 0 WBSEDCL 0.95 0.00 0
2155 Northern Mechanical Division II Quotation for new connection service connection at HASIMARA W/SS T/W no. IV ,Application no.4002954692 VCH/001278/2022-2023 BP-39/22-23 08/08/2022 0 WBSEDCL 1.63 0.00 0
2156 Northern Mechanical Division II Quotation for new service connection for HASIMARA W/SS T/W no. III , Application no. 4002954503 VCH/001279/2022-2023 BP-40/22-23 08/08/2022 0 WBSEDCL 1.63 0.00 0
2157 Northern Mechanical Division II Quotation for new service connection for uttar majher Dabri w/s scheme t/W no. II , Application no. 40025956327 VCH/001280/2022-2023 BP-41/22-23 08/08/2022 0 WBSEDCL 0.87 0.00 0
2158 Northern Mechanical Division II Quotation for new service connection for UTTAR MAJHER DABRI w/ss T/W no. IV. Application no. 4002956335 VCH/001281/2022-2023 BP-42/22-23 08/08/2022 0 WBSEDCL 0.87 0.00 0
2159 Northern Mechanical Division II Quotation for new service connection for PUTIMARI (Aug) Application no. 40025956347 VCH/001282/2022-2023 BP-43/22-23 08/08/2022 0 WBSEDCL 0.87 0.00 0
2160 Northern Mechanical Division II Quotation for new service connection for BANCHUKAMARI T/W no. III Application no. 4002956342 VCH/001289/2022-2023 BP-44/22-23 08/08/2022 0 WBSEDCL 0.87 0.00 0
2161 Northern Mechanical Division II Quotation for new service connection at SIDHABARI P/H NO-II VCH/001310/2022-2023 27/09/2022 0 WBSEDCL 1.75 0.00 0
2162 Northern Mechanical Division II Quotation for new service connection at SIDHABARI P/H NO-I VCH/001311/2022-2023 27/09/2022 0 WBSEDCL 1.75 0.00 0
2163 Northern Mechanical Division II Quotation for new service connection at Jasodanga W/SS TW No- III VCH/001326/2022-2023 BP-75/22-23 14/10/2022 0 WBSEDCL 1.23 0.00 0
2164 Northern Mechanical Division II Quotation for new service connection at Chuniya Jhora W/SS TW No- I VCH/001327/2022-2023 BP-14/22-23 14/10/2022 0 WBSEDCL 1.23 0.00 0
2165 Northern Mechanical Division II Quotation for new service connection at Chuniya Jhora W/SS TW No- II VCH/001328/2022-2023 BP-73/22-23 14/10/2022 0 WBSEDCL 1.23 0.00 0
2166 Northern Mechanical Division II Quotation for new connection of Sidahabari W/Ss P/H no-II, Application no. 4002994719, Ref: 402875931 VCH/001422/2022-2023 BP-70/22-23 30/09/2022 0 WBSEDCL 1.75 0.00 0
2167 Northern Mechanical Division II Quotation for new connection of Sidahabari PWSS P/H no-I, Application no. 4002994696, Ref: 402875912 VCH/001423/2022-2023 BP-71/22-23 30/09/2022 0 WBSEDCL 1.75 0.00 0
2168 Northern Mechanical Division II Quotation for new service connection at Madarihat TG P/H No-III VCH/001438/2022-2023 02/11/2022 0 WBSEDCL 1.34 0.00 0
2169 Northern Mechanical Division II Quotation for new service connection at Madarihat TG P/H No-I VCH/001439/2022-2023 02/11/2022 0 WBSEDCL 1.34 0.00 0
2170 Northern Mechanical Division II Quotation for new service connection at Madarihat TG P/H No-II VCH/001440/2022-2023 02/11/2022 0 WBSEDCL 1.34 0.00 0
2171 Northern Mechanical Division II Quotation for new service connection at Mujnai TG P/H No-V VCH/001441/2022-2023 02/11/2022 0 WBSEDCL 1.06 0.00 0
2172 Northern Mechanical Division II Quotation for new service connection for DAKSHIN PATKAPARA. Tube well no. II, Application no. 4003007835 VCH/001449/2022-2023 07/11/2022 0 WBSEDCL 1.01 0.00 0
2173 Northern Mechanical Division II Quotation for new service connection for DAKSHIN PATKAPARA. Tube well no. I, Application no. 4003007857 VCH/001450/2022-2023 07/11/2022 0 WBSEDCL 1.01 0.00 0
2174 Northern Mechanical Division II Quotation for new service connection for Bholardabri, near Modakpara t/W no. III, Application no. 4003012374 VCH/001451/2022-2023 07/11/2022 0 WBSEDCL 1.23 0.00 0
2175 Northern Mechanical Division II Quotation for new service connection at MADARIHAT T.G, P/H no. II, Application no.4002997569 VCH/001459/2022-2023 BP-81/22-23 04/11/2022 0 WBSEDCL 1.34 0.00 0
2176 Northern Mechanical Division II Quotation for new service connection at MADARIHAT T.G, P/H no. I, Application no.4002997527 VCH/001460/2022-2023 BP-82/22-23 04/11/2022 0 WBSEDCL 1.34 0.00 0
2177 Northern Mechanical Division II Quotation for new service connection at MADARIHAT T.G, P/H no. III, Application no.4002997498 VCH/001461/2022-2023 BP-83/22-23 04/11/2022 0 WBSEDCL 1.34 0.00 0
2178 Northern Mechanical Division II Quotation for new service connection at MUJNAI T.G . P/H no. V, Application no.4002997419 VCH/001462/2022-2023 BP-84/22-23 04/11/2022 0 WBSEDCL 1.06 0.00 0
2179 Northern Mechanical Division II Quotation for new service connection at Dakshin Patkapara, P/H no.I, Application no.4003007857 VCH/001463/2022-2023 BP-85/22-23 11/11/2022 0 WBSEDCL 1.01 0.00 0
2180 Northern Mechanical Division II Quotation for new service connection at Dakshin Patkapara, P/H no.II, Application no.403007835 VCH/001464/2022-2023 BP-86/22-23 11/11/2022 0 WBSEDCL 1.01 0.00 0
2181 Northern Mechanical Division II Quotation for new service connection at SALKUMAR HAT, P/H no. III, Application no. 4002994687 VCH/001470/2022-2023 BP-93/22-23 22/11/2022 0 WBSEDCL 1.42 0.00 0
2182 Northern Mechanical Division II Quotation for new service connection at Madhu T.G, P/H no. III, Application no. 4003018858 VCH/001471/2022-2023 BP-94/22-23 25/11/2022 0 WBSEDCL 0.98 0.00 0
2183 Northern Mechanical Division II Quotation for new service connection at Bholardabri, P/H no.III, Application no.4003012374 VCH/001473/2022-2023 bp-87/22-23 11/11/2022 0 WBSEDCL 1.23 0.00 0
2184 Northern Mechanical Division II Quotation for new service connection at PATLAKHAWA w/s scheme T/W no. III, Application no. 4003028004 VCH/001530/2022-2023 30/11/2022 0 WBSEDCL 1.34 0.00 0
2185 Northern Mechanical Division II Jashodanga W/S scheme T/W no. III, near Jashodanga Hospital campus VCH/002697/2021-2022 BP-40/21-22 26/03/2022 0 WBSEDCL 1.22 0.00 0
Total 76,772.10 44,977.09